Borough Assembly: Committee of the Whole - November 9, 2026

Nov 10, 20263 hr 6 minAudio
ShareXLinkedInFacebookWhatsAppEmail

Call to Order Discussion of Rockslide Mitigation Project 65% Design: Presentation from the Design Team Questions and Answers Written Questions from the Public Questions from the Mayor and Assembly Overview of Guided Hikes 11/10 and 11/11 Mayor & Assembly Discussion Items Adjournment Packet

Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.

Transcript

From the show. Tap a time to play from there.

SPEAKER_02Call to order the assembly of the whole committee for Monday, November 9th, and City Hall. Uh this meeting pertains to our port safety and security. Tonight's meeting is a work session. There will not be any question any actions taken by the assembly at this work session or any work session in the past, present, or future. Historically, assembly work sessions do not include an agenda item for public testimony. We recently conducted two work sessions regarding the budget, and there was not public testimony on those agendas.

SPEAKER_02The clerk reviewed municipal record for the past 15 years, and there's not been a single agenda item for public testimony on any work sessions. Tonight, the manager and I expanded to decided to expand the work session format to allow written questions regarding the 65% rock slide mitigation plan to be submitted to the clerk because we are very aware of the robust dialogue surrounding this issue.

SPEAKER_02Following the presentation from our mitigation team that's here tonight, we thank you for coming. We'll take a 10-minute break while the clerk prepares the citizens' questions. For brevity, the clerk has consolidated similarly questions into a single quarry. The clerk has also consolidated long text of emails into a question. On an upcoming agenda, the next agenda, we will place public toast testimony under citizens present to specifically relate to this plan a plan for the rock slide mitigation, so that people can talk directly to us and state your words as it is.

SPEAKER_02We recognize that tonight this the citizens' questions will not be ver verbatim as they were written, for we would be feared for far too many hours. However, these questions are in the packet exactly as they were submitted, and it's up, it's public. The clerk has provided it. I request your respect, your dignity, and your uh attention to this presentation. And with that, I'm gonna turn it over to Mr. Kyle.

SPEAKER_06Okay. Um thank thank you, Mayor Orion. Um, happy to be here. Um just wanted to wanted to say that you know, we we put this presentation together and some of the responses that have already been delivered um in response to questions that we've received after after submittal of our design. Um and so we're looking forward to continuing that conversation, provide a little more context uh in this presentation, answer specific questions, and and um just go from there. So, just a quick overview of what we're gonna do.

SPEAKER_06We're gonna introduce ourselves again for those of you who don't recognize us, um, talk about the the project. I'll give a little context to begin with, and then each one of our subject matter um leads is gonna is gonna give a brief talk about what we've been doing, um the design itself, and and a little bit of the philosophy and the pro of the approach to the design, um, and some of the you know speak to some of the some of the questions we were answering along the line and and and why we made certain decisions. So uh if we go to the next slide, just a quick introduction.

SPEAKER_06Again, my name is Kyle Brennan. I work with Shannon and Wilson. I'm the I'm a geotechnical engineer and I'm the project manager, and I guess we can just kind of go around the table here.

SPEAKER_10I'm I'm Rex Whistler, which is also a Shannon Wilson, uh lead rock mechanics engineer for this project.

SPEAKER_09I'm Matt DeBrock with KPFF, and I'm assisting on the waterfront side and structural.

SPEAKER_14I'm Brad Ryan with KPFF and assisting with construction management and compliance.

SPEAKER_00I'm Katie Brown with HDR. I'm an engineering EIT helping with the possible access road and plan set.

SPEAKER_04Uh thank you. Uh my name is Greg Harman. I'm the project engineer for HDR, and we're kind of the lead civil engineering team that's uh putting the ideas onto paper and uh helping out with the project.

SPEAKER_15Yeah, I'm Micah Williams. I'm uh civil engineer for HDR. I'm the one that's primarily designing and modeling this access.

SPEAKER_05Uh good evening. Uh Ryan Morin. I'm the region manager for Granite Construction Company uh based out of Anchorage, and we're the uh uh general contractor working through uh working under uh what they call a CMGC contract to help with uh constructability and getting to uh to a place where the job could get uh constructed. Uh anyway, nice to meet everybody.

SPEAKER_06All right, thanks. And uh we've got some municipality Escagway people up on the screen. I don't know if you guys want to introduce yourselves or not. You don't have to, I think. Okay, um next next slide. So I wanted to provide a little bit of context and and a little bit of history. I'll try to blaze through this um because I think a lot of you are probably familiar with how this project has evolved over the years, but um just to provide a little bit of a setting for for how we got from point A to where we are now. Uh prior to Shannon Wilson's involvement with this project, the hazard was managed by White Pass Railroad.

SPEAKER_06Um they had performed some early mapping and some constructions from rockfall mitigation, and they installed uh the the initial version of the instrumentation that was that is that has since been expanded but is up on the slope now. Um and uh and so that had been managed for for a while. I don't know how many years, but prior to us being there, it's probably uh you know five to ten years that that White Pass was was managing that work. In 2022, um the municipality hired Shannon and Wilson to provide an assessment of of the rock slope and and had had decided to um to take on the hazard um and and manage that hazard uh from a liability standpoint.

SPEAKER_06And it was a decision that that was made by the by the municipality at the time. So we came on, uh made an initial site visit, uh, recomm actually based on that site visit and review of the instrument datation data that was provided, actually recommended that the dock be closed to pedestrian traffic. Uh the municipality acted on that recommendation and closed it. And and and shortly after that that was closed, the there was a pretty substantial failure on the slope, and and I think everybody was kind of breathing a sigh of relief at the time. Um some of the other stuff that we've done since then, uh, we've updated the instrumentation.

SPEAKER_06We installed um the uh total station, the automatic total station as a redundant measure. Uh, we've we've reconfigured this the um the instrumentation up on the slope a little bit uh to answer some of the questions we were we were seeing in the data to get a clearer picture of what was going on. Um we um and and and planning for future construction work at the slope, we wanted to make sure it was less centralized and more uh adaptable to what was probably gonna happen. Um we we established an operational plan for monitoring to ensure that the that the that the dock could be used uh safely.

SPEAKER_06Um people were keeping eye we're keeping an eye on everything, uh daily updates from the from the instrumentation, um, and um just you know providing a level of comfort for both the municipality and the dock users that that this this thing wasn't gonna wasn't gonna fall on on somebody. Um we also provide a full assessment of the entire slope above the dock. Uh, you know, there's a lot of attention focused on these existing slide features, but there are hazards along the entire length of that dock at the base of the slope. Um we've helped the municipality through annual maintenance programs and doing some maintenance scaling, providing upkeep of the of the on-dock um barriers and all that.

SPEAKER_06Uh and then and then we've we've come to the the planning and design phase of of this mass excavation that we're talking about now. And and right right now, the the plan set that was developed, the 65% plan set that was developed is based on on an alternatives analysis. We identified a a range of things that could be done, um, performed that alternatives analysis, got the um you know, got the buy-in from the assembly on on the direction we wanted to take, and that's that's where we are headed.

SPEAKER_06Um and and since uh since the submittal of that, we've we've received a lot of uh a lot more comments. And and the comments are great. We want to hear the comments, we want to we want to know what's important to the municipality, to the citizens that live here and and are impacted by these decisions. And so question question as much as you want. I'm I'm happy to happy to hear them and and answer them to the best that I can. And I think the rest of the team is is in the same same opinion. So next slide.

SPEAKER_06So I want to uh before we start getting the nuts and bolts here, I I want to provide the idea of one slope to hazards. Uh this is something that we identified early on in the process. We have um, I don't know, eight or nine hundred foot long dock. Uh it sits at the bottom of the slope that's about 800 feet tall. Uh, and and there is a there is a you know, there are hazards, rockfall slope hazards along the entire length of this dock. Like I said, we're focusing on these, these, these isolated features that are that are more active, um, just from a historical standpoint, but we have two types of hazards that are exist that exist along this slope.

SPEAKER_06Um, one is an ongoing short-term rockfall hazard. And the rockfall hazard is just the natural propensity for rock fragments to fall from a slope that is steep and roll down the slope and impact whatever's down there. And so that is that is a ubiquitous hazard that exists along the entire slope. Um and that is what is being, you know, that that impacts the the railroad operations because it provides a hazard for uh damage or injury to anything that's on the dock.

SPEAKER_06Um and it doesn't extend outside the dock, it is focused on the dock. And the way we are handling that is um ongoing maintenance. We're we're provide we're performing scaling, we have the onslope mitigation, the the attenuators and the netting and the fencing, we have the barriers on the dock to protect whatever's on the you know on the other side of the barriers from from rockfall. Uh but it's all focused on the dock, and this is a this is a unique hazard to the stuff that's right at the toe of the dock or the slope.

SPEAKER_06The second hazard, the other hazard that exists on the slope, is this large-scale failure. And the large scale failure is is at this the main rock slide or the main the main north chute of the rock slide um that that is causing all this activity, that is that all this activity is is at now, or like the most frequent activity. And and essentially what's up there is you have a 30,000 cubic yard, give or take, uh, of mass of rock that is slowly moving um down slope, and and based on the failure mechanisms if we we determined, it is eventually going to fail catastrophically.

SPEAKER_06And and so that hazard is being mitigated by the monitoring that we're doing, the instrumentation that's there, and and you know, to try and make sure we're we're keeping track of how fast it's moving, usually when these things as they progress to a large-scale failure, they'll slowly increase in in rate of movement. And so we're wanting to watch that. And and then the the mitigation for this, because of of how advanced and how large this rock mass is, really the only mitigation for that hazard is to excavate it.

SPEAKER_06Um and so because of the unpredictable timing of when this happened, when this will happen, we you know we we we feel like right now is is when action needs to be taken before it turns into something that can't be dealt with. Um and and the consequences of this failure are much more substantial to the entire port area, not just the dock. 30,000 yards of material comes down this slope, it impacts the small boat harbor, there will be damages there, there will be damages to the state ferry terminal, um, the ore dock, the Broadway dock, all of these, all of that infrastructure is at risk.

SPEAKER_06And so the hazard has consequences that are well outside just uh the dock. And so like I said, that the solution for that hazard is is excavation of the rock mass, and and that is the primary focus of the project that we're working on now. The design work that we're doing now is to address that large-scale long-term hazard with this design. The rockfall hazard, rock fall, yeah, rockfall hazard on the dock is it's related to the slope, but it is a separate issue with a different solution.

SPEAKER_06So um that's the context I wanted to provide. Uh I think from here, I'm gonna hand it off to my lovely assistant Rex. Um to give uh Rex is gonna talk about about um specifically what we're doing to excavate, what the what the doc, you know, what you know, what what we're what we're trying to accomplish with the excavation and and what things are gonna look like when we're done. So with that, go for it.

SPEAKER_10Thank you, Cal. Um so as as Kyle very clearly and explicitly uh mentioned or described is is there's two hazards, uh one which is a rock fall hazard, and then the focus of this project being the rock slide hazard, the larger 30,000 cup of guard approximately sized rock block uh that is currently slowly tilting its way out towards the towards the uh cruise ships. Um so the the rock uh in this case uh the rock slide hazard being removed when we when we remove it by excavating the top portion of the hillside.

SPEAKER_10You see these two graphics, exhibit three and four. They look almost identical. The only real difference is is towards the upper portion of the hillside, is that we have a little it's grayed out indicating where it's been removed. We've taken out the knob uh of that is block three, or what we've what we've modeled or labeled as being block three. Um and so it's a slight reshaping, so we won't have that prominent uh ship rock uh or point being up there. Uh that will reduce the rock fall to at the main slide area, but it will not eliminate that hazard altogether, as the entire chute, both shoots, north and south chute, as was also labeled on the throw plot uh on the tables.

SPEAKER_10Um, those are the two active main chutes where rock fall comes down. Those will still be active channels, and there is still a rock field that is going to be uh at the head scarp area that can or will produce occasional rock fall for blocks. So while these two are two different hazards and flare mechanisms, they are linked. Um, and one will improve the other, but will not eliminate it. So we just want to reiterate that a couple different times.

SPEAKER_10And how we're gonna get rid of this problem is um is blasting and excavation. Uh it's a it's a very large rock slide. The rock is incredibly strong and is fractured, and the really only practical feasible means for excavation, uh, I mean, we can hammer, you can mechanically excavate it with uh impact hammers, is is to drone blast. Uh so that's that's the the means and methods. Um after everything's taken down, we will then uh put back up uh the existing rock fall protection systems, which consist of a t couple different attenuators, a mid-slope, a lower, and then some protections at the very top of the slope.

SPEAKER_10So it looks similar to what it is today. Next slide. Here's this close-up perspective rendering of the pre and post uh mitigation for the rock slide. Um, you know, this is the labeling the rock fall mitigation. It will reduce the the rock fall uh hazard by a certain amount, but will not eliminate it. And where is where is that really happening in a much more detailed focus? And what does that look like in cross-sectional view? Uh for those who enjoy uh cutting open the cake or uh looking at engineering plots and drafting, this is uh the kind of end all be all of what things look like when we're constructing plans uh for construction.

SPEAKER_10This is a plan set. So we have a plan view on the top uh that shows the topography uh post uh current and then post-excavation. And then down below we have three different cross sections kind of showing the extent of the areas that we are aiming to eliminate. Uh we will cut the slope back uh from the toe or the bottom edge of the slope where we're cutting is where we've seen the lower limit of the rock fall initiating and where we have uh visual expressions of current distress and movement.

SPEAKER_10So the rock slide is moving. Uh we have three different sets of instrumentation, all independent of each other, uh, that all confirm slow and continued movement. Um so using that and then uh good old classic geologic mapping, we've ascertained the boundaries for the rock slide and have picked out the bottom edge of where it is mostly occurring from. We're gonna cut the slope back to a approximately a 35 degree slope, 30 degree slope, which is like one and a half to one.

SPEAKER_10That is a stable configuration, even for like rip rap or sand. Like sand dunes are 33 degrees thereabouts. And uh that will eliminate the main hazard from continuing to come out, and then it will be a rock filled up there to the top. Uh towards the top of the slope, you'll see some horizontal lines. Those are rock dowels or supportive elements. Um, those get placed in to stabilize the hillside further up to keep this failure from progressing upwards. Uh, a common uh occurrence in rock slope and stabilities or slope instabilities is that feather mechanisms uh will work their way slowly towards the very top of the slope over time.

SPEAKER_10And stabilizing them with uh rock dowels is a tried and true method to prevent that progression upwards. And these are just also our this is the 65% preliminary plan set. Um I'll just note that these are not necessarily finalized. This is a go ahead, Greg.

SPEAKER_04Uh this is just another kind of 3D rendering showing the existing condition there on to the left, and then kind of a rendering of the final condition over there on the right. You can see there's kind of a bite out of the top of that slope where we're gonna remove those hazards.

SPEAKER_09All right, so uh right now, if you've been out on the railroad dock, you can see that we have a couple different protections in place. Uh so right now there's sand out there as well as uh a small fence or attenuator with uh with with blocks, and that'll remain during the construction. We may be adding a few elements there as well, including uh steel plates that may go on top of that sand, and then also uh some timber mats that will go behind it to help protect the piles uh when the work is happening and a lot of material is coming down behind the dock.

SPEAKER_09Um, and that'll also help it to not then run down into the water uh and fill that slope that we don't want to uh load up um underneath that dock. And then during during the the work uh at intervals, that a lot of that material will be removed uh and trucked off-site. And so there'll be a lot of activity there to remove that material, make sure it doesn't continue to load the dock. Then once after the the project is complete, um the dock will be uh restored as much as is needed, and then um and then those same protections you see out there today will then also remain uh to help uh reduce uh the rock uh rockfall issues and any rocks that may be maintain continuing to come down the slope.

