Ep.1665 - Construction Logistics: From Delivery to Installation
9 minAudio
In this episode, Jason explains why logistics must be treated as its own critical production system. Getting materials to the site is only part of the job, the real challenge is moving them efficiently from receipt to final installation. Jason breaks down the systems required for reliable construction logistics, including delivery scheduling, truck queuing, receiving areas, de-trashing, kitting, access routes, hoisting, and line-side inventory. What you'll learn in this episode: Why the "last mile" from material receipt to installation is one of the most difficult parts of construction logistics. How delivery schedules, truck queuing, and clear gate systems prevent congestion and site chaos. Why de-trashing, kitting, and planned access routes improve material flow and reduce unnecessary handling. How deputized logistical operators and daily coordination keep materials synchronized with field production. Are your logistical systems intentionally moving materials from receipt to installation, or are crews still searching, waiting, and moving materials multiple times? If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉). Also, here are links to our YouTube Channels: 路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg 路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt 路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured 路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Hey there, I'm really excited to be here with you. Let's talk about podcast number 1665. This is a podcast about what happens if you're missing logistics. If you're interested in that, please stay with us. Welcome everybody, this is super exciting for me. First of all, let me say something when it comes to logistics or logistical systems is that we cannot loop the supply chain and our procurement systems.
We cannot loop logistics just automatically into our supply chain and our procurement systems, meaning I'm fine to understand that it's a part of the overall lead time, but I don't, I think that when you loop them together, you forget how important logistics is. It's funny, the books one through six about the different lean cores are done and I have them printed at the office, ready to ship for anybody that might want them. And then the logistical book is next to it. So you have all these books that are
about an inch thick and then the logistical book is two and a half inches thick. Like it's, and all of those chapters are really, really condensed. Like I can't emphasize that enough, meaning I attempted to only hit the most important parts, but there's so much to it. So there's getting materials to the job site at the point of receipt, and then there's getting the materials from the point of receipt to the install, which is a whole other concept. And like the last mile, there's this concept
of the last mile in a supply chain is the hardest. A lot of times we can get the materials, but that last mile, right? Getting it from the point of receipt to the actual install might be the hardest, the most costly, the most difficult, the most variation, the most destructive, right? So we've got to have good logistical systems. What do I mean by logistical systems? Well, from point of, so we have, first of all, a good delivery system, a good queuing system for trucks.
We have a roadside queuing. We have good entry gates. We have a good receipt or receiving area. We have an area where we unload the trucks, inspect the materials and de-trash and kit for the zone. Then we have line side inventory. And then we have all of our access ways. We have hoisting. So for instance, your cranes, your hoist, and your telehandlers, right?
So everything on the job site that is utilized to get the materials from the point of receipt to the place of install is what I'm considering logistics. And the key here is that you have deputized operators, meaning the crane operator, the telehandler, the forklift operator, and the hoist operators are all enabled in this system to not only know where things go, but to control the hoisting on a schedule. It means that we've mapped these systems out.
We know we have the capacity. They're intentionally designed. And it means that in the afternoon foreman huddle, the foreman and the superintendent on the project site organize deliveries, organize how they'll be received, and organize where they go. And those visual maps, in addition to the schedule, go out to those operators. If you don't have this system, you're gonna be in big trouble. First of all, if you don't have a delivery system, then materials will show up whenever.
And there will be rug materials. They will bottleneck the roads. They'll end up in the adjacent emergency department near the hospital where you're building. They'll end up on site. They'll clog your gates. They'll show up while you have critical activities on site and the drivers will want you urgently to unload them right away. I mean, it will be sheer chaos. Like, it's absolute garbage if this happens. You must have a schedule. Now, if you have a schedule, but you
don't have queuing for the trucks, roadside queuing, then you're gonna have the same problem. And you will have trucks ending up anywhere. So here's what I mean. A truck shows up, maybe at a little bit different time. The hoist dock or deck is full at the moment. There's no place for them to go. And so they just end up going anywhere. So they're back right at the same emergency department. You've gotta have signs and pre-kitted information
that will show trucks where to go if where they need to land is not open, right? Queue over here and, oh, okay, I'll go queue over there and I'll call in and confirm, or I'll get a radio or some kind of text when they're ready. You've gotta tell trucks where to go, okay? The other thing is you have to have a good visual gate system where deliveries know where to go. I remember, so my dad worked at Service Rock Products in Victorville, California. And I remember Hansel Phelps provided a map
of the prison that they were building. And I remember going up in the batch plant, visiting my dad's work and seeing the big map. And whenever the dispatcher would dispatch trucks out to the project site, they knew exactly where they were going according to the map and they would tell each of the drivers. The drivers need to know where to go before they're dispatched. If not, again, they'll end up anywhere. Okay, so the gate system, I totally get it. The other thing is we've gotta make sure
that the, well, here's the deal. If you do not deputize your operators, your forklift operators, hoist operators, crane operators to follow the plan, then you will end up with materials anywhere on the site, just stays anywhere. You will have messy areas. There will be no coordination and you will move things an average of nine times. It's really quite detrimental, okay? So you have to make sure that those
deputies, those logistical deputies are in control of those areas. If you don't coordinate where things go with the foreman the night before or the afternoon before and then send that to your deputies, then they won't know where things go and they'll use their best judgment, but it won't be where the foreman expected and there will be no synchrony, okay? The other thing is if you don't de -trash and kit, you'll bring up a bunch
of materials and the trash and the packaging into the building and then have to take it all away and your dumpsters and your trash chutes will be full and at capacity all the time and it will bottleneck your site. And if you don't have clear access ways, then the entire project will be bottlenecked from a physical constraint standpoint. So these are the things that you're dealing with with logistics. I can't emphasize enough how important logistics are to the overall system. If this goes down, it's like swimming across
a mile-wide channel and drowning five feet from shore. So we've got to make sure that all logistical systems are well-designed and I would recommend reading the book Elevating Construction Logistics. I hope you all have enjoyed this podcast. On we go.
Avoiding the hardest problem rarely makes it disappear; it usually gives it more time to grow. In this episode, Jason explains why one of the best ways to improve projects, leadership, and even your own peace of mind is...
When estimating durations, people tend to drift toward one of two dangerous extremes: padding the schedule because they have been burned before, or promising unrealistic performance because they believe they can push...
You do not need authority over the entire project to start leading. In this episode, Jason shares a story from his own career to explain why the most effective way to lead from below is not to wait for permission,...
A three-week pull may look like Lean planning, but Jason argues that it can leave teams focused on what is directly in front of them instead of preparing the entire phase properly. In this episode, he explains why...
A great meeting should do more than share updates it should expose what is off track and help the team solve it. In this episode, Jason breaks down the purpose and flow of the Level 10 Meeting from the Entrepreneurial...