The worst time to start planning is when construction is already underway. In this episode, Jason explains why urgency belongs in pre-construction not in the field and why teams should work aggressively upfront so crews do not have to rush, panic, recover, or improvise later. Jason breaks down the difference between driving hard during planning and pushing people during construction. His point is simple: use the time before work starts to remove constraints, coordinate the details, and prepare the project so field execution can happen with stability, flow, and safety. What you'll learn in this episode: Why urgency should happen in pre-construction instead of in the field. How strong planning protects crews from rush, panic, overtime, and unnecessary risk. Why delaying planning until excavation or early construction wastes critical opportunities. How early preparation helps remove constraints before they become field problems. Why Jason believes an hour in pre-construction can save far more time during construction. Are you hurrying up to plan now or waiting until the field forces you to react? If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉). Also, here are links to our YouTube Channels: 路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg 路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt 路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured 路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Hey there, welcome everybody out to podcast number 1704. In this podcast, I'm gonna talk about hurry up and plan. If you're interested in that, please stay with us. Welcome everybody, I hope you're doing well and staying safe out there. I really do hope that for you. Oh, really cool thing. Went to a job site in, oh, I think it's Marfene in Hungary. I think that's how you say it, I'm not sure, but it's about two hours away from Budapest.
And on the job site, saw some cool things, really nice entry, really nice guard station, really nice entry queuing area, really nice trailers, really nice bathroom, really nice lunchroom. And people typically don't believe me, so I'll give one critique. They didn't have enough or large enough trash cans, but that was the only thing I saw that was a little bit out of hand. And the other thing I saw was showers for the first time. Oh my gosh, showers, showers for the workers, especially the people doing insulation or welding or
out in the mud or if they were placing concrete that day. I was blown away, I was like, oh my gosh, showers. I've never even thought about this. It was in a neat container. It came, and they were smaller, right? So I'm not sure you're gonna be in there like you're in a sauna or a hot tub or a spa or something like that. But they worked, the workers used them and it was remarkable. So really, really, really cool stuff. The, oh, the podcast, Hurry Up and Plan. I talked a little bit about this in
the last podcast, but let me talk about this right now. I talk a lot about trying to keep people balanced, and I also talk a lot about caring for people. And I talk about trying to comfort the workers in the foreman, so people think that, sometimes people think that I'm not a hard worker or that I'm encouraging project delivery team members to work 32 hours or to be super comfortable in life and blah, blah, blah. I believe in a balance and I believe in all of these things.
And I do believe in stopping and I don't believe in pushing, but people misunderstand me. I pride myself on being one of the hardest working people in the group area or whatever. If I'm in a group, I will regulate myself, and this might be toxic behavior, I'm not saying it's not, but I will regulate myself to where I am the hardest working person in the room or at least as hard working. And I really believe in doing a good job and adding value. And I do believe in balance, but I don't believe in laziness or comfort.
I think comfort is a disease. And I don't believe in pushing, but I will drive like crazy, especially in pre-construction. So sometimes people will see me and they're like, you talk about balance, but you work your ass off. Oh, sorry, I should've warned you for the cuss word. You talk about comforting the workers, but you don't believe in the project delivery team being only working 32 hours and being super cushy in their jobs. And you talk about not pushing, but you're
always grinding in pre-construction and being urgent about everything. Jason, are you pushing? And I will answer that. I will say like, let's hurry up. Like, let's get this going. And my saying will be, hurry up and plan. Like, let's go. We can't fall asleep on this deal. So I heard a neat quote from Hal Macomber. In construction, he's like, and I don't know if it was from somebody else or if
he made it or whatever, but the quote goes like this. Don't just do something, stand there. Meaning, if you don't know if it's safe, if you don't know if it's quality, if you don't know what to do, if you don't have full kit, don't just go do any old thing. Wait, stop. And I don't like the word wait, but stop, call, resolve. Stop, call, resolve. Stop, call, resolve. Let's get it fixed. And I would adapt that quote in pre -construction and in planning efforts to say, don't just stand there, do something.