SPEAKER_09Um and so anyway, the existing plan right now is that all the bus and shuttle systems would remain in place. Um it may be that there's opportunity to re-evaluate once it's all done, but we'll be evaluating that at that time.

SPEAKER_04And this is where I think I take over. Um so obviously one of uh one of the most uh I guess uh visually impacted parts of this project for the locals is gonna be and this is one of the top concerns is what are we gonna do to to get access and what's that gonna look like? And so we're We're talking about trail management and basically how do we facilitate uh granite and their crew getting up to the top and safely uh removing all of that all of that rock that needs to be uh kind of chipped away over time.

SPEAKER_04And so um basically we'll we'll go through and talk about kind of what the existing trails look like and what our intentions are and what our plans are um throughout construction and in the final configuration. So um talking a little bit about our objectives, basically the trail is intended to support the the heart of the project, which is mitigating that rockfall hazard, right? Um so we need to be able to get people and equipment up and down safely. Uh so one of the things that's kind of unique about this project is it's gonna happen all during winter time, right?

SPEAKER_04So we don't want uh to be working above that that dock when it's cruise ship season, and so this is gonna be basically restricted to construction during those winter months. And obviously in the wintertime it gets snowy and icy, and so we want to make sure that uh this access that we're uh providing is safe for people and equipment as they're going up and down every day carrying equipment. Uh so safety is kind of one of the top concerns for getting up and down. Um let's see here.

SPEAKER_04Yeah, the existing trail is basically not usable in the wintertime. Um, some of the slopes are very steep and it's it's a little bit narrow, and so it's not really safe for use in its current configuration. Uh, another objective of the access trail is it's gonna provide emergency access. Um, so not only during the project will it be easier to get uh people and equipment up and down, but uh when we're done with the project, it's gonna provide uh for easier access if there is an emergency uh up at Dewey Lake or up uh for a future rockfall project.

SPEAKER_04Um I mentioned future rockfall project. Um this this project and this grant is focused on the that primary large 300 cubic yard rockfall hazard. Um, but we know that that whole rock ridge has uh uh potential for future problems. And so uh one of the nice side benefits of of providing access to that area is that we're gonna be able to continue to monitor and mitigate any future problems that that might come about.

SPEAKER_04So we'll talk a little bit about the existing conditions. Um we kind of broke the trails into three different sections. We say segment A, B, and C. And if you look at our our role plot, um actually we took those labels off, but we can help uh point you to where those are. But we'll we'll describe them here a little bit in this presentation. Um so before we get into that, we wanted to talk about what uh what are we talking about when we when we're talking about these these trails. Um I know there's some some misunderstandings out there about what this is going to look like, what the impacts are gonna be.

SPEAKER_04And we thought it would be a good place to start by thinking about what do other trails in the country look like. And so we kind of went to one of the sources. Uh, there's this trail fundamentals and trail management objectives put out by the U.S. Forest Service and the US DOT, Federal Highway Administration, uh, to kind of give us a baseline for what is a normal trail, what are the typical expectations, how does it look? Because when when we're done with our efforts, we want this uh trail to look as good or better than it does right now.

SPEAKER_04Uh so those are some of the references that we that we looked at, uh trying to match what people's experiences and expectations are. Um so looking at the existing trails, um, there's kind of a range depending on which section and segment of the project you're looking at. Uh so the current trail system is is kind of a lot of class one and class two pedestrian trail, which is you know, could be you know 12 inches wide to you know two feet wide and very steep.

SPEAKER_04Um the lower sections, the segment A, where there's the existing uh maintenance road up to those water towers, that's more of a kind of class two uh multi-vehicle management use. So that's that's what that green box there is calling out. It's a class one, class two, maybe uh again, very steep. Uh, and that's that's kind of what we're dealing with right now. Um, and here are some examples from that U.S. Forest Service. I know it's really hard to see from back in the crowd, but you can download um this Forest Service manuals and and review them yourselves if you want to.

SPEAKER_04But these are examples of uh class one trails on the left, uh class two trails on the right, and you'll see those those look a lot like what we're we're dealing with, right? Class one, class two trails. Um and then what we're trying to get to is just upgrade those trails a little bit uh into class four trails, um, which I I kind of like that top left picture of a class four trail because it's kind of through the hemlocks, and uh basically that's that's kind of our target, right? We want to we want to basically clean up the trail, make it smoother, make it safe for that wintertime access, get rid of those bumps so that we can get up and down there on those winter days when there's a little bit of ice and and make sure that you know uh we're not putting anybody at un unnecessary risk.

SPEAKER_04Uh so again, these are just examples of class four trails from all over the country that the U.S. Forest Service has constructed. And again, this is kind of our our North Star, kind of what we're aiming for with what with what we're doing to the trail here. So segment A basically goes from uh the railroad tracks down at the bottom of the hill up to the intersection with the Icy Lake Trail. Um, and we categorize that. Uh that that's kind of a good stopping point. That's where the the hiking trail proper kind of begins and the the maintenance road kind of ends.

SPEAKER_04Um that existing road is actually pretty close to what we're looking for. Um it's about 10 feet wide, which is which is kind of what our design width is is going to be. Grades are you know more than more than or equal to 22%. There are sections that are quite steep. I think there are sections that are closer to 45% or maybe 45 degrees. Um and the design use right now, they they do drive up there with ATVs uh to maintain the water tower, and and they actually go all the way up to the top uh when conditions allow.

SPEAKER_04Um so sections of of segment A are already kind of class 4. You can see these photos. It's already in pretty good shape, so we don't really need to do much to it. Um so there will be a little bit of a little bit of uh widening and a little bit of flattening in different sections. Let's see. Segment B, uh this is what we're kind of categorizing as the heart of the existing trail system. This is the section that everybody's really concerned about. It's it's got those nice little bridges, it's got uh, like this photo shows, it's got the narrower trail with the roots, and this this kind of follows the wetland and ends up up there by the lake.

SPEAKER_04Uh so segment B is kind of like the most uh sensitive part. Um and again, existing, a lot of it's already 10 feet wide. There are some pinch points that are closer to five feet wide. The grades aren't that bad, but there are some some steeper sections, a lot of small boulders and routes, a lot of tripping hazards and and bumps if you're driving up there with uh with your side-by-side to do some construction. Um there's one culvert in segment B. And right now the design use it's it's pretty much best for for hikers.

SPEAKER_04It's not really a great place to ride a bike or do anything else. Um so I think a lot of segment B is already maybe class three. There are a lot of those those tripping hazards and and bumps. Um we'll be just making some incremental improvements to segment B to give us that width and to smooth out those sections. And then segment C basically goes from Lower Dewey Lake, which is uh kind of where where the recreation area is, and this goes all the way up to the top of the rock fall area where the heart of the project lives, right?

SPEAKER_04So segment C um basically tees off of segment B and kind of follows the top of that ridgeline and gives us uh kind of uh safe access to to the top of that rock slide. The grades, uh well, we're shooting for, well, I guess the the existing grades about 33 percent. Uh a lot of a lot of kind of boulders, moss-covered boulders and logs and stuff like that. Uh class two trail might even be generous. Uh it's there are sections where there's not much of a trail to be to be seen.

SPEAKER_04Right. Uh so proposed conditions again, we're gonna go through segment A, B, and C. A is at the bottom, B isn't in the middle, C is up at the top. Um, so we'll we'll talk a little bit about our design parameters. Um we're talking about trying to get construction people and equipment up there. Um this figure down here on the bottom left is just to give uh to give everybody a sense of what those slopes look like. Uh so a 30% grade there, that's that's pretty steep. And that's that's kind of our target maximum slope for the design vehicles, the construction vehicles that we're gonna be uh running up and down that that hill.

SPEAKER_04Um so we talked about uh this top left bullet, the first bullet construction grade. We normally shoot for about 20% max, um, but we're we're kind of allowing ourselves to go up to 30% max in this case to try to mitigate the impacts that we're having on the the I guess the area. Um yeah, and so this piece of equipment here on the right, um, this is called a Maruka, and it's kind of a tracked uh dump truck vehicle that can handle those really steep grades.

SPEAKER_04Uh so obviously a 30% grade that's steeper than a normal dump truck can can carry a load of gravel or or you know, even a pickup truck might have some trouble with that. So we're we're kind of using some special equipment, and maybe granite will talk more about this later, but uh this kind of specialized equipment uh makes it possible to get away with those kind of steeper grades, again, with the intention of uh uh trying not to over overimprove things, right? We're trying to find that sweet spot where it allows us to get up and down safely safely and meet our needs without uh without going overkill.

SPEAKER_04Uh so we'll talk a little bit more about the proposed trail classifications. So you can see that class four on the bottom, um, kind of designed with a a four-wheel drive, all-wheel drive vehicle in mind. So that width, you know, the class four trails eight to ten feet wide, our our design width is ten feet. Um, you can see that the proposed grade for the class four trail is 15% max. And obviously we're going well beyond that um because we're not we're not building a you know ADA accessible trail really. But uh again, this is kind of our North Star for uh, you know, we're we're making some some trail improvements, but we're not we're not going above and beyond what is kind of the minimum necessary to make this uh safe in in the short term and in the long term.

SPEAKER_04So uh we made a nice little uh GIF here on the right. Um I know some people say gif, but I'm I'm standing on that. So uh thanks for laughing. Uh so uh segment A, uh a lot of it is just needs to be kind of cleaned up. Uh like I said before, a lot of it's already wide enough. There are a couple of sections that are oversteep that we're gonna try to flatten out and do a little bit of rock, uh rock cutting to make those grades safe for wintertime construction.

SPEAKER_04Um drainage is obviously gonna be a concern. You can see out out there right now, there's already some kind of um rivulets and signs of erosion on the trail itself. So that's something that we're gonna be designing uh around. Um we might do a little bit of signage, but this section, segment A, isn't part of the the main hiking trail. This is actually off to the left if you're looking up the hill. But this we're still gonna we're still gonna make it look good. We're still gonna target that class four trail with that 10-foot width, getting rid of those irregularities.

SPEAKER_04You can see in the GIF that we're basically planning on getting rid of all the all the bumps and and potholes and making that kind of a smooth grade uh that everybody can get up and down safely. And here's kind of a 3D rendering of of one part of segment A. Uh, I don't know if a lot of people have hiked up that section, that uh maintenance road, but there's a couple of really tight switchbacks in that area. And that's kind of one of the hardest nuts to crack of of this design in this particular segment is how do we how do we get uh an excavator or telehandler or those marukas up and down those that set of switchbacks in a safe manner?

SPEAKER_04And so we've Micah here has done a bunch of modeling, he's he's looked at this from a bunch of different angles, and uh we decided this is gonna be one of the potentially visible spots from from depending on where you're standing in town. And so we wanted to do a rendering of that to kind of show like what that rock cut would look like. Um we're gonna have a little kind of potentially a long fill slope where we're kind of chasing the existing grade. And so we just wanted to render that up to give people a sense of the scale. And you can see it's it's a pretty narrow uh gravel trail that we're that we're visualizing here.

SPEAKER_04Uh segment B, we have another nice little gif where um one of the one of the other nuts of this project is that there are all those timber bridges out there. I think are there 10 10 bridges and and three culverts. Um so these bridges, they're they're in pretty good shape, but uh our design vehicle, um, well, our heaviest design vehicle is going to be a cat excavator, and those things weigh 25-30 tons or something like that. And if we use those marukas with a with a load of something on them, they could be potentially many tons.

SPEAKER_04And so our plan is to basically replace those bridges with uh bridges that have a stronger girder, which is kind of a structural component underneath the bridge, that will be able to handle those loads. And so we were up there today looking at these bridges, and and most of them, we're not gonna have to change the elevations very much. The existing girders are already 14, 16 inches deep, which is not that different from what our proposed girders are gonna be. So uh what we're showing here is that we're we're gonna basically swap out those bridges in place. Our plan is to basically do those in in a single night so that we're not having to close the trail during the daytime.

SPEAKER_04Um so that's kind of the one of the most exciting parts of that segment B is that we're gonna swap out those bridges, uh, but we're gonna try to meet the same kind of aesthetic with uh with timbers on top and and a beautiful class four trail approaching and leaving it. Let's see. A lot of the same kind of engineering features. Here's another here's another section of segment B, uh kind of a side view of one of the longer bridges that will swap out. Um we're assuming that we'll have to raise the grade slightly just based on based on the hydrology that we're gonna we're gonna complete for that creek.

SPEAKER_04And then over there on the right, you can see that's that's just beyond the last bridge looking towards Dewey Lake, where we're gonna try to maintain uh and match that left edge of the trail and widen out to the right a little bit so that gives us that 10-foot width, and so we can get our our design vehicles through that area. So again, we're we're trying to we're trying to find that sweet spot, that Goldilocks zone of how much do we need to do to allow us to do this work safely with maintaining as much as of the integrity of the existing and the the speed of the existing trail as possible.

SPEAKER_04Some additional views, um kind of a nice little rendering there at the bottom. I think that's that's the final of that gif from the previous page. Uh so segment C, this one um our our 65% design included uh basically a a T intersection off of segment B, kind of before you get uh down to the lake. No, just past the lake. It'll kind of T off and then basically follow that existing ridge up to the top.

SPEAKER_04Um so this one, there's there's not an existing trail there, really. I mean, there is an existing maintenance trail off to the side that our current plans show that to be re-vegetated and replanted with trees. Uh and we we call that obliterating. Um, so that's the plan over there, and then we'll we'll kind of make a make a beeline for the top of our of our rockfall area where we're gonna perform that excavation and blasting work. So, not too exciting. Um, and we wanted to focus a little bit on on our revegetation plans.

SPEAKER_04So we uh we want to make sure that anything that we disturb on a temporary basis, um, like if we have any staging areas or any material disposal areas or anything like that, our plan is to do a robust revegetation plan and plant local uh trees and shrubs that will survive and thrive in this area and kind of match the existing landscape, right? So uh we listed a couple of species here that that we're planning on running with. So we've got paper birch, sitka spruce, and western hemlock, uh not listed here, but you guys have a lot of lochpole pine up kind of up at the top and and throughout that area, beautiful, beautiful specimens.

SPEAKER_04And so we'll kind of use a mix of those different species, um, and we'll kind of match the the U.S. Forest Service kind of planting recommendations as far as spacing. And then as far as shrubs, um, we have a variety that that we're looking at, including the the red ausier dogwood. Um, I think there's a lot of Devil's Club. I don't think we should plant that myself, but uh basically we'll revegetate with a lot of native species and try to try to give ourselves uh kind of a jump start on on this, I think they call it succession, where nature kind of takes back over and it starts to look a lot like it does right now.

SPEAKER_04Uh so now I think I'll hand it off to Kyle. Um, we did get some some questions from I think some assembly members and maybe the public that we just wanted to make sure we we address and uh make sure uh we're we're not leaving anything unsaid that that people have burning questions about.

SPEAKER_06Thanks, Greg. Um so yeah, these are so we we've received um a number of questions. Um the the letter that we provided is uh is kind of a an overview of of an aggregate of all the questions kind of lumped together in different categories. And so some of these are are more specific questions that were presented. Um, and I'll just kind of just kind of breeze through here. Um this the first one is is asking about how many linear feet of new construction is being built and you know how much is going to overlap the existing trail.

SPEAKER_06Um and you know, we've got the total access alignment is about 8,200 feet long. Um, and and as um uh Greg mentioned, we have segments A and B, which are following existing trail uh and access. Um, and um and the you know the the part that's overlapping the the the hiking trail, which is segment B, is about 3,600 feet. And so I I believe, I don't know if it works out exactly, but I believe those different segments are each about a third of the overall length.

