Incinerator Emissions Betterment and Options Studies Presentation:
1. Incinerator Study
a. Part 1 Scope: Emissions modelling, emissions
targets, control technologies for emissions
reduction all evaluated and report by Eco Waste
Solutions.
b. Part 2 Scope: Research for alternative
incineration/waste disposal options and
considerations - report prepared by RESPEC.
2. Questions and Comments
Packet
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
SPEAKER_14Okay, I called the meeting assembly of the whole meeting for Tuesday, November fourteenth, twenty twenty-four.
SPEAKER_02All members present in corners assembly.
SPEAKER_14Do we have anyone here who would like to address the assembly? All right. Then we'll move on. Item three, MOS an incinerator project. And I think Manager Ryan, can I turn this over to you at this point?
SPEAKER_03Yeah. We're going to turn this over to Mark Pusich. I think all of you have probably heard or met Mark talk to us. We have lots of projects with him. He'll introduce his team, and then at the end, if there's other questions, you can we can pop with me, but for now we'll turn it over to Mark.
SPEAKER_13Thank you very much for the opportunity to be here. My name is Mark City. I'm a social engineer from the general office. Born and raised in Juneau and been working in your community for about 35 years. So I have a good pulse on what's going on here, and I really do appreciate the opportunity to serve your community. The reason we're here tonight is to talk about your incinerator. Your incinerator is aging, it's failing in different areas and is in need of replacement.
SPEAKER_13So we are under contract with the municipality to perform studies to look at solutions. And ultimate construction documents for the renovation of the incinerator. Your incinerator is a very key component of your community and how waste that's generated is dealt with. Currently it's being burned. But as you all are aware, we have a solid waste transfer facility that was recently opened this past summer.
SPEAKER_13So that has really helped alleviate some of the pressure that if the existing incinerator fails, you have a backup of shipping out garbage. But ultimately, we would like to have a mix of those two facilities to be the most efficient and beneficial to your committee. So as part of our um work and scope, we are under contract informed studies. Our design team has been on the ground for the last two days, uh basically going through every nook and cranny of the existing facility to get a really good understanding of what's happening there.
SPEAKER_13What are the issues, what are the problems, and what do we need to do to better ourselves to make improvements with our design and also the construction of that incinerator replacement? I want to introduce some of our team that's here tonight and also want to thank and deputy each for assisting us in this process today. Tyson and his group are just outstanding and allowing us access to places that normal people don't get to go and see.
SPEAKER_13So it's been kind of interesting. So um I have Stephen Bishop, who is a lead mechanical engineer at our office. They're from Eco Waste Solutions. Okay, so they're uh part of an incineration. They do design and construction of incinerations, and also we have on Zoom we have Doug Murray, who is our uh principal mechanical engineer who is uh very much leading this project from a management standpoint, and then we have Gene Lucas, who is the president and CEO of EcoWay Solutions.
SPEAKER_13So their firm has done multiple projects across the world and country of incineration. So they are incinerator experts, they're on our team to serve you and to make this the best project possible for the community. And tonight uh Gene is going to talk about different um uh emissions and studies and uh uh potential solutions that uh uh she has studied thus far. They were involved in the original incinerator, which also gives them a very good advantage of uh you know what's takes took place in the last 25 years.
SPEAKER_13The original incinerator was built in 1999 and commissioned right around then, so it's it's seen good use. And basically, there in the summer there are roughly four burns a week up there for waste, and in the winter that calms down to about one. So a fairly active uh facility, uh it's not day in and day out, but it's it's used quite heavily, and um you know it's a necessary infrastructure component in your community.
SPEAKER_13So I think I've kind of covered that introduction and um Jean, I think I'm gonna let you run from here if that's okay with you, just to kind of go through your um your eco-way studies, uh your different options and emissions, and just kind of overall your presentation, okay?
SPEAKER_06Okay, good. Thanks, Doug. All right, I'll just kill my video here. And uh guys over.
SPEAKER_05Okay, so um there's an old picture of the building back in the original days. Um, I thank you for the introduction. I think what we're gonna do is just jump right into this presentation. I believe all of you have the package with the full report, which goes into a lot more detail than I'm going to go into here, but it's you know good good um bedtime reading for you at another time. So jumping into this, there's there's the copy of the particular report, by the way, that you have in your package that was issued earlier.
SPEAKER_05And and the the things that we're gonna cover here are really we're gonna talk about, I'm gonna do it in a little bit different order. I'm just gonna talk about the current technology that's there and some of the advancements that it has over traditional incinerators. I'm gonna compare it against some emerging uh thermal treatment technologies that you've probably heard about, and then I'm gonna talk just about emissions in general and potentials for different types of emission control.
SPEAKER_05So um, this is actually from the Department of Energy, this overview. And I wanted to just give you this overview slide of all the potential waste conversion technologies, and we're gonna focus on the thermal conversion. The biochemical digestion versions of technologies, those are technologies that are um used primarily for organics. So organic materials can be digested and produce a gas.
SPEAKER_05So we're not gonna be talking about those. Really, there are these main three types of thermal waste conversion processes. So the most popular by far around the world is combustion, uh, gasification and pyrolysis are both used on very unique specific types of processes and are starting to be experimentally used on garbage and or have been now for many, many years and still being commercialized. So this kind of gives you an overview of what it is.
SPEAKER_05You can see the main focus of the thermal conversion technologies is to create an energy byproduct. So you can see with any type of combustion facility, you do produce waste heat, which has the potential for recapture. And gasification and pyrolysis are similar in that they also have that heat potential, but those you don't go through those processes just to produce heat because they are far more complex and require a lot more upfront work, and the the plants themselves are more complicated.
SPEAKER_05And in those cases, we're trying to produce an energy byproduct. Um, and there's some examples there. So, just to give you another overview of those technologies, so combustion has a poor reputation because it's generally not super well controlled. Um, and usually you have very poor emissions, but it gets the job done in terms of getting rid of the garbage and it keeps the bears away. Then the next phase or the next uh type of equipment that you caught you might see applied for waste conversion or gasification technologies.