In construction, I want you to hit on a rhythm. In pre-construction, I want you to start as soon as you can. In construction, I want a level flow. In pre-construction, I want a level flow too, but if we overburden ourselves every now and then, I don't mind. Yes, I did just say that. In construction, I will stop the train. In pre-construction, I will keep driving. In construction, I will advocate to try to never have late weekend overtime or crazy work
days. In pre-construction, I will allow it to happen. Okay. In construction, I'm looking for even flow and buffers and capacity. In pre-construction, I'm always like, let's hurry up and plan. Somebody would even say to me, Jason, you're a pusher in pre-construction, but you go against what you preach. No, I know that an hour of pre -construction is worth a day in construction, and a day is worth a week in construction. I have said to my teams, and they're not my teams, the teams, I'm like, if
you have to work a late day every now and then in a pre-con to get the construction right, do it. It doesn't bother me. If you're ever gonna work overtime, not overtime, sorry. If you're ever gonna work late or do an all nighter or burn a weekend, you do it in pre-construction because we're not gonna do it in construction when that possible fatigue could affect you in the field from a safety standpoint. I have said that to people, 100%, because I do not believe in doing it in
construction. I will not do it. But one thing you will find with me is I'm not going to let us get behind in the field. I'm not going to do that. The thing that you can't do is you can't fall asleep, get complacent, or get lazy, or be like, oh, we're just in pre -construction, I'm not gonna work a lot. And then in the field, try to A, be out in the field, B, manage a number of people, C, be where you don't have any decision or reacting time, I don't
know what letter I'm on, D, be in the critical moments and be doing construction and have an upcoming phase, and E, also tack onto that procrastination. Like, I'm not gonna do that, that's dumb. That is the dumbest thing. If somebody was like, Jason, I think what you're saying in this podcast is dumb, I'd be like, liar, liar, pants on fire. You're dumb, I'm not dumb, you're dumb. I'm just kidding, I would never talk like that. But like, the dumbest thing on earth is waiting, like people always say, and I hate
this, this is the dumbest thing I've ever heard. Good people, but dumb, this is super dumb. They're like, we have plenty of time when we're excavating and digging a hole to do the planting. Here's some cuss words, earmuffs. What the fuck did you just say to me? That is the dumbest shit I've ever heard in my entire fucking life. Like, why in the world would you say we have plenty of time until the project starts, and we have plenty of time while we're moving dirt, plenty of time while we're digging a hole? What asshole kind of world you fucking live
on? Like, this is absolutely ridiculous. You're gonna encourage pissing away all the good pre-construction coordination, pre-planting time that you have in order to take care of construction? That is the most dumb, here's the thing. Construction people will always be like, yep, I know two things, right? We're moving dirt, no big deal, no rush. And then they'll also be like, yep, the best time in construction to recover or to get out of the ground fast is in the beginning. You gotta get out of the ground fast. I'm like, you know those two concepts are
totally in-fucking-compatible. Like, you can't fall asleep while you're digging a hole in pre-construction and then also say the most important phase is when you're getting out of the hole. What kind of fucking dumb assery are you espousing? Sorry about all the cuss words. But like, that's so stupid. Like, I wish I could remember the quote in Billy Madison where, nowhere in your insane, idiotic rambling was there anything close to a coherent thought. Everyone in this room is now dumber for
having heard it. I award you no points and may God have mercy on your soul. That's how I feel about the dumb assery of, oh, we have plenty of time to plan the project while we're moving dirt. Your supply chains are already behind. Your design is already locked in. You're already fucked for bottlenecks and constraints. Like, you've already pissed away all of your opportunity. So yes, a million percent, you heard me right. You can quote me on it. You can tease me about it. You can post nasty comments on LinkedIn and I will fucking block you, just so you
know if you do that. Because nobody ever, I never consented to be criticized or complained against on a public social media platform. Here's what it throws me, just on a quick rant. I remember what Dave Chappelle said one time. If you didn't like my joke, and he's saying to male or females, and here's some cuss words. He's like, male or female, if you don't like that joke, bitch, remember you clicked on my face. Like, you decided to click on my face on LinkedIn or on the podcast or on YouTube. Don't come in here fucking complaining about this
shit to me. Like, this is 100% what I said. Hurry up and plan. You cannot go fast enough. If that makes me a planning pusher, so be it. Am I a field pusher? Fucking never. So I hope you've enjoyed this podcast. On we go.
Avoiding the hardest problem rarely makes it disappear; it usually gives it more time to grow. In this episode, Jason explains why one of the best ways to improve projects, leadership, and even your own peace of mind is...
When estimating durations, people tend to drift toward one of two dangerous extremes: padding the schedule because they have been burned before, or promising unrealistic performance because they believe they can push...
You do not need authority over the entire project to start leading. In this episode, Jason shares a story from his own career to explain why the most effective way to lead from below is not to wait for permission,...
A three-week pull may look like Lean planning, but Jason argues that it can leave teams focused on what is directly in front of them instead of preparing the entire phase properly. In this episode, he explains why...
A great meeting should do more than share updates it should expose what is off track and help the team solve it. In this episode, Jason breaks down the purpose and flow of the Level 10 Meeting from the Entrepreneurial...