SPEAKER_06So um maximum actual disturbance width. Um, you know, we've got the the the maximum width is about 60 feet wide, which includes the on segment A, some of the the fill areas that we've got uh in those switchbacks. And so that's you know, you know, a lot of the the trail itself in those areas is still only 10 feet wide, but when we're following the topography with a fill, it has to extend down the the slope a little bit till it catches ground. And in those, that you know, that one particular area is 60 feet wide.

SPEAKER_06And and those are those on the roll plots in the back, you can get a good sense of of where those are. And really the widest areas are on that segment A in the switchbacks. Um and in B and C the widest areas are you know 30, I think 32 feet is is the is the widest areas in B and C, but those you'll again you can see on the plots, these areas are very isolated, just where we've got some topography to deal with. Um but by and large, uh with a 10-foot wide trail, most because we're following existing access that's there, existing developed access that's there, you know, we're averaging about a 15-foot wide footprint to get that 10-foot uh trail surface.

SPEAKER_06So um, you know, I think we've got a pretty well dialed in um design that that's that's following existing access and and really really trimming as little as we can from from undisturbed ground. Um and then our acreage, total acreage of of impact, uh including cuts, fills, staging, bridges. Uh, we've got about 4.4 acres total uh along the entire alignment and the uh helicopter pad that's up there.

SPEAKER_06We're we're we've got to make that area a little bit bigger. Um, and I'm not really sure what the proportion is, but the helicopter pad probably a pretty substantial part of that disturbance, I would I would imagine the overall acreage, right? Yeah. Okay. So um, but we've got there there's a a table and a couple of slides later that shows the distribution. I I don't know that probably let me just pop that up at the end of this question so you can see. Um before and after cross sections, um, we we provided so so we've got the roll plots there to show the distribution of of all the impacts.

SPEAKER_06Um, and I believe in in the letter we provided as well, there's some there's some typical sections that show the cuts and the fills, um you know, the the widest areas. You can see what our what our assumptions are. One thing of note is um in the 65% design, we um in the fill in the assumed fill slopes, we were fairly conservative. We assumed a two to one fill slope. Um in and I I I'm fairly certain we need to take a closer look at it and and get comfortable with it. But I think we'll be able to make those fill slopes a little steeper to still um shrink that impact.

SPEAKER_06Um so what you see on the roll plots and what you see on the um on the typical sections is a conservative estimate. And and I think if anything, once final design is done, we'll probably be shrinking what we're showing here now. But we wanted to be we didn't want to get too aggressive and and you know um in this phase. Uh so we wanted to be a little more um conservative in that estimate. Um access roads, temporary. So the access trail is intended to stay.

SPEAKER_06We like Greg mentioned, we do have some some temporary staging areas for the bridge change outs and and we have a an area that um that we've identified as a potential material source disposal area if if we need it. It's about it's on segment A. Um, all of those temporary areas, and if if we do use the material disposal area, we will re-vegetate, you know, reclamate. Um, those those um and and those designs will be part of the design, or those, those parts of the project will be part of the design. And and all the details for revegetation and grading and and maintenance of the vegetation will all be encompassed into the design.

SPEAKER_06Um, and they'll you know we'll be following you know design standards that are accepted by the state and and and other agencies. So you can go to the next slide. Um final lower Dewey Lake trail width after restoration. Um the the current plan uh per direction from the municipality is to maintain that that 10-foot-wide class four trail uh after construction uh is complete. And so that is going to stay. All of the other areas, um, temporary staging areas, disposal areas, those will be regraded and and restored.

SPEAKER_06Um the the fill slopes that we're that we're creating will also be vegetated as part of the design. So, really, what will be left unvegetated in its state during construction will be the trail itself. Um and it's that 10-foot wide class four trail. Um again with number seven, will the four-inch aggregate road base be removed after construction? No, uh that that surfacing is intended to stay uh to maintain the access after construction is is completed.

SPEAKER_06Um what prevents construction traffic from permanently compacting the soils outside of the eventual rail tread. So one of the reasons why we're we're building the trail and getting this access to the to the point where we can use it is to avoid damage off the trail, right? We we want to focus the construction traffic uh and in on the on that trail surface so that it doesn't wander and and impact other places, but but it's focused on the trail and it will stay on the trail.

SPEAKER_06Um because I'm sure granite doesn't want to traipse all over the all over the forks and get their equipment stuck and all that good stuff, right? They want to stay on that trail. Um and question nine, uh, can we require restoration to original contours rather than simply re-vegetating the road, cut, and fill? Um again, um we're we're we've been directed to maintain to leave the trail as is after construction. So the the vegetation, revegetation will occur on the fill slopes and any temporary areas that that are disturbed for staging or or material disposal.

SPEAKER_06Uh number 10, what is expected time until areas visually resemble existing forest again? Um well takes time for things to grow. Uh, you know, we've got you know, that'll that'll kind of be outlined in our in our revegetation plan. Um I think the idea is to get uh good native hardy plants established so that they grow and and and continue to grow. Um, but you know, the the the area will look different uh in in these areas that are impacted. But our our goal is to try and re-establish the vegetation as best we can so that um you know, after a certain amount of years, you know, the shrubs and and whatnot will grow up quicker.

SPEAKER_06Uh the trees and and the canopies will take longer, um, obviously 10, 10, 20 years uh or 30 years, depending on the species. But um, you know, I've I've seen pictures of that whole high hillside that was clear cut at one point. And so now you know it's it will come back, it's just a matter of time. Go ahead, next slide. Um and the restoration performance standard uh will the contractor have to meet. Um what's the survival? So so we're gonna base our re-vegetation on on standards uh you know that that are common for transportation projects and and development projects.

SPEAKER_06Um, you know, DOT, uh National Forest Service or you know, what have you. Um the you know, typically it's 100% survival in the first year and 80% at the end of next year, and then after that, you know, you have um you know lower, you know, lower survivals. But you know, the actual criteria and and what we end up using for survival rate assumptions and who's responsible for maintaining it, and you know, how long after construction granite needs to come out to to maintain will all be part of the contract and part of the construction cost.

SPEAKER_06And and we'll consider, you know, we'll talk with uh the municipality and you guys and and make sure that whatever we do is is acceptable to the community and and um you know just like everything, there are costs associated with it, somebody's gonna have to maintain it, whether or not that's the municipality or granite or a third party is that'll all those all those details will be in the design and and dealt with in contracting. Um and that speaks to um question number 12 as well.

SPEAKER_0613. Uh interested in seeing a detailed cost and time analysis of alternatives such as helicopter usage, um not convinced that the road is the only option. Um it's it's true, the road is not the only option. Uh we you know, we uh we were, you know, we we'd we'd kind of gone through the alternatives analysis, and based on our our conversations with Granite, the municipality, and others, um it was clear to us that it seemed like the most efficient way to maintain a predictable construction schedule to the extent practical, um, and you know uh reduce project risk and cost risk was to establish ground access to the to the top of the slope.

SPEAKER_06We did have um granite go through and do a you know a high-level cost estimate of what it would take to have construction only supported uh operations. And we you know, this information is provided in a letter that we wrote, but it's a it's about a$35 to$40 million price tag. And and I know that seems like a lot, but when you consider everything that needs to be moved up there, um and then everything that that needs to continuously go up there every day, you have people, uh, you have uh construction materials, uh uh maintenance needs for all the equipment up there, fuel, um, all of those things would only be able to be transported up to the hill by helicopter.

SPEAKER_06And and so what that means is that's a lot of helicopter time, basically continuously during construction. Um, the other thing that that does is it draws out the construction schedule, um, at least twice as long to do it because um, as you well know, flying helicopters around, especially when you're slinging things, large loads and whatnot, very dependent on weather. Sometimes the weather here in the winter isn't that great. And so we would anticipate that there's a lot of there'd be a lot of downtime um in the wintertime for construction, just because of how much you know, how much you know, just fuel is needed to be up there.

SPEAKER_06You know, you you can, yeah, you maybe you could have guys hike up there and and work for a while, but eventually the the equipment's gonna run out of fuel. So so you're you're gonna have to, you know, they have to be constantly feeding that. And so um that's um I think that's it. I think that's all the that's all the questions that we had. Um go ahead, Micah.

SPEAKER_15Hey, um, so I'm the one that's kind of designing and modeling the road um or trail or whatever we're trying to call this, because we're trying to be as tactical and tasteful with how we approach this as we can. So I just wanted to say something real quick about the design vehicle. Um, as we mentioned before, it's maybe some of those uh tracked vehicles that need to get up there. We need probably an excavator to be able to help the guys at the top, but that won't be going up and down all the time. It just needs to get up there to do the work. And then what we envisioned is like a telehandler type forklift to be able to go up some of these steep grades.

SPEAKER_15So fire trucks are probably not going to be able to go up this. Um, this is not your F-150, can't go up this. This is still very tight and very small. Um, so it's just basically being able to facilitate the contractors' vehicles. Um, to that effect, the reason why we're redoing the bridges is in order to bring a tracked vehicle across that, we need them to be a little bit stronger. So we're not putting in huge steel girder concrete bridges. We're gonna have, I think, wood decking over some steel girders that are the same size as much of what's already up there.

SPEAKER_15So the idea is it should almost be not noticeable that the bridges have changed. We're just gonna put in the lumber again, uh, not the same lumber, but but fresh wood. We're trying to make it look as much as we can like the existing trail aesthetic. Um, the thing I want to mention real quick, the reason we're doing a little bit of gravel over the top is also to protect the roots of the trees. And we don't want a bunch of rutting. We're not trying to tear up a bunch of mud, throw it all over the place, and we don't want to tear up the trees. Um, we've done a lot of sightwalks already, and we're gonna continue to over the next couple of days and ongoing with this project.

SPEAKER_15There's a lot of cases where we're gonna try to be really careful about avoiding cutting down trees. We're gonna definitely have to do that, but for the most part, we can go around trees. We can scoot the trail over a little bit. We're trying to keep as much vegetation up as possible. Um, something else I just wanted to mention to that effect is for the part of the trail that we're on top of the public hiking area is pretty limited. We can show that back there in the roll plots, but I just really want to emphasize we are not building over the top of the main hiking trail.

SPEAKER_15Um, when you go up there and you cross the tracks, it says like the service road that goes straight, and then the main hiking trail, it's really beautiful, is off to the right that goes around. I know folks use both, but we're improving that that service road that goes up towards the water towers, and then a limited section around um where it cuts across uh basically on the town side of Dewey Lake. Um, we're not affecting the trail that goes all the way around the lake. Um, we're trying to stay off of the trails as much as we possibly can and only be on the spots that are necessary just to get to the project.

SPEAKER_06Thanks, Micah. Um and I I don't know, I mean I might put Ryan on the spot. Uh the engineers have been talking a lot about equipment and stuff. Uh maybe the contractor might want to just kind of, you know, if you want to share your your take on what the project is and and access and limitations from helicopters and things like that, that'd be good.

SPEAKER_05Yeah, sure. Well, yeah, I don't know. You guys are doing a pretty good job. Although I think you everybody here is probably living it a lot longer than we have, as we've just been involved here for the last uh uh year or so. So um obviously you can do anything uh if money is uh no object. Uh I would say, you know, and they kind of already touched on this, uh, there's a lot of stuff even beyond equipment that has to get up there. I'm pretty sure there's probably a million pounds of steel and grout just for doing the rock bolting.

SPEAKER_05And at a couple thousand pounds at a time going up with a helicopter, you're you're constantly doing that all year round. And you're only doing that 50% of the time because you're shut down on standby for 50%. So from that perspective, it's not a very feasible option, yet still an option. Um I think the most important thing, and everybody here is super conscious about the goals of the project and including uh the impacts to the community.

SPEAKER_05And you know, we would love to have an access that you can drive up with a pickup. I mean, if we asked for what that what we needed, that's what we would ask for. And that's not what this is going to be. And so the team has really done a good job at identifying uh vehicles that we can do the most limited amount of impact to get just what we need to get the things up there to do the project. And that's what's been great about the collaboration of the team is working through that and and not overbuilding something that you don't need just because someone asked for it.

SPEAKER_05You build what you can do just to get the needs of the project done. And so I think you got you guys should be happy with the team that's uh put this together. My last thing I would say is uh, you know, I'm not a member of the community here, so I don't have a personal attachment, and I totally understand that. Um, but this to me is a really good uh end benefit when it's all said and done. It's gonna be a beautiful uh trail that may be a little bit upgraded, but it also provides emergency access up to the top for future problems and issues and mitigations that not having to go respend the money all over again when we got to go up there again in three or four years or 10 years.

SPEAKER_05So I think a lot of benefits, a lot of people put a lot of time into it. Uh and you know, we're not building this to this extent that we actually need. We're building it to the minimal extent possible to get it done. And uh I don't know if we can probably reiterate that enough. I don't even call it, I don't call it an access road. It's just access trail. And it's that's really what it is.

SPEAKER_06All right, thanks, Ryan.

SPEAKER_05I think um yeah, here's here's just some some visuals on the helicopter there, and you can see so there's some there's some options for, you know, you can do some of the Tempsco like local helicopters, but they can only carry three or four thousand pounds. Anything substantial, like if you want to get drill rigs or uh a drill or any sort of an excavator, which uh this thing, these helicopters can only lift, I think, up to 25,000 pounds, which is really just a mini excavator size. Uh, so you really can't even get the size of gear that you'd really actually want up there with a helicopter for all the money that you spend on it.

SPEAKER_05Um, but in theory, you would need something like this uh Chinook to get you your big loads up at the beginning of each season. And then you'd have to have a smaller helicopter service daily throughout construction. And again, uh, you know, a two-year project would turn into a four-year project pretty quickly uh if you're relying on helicopter access. And and that's even if it's possible to get the things you need up there with the helicopters, which I don't know that we've necessarily vetted that all the way to its fullest either.

SPEAKER_04Um I think uh this is just kind of retouching on some of the some of the design parameters that we talked about. Uh we were kind of intending for uh for construction to kind of close out this conversation. And so we mentioned earlier the kind of typical construction grade, the preferred design vehicle is like an F-150, F-250 pickup truck. And and obviously, like like we've said a couple of times, that's uh uh that's not quite acceptable, right? We want to we want to minimize our impacts even more. And so we're we're designing for those uh all-wheel drive, four-wheel drive, you know, uh articulated vehicles that that can get the equipment and materials and and people up there and down safely.

SPEAKER_04Um and and again try to find that Goldilocks uh sweet spot where we've just done just enough to make it uh constructible and safe, but it uh not not too much.

SPEAKER_02And that concludes the programming. Thank you, team. Uh we'll take a short recess while the clerk uh prepares the questions from uh that were submitted. Um it's eight o'clock, so we'll hopefully reconvene when the clerk's ready at about eight ten. Go back to order of this meeting. Uh uh we have quite a few questions here uh from the public.

SPEAKER_02There are 13 for the engineering design team, another five for municipal management, and several more for the mayor and assembly. We'll try to get through them all. Some of them might be a little repetitive, but we're gonna try to be thorough, but not be here all night. Um, and they are uh now uploaded onto the website. So um what we have you can access. And the clerk is going to begin by asking the questions.

SPEAKER_03Uh thanks, Your Honor. Um uh before I get into the questions, I'll just say uh the questions um were compiled from written submissions received before and during the November 9th, 2026 Assembly of the whole meeting. Uh similar questions were combined, edited for clarity and neutrality, and sorted according to which group is best positioned to respond. AI-assisted tools were used by the clerk's office to help consolidate, clarify, and organize the submitted questions.