SPEAKER_05And and the system that exists in Skagway, Alaska actually is a form of a gasification technology in that it converts waste from a solid to a gas. And in that process, um you generate a gas in the first stage, which is like a synthetic gas in that it has very similar properties to natural gas, for example. But in order to clean it up, to be able to put it into a pipeline or do something with it, a tremendous amount of um of refinement of that gas is required in order to get there.
SPEAKER_05And also, you really need a clean feedstock going in. You can't just take general unsorted garbage if you really want to produce those fuel byproducts. But in our case, we do gasification in the first stage, and in the second stage, we fully oxidize those gases. So they're used as a fuel to clean up the gases, and we'll go into more detail on that. Another example down the chain of complexity would be a pyrolysis system, and that's just a very overall reactor.
SPEAKER_05Reactors, in any of these cases, pyrolysis, gasification, there are a million different types of reactors. In fact, you could build a reactor that could do all three, three of these processes and not look very different from the outside. But what really happens is all of the gas cleanup that's required. In a pyrolysis system, now we're completely restricting the oxygen, whereas in gasification, we've just starved out some of that oxygen. In pyrolysis, we've completely starved the air, reduced the oxygen completely for the sole purpose of preserving those hydrocarbons.
SPEAKER_05So now you have either a rich hydrocarbon-rich gas or an oil or a char that you're producing as a byproduct that you can now potentially take to market. And um, that char may or may not be clean enough to use uh for a soil amendment. In fact, usually isn't if it's coming from municipal garbage. And also, again, tons of pre-sorting, tons of upfront work to get the waste to be the chemical uh profile that you need to produce good pyrolysis.
SPEAKER_05So, again, another complicated way of doing it, getting more complex, and very frequently they too have a second stage that just uh fully combusts because many of these pyrolysis reactors are just simply not fully commercialized. So you're not really seeing anybody taking black bag typical trash and putting it through any of these more complex systems and actually producing an energy byproduct. It's usually very highly separated, highly processed waste that goes in that's like a fuel or a feedstock, and it can produce these byproducts.
SPEAKER_05And if you really want to go one step further, you can add plasma to this process. So any of these reactors, you could add a plasma torch to any of them. And basically, the addition of the plasma torch is, of course, it's higher temperature, operating at thousands of degrees uh Celsius or Fahrenheit. And it and it really that whole purpose of the plasma torch is to increase your amount of thermal waste conversion and your amount of treatment of the gases, but now you're doing it in this very concentrated form.
SPEAKER_05Of course, it used tons of electrical energy to do this. Um, plasma gasification uh is a very expensive process, it's complicated, it uses a lot of power, and it does do the job, though, of cracking the tars that are generated in a gasification or pyrolysis process. So, in order to get to that fuel that you want to produce in the end, you use uh plasma torches in that way. You can also use it to vitrify the ash, and so that's why often it's being touted to be used for things like um hazardous waste.
SPEAKER_05So you could have any kind of hazardous waste, thermal process, rotary kiln, combustion, gasification, whatever you want, and you can add a plasma torch to it, and you can vitrify or turn into a solid piece of glass your ash. So, again, it's a lot of energy required to produce this byproduct, which in the end is most likely going to be a waste product, but it could potentially have other benefits. So I just wanted to give an example of this.
SPEAKER_05Is this a project you guys may have heard about in Canada, happened at the city of Ottawa. This was a um, this is a pilot scale project. This is only doing 10 tons a day. You're mostly only able to see all of the stuff that goes around it, and that's because what a these waste energy projects are they really are mini refineries. You're trying to take waste, dirty, raw garbage, you're gonna do a ton of things to it, and then you're gonna put on all this equipment to clean it up.
SPEAKER_05So although these companies are saying, hey, we've got this amazing process, which can do all this great stuff, for sure that might be true at very high at uh large scale, where you can really um have more of an economy of scale to support the project. But another issue with it is just the you can see the amount of complexity. Just for this being a small pilot scale project, you can see how extremely complicated and expensive it got very quickly.
SPEAKER_05And obviously nothing anywhere close to what you're operating currently in Skagway. And and uh, you know, we're talking hundreds of millions of dollars potentially, even at small scale. So that's that's the the reality of uh a lot of these uh other types of treatment forms because you are trying to get after a very high quality fuel or some other byproduct, so therefore you need to go at it, and that's why you have no emissions, because after you do all that to it, there really shouldn't be anything coming out of the stack because you've basically removed everything from the gases.
SPEAKER_05And you can again add all that complexity to any type of technology if if depending on what your goals are. Here's some other examples. Uh, one very big recent example is the Enercam plant, which just closed in Edmonton, Alberta. Um, so there was all there was about a billion dollar investment made in that facility, as well as additional um$100 million or so that was spent on the campus uh in order to support this particular project.
SPEAKER_05And they were trying to uh produce um a fuel byproduct from regular garbage. And by having there, in addition to the plant that you see here, they also had lots of different additional buildings where you're doing tons of um removal of unwanted products, you know, really reducing the amount of waste materials that are going in and then chopping them, pre-sredding, so and all of these kinds of things.
SPEAKER_05So it took them years to work the bugs out of that plant, and eventually it finally did do what it was supposed to do, although it's a uh it's a private company, so there's not a lot of details available, but we do understand that it did come online about four years ago, and now it's been closed again, and so it closed permanently. Um, so it's kind of a shame that that huge investment went in there. It's still considered to be a project success, but it is a um a lot of money to get there and kind of prove the point.
SPEAKER_05And now they've moved on. On the right is another product project. They'd only spent about half of the money. There, they'd already spent about a billion dollars. This is a a much bigger bulk. The Enercom project, by the way, was about um was supposed to be able to process 500 tons per day. So, not a really big plant for the price tag. On the on the right, this one is bigger, closer to a thousand ton a day. And with all the money and all of the best companies working on it, they were never able to get this project into operation.
SPEAKER_05It was abandoned. Multiple other technology companies have been there trying to uh reinvigorate it, but um it's now been shelved. So that's kind of the challenge with all these emerging technologies. They sound great, they sound very sexy, but in reality, they're fairly complicated and very expensive. And when you're you're looking at small scale, they just don't tend to be feasible at all. In the report, we go into a lot of detail about the different types of uh processes and what's required in terms of the feedstock and the processing and and all the details about what things happen, what what which ones might be more beneficial.
