Going to bid is not just about sending drawings to trade partners and waiting for numbers to come back. In this episode, Jason breaks down the planning, estimating, scoping, and documentation that need to happen before a contractor can confidently determine whether a project is truly within budget. Jason explains how the macro Takt plan, logistics plan, zoning strategy, risk and opportunity register, general conditions, general requirements, contingencies, and subcontractor pricing all connect. He also walks through bid packages, quote leveling, control estimates, and the information trade partners need before a reliable GMP or project price can be established. What you'll learn in this episode: Why the overall construction plan must come before accurate estimating. How schedule duration, logistics, zoning, and risk influence project costs. Why bid packages need clear scopes and complete project information. How quote leveling creates an apples-to-apples comparison between trade partners. Why early planning is essential before committing to a GMP or final project budget. Are you going to bid with a complete construction strategy or asking the market to price a project you haven't fully planned yet? If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉). Also, here are links to our YouTube Channels: 路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg 路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt 路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured 路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Hey there, welcome everybody out to podcast number 1725. In this podcast, I'm gonna talk about preparing to go to bed. If you're interested in that, please stay with us. Welcome everybody, I hope you're doing well and staying safe out there. I'm excited to be with you and gonna do another podcast here over the weekend, try and get caught up. The topic that I wanna talk about right now, I'm not an expert at, I've been through it a bunch of times.
Though, it's a fun process in my opinion. When people are good at it, boy, I tell you what, it makes all the difference. But I'm gonna talk about preparing to go to bed. There's so many different, the ways that you can go out to bid to trade partners to find out if you're under budget. There's so many different ways, it would be
super irresponsible for me to try and summarize or loop everything into one category. I've seen public-private partnerships, I've seen contractors in Europe go and basically have a general allotment of money and design two general contractors in a multi-prime agreement towards a budgeted
outcome underneath the stipulated sum, to the point that they really didn't know if they were within budget until they had the core and shell in. I've seen situations where the contract is, or the contract delivery method is design-build or a CM at risk and you're reaching a GMP early, a guaranteed maximum price or a GMP quite late in the pre-construction process just before you sign a prime agreement. I've seen design-bid-build where you come
back with a bid. But I'm mostly familiar with the CM at risk framework or the design-build framework where generally you have a design and you're doing target value delivery where you're designing to a budget, which means that you don't just design whatever the designers want and then react to it. You legitimately price as you go and you select equipment and systems and you basically shape
and scope the building in a way and select systems and design development to where you can meet budget, right? But either way, you have your design effort and you need to make sure that that is priced properly and that the general contractor who is at risk to build the project for that amount can actually build it for that amount. Now, in a cost-plus environment, the general contractor has to build the project and basically
account for all of the costs. And it's paid for by the building owner and then that general contractor is paid a fee. In other scenarios, in a guaranteed maximum price, especially in a CM at risk environment, the construction manager works in pre-construction to price it and then once they reach a guaranteed maximum price, then they become the general contractor and they are at risk to build it for that price. And that's basically what it means.
So the idea in either scenario, you're really targeting a guaranteed maximum price, but in a cost-plus scenario, it's not really a guaranteed maximum price, it's an estimated maximum price. But either way, the process isn't that different. The steps that I wanna take you through that kind of bring everything together is just an overview of the key things that have to be done at a minimum. And if you have a good estimating team,
they're gonna know how to do this. But I always had to learn this on the fly, on my own. They don't teach this in school. So I figure a nice little podcast that you can add to or critique, it would be super awesome. So first of all, what we're attempting to do is understand if we're under budget, right? And that's if we're reaching or what the budget actually should be. That's if we're reaching a guaranteed maximum price or an estimated maximum price for the overall project, right?
And that's going to include some major categories. Your general conditions, the way I define them, are your staff and insurance. Your general requirements are anything logistics. Now, people define them differently. Some people call all of that GCs. Some people call that all GRs. And I don't care how you define it, but it's typically your division one items. It's your, what they would call indirects, things that don't directly go into the build.