SPEAKER_03They're not verbatim questions, and the original submissions have not been replaced or altered. Um, where to find the originals? Uh, this consolidated list and original written submissions are available with the November 9th, 2026 assembly meeting uh assembly of the whole meeting materials on the municipality of Skagway website, um Scagway.org. Um so as the mayor indicated, the first 13 questions are um for the engineering design team, uh some of which might be repeats, but um you can answer or tell me that it's a repeat or just um so uh number one, which rockfall hazards will this project address?

SPEAKER_03How much risk will it reduce? And what will change for cruise ships, trains, and pedestrian access at the railroad dock?

SPEAKER_06All right, I'll go ahead and start. Um as as stated in the presentation, the rockfall or the the the slope hazard that will be addressed by this construction project will will be the large-scale failure of the unstable rock mass. Um the the hazard that that addresses is the is the hazard to the dock as well as the the rest of the port Ascagway and all the other infrastructure that's in there.

SPEAKER_06Um the the changes to how the dock area is going to be used are um at this point um not substantial. We will be able to take the the uh cruise ships all the way to the forward berth. Um as it stands now, the the the forward berth has been moved back towards the aft um to get the the cruise ships away from that large-scale failure hazard. Um but once that's gone, they'll be able to move all the way up and dock as as they had been prior to adjustments that have been made recently.

SPEAKER_06Um the the other improvements to that area uh are the landside improvements and and the usage of that of that area at the at the base of the slope. So um currently there's a large area that's blocked off. Uh the the tour building is not being used now. Um, and there's some other facilities that are not being used with this excavation. Um, I think a lot of that can be taken back and and used um with with the caveat of we would we would want to take a another.

SPEAKER_09look at the rock fall and and make sure we're we're we're still good there but but a lot of that a lot of that area will be able to be reclaimed um it through this process um the and and as as it stands right now the the pedestrian use and and train access to the dock is not changing with this project um that's not to say that it can't change in the future though uh this this project is a step in that direction in my opinion in the way I see it any anybody from the panel want to add to that I I would love to add sure once again Rex Whistler uh just to reiterate that uh this project focuses on the hazard that is presented to the city as a whole and the harbor as a whole uh this is the removal of 3000 approximately cubic yards of rock an unstable rock mass that when failing impacts the entirety of the harbor area not just one specific cruise ship dock so that's the the intent and all be all of this project is a ru is to remove that risk and that hazard okay uh number two what additional projects and costs would restore historic dock use and has relocating or redesigning the dock outside of the rockfall hazard area been evaluated Rex will take this one yeah actually Ed would you lead us off with the alternative analysis for a second yeah so as as uh I think a lot of you know we started out with an alternatives analysis before we got to this where we're at today uh the as a normal design process but also as a requirement of the BRIC grant uh and FEMA is that you have to go through alternatives uh we went through and evaluated many different alternatives everything from doing nothing to letting it all come down and rebuilding everything um and then multiple options in between and so that's uh how we landed on where we are uh today and so for uh restoring the the dock to its historic use um would require additional work down at the dock to help evaluate or help uh mitigate that rockfall hazard that we'll have can continuing on and so I think Rex is going to talk a little bit more about what needs to happen there uh as far as the rock slope but for as far as on the dock side um we know that the what's there today has been uh put there to protect the different uh means and uses that we have with the different hazards we have um we still need protection from the rock fall hazard after uh the rock slide has been been mitigated um so Rex I'll turn to you to talk about the hazard levels yeah so additional projects would be uh design and construction of supplemental rock fall mitigation measures principally in the form of either drape mesh uh hybrid attenuator systems that we place on the slope similar to the existing mid-slope attenuator that you see on uh in the main north chute or south chute sorry main chute of the slide uh for the north slide andor the lower attenuator uh that's just off the dock.

SPEAKER_09Uh so similar uh construction efforts uh as what was utilized to emplace those would be placed uh in along the main slide portion of the dock as as well as areas to the south as a rockfall hazard does exist uh along the other portion of the dock we have documented rockfall occurrences most notably one a few hundred feet further to the south um that is outside the scope of this project but we are very much aware of it and uh so it would be a suite of rockfall analyses and then design uh abatement uh I guess measures and engineering design for those structures um and then implemented them having them constructed and that would facilitate um reopening the dock to to a full use or historic use under current standard of practice and globally accepted uh probabilistic risk of rockfall occurrences yeah and then again to part of the question about redesigning the dock outside of the rockfall hazard um what that was something one of the costs that and alternatives we looked at it's many hundreds of millions of dollars to rebuild that dock um and then as we know there's a steep slope right below it you're in very very deep water as soon as you get off the edge of that slope that just makes it even more um prohibitive uh you also start getting into blocking access to the small boat harbor the further out you come so all things that have uh we've looked at I know that others have looked at moving that dock in the past um and again have come to the the same conclusion so uh definitely all things that have that have been on the table from the beginning uh number three what access alternatives have been evaluated including periodic helicopter lifts foot or ATV access rigging and smaller equipment and how do their cost permits and schedules compare I guess I can start with this one um you know we we have we have through the alternatives analysis process um evaluated lots of different types of of access um and and we've been trying to balance the the need for um the need for equipment and getting the equipment and materials up to the slope um with the amount of time that it takes to do the project and the costs associated with with that.

SPEAKER_06And so you know the alternatives analysis that we've done at several stages we've developed uh in you know incremental cost estimates to do some of those things and so I think we've we've hit on all of these all of these ideas uh in one way or another through the process um especially now with with granite here um as a part of the team um and you know the um you know I I think the I think the um you know the the the cost of of providing ground based access uh where we have now is is um you know it's kind of a we've hit a sweet spot I think in my opinion on on on providing that access and and balancing the the schedule and costs I think the the helicopter option helicopter only sport option uh presents uh kind of a high end um cost uh uh impact and and and you know it it doesn't really save much it in fact it it will draw out the schedule and one of the one of the things that I I want to also emphasize is is the the excavation of this rock is is something that you know this is the you know how this rock is taken down and how it's excavated and this and the sequencing of the excavation is going to be a significant part of the design.

SPEAKER_06We want to we don't want to take the rock down too rapidly but we also don't want to take it down too slowly. Because if you think about you know if we're we're we're trying to shoot for a two season construction window here um to to try and minimize or mitigate the the risks that we have associated with starting and stopping construction. If we have a method that provides less reliable access to the top and less reliable access for construction, there's a lot more risk involved with that construction process because if we're if we get to a point where you know we we come up against the end of a construction season but we don't have the rock face in a condition that we like it to be, that we want it to be in that's stable for operation of the dock, you know that could be a pretty serious problem when you know if we have to if we have to consider not letting ships dock there because we didn't get to a construction pause point that that works.

SPEAKER_06And so the more starting and stopping that you do here, the the the greater the construction risk. And sometimes that's hard to uh accommodate in a cost estimate because you know it just there's a lot there's a lot more question and uncertainty and so we can provide contingency but it's it's it's pretty squishy. And a lot of that comes through in the helicopter estimate because you know we we know that we're going to be limited uh in in the amount of time we're gonna be able to fly but we don't know how much you know maybe we get lucky and we get a really good year and everything's clear all winter and it's nice and sunny and calm and you know all that stuff for long stretches of time but the opposite could could be true as well.

SPEAKER_06And so it's really hard to quantify that we do our best but but we have to weigh some of these more squishy risk items um internally when we're making decisions about which way to go with the project.

SPEAKER_15Anybody want to add anything hello um I will say at least for the access the site access on the ground um we did I believe we are on the seventh iteration of a different path chosen we looked at trying to provide what would it take to get a dump truck up there? What would it take to get an F-150 up there? And that means cutting massive a whole new road really uh there isn't a way to get that vehicle up the current service road it's just too steep.

SPEAKER_15And so we're trying to find again what Kyle said that balance of like what is it that if the contractor can work with some tracked vehicles some smaller vehicles some all terrain vehicles we think we can make it work but the other alternatives were much more dramatic.

SPEAKER_10In fact last time we were here uh to present before the assembly we actually had on our on our preliminary kind of alternatives that we were considering much more dramatic uh access roads so we have looked at some other alternatives and tried to really narrow it down to something uh as effective as possible um number four has the alternate alignment east of the APT reservoir and the rock knob above the clock been evaluated for its potential to shorten the road and preserve or add trails your design team would like some clarification on where the clock is I'm I think more holistically we this this builds off of Okay's giant cliff that the clock is painted on yes hanging that in uh so someone would think that's a cloop yep I see what they're we now understand the location that is being asked as far as cut across we have evaluated a litany in series of locations including areas along that um but they all uh did not prove out due to complexity of cuts and fills in in increasingly steep terrain so so that area is much more steep than what the current alignment is propose is proposing or follows because it we're just following an existing system and uh it became a uh magnitude order larger cuts and fills uh for for that area and similarly other locations along that could potentially be thought of as access um apart from what what is currently proposed this this really is the sweet spot and the minimal impact most minimalized impact to the system as it stands and just to add you know that that is you know that is a the impact question is also you know it's it's it's a part of the equation but but in addition to the impact and and you know impact to trees vegetation uh visual impacts the the more material you have to move the the the more you pay um and so that's that's the other you're balancing not only the impacts but also the cost of the project and so trying to notch in a a road into really steep terrain with these big cuts and fills you're moving the the volume of material you're moving is much greater and that that has a big cost implication as well.

SPEAKER_15And I will say we we did look at an alternative that at least was in that vicinity we're using LIDAR um surfaces so it's not just a visual inspection that we're doing to try to figure out where these can go and we did a lot of route analysis and yeah it leads into huge rock blasting for the road it would mean a kind of a scar along the side of the the mountain from down here that you would see there wasn't a feasible way that we could see through that area number five how wide would the proposed route be compared with existing trails or roads including shoulders and passing areas what equipment and vehicles would use it and how would it be used after construction?

SPEAKER_06Yeah so uh we we touched on this in the presentation quite a bit uh you know the existing the existing trails that we're following are it in so especially in segments A and B you know they're they're anywhere from you know six to ten feet wide already um you know so in in in many locations we're we're just widening by a few feet um you know there there will be in areas where we're filling in areas where we're cutting you know outside of that 10 foot wide um surface there there will be impacts um in the presentation we referenced in the majority of places we're only about 15 feet wide with inclusion of cutting and filling zones there are places that are that are wider than that um and you can see that on the roll plots the um the the equipment and vehicles we touched on that quite a bit tracked vehicles uh this is not a pickup truck road appropriate road this is uh four wheelers six wheelers um side by sides at vs tracked tracked equipment um and and things that can handle grades that are up to 30 percent so um you know this is and it and it's 10 feet wide it's it's uh one lane all the way um there's no you know you can it it maybe at two bike lanes you could you could get bikes going back and forth but that's about it so um and then after you know the use of this road and and this access to the area after construction in in my mind is is really a a question for the municipality um you know it can be blocked permanently it you know but but there is value um in in keeping that trail uh after construction because um in inevitably you you will need access to the top of this hill at some point in the future um to respond to you know other locations along the hillside you know like i said before there's uh there's rockfall risk and and slope hazards along the entire length of this slope um having access to the top uh will will be something that is is permanent um and will be able to be taken advantage of after construction there's a lot of value there um and you know if if you know we were talking earlier uh before the meeting you know if we used helicopters or something you're gonna pour a lot of money into that if you can make it work and then when you're left after construction you don't have anything uh you know that there there's you're you're there's no access and if if you need to get back up there you're gonna be dealing with this question again so um I think that's covers it unless anybody else we have any visual we have a visual yeah um uh we'll be happy to provide demonstrations after the after the questions for for uh for this and we and we will be up uh on the hillside uh tomorrow to to actually look at these places so okay uh number six where will staging areas be located what road surfacing and fill will be used and where will excavated earth and cleared vegetation go Greg and and others will be responding to this are gonna get the visual up on the screen for people maybe not I can vamp do we can you repeat the question please oh never mind we I got it up here okay um you know with sta staging areas uh we we project to have some staging areas near uh each one of the bridge crossings that are that are temporary um just for laying down the bridges and and and allowing that work those those will be revegetated and reclaimed uh once once completed um we have uh for road surfacing and fill we're we're we're gonna try and source as much of that from from the the actual construction of the road as possible uh it's gonna be a crushed rock material something that can be worked and graded and provide a stable base for the equipment that's that's being that's using it um and then and then we have uh we've identified the the revegetated possible material disposal site um here on on segment a you know this is uh this is um an as needed uh location and that's gonna that's gonna receive unusable excavation material or excess rock material um we'll we'll have a design for that fill and and the reclamation of that fill uh in the plan set um and then as well as these these larger fill slopes here on on segment a will also be revegetated um greg uh you guys you want to add anything to that or did I cover it okay I think we're good okay um number seven if the road is temporary how will disturbed trails and terrain be restored and how will unauthorized vehicle use be prevented yeah um so so our charge uh is is that the road is is not temporary uh the access will remain um as discussed several times um you know all the temporary staging areas will be reclaimed um but the road itself the 10 foot wide access will will main be maintained uh or not maintained it will exist after construction is over there are no plans to reclaim it um how it's used in the future um is in my mind is up to the municipality to decide um we've discussed before this is not a this is not a pickup truck road this is you know essentially it is going to be usable in the capacity that it is currently used um and not more so um but access and and use of this of this access will be uh up to the municipality to decide uh number eight have the engineers reviewed geologic work associated with the Skagway Traditional Council and sought input from the Alaska Landslide Preparedness Partnership um put them on that one program we've I we've reason we've reviewed work products from the uh landslide preparedness partnership um um and so we've seen the work that they've done i i think from what i recall um the the work and the modeling that was performed by that entity is is uh is a much is at a much larger scale than than what we're looking at here um and so while it while it provides I think good information for uh the municipality and the community as a whole um you know the the focus that we have on this hillside and this slope is is at a is at a granular level that's that's much finer than than what that project or that work was performed under um it's not it's not unusable by us but it's it's um it's it's information that that we reviewed and considered but ultimately you know we're looking at things at a much more granular level than than that is for for this project okay um number nine what safeguards and modeling address rockfall risks from blasting road widening and altered drainage including erosion frost effects So as it pertains to the road construction, um you know the the the blasting that we're that we're going to be doing to create the the access is pretty minimal.

SPEAKER_06Um I I really don't see um significant impacts at all uh from from that work. It's it's low impact, uh the amount of rock we're excavating is very small. Um, you know, the immediate vicinity will will obviously be impacted just because it's a construction site, but you know, beyond that, um impacts are are very minor. Um the drainage is is you know, the the drainage on this road is a significant design issue, and that's that's one of the reasons why we're creating this access, is because um you get icing because of poor drainage in the wintertime, and so managing that drainage is is a big part of um you know of preventing that from happening and and reducing the amount of maintenance that's gonna be needed on the access trail.

SPEAKER_06Um frankly, you know, the you know, we're not gonna be really focusing drainage rather than um just allowing it to cross um the alignment without impacting the alignment. Now, when I think about um impacts from blasting an excavation on this project, I immediately think about the the rock excavation itself at the top of the slope. You know, those those are the largest impacts. Um and and that's why you know earlier I was talking about how the staging and the sequencing of the excavation is is going to be a huge part of the design so that we are mitigating those risks.

SPEAKER_06Um it's a very tender site. Uh and and we don't want to we don't want to make big changes rapidly. We want to be able to make those excavations uh in a deliberate and organized manner. We want to maintain the monitoring that we're doing while we're excavating, um, constantly evaluating what's happening on the slope so that we can react and and and not not get into trouble as as best we can while we're while we're performing the work.

