In this episode, Jason continues his before-phase planning series with practical strategies teams can use to prepare construction phases more effectively. He explains how work packages, zone planning, buffers, multi-train flow, crew planning, and coordinated 3D models can make installation easier, safer, and more reliable. What you'll learn in this episode: How to align construction, engineering, procurement, and installation work packages. Why zone maps, density analysis, and deliberate buffer placement improve trade flow. How multi-train planning allows crews to work at their natural production rhythms. How Build Your Lego® sheets and coordinated 3D models support reliable field installation. What can your team prepare before the next phase begins to make installation simpler and more predictable? If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊). Also, here are links to our YouTube Channels: · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Hey there, welcome everybody out to podcast number 1645. In this podcast I'm going to continue talking about before-phase planning. If you're interested in that, please stay with us. All right everybody, I'm jamming out, ready to go. I was excited yesterday to keep going through this list, but there's so many things. And I do want to say before I keep going that I don't want to overwhelm anybody. This isn't something that everybody has to do, every single thing.
And I'm not trying to make everybody's job harder, although installation should be the easiest thing we do. I'm just giving you some options. So I'm going to start back with yesterday I finished with more detailed IWPs, and today I'm going to continue with the CWP to IWT breakdown sessions. So one other thing that you can do for before-phase planning is you could align the designers and make sure that you have
construction work packages, engineering work packages, and procurement work packages for each tax wagon in the tax phase. And really make sure that everything is detailed and broken out for that wagon. You know, essentially that's what a lift drawing is. Shop drawings to a certain extent, but a lift drawing, it's really trying to unbatch drawings. Drawings shouldn't be batched where it's like, here's the whole project and it's architectural, structural, mechanical.
It should be building one phase interiors, blah, blah, blah. And then you have the architectural, sorry, structural, architectural, mechanical, electrical, plumbing, IT drawings within that. Like we should be designing to the work packages and how we're going to build the actual project, but the design world isn't there yet. Anyway, another thing is we can, I have a note here, it says classify IWP complexity, meaning size each package low, medium, or high
before committing. Complexity is not duration. A short package can be high risk and it deserves more preparation, not less. So if you're like, hey, this IWP talk has got me all nervous. How am I going to do that? How am I going to create a visual feature of work for each trade? Then just focus on the more complex or more high risk packages and make sure that those are planned or prepared. Another one is zone maps plus a density
and leveling analysis. We do this all the time at LeanTAC, so it's a given for us and it's a given for the TAC production system. But if you're heading into a phase, one of the things you can really do is carve out zones beautifully so that the trades don't have any difficulty really going from zone to zone to zone. You have your horizontal flows, you have your vertical flows, you've identified workable backlog, you've really done a good job of identifying zones and
you've leveled them according to density, not square footage. Another one is buffer placement. This is really cool. A phase that buffers are just at the end or they're at the end of the entire schedule itself, which is according to critical chain. But what we can do is decide deliberately where capacity, time, space, and our planned backlog buffers sit. We need to understand that buffers are not
slack you forget to remove, they are protection you placed on purpose where the risk analysis told you to. The other thing is according to drum buffer rope we should know even although we've optimized it where our most complex zone is, most complex trade is, and buffer ahead of it. You see for before phase planning and any kind of planning, especially in the TAC production system, we better know where our most factors are, where our constraints are.
We can do so much by way of optimizing and getting ahead of things if we just know these things. So really really really cool stuff. Obviously buffer your constraints. Multi-train design. I talked about this the other day that it's super frustrating that people keep harping on single train as the only option. That's absolutely not true. Multi-train, this lets trades run at their own natural rhythms rather than forcing every trade
onto one beat. And I will tell you that when you do the analysis a lot of times, a lot of times multi-train is faster from a throughput standpoint and it's better buffered. It's buffered better because you don't have so much dependency between one trade and another trade. It's absolutely beautiful. So we've got to be really intelligent when we're designing these things and we've got to make the call according to what the project
needs and wants because multi-train is pretty phenomenal. If you want to do single train that's obviously really your decision, but looking at it in a deeper way is really helpful for the overall phase itself and it can also enable other strategies. One thing that I want to say here
is that you know when you think about single train and multi-train, single train is really one single train on the train tracks. Multi-train is kind of like a well -flowing freeway. You got fast cars going, you got trucks going slower, you got a camper in the slow lane, but everybody's flowing beautifully. So it's actually you know and here's the thing like when people are really strict about single train tech planning it's like why?
And even in Germany like the whole country doesn't run just on rail lines. You have surface roads, you have the Autobahn, you have vehicles, you have bicycles like there's a lot of variation in how you choose to travel somewhere. Focusing on single train tech planning is like saying all right Germany you can only everybody can only travel by train which would be absolutely ridiculous. Okay another one is build your lego sheet. Now build your lego sheet should be done
before the the pull plan if you really want to leverage this. But if you haven't done it in the pull plan, doing a build your lego sheet is pretty phenomenal. A build your lego sheet is a sheet that enables the trade to understand what their durations are, their tech time, their crew composition is, and then they're actually able to plan and package a really nicely organized crew within the cycle time that fits within the tech time. Really it's additional form and planning to make sure that all of the numbers pan out
in order to keep the rhythm. The other one is confirm the 3D model is a single source of truth. Make sure that that 3D model is you have one federated model right that everything is coordinated everything it's it's clash free for the areas that you're installing. You can utilize it you have access to it in the field and it's used for install. You can the data is tagged quantities and component IDs are aligned. You can get quantities from it and it's
ready to go in the field and it's broken out by room or by area on something like a BIM 360 glue right. Basically you have access to it in the field. So that's going to finish the list for this next little segment. I'm already at eight minutes so I'll stop here. One other thing I want to say is that there might be some things on the list as I keep going through these that that that or there there might be some
things sorry I forgot what I said there might be some things that are not on the list. Like really amping up your field engineering team or really getting a great layout person to run at the building or really setting up your logistics system or or or like there's the the question is what things can we do before the phase starts to really pull out all the stops and make sure that it goes well 100%. Anyway I'll see you on the next one where I'll continue the list. On we go!
Avoiding the hardest problem rarely makes it disappear; it usually gives it more time to grow. In this episode, Jason explains why one of the best ways to improve projects, leadership, and even your own peace of mind is...
When estimating durations, people tend to drift toward one of two dangerous extremes: padding the schedule because they have been burned before, or promising unrealistic performance because they believe they can push...
You do not need authority over the entire project to start leading. In this episode, Jason shares a story from his own career to explain why the most effective way to lead from below is not to wait for permission,...
A three-week pull may look like Lean planning, but Jason argues that it can leave teams focused on what is directly in front of them instead of preparing the entire phase properly. In this episode, he explains why...
A great meeting should do more than share updates it should expose what is off track and help the team solve it. In this episode, Jason breaks down the purpose and flow of the Level 10 Meeting from the Entrepreneurial...