SPEAKER_05And in any major community where they were wanting to consider something that's an alternative to traditional waste energy, they would need to look at all of this. In the context of Skagway, it's much more acute, the issues here, because although you have relatively inexpensive electrical um costs, say for example, that could means that you could run a plasma torch uh um without it really having a huge operating impact.
SPEAKER_05But then again, um, can you do all of that upfront sorting and all of the buildings that would be required to do all of that, everything else that's required ahead of it. So again, I won't dive into all the details of this, but I think the report kind of went into a lot of how all these different technologies work and why someone might choose one or the other and the benefits of each uh and the impacts of each. So um, just going back to more simpler methods.
SPEAKER_05So I want to talk to you about the close couple gasification technology that exists currently in um in Skagway. Quite frequently, people just call it incinerators. And as a company at EcoWaste, we know that the title incinerator is synonymous with something that gets rid of your garbage. And so, therefore, we've never really hidden from the I-word incineration, and we we're not afraid of it because our customers are looking for something that works. And a lot of times, um, if they really understood that it's a closed couple gasification technology, they really wouldn't be interested because they could put in the same bucket as things that don't really necessarily work.
SPEAKER_05But the difference with closed coupled gasification is that you're taking all of the waste as received, you load the primary chamber, you completely uh allow that waste to be converted from uh solid, wet garbage down to dry, clean ash that is safe for disposal, non-leaching, and considered non-hazardous. And the gases that are generated in that process are oxidized at high temperatures where they're highly mixed before they're allowed to go out.
SPEAKER_05And there is the ability to add on additional air pollution control. You can also recover energy in this type of a system. So, really, what makes it really clean is that it's very high. Highly controlled. It is using a starved air process, similar to gasification, and it does produce a syngas in the first stage, but we don't try and you know add a refinery in between there and the exit to try and take that gas and do something with it.
SPEAKER_05We fully oxidize it in that second chamber where it's mixed with a lot of air and it's turbulent conditions and there's sufficient retention time so that when the exhaust gas leaves that system, if it's being properly operated and it's it's under good maintenance, there should be absolutely no emission that's visible at all, and you would just see a heat wave from this. But in some cases, we need to meet different air pollution control regulations, and EcoWaste Solutions does that all over the world, including with EU, US, Canada, wherever.
SPEAKER_05And in some cases, we're needing to add air pollution control. And there are many different ways. This is a super simplified image, of course, but there are many, many ways. And the report goes into some of the key air pollution control technologies that you might apply when required. And many of our customers do not add any of those air pollution controls because the cost and the benefit are not in line with the outcome.
SPEAKER_05But it's very beneficial technology in comparison to all these emerging technologies, because it still gets the same thing done. It reduces your waste volumes, in fact, reduces them more than you will in those other technologies quite frequently. And unless, of course, you manage to find a buyer for your end product, the glassy rock that you produce. As far as I know, there isn't really a market for that, but there could be locally, I don't know.
SPEAKER_05There um also, you know, you're going to be getting rid of any disease-causing pathogens, which is a concern. That's a concern a lot of people have when they're producing these doing other technologies that are restricting temperatures because they're not fully burning out the carbon, which is where the disease-causing pathogens lay in the waste. Also, because we're not going to landfill, we're avoiding methane, which is of course a 30 times more powerful greenhouse gas. So by avoiding producing methane in the first place, by not allowing it to decompose, we've um we've benefited the environment there as well.
SPEAKER_05Of course, the ash residual is not attracted to wildlife, and the waste itself is being treated as you're producing it rather than having a long-term uh impact on future generations. And of course, it's fairly simple and it has minimal emissions. So I want to talk about emissions. So in the report, I don't think this was summarized as well as this table. So we produced this table today to go along with this presentation just to really summarize for you exactly where things stand.
SPEAKER_05So we've taken the estimated emissions from the system and produced them here on the left. And this is these have been um, it says the reference conditions, they've been adjusted to reference uh conditions. That's how you compare all air emissions that are having all different types of conditions. So that's the on the left is what we would estimate comes out, and on the right is what um what the EPA regulation for other solid waste incinerators is.
SPEAKER_05Now, OSWI is not applicable to Skagway because of the remote location that you don't have to meet this regulation. But if this were enforced upon you, which is it is written for uh larger communities, if if you did have to meet this standard, you can see by looking at the numbers that the only real area we'd have a challenge meeting the uh regulation is really when it comes to hydrogen chloride and sulfur dioxide.
SPEAKER_05Both of these compounds are what we call acid gas compounds. They produce acids and those are not in compliance. Now, those are not necessarily harmful. These are are gases that we're mainly tracking from a greenhouse gas, uh, sorry, from a not a greenhouse gas, but from a photochemical smog perspective. We looked at some of these and um we see this in more environmental side of things, but again, with dispersion, these numbers are very, very low.
SPEAKER_05But these are in-stack concentration. If you looked at dispersion numbers, they're really become background numbers for the community. But if you wanted to do something about that, if you said, okay, well, we want to at least comply with that EPA particular limit, then we would be looking specifically at those two pollutants to control. So the simplest way, and the report, like I said, goes into all the different technologies. There are many different ways to do this, but here's a simple summary of a basic wet scrubber.
SPEAKER_05So this is a piece of equipment. Now instead of going out of the stack, um, you would now have something that kind of is a duct that goes over into this, and this will have another stack at the end of it. And so now you're gonna take the gases, you're gonna pull them through all of this stuff using a fan on one end, which is over there by number four. That fan's gonna pull all the gases through these different vessels and expose them to all these stages of treatment. And really, what we're doing here, first we have to rapidly quench those gases.
SPEAKER_05If they're coming out at 1800 degrees Fahrenheit, which is the stack temperature currently, um, then you have to cool it super fast down to about 170 degrees Fahrenheit. You can't do anything with gases unless you've cooled them. So that's why this is a very essential piece. If you don't do it quickly, you can create new toxic emissions. So it's very, very important that you get this part right because it's air pollution control can also become pollutant generators if they're not set up properly and they're not operated correctly.