SPEAKER_04Anyone else? Yeah, I'll uh oh sorry, Rex. Um I'll add in a little bit about the the drainage. Um so part of the next uh effort on this design, we've we've completed the 65% and we're working towards final design. And and I mentioned we're gonna be replacing those bridges. And so we're doing a full hydraulic and hydrologic analysis on on the entire area as part of the final design. Um we're kind of we feel like we're really getting dialed in, honing in on our preferred alignment, and now we can start assessing what those hydraulic impacts and where the drainage is going to end up, and kind of settling on a design storm and what's an acceptable level of water crossing uh the trail uh and and how do we mitigate for those sorts of things.

SPEAKER_04Um there are there are some uh standard plans and standard drawings that the U.S. Forest Services has put out for like stream crossings on trails and stuff like that that we'll be considering and and wrapping into our design uh for the next submittal.

SPEAKER_10And I would just add that uh in regards to blasting, we're gonna be following and adhering to kind of standard the standard of practice in any other given uh state or uh condition for a highway or a project, where we're following geologic design manuals and procedures for limitations on vibration and air over blast pressures. Um we'll be including monitoring and equipment uh for you know having to prescribe test blasts that are smaller in nature to demonstrate the means and methods, um, you know, stipulations on specifications such as zero fly rock, uh exclusionary zones, uh, you know, the standard you know, warnings and and bells and everything else that go along with it, um, with proper public notification and uh communication.

SPEAKER_10So and then and then also key difference of blasting, uh, such as with the rock slide area or uh what we call as popping, where you use a singular charge, um, which is also underneath strict guidelines, um, but is done more frequently. And uh there's you know, it's just a singular charge, just a break of boulder. We call it boulder bustering. So that's what mostly will be used along the axis area.

SPEAKER_03Um number 10. How will tree and forest canopy removal be limited? What restoration is planned, and how will slow wildlife and invasive plant impacts, including white sweet clover, be monitored or prevented?

SPEAKER_06Yeah, I think we touched on this a lot during the presentation. I think um, you know, we we've we've selected the alignment, um, trying to follow existing access to to generate the the least amount of impacts that we that we can. You know, I you know, with with the with sightwalks we've been doing and and the ground truthing we'll be doing here, you know, we we're pretty confident that that our impacts, you know, with the exception of some of these larger fill areas, are gonna be are gonna be minor. Um and we'll be able to, you know, we have our design, but we'll also be able to kind of when we're out in the field and constructing this, we'll be able to field fit some of these things and try to avoid um, you know, with with the help of granite to make sure we're not creating chicanes that are too hard to negotiate, but um we'll be able to we'll be able to do that.

SPEAKER_06And then, you know, for all of the other uh revegetation and and um you know all these you know the the environmental impacts, the invasive species things, those are all be folded into our design specifications and we'll be following um you know accepted standards that that are used all over the state um to you know to manage that.

SPEAKER_04Yeah, I'll I'll add on a little bit. Um there uh there are some standard uh uh requirements and and special provisions about invasive plant species that we're planning on including with the project. I don't know if we'll do an invasive species survey um prior to construction or sometimes we we uh uh require the contractor to hire uh biologists or botanists to go out there and identify those invasive species, make sure they don't get propagated and spread. And then, of course, I mentioned we're gonna be planting those native species that um that thrive in this area.

SPEAKER_04We'll be using certified weed-free um grass seed where we're doing some grass seeding uh and and trying to make sure that we're only putting back the the right plants in the right place.

SPEAKER_03How will creek mouth brook trout spawning habitat, including areas around the bridges, be protected from construction runoff? And how will adjacent wetlands, streams, and wildlife habitats be protected?

SPEAKER_14So um, yeah, we all I think everybody that lives here knows the brook trout are spawning in that stream uh near the uh some of the access that's gonna be constructed. Uh and uh Kyle has a team up there, had a team up there. They've looked at wetlands, they're looking at the bridge crossings, they've been working with um Alaska Department of Fish and Game uh and going through the NEPA process. Um the NEPA process will go through and identify what the environmental impacts are, and then that will push into the permits, whether it's uh you know Section 106 permits, there's a list of permits.

SPEAKER_14You know, there's fish habitat permits. We know that uh Brook Trotter Not anadromous, Clean Water Act. Uh right now the wetlands that have been identified don't have a nexus to U.S. waters. Um, but uh the whole process will be taken through NEPA and then the permits will be identified. Um it's federal funds, so it'll what's that?

unknownImpacts.

SPEAKER_14The impacts will be identified, and uh the the permit process will be followed through the federalization process. Um and I, you know, then I could list there's a there's a bunch of permits, but they will be decided as it goes through um which permits are required and which are not. Um, and you know, things like 4F will play in if that um does come to fruition in there to address the park service. Uh and I don't want to go through and read all the permits, but uh I think that's probably plenty.

SPEAKER_09And then just to add on the general construction sequencing of the bridges is that again, we'll have to be permitting the process at which they would be built, identify impacts, identify any mitigation that would have to be done if there was any uh work that needed to be done within the habitats. And then, of course, just regular um best management practices are held. We're not just ripping out ripping apart the streams to build the bridges, it's all as low impact as as possible.

SPEAKER_04So yeah, I'll butt into uh uh well uh uh in in Alaska there's the Department of Environmental Conservation, which is kind of like a mini EPA, and they issue a construction general permit for any any project uh that basically forces the contractor to uh prepare and maintain what's called a stormwater pollution prevention plan, a SWIP. Uh and so that that SWIP that the contractor is going to create and maintain is gonna identify any of those potential um pollution and runoff sources.

SPEAKER_04And then uh, like Ed mentioned, they'll have to install BMPs, best management practices, which could be uh SILFENS or fiber rolls or compost socks or any number of options that are intended to keep that that runoff and that sediment from from ending up in those streams. And so that's all that's all kind of standard boilplate uh construction specifications that we'll be uh that we'll be including in our project. And granite is very familiar with doing all those things. And so uh that that is all kind of, like I said, standard practice. And uh I guess I'll also mention that those SWIPS are um reviewable and available uh to the public if you want to go out there and and make sure that Granite is is following the construction general permit and all those sorts of things.

SPEAKER_04It's like a thousand pages long, so um make sure you give yourself lots of time to flip through that.

SPEAKER_03Um I think you touched on this answer, but I'll read it out anyway. Uh question. Which federal and land use reviews and permits apply, including the possible Tongas National Forests, National Park Service, NEPA, Section 106, Section 4F, and FEMA requirements. And has the Skagwa Traditional Council been consulted?

SPEAKER_14I think I kind of already bowbled through those and those will get identified through the NEPA process of which ones are going to be required. So I wouldn't want to speculate on all of them at this point, but there will be a thorough process and they will get identified. I cannot tell you whether the Traditional Council has been um engaged with or not.

SPEAKER_04Yeah, and I'll I'll add in a little bit that uh since this project is funded by a FEMA grant, um, FEMA is the the lead agency on the NEPA process. So FEMA, they have uh uh I think it's the EHP, the Environmental and Historic Preservation Office, um, that's leading the development of where we're assuming is gonna be an environmental assessment in EA. Uh and during that process is when they'll go through and do that coordination and identify that which permits are required. And so uh our team, our our job as the design team is to give them the information, identify our impacts, identify our design, and then they're gonna take that and prepare the NEPA documents and then help us with those permit applications.

SPEAKER_03Okay. Um this is question 13. What supports the safety of berthing ships forward under the slide area now, and what risk will remain after mitigation?

SPEAKER_10The ships are currently slid backwards uh as part of the safety measures for them, but the safety measures that protect the general area for the ships uh is a suite of instrumentation monitoring that's on the current ill side, including in tilt meters, excessometers, and uh prisms that are shot every 15 minutes to 30 minutes from a total station down near the uh state ferry terminal. Uh and in and in combination with a DSSMR, which is just a big fancy acronym for a uh instrumentation monitoring plan for the dock slide safety, um, where during the cruise ship season, uh a suite of uh professionals, I hesitate on that word because I'm included in that list, um review the instrumentation uh each morning prior to a cruise ship arriving.

SPEAKER_10And we have staff that go up on site to document the state of the rock slide and check uh physical measurements as well as those that are online through the instrumentation uh to confirm the lack of movement in the last 24-hour period and uh or the last week as well, because we review longer time periods. And then um that's against the larger rock slide movement, and then for the cruise ships for the smaller rockfall occurrences, we have done an extensive suite of rockfall modeling and have emplaced uh drape mesh on the top of the hillside, a mid-slope attenuator and a lower slope attenuator, and an on-dock 500 kilojoul flexible rockfall barrier fence with a sand dampening field.

SPEAKER_10Um, all to then capture and slow down uh what rockfall may occur that would be smaller than what is being captured reflected upon by the instrumentation. So that is our current set, and that takes the cruise ship protection uh well in exceedance of any highway uh standard or practice or design manual across the nation and gets us into the top tier of internationally recognized Rock Mechanics Society's recommended um probabilistic hazard levels.

SPEAKER_10So you're a plus star all the way across the board for that. What will risk will remain post? Uh the rockfall hazard will still uh currently be there, which is why rockfall mitigation measures will still need to be in effect, but the rock slide hazard will be uh massively reduced and eliminated through its removal. And so then the cruise ships could slide forward into a more forward-position berth, and that would be the risk post.

SPEAKER_03Um, Your Honor, the next uh five questions are for the manager if that's okay. Yes, manager Deach. Um number 14. What is the current project cost and schedule? And could construction be completed in one winter?

SPEAKER_13Um so currently uh the the last cost estimate we had before the 65% um design phase was about 65 million for alternative two. Since that time, based on the 65% drawings, what what we were required to do by our FEMA grant was to get an independent cost estimators uh estimate. So right now we have the engineers estimate, we have the independent independent cost estimators estimate, and we have granite construction's estimate.

SPEAKER_13And we're going through the process of um analyzing those. And I'm I'm not totally clear on what that process is, where we need to compare them to each other to make sure that the cost estimates we're getting are realistic as to actual constructibility. I would say though that the current cost estimates, you can shave$10 million off of the 65. So we're somewhere we're more in that range. Um according to the 65% estimate of alternative two.

SPEAKER_13So if the project changes, that that would change as well. Um the schedule, I know we would could optimistically, and please correct me if I'm wrong, because I think you guys are more familiar with this too. Um, I think optimistically we could start fall 27. And that's if all the permitting goes through in time. So really what we're waiting on right now is the NEPO process. Um, we can move, you know, we have to get through certain steps before we can move forward from 65% to 95%.

SPEAKER_13And um FEMA has certain go no-go points. And the first go-no-go point was I'm getting a little beyond the question because it'll help me answer another one. And I won't have to explain it then. There's no go-no-go points. Um, the first or one of them recently was um the alternative choosing an alternative and doing a benefit cost analysis of it. So we got the four alternatives that they whittled it down to four.

SPEAKER_13We chose two, or the assembly chose two, and so we were required to do a benefit cost analysis. And that weighs, you know, what is the quantitative benefit in dollars of the project, and what is the cost of the project? So that bent BCA came out to be it's a feasible project, it's worth the money, right? At for alternative two. And I stress, please correct me if I'm wrong, because you guys are the experts at this.

SPEAKER_13Um, so that was a no a go-no-go point. The next one is going to be when we get to 95% design. So we're in that spot between go-no-go points where FEMA can say this isn't gonna work or this is going to work. Um so that's where we're at. And we need to get through that and get through through the NEPA process, which is required before we can start doing anything very optimistically next fall, but realistically, probably later.

SPEAKER_13Um, construction, could it be completed in one winter? I think, yeah, we're planning on two seasons, and everyone's shaking their heads that it could not be done in one season. Uh remember considering that the season is basically October, you know, whenever after the last ship is through as long as you can go in the spring before the next ship or before the first ship comes and there'll be weather issues and stuff.

SPEAKER_13So it it's a two-season or season project.

SPEAKER_03Um number 15. Were competitive proposals sought from multiple engineering firms, or were design alternatives developed all by one firm?

SPEAKER_13Um I think the the answer is yes and yes. Uh so the FEMA process, we're required. Well, we're required by we have uh procurement processes in our code that we're required to follow. We have to follow the code about regarding how we you know procure services, um, as well as the uh FEMA requires that we follow federal procurement processes, which just happened to be about the same as what we have in code, luckily.

SPEAKER_13So, yes, we did um we put out an RFP, it closed March, end of March in 2025. We received one proposal. It was scored as we were required to do by the RFP, but one proposal from Shannon and Wilson. So Shannon and Wilson was awarded the contracts, the assembly approved the contracts, and they have subcontractors that they work with, uh HDR, KPF. Um, but they have the contracts.

SPEAKER_13So, yes, one uh firm developed the design alternatives with the help of their subcontractors, but we didn't go out to competitive RFP.

SPEAKER_03What indemnification agreements or liability protections exist or are proposed for the municipality, White Pass and cruise operators, and would the municipality proceed without White Pass indemnification?

SPEAKER_10Emily, I'd like to add to the previous question. Uh in our meeting in Seattle when between uh representatives uh from the cruise ships and then also White Pass and then the the municipality, uh during that meeting, the collection of geotypical engineers represented by Shannon Wilson, Delve, Underground, uh Blackwood, and Halen Aldrich uh did all collectively discuss alternative mitigation measure measures at that point in time.

SPEAKER_10Although I will admit and state that those were preliminary as as that was prior to a lot of evaluation and rock hole modeling. But those mitigation measures were largely in line with what was in uh presented as our four alternative measures later on.

SPEAKER_13Okay. Thank you. Would the municipality proceed without white pass indemnification? I think that I ultimately how the project goes is up to the assembly, but I think the answer is no or this is what the assembly has has expressed before. I think it's a risk not to uh from a just a liability and safety uh liability and risk uh perspective um so what indemnification agreements or liability protections exist indemnification agreements we are working on we're expecting a draft from the attorney uh from attorney Brenna for a um an agreement with white pass for this project and who's responsible for what how the risks are being mitigated what happens if some you know we're we're gonna cover all of that in an agreement which will come to the assembly for approval uh and it will include indemnification um liability protections I think right now I would say that is our general liability insurance um we've got you know we're we're insured appropriately for general liability and various we have various policies that sort of cover us so I I don't know I mean I wouldn't rely just on that for a project that has risk like this um let's see I think um so we're working on agreement an agreement with white pass that will include indemnity indemnity which will come to the assembly for approval cruise operators using the railroad dock we don't have birthing agreements with them because it is not it's a private dock so I don't know um what sort of agreements there are between we do have use agreements where they have if they use the port which I think is you know while they're in port they need to do specific things and agree to the tariff and all these other things um but they would have an agreement with White Pass for use of their dock.

SPEAKER_13And so I don't know the answer to that. I think that's it.

SPEAKER_03This is number 17.

SPEAKER_13What liability protections or risk notices have been considered what coverage applies to the consultants and how have other communities handled similar risks um so I covered it a little bit right now liability protections includes our general liability policy uh for the municipality um and I'll have to look and see what you know what those claims what it cut up to what amount it covers um I think it's pretty big.

SPEAKER_06Um coverage applying to the consultants um we have contracts with the consultants and they are required to hold insurance um per the contracts including like um professional errors uh I think I don't know if we have an in uh environmental clause in yours or not but um they're required to hold insurance for their work and I don't you can probably yeah per the contract requirements we we hold professional and and general liability and the professional liability includes um coverage for work products uh technical products errors and omissions and you know technical issues with with the products we've produced and the general liability is all of the um you know all your stuff like that doesn't fall under that umbrella that that covers us but um you know we have we have that coverage that's required of the contract with municipality and then all of our subs are required to carry the same coverage um and so that's yeah it's per the contract.

