In this episode, Jason explores why buffers are critical on construction projects and how proper before-phase planning sets the stage for smooth execution. Using a humorous analogy of navigating an In-N-Out drive-thru, he explains how insufficient buffers not only disrupt workflow but also put workers under unnecessary stress. What you'll learn in this episode: The difference between waiting you pay for versus waiting you don't. Why buffers are essential for both workflow and worker safety. How before-phase planning prevents delays and maximizes flow. Key pre-planning activities to execute a phase successfully. How small adjustments upstream save massive time downstream. Are you fully leveraging before-phase planning to keep your projects flowing without unnecessary stops? If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊). Also, here are links to our YouTube Channels: · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
All right, welcome everybody out to podcast number 1640. In this podcast, I'm going to talk about the In-N-Out drive-thru problem around the corner. If you're interested in that, please stay with us. Hey everybody, I hope you're doing well and staying safe out there. I might merge a couple of concepts here in this one, but let me just go ahead and get started and say that at In-N-Out near our home, and I go there a lot because I was born in California, so it's in your blood, like
it's cellular memory. Everybody's trained through cellular memory and genetics to love In-N-Out. Anyway, so if the rest of you are like, I don't know what the big deal is, just know that I grew up with it. Anyway, coming around the corner, especially, no, no, it happens with all the vehicles, but especially with the Ford F-150, the extent, the crew cab, that I have, my truck, when I'm coming around the corner to get into order, I have to do like a three -point turn there because it's too sharp.
In-N-Out lines are so long and chaotic that they have to use barricades and basically route the line almost off into traffic and into the roadway. It's interesting. I really attempt to like jaunt forward and then quickly reverse and go forward so that the person behind me doesn't take away my buffer, and inevitably what will happen is no matter how fast I go, somebody will ride right up on my backside and give me no room to back up, and then it's
like a thing, and they're upset, and it's like they don't understand, well, this truck doesn't fit if I can't do my little three -point turn over here, and I realized that buffers, not having buffers not only hurts successor work, but it actually hurts the person in the game that's attempting to finish. What if somebody does have to back up and do something? Nobody's perfect. We're attempting to make sure that everything is jamming and that everything on the construction site
flows, but how disrespectful is it to say, hey, we are rushing you so much that you don't even have a chance to make a mistake? That's what Kate always says. If you don't have buffers, that means nobody on the project site can make a mistake, and they're human beings, and that's unrealistic. So I wanted to make a point that buffers not only protect the successor work, but they protect the person in the work, and if we don't have them, it ends up like going through an in-and-out drive
-through, and it's not in-and-out's fault. It's the fact that the people in the United States are trained to tailgate everybody. That two or three feet is going to make a damn bit of difference. It's a mindset problem, and we will know in construction that we're ready to flow once we on our freeways stop tailgating people. I'll just say that right now. It's a mindset thing. Now, what I said earlier was that some of these might not make a lot of sense if I'm combining these. I don't want this to be a three
-minute podcast, so I will say that if you don't have a lot of buffers, you have to increase the level of planning. So I want to cover two other quick little topics. I call it before-phase planning, and I call it that because obviously it's before-phase. I don't want to say pre because I don't want to confuse it with pre-con meetings or pre-construction, but the phase coming up, whether it's structure, foundations, interiors, exterior, the four to six months before that phase happens
is more important than when the phase begins. Let me make a point here. Before-phase planning, you're doing the full plan. You're doing your pre-con meetings. You are doing your look-ahead planning, right? You're doing your normal stuff. I also would say there's a complete list of things that could be done. You could start to engage 4D to sequence it out. You could do advanced sequencing with drawings, advanced models, first-run studies, mock-ups, visit other
trade crews or other sites, and I could just keep going on and on in my list. I don't know if you want me to or not, but the bottom line is that we don't do enough of this. We are like, oh, the phase is here a couple weeks ahead of time. I better get to go. This is going to be a tough grind, but we haven't started soon enough if we're a couple weeks ahead. Let me just list out some of the other things that you can do. I'm just going to give you a whole
gamut of things. Fresh size meetings, pre-mortems, advanced visualization using foam, kinetic sand, physical 3D models, breaking out your CWPs all the way down to your IWPs. You can do an advanced density analysis for your zones, place buffers strategically, switch to a multi-train design, build your Lego sheets and do a killer pull plan. You can do, like I said before, mock
-ups, control samples, make sure that the conditions of satisfaction are proper. Onboard and orient and even train the trade. Make sure that your quality planning is done. I already mentioned first-round studies, but it's so important I might mention it again. Test your sequencing in any way you can before the phase actually starts. Onboard and align your workforce in the dojo before they show up. Make sure that non-participating trades are identified and that you correct the situation.
Make sure that production rates are verified. Make sure that you have a labor commitment. Make sure that you have all of your commissioning figured out, that pre-test planning for safety is figured out, that all of your advanced kitting for logistics is 100% mapped out. Maybe you want to do more pre-fabrication or room-kitting or on-site pre-fabrication. Maybe you want to make sure that the trade ahead because this is a bottleneck is going well or that there's a buffer ahead of time. Maybe you want to swarm some middles. I could keep going on.
The list just keeps going and going. In fact, on the website under before phase planning quick read I've got a full list of things. The bottom line is we've got to make sure that before the phase starts we're pulling out all the stops and doing the hard things to make sure that that trade can start and actually finish without stops and restarts. And so the big things that I would do 100% I would 100% if I had to choose any one of them I would do the advanced sequencing. I would do a first run study or
a mock-up and I would definitely visit the trade to make sure they're 100% ready to go in addition to my pull plan, the pre-con meetings and my look ahead planning and the supply chain management that happens ahead of the work actually taking place. Experts live in the before phase planning and for all of your project superintendents and project managers out there you're going to mainly live there and you're going to hand off the work at some point when it's appropriate to
assistant PMs and assistant supers. So most of your work happens in the before phase planning and then you go off you don't go micromanage the actual work you actually go to the next before phase planning effort. So very very crucial and it's got to become more of a habit for everything that we do and if we don't do this you've got to have buffers and if you don't have buffers you've got to do this. You should do this anyway. I hope you've enjoyed this podcast. On we go.
Avoiding the hardest problem rarely makes it disappear; it usually gives it more time to grow. In this episode, Jason explains why one of the best ways to improve projects, leadership, and even your own peace of mind is...
When estimating durations, people tend to drift toward one of two dangerous extremes: padding the schedule because they have been burned before, or promising unrealistic performance because they believe they can push...
You do not need authority over the entire project to start leading. In this episode, Jason shares a story from his own career to explain why the most effective way to lead from below is not to wait for permission,...
A three-week pull may look like Lean planning, but Jason argues that it can leave teams focused on what is directly in front of them instead of preparing the entire phase properly. In this episode, he explains why...
A great meeting should do more than share updates it should expose what is off track and help the team solve it. In this episode, Jason breaks down the purpose and flow of the Level 10 Meeting from the Entrepreneurial...