SPEAKER_05So first we have to quench the gases short period of time. Then we can do some capturing. It's fairly easy to grab a little bit of particulate matter. We're still fine with the regulations, even without this system. But since we're there, we could grab some particulate and reduce it further. But our main purpose here is we're going to do some absorption, where we're going to take the acid gases, we're going to react them with a chemical uh solution, and that's going to neutralize the acid gases and produce uh by so we take an alkaline reagent like sodium hydroxide, uh, which will come in a bulk chemical that needs to be mixed, or you're buying it pre-mixed, and you're you're basically mixing that chemical into this process where we're raining it down on the gases.
SPEAKER_05The gases come in contact and they get neutralized. So that's the simple simplest way to control acid. It's also a super effective way. So we can reduce the emissions that we saw in the previous table by by over 97%, um, and definitely going to be well within the meeting of those regulations. That's that would be not a problem with adding something like this. So, what are the impacts of adding something like this?
SPEAKER_05So, really, the the capital costs depend on you know how much contingency you want to put on things. How long do you want this thing to last? How complex, how much monitoring do you want to have? There are a lot of different things that go into the choice of an air pollution control equipment. So that's why there's a bit of a range. And then the operating costs, based on the details we went into in the report, are approximated there. And these costs I should mention, this doesn't include, you know, getting it there.
SPEAKER_05These the operating costs may not include all the shipped-in cost of chemicals, um, the the building itself. This doesn't include making the building twice as big, putting all of this equipment up, all of the additional stuff that goes along with it, as well as the connection of utilities required. So this is just super high level. Um, the big impacts really, besides, I would say the doubling of the size of the building or making it certainly bigger is a problem.
SPEAKER_05I, based on the current site, it may not even be feasible. And I know that's something that the respect team could look into in more detail. Um, but perhaps it starts to become more sensible to move to another location. Regardless, I think adding this piece adds so much to the construction that this could delay the project by years, which is a real concern given the current situation with the um current system requiring replacement.
SPEAKER_05And then, of course, the other impacts besides cost and operating complexity and all of those challenges are now we need some water in order to accomplish this. So we need quite a bit of fresh water, depending again how we approach it. There's a range given. And then there's also going to be some water discharge that's coming out of the system. It's collecting basically a dirty salt water that's going to need to get discharged on a daily basis or stored until it can be discharged. So those are a summary of some of the impacts.
SPEAKER_05So this is that's the end of the presentation. I just want to summarize in general. I, you know, of, and of course, I recognize the bias, but we uh we do build pyrolysis gasification technologies when people require something that's specific to do that. But we don't believe that anything like that makes any sense in a community like this, and they cause they pose a lot of risk and also just are not practical. So we think replacing the old system with a more modernized version, everything being up to date will make a big difference in terms of emission quality and overall functioning of the equipment.
SPEAKER_05And you could still consider that APC option if you really think it's worth it to have that additional reduction in emissions. Um I would say that probably if you looked at the environmental life cycle cost of doing so, it probably doesn't make a lot of sense, but it is also something that could be added later if it's required. So I think I think that's it for my presentation. I'll leave it up just in case uh in case people have questions uh and you want me to go back to any of the slides.
SPEAKER_08I have a question if I might.
unknownSure.
SPEAKER_08Uh Alex Rodney. Um, so a lot of um discussion was given to the wet scrubber system, which um among other things discussed, it says that the waste byproduct should not be put into bodies of water, which is where our water treatment goes into an ocean. Um so I don't know if that is something, I mean, it's treated first, but I don't know if that's something that should be considered. But but I'm I guess um a lot of focus has been given to the wet scrubbers.
SPEAKER_08Could you tell me more about the bag houses and fabric filtration systems? I don't see too much in here in the report on that, and I am a little more interested in learning about that. Or I guess you would like to think about it for a second.
SPEAKER_05Yeah, let's go now. I didn't add any of those pictures in here specifically. However, um I do it the the big problem with the wet with the dry, fully dry scrubber, and I can see why they they would be of interest. First of all, the bag house, its main job is to collect particulate matter. So when you look at the emissions, you don't have a particulate matter problem. So, first of all, the the core purpose of the technology is really not for controlling acids.
SPEAKER_05So, how would you control acids? Because that's the the one thing we know we need to address in a dry concept. So, because of course of course we don't want to deal with all this water. So that would be nice. So now we need to cool the gases because a fabric filter, of course, would catch fire if it were exposed to anywhere near these temperatures. So even the Gore-Tex, the very best fabric filters in the world uh nowadays still can only handle a few hundred degrees Fahrenheit.
SPEAKER_05So before we get down to that temperature, we need to rapid cool the gases. So one way to rapid cool the gases is with water, as we demonstrate in the wet scrubber. The wet scrubber can really cool the gases the fastest, but of course, it has a huge cost in terms of water. So if we don't use water, um, we want to be fully dry. How can we cool those gases? Well, of course, you can put in big, huge cooling towers and things like you see everywhere else that you're when you see processed plants have gases cooled down.
SPEAKER_05But that doesn't happen quickly. Cooling towers, air to gas heat exchange is not a quick, it's a it's a slow process and it's it requires a lot of electrical energy to do that. But also now you've had this slow cooling of the gases. The issue with slow cooling of gases is that you can produce new toxins. As I mentioned earlier, if you don't do air pollution control correctly, you can actually generate a lot of unwanted chemicals that wouldn't have been produced otherwise.
SPEAKER_05So if we don't rapid cool the gases, we can enter into a zone which is known in the industry as the de novosynthesis of dioxins and furans. And what this means is if you have within the gases from whenever you're burning solid waste, you end up with there are, even when you're burning in your fireplace, there are precursors of dioxins and furans that exist in their products of incomplete combustion.
SPEAKER_05And anytime there's the presence of chlorine, which there's a ton in waste, um, then you have that potential to form dioxins and furans. Now, if you you do the three T's very well, the time temperature and turbulence in the second stage, you'll avoid producing those. But now, if you don't cool your gases rapidly, you don't just allow them to go out the stack and you go through a slower cooling process, like is described with the cooling tower I mentioned, or in a boiler or some other method of taking the heat down, because heat recovery boiler would be a great idea.