SPEAKER_13Yeah and it's our standard contract. How have other communities handled similar risks? I know these sorts of things are happening all over and I think you probably are aware of other mitigation strategies that other towns have used. I know they're continu the risks are continuing to happen um and basic from what I know like in Ketchikan they have a slide and they go and clean it up you know they do studies they I think we're doing what is typical for I I don't know that any of them have this particular risk of a massive rock hanging above the port.

SPEAKER_06So yeah I it just I the the hazard that exists here that you guys are dealing with is is unique. Um and and I and so it it's there's there's kind of a it there's a different It's difficult to comp compare it. You know it's there's difficult comps out there. But I will say based on my experience in in dealing with other hazards and other communities um I I think that the approach that the municipality is taking taking here is unique and that you're being proactive about it.

SPEAKER_06I see a lot of a lot of communities are are a lot more tend to be a lot more reactive um and and you know wait for things to happen and then and then react to that and and so um so I think it's another unique aspect of this project and how you guys are handling it. I think I think the the proactive approach is a is a good one because you know typically it's a lot it's a lot cheaper and and a lot cleaner to deal with things um before they happen rather than waiting especially for something that's such a significant consequence here um and a and a and a difficult thing to anticipate you know when it's going to happen.

SPEAKER_06And so um I think that's it's a unique situation on both ends.

SPEAKER_17Okay.

SPEAKER_03This is the last one for the manager. What safeguards ensure that the project's engineering recommendations are independent of any financial incentives for additional work?

SPEAKER_13I think aside from it being completely unethical and something that I would not consider, as I said before, we have code that requires us to go through certain a certain process depending on how much it is, what the work is we have multiple approvals. I in code I can approve certain work only if it's already included in the budget specifically anything that falls into any sort of different category or a particular category then I have to seek additional approval.

SPEAKER_13And then certain things I have to the assembly has to approve it. So I there's plenty of safeguards in for how we procure services in code. The scope like the scope of work the we're paying for the scope of work that was agreed to and that is in the contract. And I it it just seems a I don't even know how to answer it almost because I just don't I imagine this maybe someone thinks that someone would come to me and say hey we'll do this if you give us a contract later or something like that.

SPEAKER_13And it's totally outside of our processes and totally unethical. So I I don't know how to answer it.

SPEAKER_02Different approval uh safeguards um are we have we get audited we have we get thoroughly audited every year um we have before we even cut a check it goes through many different checks you know so I think we're set up we have a great finance department who is very uh you know they've got all their policies out and we follow the policies um your honor uh the questions um uh six at the end here uh 19 through 24 um that um may go towards mayor and assembly um 19 uh what is the rationale for proceeding if rock fall hazards and limits on historic dock use will remain well thank you uh to go back to the rock slide in 2022 we were uh educated on a supreme court of Alaska decision involving a I think it was a rope swing in Yakutat that basically said um ignorance is not indemnification if you pretend you don't know something's happening and there's an accident as a government you're still liable so at that point you know we we we definitely discussed what if we don't do anything and um we were uh you know fully cognizant that that's roughly half our business uh that comes on the railroad dock but further than that for the safety aspect of of being proactive so you know we began with the process of of hand scaling and uh the attenuators that were put down and that's occurred uh I think every off season since since 2022 um you know huge effort uh at the same time we went into um negotiations and uh thus construction for the ore dock to protect our economy um but I think my my main answer is that we're trying to be proactive and that this is the first step in being able to get that the railroad dock back into function.

SPEAKER_02To have pedestrians as I understand it, there will have to be an additional 500 kilojoul attenuator put down there or a very large um wall of sorts. And who pays for that is something that we're definitely going to have to straighten out with Whitepass. I think that's we're we're we're in in very good communication with White Pass right now about how to get back to that historic dock use. But we definitely understand that's their desire um at least to have pedestrians be able to use the railroad dock again.

SPEAKER_02In the big picture, you know, if we have a cataclysmic failure on the mountain you know we're losing a lot let alone life but small boat harbor I think the ferry floats in stake um it's kind of hard to predict what happens if you have that kind of and I'm I'm gonna you know be doomsday but we're talking about an earthquake probably or a big tectonic slip um and that's you know a very awful scenario you know our whole town is based off the port.

SPEAKER_02So I think we're trying to be proactive and this is a very large step in how you'd address the first phase of it. Number 20 how does the assembly weigh public spending and White Pass's financial responsibility against the docks benefits, tourism demands and effects on Dewey Lake's recreation and residents' quality of life well I would be uh I would by every uh consideration the the Dewey Lakes recreation area is a sacred area um and I think that if anyone is you know give an honest listen to what's happened here tonight this this trail access is is uh trying to minimize that impact uh but getting excavators and equipment and thousands of pounds of steel and fuel and people up and down to do you know move remove 30,000 cubic feet of cubic feet or cubic tons cubic yards 3000 washing machines more or less um takes a lot of work takes big equipment and especially to do that in a in any kind of um achievable timeline um you know it it it's not going to happen with picks and crowbars uh that's not that's not real you know to to reroute the course of geology in a mountain takes a pre-herculean effort so uh in terms of public spending um I mean I'll I'll roughly break down where we sit right now to my understanding and this is by no means you know Heather would slap me pretty hard if I did this in an assembly meeting but 20 million or so from the BRIC grant I think we'll by the time this can starts we'll be around uh 20 million from um from from the vessel impact fee that we've we've put in reserves and saved which is five million a year um and the nine million that I lobbied for uh and we received from the state legislature so that gets us close you know we're up we're up at close to 50 million um you know another year goes by another five million from the vessel impact fee um so this is not coming from sales tax we're trying very hard to make this coming from you know both grants and the users and to get that you know has been quite an effort um I I I know how hard we worked on the brick grant I know how many businesses I went out and recruited to write for that uh how well we worked with Princess and their grant writer to get that money um will it be easy dealing FEMA?

SPEAKER_02I think it will be very difficult. Uh it's also their first time dealing with this kind of process in the state of Alaska were the first one to be awarded the BRIC grant. Very recently we voted to raise the vessel impact fee substantially to meet our neighbor KetchCan's fees and those will remain this does this these vessel impact fees will not sunset the way it's written in code but we took it to um 28 and 29 to meet what Ketchikan's doing.

SPEAKER_02So on the white pass financial responsibility side of it I think that 500 kilojun tool or fence attenuator is something that I I feel they should be paying for because it'll be on their dock and you know I think we're gonna have to get an agreement of continual maintenance of the rock slope which is probably falls on the municipality and their dock is on them that's would be my take on it question 21 is the proposed access route a new road an upgraded road or a trail what authority under Skagui Municipal code chapter 16 point one two permits it and how could future road construction be prevented trail that's I think it's you know when I was young there was no icy lake trail it did not exist it was created in the 90s um I believe under Mayor Selmer um to get up to the reservoir and to help with the hydro you know maintenance up there and um you know this is improving that trail for a new risk a new problem I don't know that I can answer what authority we have in 16.2 but you know we I think you've heard tonight that we're trying to keep this aligned with the existing trail and not make it you know a different change more than we have to um I think it was a really good comment uh that I heard that by putting gravel on top of the trail it helps protect the trees something that uh I think you know we've got a real good team that's looking after um trying to be as as uh conscious of of the um the trees as and and the nature as possible um I don't know John maybe you could talk about the trails plan and how that ties into that but I don't think it's anything different than what we've always had in charity by all means weigh in.

SPEAKER_01So uh at the end of this we've heard here tonight multiple times that the the end uh goal for this is is not going to make this accessible to my truck um it's not going to make it accessible to a standard vehicle and therefore it isn't a road um in my uh estimation it is uh a an enhanced trail i uh obviously all of the major erosion uh marks that we've seen along that access trail uh over the past uh decade are are going to have to be fixed and some of the rocks that I do love very dearly are going to be scaled down but at the end of the day this is not something that is going to be accessible by uh a standard vehicle and I would not be uh opposed to ensuring that we don't have some local cowboys with their modified Toyotas wanting to go up that road and create havoc I wouldn't uh mind looking into creating some kind of a barrier to keep that trail a trail uh that I think Your Honor this is something that I've been thinking about a lot um there is aspects of um Lower Lake that where um motorized ATV usage is allowed um one of my concerns and I guess that comes back to us um I think we've seen it um in other projects I think it's on us to make sure that this doesn't um create a I am not going to use a rock slide uh a rockfall metaphor um of you know increasing usage of an improved trail that is is it's going to be put in to accommodate large vehicles so I I think that would probably fall on us too I don't know once again this is something that just popped in my head today um possibly shore up the Lower Dewey Lake um management plan just to ensure that um this road you know I I I I do have concerns about um groups coming forward with oh well now you have this road that can accommodate my ATVs so let's open up access to ATVs um that is something that's on my mind and I think we can um explore um you know kind of showing up the updating the the management plan um is something that I'm thinking about.

SPEAKER_01But at the same time while this meeting has been going on tonight I've been thinking about how this will also really open up um um greater use for mountain biking there. You know the the folks from Whitehorse our spring happens at least a month before it does in Whitehorse and they are real sporty people and they like to come down mountain biking. So um you know there's I I think there are positive aspects of trail improvement um that can help with our um recreational economy um but um but I'm not gonna let go of you know concerns about making sure that it is not expanded um motorized access.

SPEAKER_18Thank you Your Honor um I I mean setting a rock at the bottom of the trail that's been the way that there hasn't been any vehicles up there other than ATVs. Um as of now yeah the the ATVs have been going up to Lower Lake I've been taking mine up there all the way to the helicopter place. Um it I mean we're already using it for ATVs, but what it'll do I'm thinking is take the ATVs off of all the walking trails and the trails right along the lake and everything.

SPEAKER_18So I I could see how that could be a benefit. But um yeah, I d as far as not getting it used by trucks and everything else, yeah, there's always been a rock right at the bottom by the water tanks. 'Cause the public works goes up there with a vehicle to the water tanks to do maintenance and things. So that's my two cents.

SPEAKER_12Thank you. Um I just I'm I'm stuck on a word here. I'm stuck on the word road. Um because people keep calling it a road. Okay. These plans that we've seen have called it a road. We can't expect our community to not go up in arms and get upset when what they're being presented with is being called a road. I get it. If we want it to be an enhanced trail, then that's what everybody in this process needs to get on board with. Um, because I don't like the idea of a road when we call it this.

SPEAKER_12Um so I think that that's just something that we all need to be mindful of. If we if we don't want the community to view this as a road, then everyone needs to be on the same page and change our wording and change our verbiage to be mindful. Because our words up here, our words in this construction phase and design phase, it it really does matter. And that's what's gonna really spur a lot of people's strong emotions about these building plans and what we're doing to the lower Dewey Lake Trail system, because it is a special resource that people care about.

SPEAKER_12So I just want to point that out because I I do think that distinction is pretty important why people might be feeling the way they feel.

SPEAKER_03Um number 2020 22. Um at 65% design, what alternatives remain open and how will public concerns, including feedback from the guided hikes, be recorded and considered?

SPEAKER_02Can I defer that to the design team? I don't um I know 65% is a significant threshold, but how it advances past that I would I would defer to the design team.

SPEAKER_06Yeah, so so the 65% design um at that stage, we you know, we kind of see that as as establishing our project layout uh footprint and impacts, which is used for the permitting process. Um and so from 65 to 95 percent, we are we're fine-tuning the design and you know, dotting our i's and crossing our t's and and and making you know, making everything kind of kind of fit and and and getting it all sorted out, all the specifications are are developed at that point.

SPEAKER_06Um and so um, you know, that's that's where we're headed at this point. We've paused that process because of the feedback we've gotten now. Um and you know, in in reality, um we can do whatever you want us to do. Um we can we can make wholesale changes and and and start from scratch. Um you know that has cost and schedule implications that that would need to be discussed and and uh and and so um you know right now we're we're operating under we're taking alternative two based on our based on approval from the assembly in the summer and and barring any any changes in direction as a result of of this um these meetings and the site walks will continue along that route.

SPEAKER_06If if after the site walks um you guys want to discuss changes or other alternatives, you know, we we we would we would handle that as needed. Um the the site walks um we'll be having those. Uh we'll we'll be recording notes. Um any feedback that is has that is uh resulting from that, we'll we'll bring it all back, compile it and digest it. And and then I'm sure we you know we have meetings, um, we've been having meetings two or three times a week with the municipality these last month or so, um, working through these issues.

SPEAKER_06But um we have regular meetings for planning and amongst the design team and with the municipality to coordinate, and and I'm and I have no doubt that after this trip we'll be discussing how we go forward and and um and and right now, like I said, we paused the design to handle this and then and then we'll pick it up when when it's when it's done.

SPEAKER_03Thank you. Um number 23. Why hasn't a citizens ad hoc committee been established and will the assembly consider a community vote on the road proposal?

SPEAKER_02Um I would assume that means a mirror ad hoc committee. And I would say that until the 65% design came out, it would have been premature. You know, we really didn't have the level of detail to uh people to really uh give a lot of input, I would say, you know, until I mean we had to do LIDAR and all kinds of things to even really be able to analyze the the conditions of the mountain and um best method of dealing with it.

SPEAKER_02Uh I think there were different concepts of how to deal with it for sure, and and I think it would have been premature to to speculate on the citizen side of it before we had the real you know expertise of of of advising us how to how to move forward. Um I mean helicopters are an option. I it's an expensive one and it will be a very long timeline.

SPEAKER_17Um vote on the road proposal tab, I'm gonna pass that to you.

SPEAKER_01Good thing I'm still paying attention. Um this uh this weekend um kind of garnered a lot of uh um social media interaction, engagement about this important issue, um, which isn't my favorite way, but um, you know, I think we have to acknowledge it. It's a way that people engage, and um engagement is is what we are after here.

SPEAKER_01Would we consider a community vote on the road proposal? I think what I read at some point this weekend, um, you know, it kind of came down to some of the talk was if if we don't do this enhanced trail, um then the really the only alternative, what I'm hearing, would be a the highly expensive helicopter option, um, which adds a lot of cost to the project.

SPEAKER_01Um and that is furthered by the complication that this is all permanent, not under the municipality of Skagway, but FEMA. So it's kind of like FEMA is running the project, not so much us. We have input, obviously, we're figuring out the design. But um when the costs escalate, then there would be another, um, I think as as Kyle mentioned before, um, there's another cost-benefit analysis that has to happen to um to keep us qualified for the BRIC grant.

SPEAKER_01Um and if it gets too costly, then it doesn't pass the cost-benefit analysis and we lose the BRIC grant, um, then you know we don't really have to make that decision, except we are still left with a situation in which I think really what it comes down to, and and I think the question that I appreciate appreciate the most is how do we weigh public spending and white pass's responsibility, the benefits, the costs, quality of life.

SPEAKER_01Um what we can what we can't shy away from or ignore is that we have a giant hunk of rock that is not a matter, as the engineers have told us, and I am not an engineer, and I do tend to trust science and data. And what that has told us is that it's not a matter of if, it's a matter of time of when it's going to fall and cause catastrophic damage.

SPEAKER_01It might be past the time when I'm on the assembly, it might be past the time when I'm in Skagway, it might be past the time when I'm alive. But um, for me not to do anything about it would still hold me um culpable for um for some some very serious damage and and possibly loss of life. So the the fact of the matter, it does appear before us is that we have to do something. Um so when thinking about how to take that to a public vote, um, I'm not here to rule anything out.