It's things that allow you to build, okay? It's like the scaffolding for the project, meaning the scaffolding that supports the actual end product is not actual scaffolding. But anyway, so you'll have those estimates and then you'll have your subcontracts, your self-perform. You will have your contingency buckets, owner contingency, contractor contingency, contractor fee. And let's see if I'm missing anything.
I think those are most of the categories. But the bottom line is, I'm doing this all without looking at a document, so forgive me if I miss something, but you need to estimate all of those. And the bottom line is that your overall strategic plan comes first. So when I say, let's get started with a macro level tag plan that gives you your overall total project duration, when I say, let's go ahead and map out your logistics
plan that shows you logistically how you're gonna build the project. And when I say, hey, let's map everything out from a zoning standpoint, let's go ahead and understand the general approach of the builders, that's super important. How are you going to know how much your staff is gonna cost if you don't know how long the project is gonna take and how you're gonna run it? How can you estimate your insurance costs and
bonds for that matter if you don't know how long the project is gonna take? How are you going to estimate your general requirements, all of your logistics items, if you don't have a logistics plan and zone maps? How are you going to estimate contingency buckets if you're not starting to fill out a risk and opportunity register, right? These are all very, very important things. So it starts with the plan. Now, people that generally know from a fingertip feel how much it should take, I think
that's great. I never trust that so much because of the statistics, right? Only 48% of projects around the world are under budget. So I don't really trust that very much. I like to tear it apart and have it done. Now, when, and I've been through this at DPR, at Hensel Phelps, massive companies, it's usually pretty much the same thing. Once you get close to having a decent set of drawings, and I've seen design builders do it at design development.
And I've even heard of people doing it sooner. I'm not sure I would recommend that. But once you've selected your systems, I've seen people reach a guaranteed maximum price, okay? But the bottom line is, you either have to have a good enough control estimate in -house to know what it's going to take and then buy out your scopes later, or, which is I think the safer one, and what I'm more familiar with, is you create scoping documents and your bid packages, and you
go out to the market and you get pricing, and you select at least one of three to get a good feel for the pricing. You do your leveling activity, which means that you compare all, and you might have more than three, but all three or four of your quotes, and you make sure that each of the comparisons are apples to apples, not apples to oranges, and you fill in any gaps, right? And you hold contingencies and allowances, and you
basically total your general conditions, your general requirements, all of your subcontracts. You add your buyout contingency, whatever contingency you want to buy out the remaining trades, or any gaps. That's especially if you don't go out to the market. If you're doing it from a control estimate, your buyout contingency will increase, and you will tack on a fee, you'll estimate contingencies, and you will make sure that any other costs
are covered in that process. But what I'm trying to make clear here is that when you're sending out bid packages to get your pricing back, you've gotta have your schedule, your logistics plans, your zoning maps, your job information policy brochure, your basis of estimate, your basis of schedule, and any other relevant documentation. I would recommend the template prime agreement that they're going to sign in the template subcontract
that they're going to enter into so they know what they're dealing with. And then you should have a pretty solid price. Then the project will either go if it's cost plus, or you as a general contractor will agree to a GMP, a guaranteed maximum price, and now you're at risk to build it for that price, or whatever the other scenarios are. But I have never had anybody explain this. I've never seen a video that explains this, so I figured I would do my best,
even though I'm not an expert at this, and basically explain how that happens. So I mean, biggest takeaway, if you're a builder, you can't get that planning done soon enough, right? You can't, because everything else depends on it. I hope you've enjoyed this podcast. On we go.
Avoiding the hardest problem rarely makes it disappear; it usually gives it more time to grow. In this episode, Jason explains why one of the best ways to improve projects, leadership, and even your own peace of mind is...
When estimating durations, people tend to drift toward one of two dangerous extremes: padding the schedule because they have been burned before, or promising unrealistic performance because they believe they can push...
You do not need authority over the entire project to start leading. In this episode, Jason shares a story from his own career to explain why the most effective way to lead from below is not to wait for permission,...
A three-week pull may look like Lean planning, but Jason argues that it can leave teams focused on what is directly in front of them instead of preparing the entire phase properly. In this episode, he explains why...
A great meeting should do more than share updates it should expose what is off track and help the team solve it. In this episode, Jason breaks down the purpose and flow of the Level 10 Meeting from the Entrepreneurial...