SPEAKER_05Let's take the heat down with that. But the problem is we generate dioxins and furans because we end up hanging out in the temperature range, which is specifically conducive to producing that. So now we need to add additional air pollution control pieces at the end to now remove the dioxins and furans that we've produced. So that's one issue. Another way we could approach it is let's say we said, well, forget about that. We're gonna do rapid cooling. So we'll rapid cool it, we'll spray a ton of water at it, we'll reduce the gases, but now we've got a bag house.
SPEAKER_05Well, a bag house can't handle a wet gas stream coming at it. Wet flow of gas is gonna completely fill, you know, cause your bag filters to blind, and you're gonna have all kinds of problems. So, in order to avoid that, one thing we can do is reheat the gases before it goes into the bag house. Of course, there's gonna be an electrical or fuel cost associated with doing so. And it's not the easiest thing to do, especially with a large volume of gas like you're gonna have coming off of eight tons of garbage.
SPEAKER_05So now you're gonna reheat all that gas to really try and dry it up before it goes into the baghouse. Another thing that you've got with this that's a very effective way to go, by the way, the wet, dry. You're still gonna use a lot of water, you're still gonna have a water discharge to some extent, but you're gonna not have the dioxin problem. Let's say though we're not worried about that. We said, we'll just we don't want water. So we're gonna cool the gases, we're gonna use whichever way we're gonna do it, we're gonna take the heat out.
SPEAKER_05And now we're gonna do it all dry, though. Then we have to be concerned about well, how are we actually taking the acid out, which is the whole purpose of meeting the regulations? We need to remove this acid gas. So the only way to do it is with like something like lime. You use lime, it comes in huge bulk bags, and you blast the lime dust into the gas stream. When you do this, you get a lot of unreacted lime. So there's a ton of waste in the process.
SPEAKER_05And then you also end up with not as good weight. You'll never be able to reduce the amount of acid the way a wet scrubber can. It'll reduce a far lower amount, but it'll probably still meet the regulations you need to meet. Then you have a the bag house is going to filter out all that stuff. And in case you thought you produced a lot of new nasties in the process, you would add an activated carbon filter in that in line with that same group of technologies, and it would do the job of trying to take those out.
SPEAKER_05And then the filter bag house would then remove all of those particles back out, and at the end, you'll have a waste stream there. You'll have filter bags that'll be now have fly ash contamination, and they will have chemical contamination, and those will need to be dis disposed of as hazardous waste. Does that explain the the dry scrubbing concept of the fabric filter?
SPEAKER_14You mentioned that there could be a market for the glassy rock that just that remains after the process that we have in place now. Um what what type of market is there? What kind of uses are there for that material?
SPEAKER_05Well, um I mean technically the same use you would have for any glass. So if you had glass bottles that you collect for recycling, do you have any markets that you can sell the crushed glass?
SPEAKER_14Not that I'm aware of, no.
SPEAKER_05Because I would say it's probably similar markets, and that that tends to be the issue. As far as I know, no none of those facilities are actually selling on the open market, this material. So it can be reused, just like there are people experimentally looking at crushed glass in roadbeds, for example, and other uh applications. So if there's a you know a use that you could use something like that, then the best way to do it would be because there's no way is somebody going to buy it and pay to have it shipped to them from there.
SPEAKER_05So it's it's really needs to be a local use because you're also not gonna produce a whole lot of it, because ultimately you don't produce a lot of ash overall, like not uh in industrial levels. You know, when people look at like if there was a cement company that said, hey, I'd like to use your ash, because you technically could sift your bottom ash right now and use it as a replacement for Portland cement in a concrete process. And that's available to anybody that has produces an ash, but that company has to be willing to take your relatively small amount of ash, test it, and have a whole stream of process going in their facility.
SPEAKER_05And a lot of them won't take it, they won't even take it as a waste product for free. So that's why the ash is recycling doesn't happen as frequently as we'd like to see, because it does have value, it can be used, but again, it's you know, you can't really attach a this is going to reduce my overall operating cost to it because we don't know that there's a market for it, so it would be disingenuous to say otherwise.
SPEAKER_03I just wanted to clarify we're not producing a glass slag right now. No, you're not in the plasma education.
SPEAKER_05That's right. Plasma gassification, you can take the ash and make it into that. Right. Right now you just have a an ash that looks a lot like fireplace ash with like metals and glass co-mingled in there that technically could be recycled or just inert filled.
SPEAKER_12I believe uh we had requested a volume for volume uh you know, the proposal for both refraction. Factories with the new transfer station, uh prices have gone down, and I think our our efficiency with that is is uh seems to be working pretty well initially. Do you recommend keeping volume for volume of the existing incinerator or you know, and I know there's you know shipping considerations whether the uh the landfill and or the processing place in Washington will continue to take it, but do you recommend keeping volume for volume uh with the new design or downsizing it to really focus on just dealing with the uh biohazard waste, the medical waste, and some of the other household things that we cannot um bail?
SPEAKER_05Yeah, I mean, I I don't know the actual um the differential and and how much more smaller you could potentially go. Of course, when you if you go with the something, the same footprint, then you've got contingency um for downtime, and it it does give you that. Um, but I think that when we looked at this before, um it still seemed like it made sense to go with a similar size because even though the population has grown and is expected to grow somewhat as well, um, and waste volumes have gone up.
SPEAKER_05Overall, it's been a good size. Um, and in the summer months, um you know, may come in handy more. But uh I I don't actually have an opinion on it. I don't know if my colleagues, Neil and June, who are more involved on the volumetric side of things, if they have a comment on that.
SPEAKER_10This is Neil speaking. Um so I've spoken a bit with Tyson here locally, and at least during the summer months, it does seem that you guys are reaching full capacity, almost back-to-back burns with the system, to the point where the current size system is just keeping up with the amount of waste that you guys are handling, not necessarily leaving a lot of room or overhead for maintenance or downtime for the system. So if something did go wrong in the summer months, potentially having a smaller system could pose a risk to the community just because it wouldn't be able to catch back up on throughput, which is something that we often see in remote communities with extended periods of downtime.
SPEAKER_10Um, the ability to catch back up on waste is is critical.
SPEAKER_06Thanks, Dan.