SPEAKER_01I think we would just have to discuss exactly what the question is. I think we've recently learned a lesson of what happens when a question is not worded um um uh accurately. It comes with some complications. So I think we would have to kind of it would have to, you know, we would have to look at what exactly is that question that we were taking to a community vote. Um I don't think any of us up here want to do anything that the community is absolutely opposed to.

SPEAKER_01So how do we measure that against, like I said, we have to, we, we have to address um the rock slide. Um so I guess that is a maybe the most politician answer answer I've ever given. Um I think I'm starting to feel the 937. Um you know, I'm I'm not here to say no to to the community. Um, I'm just here to to gather information and and hopefully the community gets more information.

SPEAKER_01And you know, we're still we're at 65 percent, so definitely have a lot more answers when it comes to 95 percent. Um, once with the the hydrology report, that's gonna um reveal a lot. Um, and if the sentiment is strong enough that we want some community vote, then um I would be opening open up to uh open to to looking at what that would look like.

SPEAKER_02Thank you, Charity.

SPEAKER_11Um thank you, Your Honor. Thank you, Your Honor. Um obviously we would want to uh make sure that the community is on board and kept on board um throughout this process. Um I uh I say process, but we're looking at in my mind, two things. We are looking at that the the rock slide, the constant rock slide that uh is uh movement of mountain is erosion, is all sorts of things.

SPEAKER_11And then we are looking at ship rock. And either both of those things um require us to get all of that equipment up to the top of uh the mountain. But more importantly, in my mind, is I'm gonna keep calling it ship rock. Um if that, not if, sorry, when that comes down, that wipes out our waterfront, that wipes out our small boat harbor. That is a potential for a catastrophic loss of uh life and livelihood here in our community.

SPEAKER_11So in my mind, um putting this off uh and saying, well, let's let's stop now and let's take this to a vote. Um I would want it to be a more narrow question. I would want it to be uh a question that we are not um all in agreement over. I wouldn't just want it to be, should we just abandon this now?

SPEAKER_11Because again, that big rock that we, especially those of us who worked extensively on the railroad dock uh and stood under and looked up at and and hiked to, and I've never stood on it because I'm chicken, but watched our crazy friends stand on it. Um that rock has the potential to take out what we know of as our lives here in Skagway. And to me, that that is the purpose of our government is to make sure that we have the well-being of Skagway and uh the residents of Skagway and our ability to live here uh always um that we are preserving that, we are continuing that.

SPEAKER_11Um, and that portion to me, should we just let this rock come down and take out what we know as our life and livelihood in Skagway altogether? Why would we even put that to a vote? That question. So to me, it would have to be a much more specific question in order for me to consider like, do we need to take this to a vote?

SPEAKER_17Thank you.

SPEAKER_03Um last question. Uh will residents have an opportunity to speak and discuss the project at another public meeting before final decisions are made? Yes.

SPEAKER_02Next meeting and probably more meetings after that. But I will, with manager Deach and the clerk's assistance, draft this so that we have something under citizens present that is specific towards the 65% rock slide mitigation design so that when you come up and speak, it's only about that topic. And then when you want to talk about school lunch or boardwalk issues or anything else, snow plows, garbage pickup, whatever it comes up, that'll be a separate um bullet on on the agenda.

SPEAKER_02Clark and I have talked about that, and we will make sure uh that that is uh well known. Um I know a lot of people were upset tonight that they couldn't, you know, say that, but we're here almost two hours and 45 minutes into it, and I wanted to make sure that the presentation was given time to be thorough and be informative without um uh without too many eruptions, or we never would have gotten through it.

SPEAKER_02So uh yes, uh I I very much will uh make sure it's on the next agenda, Greg.

SPEAKER_04Uh and I'd just like to mention that as part of the NEPA environmental process, there will be required public comment periods. Uh, if it's an environmental assessment, I think there are two separate uh comment periods that are uh again federally required. So those will be uh publicly posted and there will be opportunity for comment and feedback at that time too.

SPEAKER_17Thank you. Okay.

SPEAKER_02That has brought us through A and B on our agenda. We're now to see overview of guided hikes uh on uh November 10th and November 11th. Could someone from the design team outline what to expect, what to bring, what to what to do?

SPEAKER_10I'm just really excited for them. I'm probably not necessarily the best person to explain all what's going on to them. But yes, tomorrow at 10 o'clock and 2 o'clock, and then on Wednesday at 10 o'clock and 2 o'clock, uh the design team will be leading a uh total set of four. So 10 and 2, and then 10 and 2 on Wednesday. Uh hikes along the enhanced trail, uh segments A, B, and C to the top of the rock slide. And the whole point will be to have an open-ended discussion with uh the anyone, council and then the public as far as the impacts, what the design looks like, to kind of go through the presentation that we have given here, which has a lot of moving pieces and a lot of things that uh were theater of the mind, if you will, as far as how they're described.

SPEAKER_10Uh, and we can point out we have a Jacob staff in the corner uh to demonstrate actual uh widths and changes uh that we'll be bringing along. Um so pretty please bring uh gear appropriate with the forecasted weather, which is cold, snow, something like that. Uh and and then good questions. And you will be met by me, overly talkative and cheerful. Uh Kyle, uh, Greg, and who else do we have?

SPEAKER_10Uh Brad will also be there with us, and maybe Micah or Micah, uh, to discuss uh the details in and outs of extents of fill, extends cuts, areas that are currently been flagged uh for improvements, um, and just the different sections and where we're talking about, oh, this area needs to be cut down from 45% to uh to a 30%. And then when we get to the rock slide, um, then I'll probably wave my hands and do a lot of talking and answer any questions that you have about rock mechanics.

SPEAKER_10So that's that's the goal. Mean at the the row tracks um at the bottom of right there at where the the trail starts at the road tracks at 10 o'clock, and we'll we'll start heading up very shortly thereafter.

SPEAKER_02Thank you. Um I got ahead of myself. I skipped B2 questions from the mirror in the assembly. Um and I see that Assemblymember Burnham has a burning question. So, Jay, go ahead.

SPEAKER_18I was just gonna remind you you skipped it, but I did come up with a question while I was sitting here. Um actually, this is something I mentioned earlier, but some of us bad old guys don't really like hiking up hills anymore. And I was wondering, just for fun, is there going to be some kind of a ATV, something accessible? Yes, I can still climb up a hill, but I'm just saying for other people that might want to, and it would also be a good experience to actually go up what is there, because I've gone up in a four-wheeler, it's gotten a lot better in this summer.

SPEAKER_18There was some uh routine maintenance done on it by the municipality. So it it is doable in a four-wheeler. If you had a six by, that would probably be more comfortable, or if the fire department could. So I was just wondering if there was going to be one of those available to do that.

SPEAKER_13Uh we hadn't planned on that, but there um I just got notice from the back of the room that there is a six by six that could be utilized. Um but we'd have to arrange that, I guess, figure out the details of that.

SPEAKER_18I just think it would get more community uh participation if if they knew that there was a backup plan if they couldn't make it.

SPEAKER_13I would be I mean, I don't know if we have to worry about liability carrying people up if they fall off or something. That's of course that's all I'm thinking about, right? Is that someone's gonna fall off. But we can we can see look into it and see if we can make that happen.

SPEAKER_06Yeah, I I would add that that we will be on foot. Um we we will not be operating ATVs for the reasons that that Emily um has expressed. But if if people want, if it's a you know BYO um ATV, you can if you wanted to do that, wouldn't we won't stop anybody? Um so so certainly.

SPEAKER_18Yeah. And I did have one more question for the the I guess the gentleman in charge of the construction kind of thing. I'm sure that your forte is the big rock and getting rid of it and all that kind of stuff. Are you also gonna be in charge of the doing the the trail improvement for going up to the site? Yeah, absolutely. Um, okay, then I the question I have, have you done something like that before?

SPEAKER_05Uh we have, yeah, as a company. Yeah, we have people that are pretty familiar with uh some of the like remote trail building type environment.

SPEAKER_18Okay, and then that all led to this question, which is have you gotten complaints about the way that you left an area when you were done doing what you do? And if so, did you correct them?

SPEAKER_05So um so I'll speak to some of my experiences, and I you know I try to use uh examples. So um, you know, I worked on a project in the Kenai National Wildlife Refuge on the Sterling Highway um probably 10 years ago. And part of the challenge with that job was um finding gravel. And we uh expanded and worked with the Kenae Refuge on expanding and utilizing their site for a gravel source and then reclamating and restoring it uh at the end for uh long-term vegetation and use.

SPEAKER_05And we actually uh did a five-year monitoring program at the end to make sure that all of what you know the plan was took over the course of the next five years. And I can tell you that uh, you know, that's all closed up, and that site is, you know, obviously after 10 years now looking much more not like a gravel pit anymore. So what I can say is do we do do we get complaints about how we do things? I would say that's probably a fair assessment. Do we take care of complaints?

SPEAKER_05Uh absolutely. I uh the the one thing I will say you can that I can confidently say about granite is we will do what we say we're gonna do. Um, we're we're very conscious of the goals of a project, and it's not about what's best for granite, it's about what's best for the project. And what's great about what the group here has done is they've created this project in a collaborative environment where people are brought on early to get involved, and we're gonna do everything on the front end to make sure that everything on the back end is successful and uh no shortcuts are taken.

SPEAKER_05So I can say that the process is set up for success here, particularly with all the players in the room and the way that it's done.

SPEAKER_18Thank you.

SPEAKER_02Assemblymember Hillis.

SPEAKER_07Thank you, Your Honor. Um this is a question that I've been asked a couple times, and it I feel like it should be asked. Um there was uh there were several options given to us for this project, but there was one that that's been used around the area for mining and stuff that wasn't on there, and I'm just curious if you guys know why, and that's a cable, um, like a cable car type thing. I had the unfortunate experience of working in a logging crew for a while, and I've seen the big cables that have run huge equipment up very steep slopes.

SPEAKER_07I'm curious why, or if that is just not an option in an area like this.

SPEAKER_05That's a great question. I've I've I've actually brought up the idea of a trolley uh uh uh system of some sort. Um I don't think I have a good answer for you on that. I I'll be honest. Like, I I don't know that we've necessarily looked into that process. I haven't done that personally, um, but it's probably worth exploring. Uh people that maybe have some expertise there. I we we've wenched equipment before, and to be quite honest with you, we're probably wenching stuff up even on the current trail design as it is uh at a 30% grade.

SPEAKER_05Um but if you're talking about everyday access for people and gear and equipment, I just don't know that that type of system is is is good for like daily use. I mean, it may be good for like initial access, but if you're constantly going up and down, I do we are very cognizant of the safety of employees and workers and getting to work every day is is as important as anything, and making sure that people uh go home with the in the same way that they came to work.

SPEAKER_05Um, and so that's also very much on the on the forefront, as much as you know, making sure we're not impacting the environment of the of the sit of the community too. So I I really think all things have been taken into account. Um, but I I think I'll take that one back to my team and just you know make sure that we're checking in on some of those types of ideas as well. So thank you.

SPEAKER_07Thank you. Go ahead. And I have a follow-up question actually on the the trail this time. Um on I I go up there all the time in the winter. I I love the winter up there. And uh one of the things that I've seen happen multiple times is lower lake overflow in the winter. Um, it freezes around the outside edge as lakes tend to do, and then there's still flow coming into it, and it causes it the um culverts and what are there block up and it flows over the road sometimes over the existing trail, um, sometimes to mid-calf deep for quite a section up there.

SPEAKER_07Um how will that be handled with a built-up trail? Will it just be raising the trail up, which would cut off that water from going across the road now into the the marshy area area closer to town? Or would the culverts just be larger? Is there a plan for that type of overflow?

SPEAKER_10Um I just wanted to uh add on to the the previous question if if if that's okay. Um we uh the team had looked uh preliminary at such things as an aerial tramway or cable car system. Uh and while perhaps in a deeper dive review, and I would I certainly welcome our compatriot here to to dive into that and come back with some numbers. Um our preliminary look into it was that it was uh exorbitantly expensive.

SPEAKER_10Um a similar aerial tram cable car system was as completed or scheduled to be completed in Colorado for height and elevation offsets and not even close to the same loads that we would be needing. And they finished theirs for$70 million. Um you look to Europe where they do these things a lot, and they're all in the tens of millions of dollars, and that it would access. And then as is also brought up in that round tabletop discussion, is oftentimes these systems need access uh to the top to get the large pieces equipment to install the tops anywhere.

SPEAKER_10So then it falls to that helicopter cost to construct the thing than to bring up the non-helicopter construction things. So it's a little murkier, loopy on that one. Um, but we will definitely look into it deeper. I think it's worthwhile um uh to then flesh it out. But I just want to present all the information that we had at this point in time.

SPEAKER_04Yeah, and I I pulled up the the role plot here. Um I guess if you could identify like where where the freezing and flooding happens, that's something we certainly want to know about and and mitigate against.

SPEAKER_07Yeah, so it's from crossing 11 to just before the uh crossing eight is pretty much all of flood zone. Maybe a little bit short of that, maybe like crossing nine. I I'm looking from a long ways at that map, so kind of guessing, but it's a pretty big area. It's just under a quarter mile that floods.

SPEAKER_04Yeah, yeah, uh you can't see it from there, but you can see there's like multiple creek uh kind of braided stream happening there. Um, yeah, and so our our plan includes replacing those bridges with you know the the steel girder bridges. Um, and that's kind of one of the hot zones that my hydrologist is gonna be focusing on and looking at what is the design storm. But icing is something that's hard to predict. And so having having input from you and other locals is gonna be great.

SPEAKER_11I I filmed a lot of it last winter. Um if you go to my TikTok, you'll see that I forgot my my spikes and I got to scooch on that ice. But yeah, it's it's pretty extensive and it isn't where the bridges are.

SPEAKER_04Okay.

SPEAKER_11So it's in between them.

SPEAKER_17Yeah, that's really good to know. Thank you for sharing that. Assemblymember Protter.

SPEAKER_01Thank you, Honor. Um, I just want to make sure I kind of have a a good vision in my head of what's happening. So the there's basically are there the there's the two vehicles? There's the um excavator and then there's the forklift um thingy. And are those those are not uh are those coming up and down daily, weekly, or are they just kind of staged at the top? What what is the actual um enhanced trail?

SPEAKER_01Uh what exactly does that traffic um uh is that traffic comprised of?

SPEAKER_06So I'll start, but Ryan I'll want to uh finish. Um the uh you know there's some equipment that's just gonna go up at the beginning of the season and stay up there and then come back, and then there's some equipment that's gonna be used to ferry people and fuel and and and things like that. Um and that's and so the the larger the large equipment is is only making infrequent trips.

SPEAKER_05The smaller track vehicles are are are making daily trips, but you wanna yeah, I would say people and fuel are the two most critical uh uh activities going on every day. Uh there is a you know, as much as you know, there's powder, there's things to do with blasting, that's materials, there's a significant amount of steel going into the slope. And the and you know, I was listening to the is this a one or two season job?

SPEAKER_05It's a one-season job, and then there's a whole season of bolting and dowel rock dowel work, which is you know, a million pounds of steel and a bunch of grout, and so that that'll be a significant amount of traffic up and down to do all those materials, you know, plus the couple hundred gallons of fuel every day. So it's it's it's a lot more stuff than you would probably think for just talking about excavating a rock slope. You think a piece of equipment and some people there's a lot more materials involved, particularly when it comes to all the the bolting or the rock doweling effort that happens.

SPEAKER_10And so uh Ryan, would you say that a Maruka is likely a similar type of vehicle that would be used to shuttle people, fuel, and then and or could carry uh steel if it's not on like a separate sledded uh concept or trailer.

SPEAKER_05Yeah, you I we're looking into this track Maruka vehicle. We've used them on steep slopes in some of the mine projects we've done. Um and you can build sleds for them too to bring materials up, but that would be right now, that's the the probably planned haul unit. If we can get some sort of an off-road forklift that would work, yeah, that's probably a possibility. Otherwise, it's uh people in some sort of an off-road, you know, side-by-side or four-wheeler.

SPEAKER_18Some of my member burnham. Just just to ask a little further on to that, um, that wouldn't be like round trip traffic all the time. That would be like a move in the morning to go up and work up there and then a trip down in the evening, or is this a back and forth kind of thing? Because we were just there was the the question of uh passing and and getting around people. I mean, it there's one-way roads all over the place to go up, you know, from this time and you come down from this time.

SPEAKER_05But I just I don't I don't know that I would commit to saying it's once up and once back at the end of the day, maybe for the people that are up there working, but it's not going to be like this this routing of it's not just constant construction traffic. I mean, it's it's one vehicle that brings some stuff up and then comes back down. I mean, maybe he does four trips. I I don't I don't have that answer probably for you, but I wouldn't consider it like just constant construction traffic. Uh I think the biggest impact that you would see is just during construction on the trail itself for that timeline.

SPEAKER_05And after that, there's just going to be ongoing, you know, sporadic traffic. Um, that's probably heaviest at the beginning of shift and heaviest at the end. I don't know if that answers. That's probably a pretty roundabout way to answer that question with a lot of detail.

SPEAKER_18You shouldn't specify by saying in absolute perfect conditions, and you've got all the planning, all the bugs. Made your four trips to the hardware, then yeah.

SPEAKER_10Uh Jay, I'll add in on similar projects I've worked on as far as um volume of material being excavated or linear feet worth of rock dowling uh that are remote and difficult to get to. We typically had two or three trips in in the morning with our equipment, and then it was it was like two trips out because one of those morning trips was just fuel, and then the fuel doesn't have to come back out because it's being used on site. So it it we had this heavier in the morning and a little bit lighter in the afternoon.

SPEAKER_02Uh assembly member Howard.

SPEAKER_12Thank you, Your Honor. Um, so if the most most of this work is being done in our winter season, um, in the summer season, this year we had 53,000 hikers on the lower Dewey Lake Trail system. If we're talking about building an enhanced trail up there, um, well, now we're just advertising folks to follow that trail, 53,000 of them potentially, to a very dangerous place up on our mountainside. Um, what thought or um actions would be taken to ensure like closure of that during the off season of construction for visitor protection and safety?

SPEAKER_12Because that that is actually a big concern. Uh people also don't like to read signs, they don't do it very well sometimes.

SPEAKER_06So yeah, we we've discussed we've discussed this uh with the municipality in our design meetings. Um the you know my my understanding is that the sections segments A and B are are essentially just enhancing existing trails that are used by by hikers and and people already. The the new segment C, which is going up the ridgeline, we've discussed whether or not that's a a gated uh thing that that's blocked or or signs, you know, you essentially have you essentially have access to the top of this thing already.

SPEAKER_06And we've seen, you know, just through the monitoring that we're doing during the season and and having people come you know up there uh to look at the rock slopes every day, you know, people and and and the work that I've watched, you know, during the even during the off season, people will people come up that trail even though we have signs that says you know, danger don't come up here. But but so you're gonna get lucky lose and people are gonna are gonna follow that. But but how you know the best way to handle that is is you know, we're just gonna have to work with the municipality and to figure out what what's gonna be the most effective thing.

SPEAKER_06Because you just want people to avoid the area um because it's not a safe place inherently, even if we weren't working there.

SPEAKER_04Yeah, they're kind of uh and and going back to Jay's question, it's it's kind of a matter of timing. Like there are different stages and phases. Uh, and during the construction stage, um obviously we're gonna be working on the trail. And my vision for that was we could potentially restrict that trail work during the summer months to nighttime work. Uh that way we're not uh having conflicts with you know equipment and and you know dozers coming up and down the trail. Uh another thought that that we kind of put some placeholder dollars in the plans for is uh potentially some flaggers, uh basically somebody at the bottom of the hill with a radio and somebody higher up the hill, just to help keep track of those people and make sure those conflicts aren't in place.

SPEAKER_04And then long term, uh, once we're kind of done with our work and we're we're walking away, uh, yeah, I think potentially a gate or some bollard or something like that, just to make it clear like this is a dangerous area. Um, but yeah, people are gonna do what they want to do, and we just have to try to make it as clear uh as we can. And uh that's that's something that we're we're open to suggestions and and um you know what has worked previously in this area to to try to keep people yeah save them from themselves in a lot of ways.

SPEAKER_01Thank you, Ronor. Um hoping this can be my last question. Um possibly a question for manager Deach. Um given that this is a lifelong um access trail, have we done any kind of budget projections about annual maintenance costs? Um and I'm assuming that would come from the port budget? Or uh uh no, I think um you mean maintenance cost for the rock slope or I guess I'm wondering what kind of so maybe it is a question for the for the team, um, what level of um maintenance in perpetuity um would we be expecting to to uh or might be required to keep this as a a usable um access trail?

SPEAKER_13I I you the team probably knows more about what actually that material needs and you know for upkeep, but um we do have our trail crew goes up on the trail every day. Um so we've got eyes on it every day. Um, not all day, unfortunately, sometimes. But um so we do we do have people who are up there and we do have a budget for trail maintenance that's just built into the parks and recreation budget. So that because it's a trail, I think that would fall under the parks and rec budget and not the port.

SPEAKER_13Or maybe we can talk about that.

SPEAKER_04Uh yeah, I guess during during the construction, while granite is under contract, they'll be responsible for maintaining the trail. Uh I I think that is obvious, but might as well say it for the record. Uh but then long term I think it's gonna depend on if you guys restrict access to ATVs and that sort of thing. Obviously, uh motor vehicles are gonna tear up the trail quite a bit more than if it's restricted to you know horses and pedestrians. Um I think that that's something we haven't put a whole amount of thought into just yet because we're not sure where you guys are gonna land as far as future use.

SPEAKER_04Um but I think that's something we can we can take back and think a little bit more about and try to factor that into the materials that we select uh for that surface course, for example, um something that's a little bit more angular and um less resistant to erosion and and things like that uh to try to minimize the the long-term maintenance obligation and and expense.

SPEAKER_02Thank you. I've got a question for manager Deech. Um with consideration of the helicopter only option, the cost-benefit analysis of the grit brick grant has an equation that you know kind of analyzes whether it's uh going to go or it's not going to go. And this has been touched on a little bit by you and a little bit by uh Vice Mayor Potter. But if the cost uh increases by 35 to 40 million, what do you anticipate that would do to the uh the no-go cost analysis equation uh and uh funding um that accompanies that?

SPEAKER_13Um yeah, if if we do choose a different alternative, we would be we we basically have to do those steps again. Um so you know, we develop the alternative, um evaluate it or add it to the analysis, right? And then you make a selection again. And then we do another benefit cost analysis of that alternative. Um and I I feel like the team can probably speak to this more, maybe you, Greg, um, because there is a ratio, you know, you have to try to quantify these sort of unquantifiable things, like what the benefits.

SPEAKER_13So you can it's an economic driver, right? Uh, or there's that benefit of having the port intact, right? And not doing nothing. There's a benefit to that, right? Because we're taking that risk away. So there's it's an he's an economist, not you, but um, the person doing the BCA, and they look at those things and say, and they put a number to it. And then you take the cost of the project and you do the formula. Basically, it's a ratio, and you've got to be above one.

SPEAKER_13You've got to be above one. If the cost outweighs the benefits, you go below one. And that is a go no go uh point for FEMA. So I I don't want to predict what would happen, but I think that that shows that it shows FEMA that it's not feasible. And maybe Greg.

SPEAKER_04Yeah, that was that was pretty much all spot on. There are different factors that go into that benefit cost analysis. And I'm I'm not the economist that that did this. I have uh people in Omaha and and I think Boston that uh kind of specialize in these FEMA grants. And it sounds like you guys are familiar with it too from the original brick grant application. Um so yeah, so uh it it it's a pretty simple equation when you boil it down. It's is the juice worth the squeeze, is the cost greater than the benefit, or is the benefit greater than the cost?

SPEAKER_04And if the benefit is greater than then that's a go for FEMA, like you're still eligible for that, for that grant funding. Otherwise, why would they why would they spend the money here instead of someplace else where they get more bang for the buck, so to speak? Uh and so obviously the more expensive the project is, the less, the less likely that benefit is gonna outweigh the cost. And so it's definitely something I I don't remember what the numbers were off the top of my head. I would have to look at look at our report. Um but I mean, if we added$50 million to the project, I I can I can imagine that would get us very close to one, if not below one.

SPEAKER_04Uh and so it's definitely something we'd have to look at. And uh another factor is like the um the design life of the project. I mean, that's one of the reasons why uh we liked this alternative, removing that material, because the design life of that is you know 75 years potentially before you need to really worry about doing something different versus just adding a whole bunch of steel up there and trying to pin everything in place, which has like a shorter design life. There go, the benefits are less than different alternative would be. But I guess that's a long-winded way of saying, but yeah, Emily got it right.

SPEAKER_02And the brick grants close to 20 million left uh in the phase two.

SPEAKER_13I think it's more eight eighteen and some change. The total phase one and two is 19.9. And so in phase one, we got 1.3, or I keep looking at Greg. I don't know if he knows. He's very he makes me feel more confident in what I'm saying. Um I think uh it was wait phase one was 1.3, and then we had a match, and then what's left is like 18 point, whatever that is, six or something.

SPEAKER_02So it would be if we were not meeting that equation anymore and dropped underneath the the point, the one, the the one you know ratio, it would be 35 to 40 million and increased cost and eighteen point five added to that cost as well because we no longer have the brick grant. So I do as much as my math about right there.

SPEAKER_13Municipal funds.

SPEAKER_17Yeah.

unknownOkay.

SPEAKER_02All right. I see no more hands brings us to where I thought we were 45 minutes ago. Item three, mirror and assembly discussion items. Assembly member up.

SPEAKER_03Hmm. Look, Burnham. Um Your Honor, I thought I would just read out the hikes again so it was clear.

SPEAKER_08Okay.

SPEAKER_03Um the dates uh is tomorrow, Tuesday, November 10th, and Wednesday, November 11th, um, which is Veterans Day. Um, and the times each day is 10 a.m. and 2 p.m. Meet at the Lower Lake uh trailhead. Thank you.

SPEAKER_18Um I think you summed it up. I was gonna say something along the lines of the cost of the the helicopter would make the project not be able to be done, but you made it even worse somehow. So um I I realize the concern of the community and uh the ability of a construction company turned loose on a hillside to do whatever they want to kind of thing to be able to get equipment up.

SPEAKER_18I used to work for a railroad like that, and we could do a lot of things because there wasn't foot traffic, there wasn't anything, and as far as foot traffic coming into the area, those blasting and live blasting in the area, those signs usually slow people down a little bit. But um uh all that said, it seems like the most straightforward way forward is to just improve the trail that's there.

SPEAKER_18Um, as far as working on the section from the water tanks to the T intersection up at the Icy Lake to Lower Lake Trail, we could just close that whole thing down and you could just have it for daytime, nighttime all summer long and back because there's no real view there from that section. That was the added trail to get to the the uh reservoir, so that that's kind of new.

SPEAKER_18So you could just keep everybody on the regular historic trails. Um, and one more thing I think I kind of got to thinking of when looking at the big picture, that we're gonna get rid of this rock that could cause a serious catastrophe, and then the we're not gaining anything with more use of the dock or anything, but we'd still have to get rid of that rock to do the next step to be able to gain full access, is what I understand.

SPEAKER_18So we I mean, we gotta do the rock no matter what, and so once that rock's gone, then that leaves us access and the ability to do more to where we can run the train out on the dock, or which I mean isn't our real end result, it's just we don't want to lose the south half of town. So that's our end result, it's just the bonus that we can use the dock. So that's about all I gotta say about it.

SPEAKER_02Thank you, Assemblymember Howard.

SPEAKER_12Thank you. Um, the hour is late. I don't have much to say. I'll be at the 2 p.m. hike on Wednesday. So thank you all for being here and for your valuable answers to everybody's questions in our community.

SPEAKER_07Thank you, Assemblymember Hillis. Thank you, Honor. I'm just eagerly looking forward to the public comment at our next assembly meeting. Assemblymember Potter.

SPEAKER_01Thank you, Honor. Um, thank you, everybody, for being a part of this. I think I'm gonna do the Wednesday 10 a.m. I'm a little bit afraid of the Brad Ryan pace, but um are you not gonna be there? Okay, so uh, because I did make it to the gym for 20 minutes today, but I don't uh think that's gonna help me. I think I've hiked with you twice um back in my younger days. No, thank you so much for your time. Um, what I really want to extend thanks to perfectly in time for the air to stop, so it got really loud, is um I really appreciate the community showing up for this one.

SPEAKER_01We've had a lot of these meetings over the more than a year, and they're typically not attended at all. This is possibly the biggest project in Skagway's history. It might be one of the biggest projects in the state. Um, and so it's nice to see everybody engaging now.

SPEAKER_02Thank you. Uh Assemblymember Pomeroy.

SPEAKER_11Yeah, seconding what uh Assemblymember Potter said, it has been wonderful reading everybody's questions that were submitted. Um, they were fantastic. It's been wonderful hearing the responses to those questions. And please don't cut off my access to circumventing the tourists by going up the road. I mean that the enhanced trail. All right, that's all. A little sacrifice.

SPEAKER_02All right. Well, thank you for all of you coming up and and and eloquently you know offering your expertise. I hope that uh gave a much better description uh for the community. Uh and thanks for the community's patience. I know there was a lot of discussion and frustration uh about the process, but you know, here we are, we're over three hours into it, and I shudder to think of what it would have been had we not started um when we did um with uh other people speaking in the microphone.

SPEAKER_02Um encourage everyone to go on the hike if you can, and uh this will be on the next assembly uh meeting, and you can come and speak to us then. Steve, can we adjourn? Meeting adjourned.

Open the transcript file

Hosts and Guests

Nobody is credited on this episode yet.

Credit the people on this episode

Be the first to rate this episode

More episodes

All episodes
  1. Borough Assembly - November 19, 2026

    Nov 20, 20262 hr 52 minAudio

    Call to Order Roll Call Approval of Minutes: November 5, 2026 Approval of Agenda Reports of Officials and Committees: Mayor’s Report Assembly Committee Reports Treasurer’s Report Manager’s Report Presentation from...

    Credit the people on this episode

  2. Borough Assembly - November 5, 2026

    Nov 6, 20261 hr 34 minAudio

    Call to Order Roll Call Approval of Minutes: October 8, 2026 Special Meeting October 15, 2026 Approval of Agenda Reports of Officials and Committees: Mayor’s Report Assembly Committee Reports Treasurer’s Report...

    Credit the people on this episode

  3. Borough Assembly: Committee of the Whole - October 22, 2026

    Oct 23, 202651 minAudio

    Call to Order Review of Proposed FY27 Budget - CIP & Special Revenue Funds: School Funding Debt Service Permanent Trust Capital Projects Sales Tax Fund CPV Excise Tax Fund Mayor & Assembly Discussion Items Adjournment...

    Credit the people on this episode

  4. Borough Assembly: Committee of the Whole - October 21, 2026

    Oct 22, 20261 hr 4 minAudio

    Call to Order Review of Proposed FY27 Budget - Operating Funds: General Fund Visitor Fund Clinic Fund Harbor Fund Port Fund Water - Sewer Fund Solid Waste Fund Mayor & Assembly Discussion Items Adjournment Packet

    Credit the people on this episode