SPEAKER_12If I can just follow up on that, because I don't know if my question was completely clear, but I I think we're, you know, I'm asking the question because we had different options when it came to you know what we were requesting. And one of them was to downsize the size of the incinerator and plan on shipping it out long term. Um that's not the that's not the option that we chose. We chose volume for volume. So I mean my my question is really, I think probably whether it's viable to ship it out long term, or if that's a risk.
SPEAKER_12Um, certainly with shipping, I think that's always an unknown in terms of the costs of that. Um that that's really more of a policy, I think, question of whether it's it's you think it's long-term viable to ship. Um, or if, you know, and I I know I've had a lot of cuss discussions with with uh Director Ames um about having redundancy and having you know fallbacks if things don't go smoothly, as you just stated, uh Neil.
SPEAKER_12Um and I personally believe that we should try to deal with our own waste as best we can within the municipality and not try to ship it down to Washington State. But I think this is more of a question of which track to go on, because I mean we we've said let's go volume for volume, but we've also just built a nine and a half million dollar transfer station to bail garbage that seems to be a pretty effective so far. So I mean that's you know, it's not necessarily about the technology of it, it's more about the logistics and economics of it.
SPEAKER_05I think I don't know if the the people from uh respect they have definitely done more of the analysis of those uh of that side of of the equation. We've mainly been focused on the the technology options and the practicality of them.
SPEAKER_13Yeah, so I Dominic, are you on yes I am? Okay, but could you maybe speak to um Hansen's uh uh comment then about the one-for-one uh volume analysis?
SPEAKER_07Yeah, so uh in our analysis, we didn't really go too deep into um the possibilities of incinerating versus shipping out uh as it it would be more of a life cycle cost analysis of comparing the two and shipping rates and um you know what it would cost to have a third party process that waste. A lot of ours was focused more on what the incineration options were for Skagway um based off of you know our our southeast logistical limitations and um ways that they could or uh maybe the best way to say it is future focuses for um ha uh for looking at making the incineration process more efficient and using the same scale incineration process but then implementing um more robust sorting and recycling processes to try and cut down on the amount of waste that's being uh incinerated and try and reduce the amount of ash generation from the incineration process.
SPEAKER_07Um because as I understand now the incineration ash is then uh deposited into an ash field which has a you know a limited lifetime, and there's not a lot of uh area that can be developed for additional ash field you know in the distant future. So is that something where we can reduce the amount of incineration and reduce the amount of ash generation so that we're not we're not reaching the we aren't capping out those ash fields as quickly as we would if we were just you know burning everything in Skagway without a more robust system.
SPEAKER_07So that was more what we focused on, and um I I can't really speak to the bailing and shipping versus incineration process.
SPEAKER_01Yeah, this is Doug Murray with respect. Um at the very beginning of the transfer facility design, uh we investigated pretty heavily the uh the shipping option and uh really came up to the conclusion there's a lot of uncertainty and cost uh uh in doing that, as well as uh the limited vendors in Washington and Oregon that we were uh contacting and getting information from, they really don't want uh our garbage.
SPEAKER_01And and it was very evident to us that um they could easily adjust costs to fit whatever you know scenario they wanted. So it's a real big uncertainty on that. Uh, and I realize you guys are doing some of that already now, um, but just uh the process of getting that waste down there and then finding uh places to put it uh was pretty limited and expensive, uh, which really kind of led us to you know to try to take care of all the garbage um in Skagway with that method, and then use shipping as essentially an emergency and overflow method.
SPEAKER_12Uh thank you for that uh description, and uh that I think falls in line with how I feel that it is uh a volatile thing to depend on another state to take your trash. Um I was gonna ask about the ash capacity that's uh table one-two. Is that based on the projections of the way the incinerator has run, or is that based on the projections knowing that we're going to until the incinerator really is repaired, we're gonna be operating it a lot less, and therefore that 3.56 years?
SPEAKER_12Is that saying assuming that of the amount of volume that was going through the incinerator up till the point that the transfer station was completed? Or is that also taking into consideration that we'll be using the incinerator really just for uh for biohazards and uh the byproduct of the sewer plant, uh as well as uh some household things that we can't uh bail and send out?
SPEAKER_13Um Assemblyman Ryan, I'll speak to that, Orion. So we have two phases um of ash field disposal in the facility. There's a phase one zone and a phase two zone. So with the phase one zone, we have about three and a half years of life left for placement. And then and that's based on the existing incinerator and the volumes going through there. And what we analyzed was a similar size structure with a similar waste stream. Okay, looking at that.
SPEAKER_13So we have 14 years left uh in the phase two um ash field zone. If you look at that table, you'll see the phase two area. So I was up there today kind of looking around, and um they've the operators have done a really good job of placing compacting, but there is kind of a there is quite a bit of an area left still where we can place the ash and get our proper four to one slopes graded for the ADEC permit that's been issued for the facility. So um, you know, we've mapped it and so we've modeled it and we've looked at that, and that's kind of the life that we have.
SPEAKER_13Now, there's some some things we can do. Um, as Dominic mentioned, if we cut down that waste stream a little bit, there'll be less ash generated. Also, if there's more efficient burning used, there could be less ash as well that's just generated. So I the 14 years is really what we have in the phase two zone, and we're kind of just kind of on the limits of that right now, just starting the placement. Um, and I could say it's it's a very uneven topography up there right now.
SPEAKER_13So there's very the low areas will be filled first and then built up, and then the slopes that will have to be graded out to meet the four to one requirement of ADC. So I think the three and a half years would be just for that phase one. If you the phase two is has a longer life expectancy with uh similar size incineration, incinerator.
SPEAKER_12Can can you clarify what phase one and phase two are?
SPEAKER_13There are areas on the site of where there's disposal. I thought I had I think I had a uh a diagram in the uh report. But if not, we can get there. So there's there's two areas that have been permitted um through the process uh through DEC of where the ash can be disposed of on site. Phase two would be more downhill, downslope, closer to the property line. And so phase one is kind of the upper area closer to the incineration building.
SPEAKER_09John talking about ash uh and the storage space for it. Um can that be shipped if we run out of space?
SPEAKER_13Yeah, I I suppose it could be shipped, but I I think it's an inert material. I think Gene mentioned that earlier that um if there may be a spot in the community that could where it could be placed and used just as non-structural fill, but just a fill, and then maybe someone could put topsoil and yard over it, I you know, something of that nature or just filled. So I I'm sure you could ship it out. Um there's obviously a cost to do that. Uh you have to have someone on the receiving end that would take it and use it and that kind of thing. But there may be an opportunity in the community to use some of the ash.
SPEAKER_13It's you know, we just haven't looked into that before with uh Tyson. We haven't explored that, but it is an inert material, it's um it could be placed there, it could be moved off-site. So um if there is a um you know concern for the volume in 14 years, what do we do? Which is I think what you're alluding to is you know, how can we reduce that? How can we increase the life of the Ashfield area and uh still have a place to dispose of it?
SPEAKER_13So um I we haven't looked into that, but we can certainly look in to see whether it can be shipped and who would receive that and what the cost would be, that kind of thing. Good question.
SPEAKER_07So uh just related to that, I wanted to point everyone to um in the the packet that was handed out under tab three, that's our short little summary report. On page two of that report, there is an example of how um Japanese communities have implemented more robust sorting and recycling programs to try and offset the amount of waste that's being incinerated.
SPEAKER_07And uh it gives a good example of how uh something that this doesn't talk about is that you know, over time these these incinerators got more and more efficient. But that the chart that's there, the bar graph, shows that over time with those recycling programs and with the sorting facilities that they implemented and the efficiencies in their incineration processes, they were reducing their uh direct uh landfill disposal down to 1.3% of their total waste generation from in the 1990s it was 20 percent.
SPEAKER_07So that's one of the things that this report kind of emphasizes is that one of the future directions that Skagway could look into is how you can take this existing system or one similar to it and find ways to make it b burn more efficiently to reduce that ash output and then also implement other programs to try and reduce the amount of waste that's going into that incineration facility. Just to then increase the lifetime of your ash treatment options, whether that's in some sort of landfill or if you find someone that will take ash, a third party that will take the ash for you, shipping that out.
SPEAKER_04I am dead. Uh just a follow up on this topic. Um my question was where where would be the the phase three ash field? And it seems like that hasn't been identified yet. Is am I understanding this correctly?
SPEAKER_13Yeah, but we have phase one and phase two identified, and um, you know, we can't go beyond the property limits right now, property line limits. So there may be other areas. It's like I say, it's a very uneven topography, and so phase three could push potentially to the north, to the south uh west somewhat, but the ground is very steep there. No, no. We where we've kind of identified the two phases now is is um natural kind of spots to deposit the ash that's generated from the facility.
SPEAKER_13So beyond that, would we have to really look at exploring um could we construct some walls to kind of contain the ash? You know, we have to go beyond um natural sloping. So we'd have to maybe look at retaining structures to kind of push it right to the limits of the property line and those kind of things. So it's um it's not quite as easy to go into a phase three mode, but as we develop phase one and get that kind of closed out and move into phase two, then I think we would look and explore where phase three potentially could go, or what could we do on site to kind of create more space where the ash could be deposited within the municipality's property limits.
SPEAKER_04Thank you.
SPEAKER_12Brian, thank you, Mayor. Uh Gene, to go back to your uh summary, and I just want to revisit the gasification real quickly. I think you you you noted that the building would not fit. Um, if we were we were to try to pursue that, we would have to significantly increase the size of the building. And I do know what the east side of that area looks like. It's there's a little bit of flat ground, but not a lot.
SPEAKER_12Um and it is quite steep beyond that. I I guess my main question is could it even be physically possible to make that building bigger without really starting from scratch?
SPEAKER_05Yeah, the construction question that would go to risk respect.
SPEAKER_12Thank you.
SPEAKER_13I'll try to respond to that. Um you're correct on the topography. I've mentioned that several times tonight. It's it's um a lot of bedrock outcroppings, very steep terrain. Um, the existing building now is kind of notched into the bedrock, so the foundation is very well stepped down the hill uh to expand the footprint to twice the size would be very, very challenging and expensive in my professional opinion. Um maybe to the point where we would examine looking at an alternative site if we were to do um you know need the requirements uh of another building for the uh air pollution control devices.
SPEAKER_13And that I mean that would drive that extra building requirement. So um I would say it it would be um very challenging to construct there. I have the topography I think is in the packet. You can kind of see the terrain, what the existing footprint is if we were to double that. Um maybe one thing is we could um, and I don't know how the orientation of the buildings, uh how they would um align with each other as far as the process goes and what elements we get, but it could require a complete renovation of the interior of the existing building to then cool commingle with the new building, you know, for the process.
SPEAKER_12So if I'm interpreting what you're saying, it would be significantly more than a couple million dollars. Yes, correct.
SPEAKER_11Let me add um uh Stephen Bishop. Uh one other uh one other portion to get back to is the water and wastewater requirements. That site does not have any ready access to water or for processing that wastewater. Uh from the their estimates are up to 300 gallons a day for wastewater, 600 to 6,000 gallons of freshwater required for that scrubber system. So that would have to play into that site as well. It's a remote site because we have to water to be trucked in or we have to locally source it and get that wastewater out of that area as well.
SPEAKER_11So it's supposed to be additional uh issues that would have to be resolved in the case of that site.
SPEAKER_09John Gene, uh regarding those numbers on the um acid gases that are that are coming in and over EPA standards or whatever it was, do those change depending upon what is being burned? Um could it be something that's sorted to lower those rather than looking at uh these come the complexity of moving the site?
SPEAKER_05Yeah, that's a really good question. I mean, the um hydrogen chloride, what we found is that it is ever present in everything. In fact, um, you know, at one time it was very closely tied to medical waste because medical waste tends to have a lot of PVC plastics. So when you have a lot of PVC plastics, you can generate more acid gas. And there's no doubt that's true. If we were looking at numbers coming out of a medical waste facility purely where we're doing a lot of plastics, you would see those numbers would be could you know be twice as much.
SPEAKER_05But um basically it's it's it's interesting how hydrogen chloride forms. I mean, really, all you can have table salt NaCl and you mix it with um water in the right conditions, you can produce this HCl gas. So it's it's not a chemical that's it starts off very benign, is what I mean. This little bit of chloride gets together in the right conditions, and you can generate this.
SPEAKER_05So you can, of course, try to limit the amount of chlorinated products ending up there, you know, PVC end cuts, whatever, but that would be a challenge. And what we have found, even when we looked at mining camps where they have just food waste, pretty much food waste and a little bit of paper and cardboard, they will still produce HCL because it is just a byproduct, like a set of table salt. It's literally in everything. Um, so that's a more difficult one to control.
SPEAKER_05Sulfur dioxide, um, the a lot of the source of that is actually in the diesel fuel, even though you're using lower sulfur diesel as a standard in North America. There's still some amount of sulfur dioxide that's produced from this. And these numbers are relatively low. Again, if we did a dispersion analysis and compared it to trucks going down the highway, it would not show up as a lot. But as an in-stack concentration, it sounds higher, um, but it's still relatively low.
SPEAKER_05So it's challenging unless you were to be able to do propane or natural gas burners, those could reduce the um, like liquid propane gas would reduce the sulfur content. Uh, that would be one way to do it, for example.
SPEAKER_14Any further questions from the table? Manager Ryan, would you be able to just give us a quick recap of where we're at with the incinerator program or the uh the the project? I know I remember earlier when we went through uh public works, we were in the assembly table, we were talking about this. We chose that uh volume for volume option. I think it was eight tons. We're at an eight-ton incinerator now. There was talk about maybe going to a four-ton, but I think we came back, we said eight ton was already being maxed out with our current usage, and that uh we really felt that eight ton was appropriate.
SPEAKER_14We moved that project forward. Can you just tell me where we're at with the project and what our next steps are going to be?
SPEAKER_03Yeah. Where we're at is we're really on hold right now. So we we we put things on hold. It is a volume for volume design. That's that's our understanding right now. Unless you, as the assembly, change your minds, it's volume for volume. Um it's it's it's an incinerator that fits in the current existing facility. That's really what it is. Um, but where we're at is we we we went down this road of looking at some environmental upgrades, and that's what you're hearing about tonight. And if you want something besides that, we'd like to know that, hear that from the assembly.
SPEAKER_03Um, and that will change the design. So if you know if you wanted a uh a wet scrubber or you wanted you know some other environmental upgrades put on this, then we would like to know that so that we can give direction to uh respect to modify their proposal and their bid to us for design. Um, if not, and you want to stay the status quo essentially with a new incinerator and an upgraded incinerator. Sorry, I didn't mean to call it status quo. Uh, but you know, volume for volume with a new incinerator going in there, that's fine too.
SPEAKER_03We need to know that. And I think that's the scope of work that they're prepared to launch on right now as soon as we hear from the assembly. We know this is uh you know an assembly of the whole meeting, so there won't be any direction. I'm anticipating that we'll get direction from the assembly table on this after this meeting.
SPEAKER_14And where where were we at before we kind of got to this position where we're on hold? Were we at design? How far into design were we? What are we?
SPEAKER_13Yeah, we've um completed the 35% mayor um design, which included narrative, um, some drawings, basically the information in the packet that was handed out tonight is kind of our 35% submittal. Um and like um manager Ryan said, we're ready, you know, once we kind of get approval or direction to proceed, we're ready to move to 60 65% design phase.
SPEAKER_14And manager Ryan, the uh the budget issue. I know we're looking at the budget for 2025, 2026 for the incinerator. Real quickly, can you just talk to us about the uh the monies that we're we're projecting uh for the incinerator replacement?
SPEAKER_03Design or the replacement?
SPEAKER_14Well, both, I guess.
SPEAKER_03Yeah, I mean I think design is budgeted for, we have that in your budget in your capital projects, and I think the total was eight hundred and can't remember exactly, somewhere in the eight hundred thousand dollar range. Um but then the you know the construction of it, we have estimates of six million dollars or eight million dollars um somewhere in that range for constructing a new incinerator facility without any changes for a wet scrubber or something like that. We were gonna add plasma or wet scrubber, obviously, prices.
SPEAKER_03Yeah, yeah, we'd have to revisit those and and give you new estimates. Well, respect would have to do that.
SPEAKER_14Okay. Um any further questions? All right. Well, I'd like to thank everyone who came in tonight who's done all this work to provide us with all this information. This is really making it much easier for us to kind of see the bigger picture and the bigger scope of things and see where we want to go, make our decisions. It's very much appreciated. Uh Manager Ryan, thanks for uh putting this together and getting this in place for us. Um if there's no any if there's no other questions or if there's no other input from anybody, if there's any uh information anybody thinks we should have before we adjourn, then um I would entertain a motion to adjourn.
SPEAKER_13I guess I would just like to say thank you as well to the municipality assembly and your team here. You've got an excellent uh staff. We do appreciate uh the opportunity to serve you. That means a lot to us and uh look forward to continuing work on the project. Thank you.
SPEAKER_02Thank you.
SPEAKER_04I move to adjourn.
SPEAKER_14Second motion by Potter, second by Collodi to adjourn. Discussion? All right, roll call, please.
SPEAKER_02Yes. Henry Yes motion passes.
SPEAKER_14All right, thank you everyone. This meeting is adjourned.
Call to Order Roll Call Approval of Minutes: November 5, 2026 Approval of Agenda Reports of Officials and Committees: Mayor’s Report Assembly Committee Reports Treasurer’s Report Manager’s Report Presentation from...
Call to Order Discussion of Rockslide Mitigation Project 65% Design: Presentation from the Design Team Questions and Answers Written Questions from the Public Questions from the Mayor and Assembly Overview of Guided...
Call to Order Roll Call Approval of Minutes: October 8, 2026 Special Meeting October 15, 2026 Approval of Agenda Reports of Officials and Committees: Mayor’s Report Assembly Committee Reports Treasurer’s Report...
Call to Order Review of Proposed FY27 Budget - CIP & Special Revenue Funds: School Funding Debt Service Permanent Trust Capital Projects Sales Tax Fund CPV Excise Tax Fund Mayor & Assembly Discussion Items Adjournment...
Call to Order Review of Proposed FY27 Budget - Operating Funds: General Fund Visitor Fund Clinic Fund Harbor Fund Port Fund Water - Sewer Fund Solid Waste Fund Mayor & Assembly Discussion Items Adjournment Packet