Ep.1697 - The Most Important Things in Construction Planning
10 minAudio
In this episode, Jason breaks down the five planning practices he believes are essential to successful construction delivery: pull planning, look-ahead planning, pre-construction meetings, morning worker huddles, and material queuing. The goal is to stay ahead of the work, remove roadblocks early, and make sure every crew has what they need before they begin. When the work is truly ready, teams spend less time reacting and more time executing. What you'll learn in this episode: Why pull planning should begin months before a phase starts. How look-ahead planning identifies and removes roadblocks before they impact work. Why pre-construction meetings ensure each trade is fully ready to start. How morning worker huddles align crews before they enter the work area. Why materials must be inspected, staged, and fully kitted before delivery to the crew. Are you planning far enough ahead to make tomorrow's work predictable? If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉). Also, here are links to our YouTube Channels: 路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg 路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt 路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured 路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Hey there, welcome everybody out to podcast number 1697. In this podcast I'm going to talk about the most important things in construction planning. If you're interested in that, please stay with us. Welcome everybody, I hope you're doing well and staying safe out there. I'm super excited, still driving to Santa Fe, New Mexico to go meet with a client. So I'm getting caught up on podcasts. Things have been a whirlwind. I'm pretty much going to be... Do I not do this every year where
I'm like gone for two or three months? I don't know if I'm just crazy, or if this is a one-off, or if I do this to myself every year. But anyway, super busy out there, gentlemen. I want you to know something transparent. Our company, Leantact, had to get really, really big and scale very quickly. We scaled pretty well with standard work, instructions, our books, and we scaled with a gate system that keeps our internal quality. And right now, we're at a point where
we're really focusing internally on how well we execute meetings. We're focusing largely on the quality of our product, consistency throughout the organization, making sure that every client is actually a raving fan. And I just want you to know that as good as I think we are, we're always like we grow a little bit and then stabilize it. Grow a little bit, stabilize it. And I've just noticed that like it takes
that kind of drive to make sure that our quality is up to par all the time. Anyway, I don't know why I said that, but I just want you to know that we're wildly imperfect. We're doing our best. We try and keep prices as low as we possibly can. And our focus is on people, quality, and process. So, yeah. Okay, so into the podcast at hand. I'm thinking about this a lot because project delivery teams have a really hard job from the standpoint that like, not only is it
hard to do construction, but usually the two -thirds point, we've got dissolved logic in the overall system. Typically in a CPM schedule, typically that doesn't happen too badly with tact. So that's one reason why projects shift at the two-thirds point. But the other day it hit me that projects are difficult because at the two-thirds point, you're beginning a large phase of work essentially or multiple phases while executing a current
phase, while you're doing the pre-planning for the most difficult upcoming phase. So you're distracted. And I've already talked to you about all of the 47 different things that have to be done for a single work package to be made ready on time. And then you add onto all of that, all of the different complexity, and you're in a really difficult spot. You're in a really difficult situation. And so I'm constantly anchoring back to these key habits that will save you.
They will save you. The concepts, and it's pull plan, pre-con, meetings, look-ahead planning, orientation, and morning worker huddle or morning worker queuing and logistics queuing. Let me go through these one by one. Let me tell you why I think they're so important. Number one, the pull plan. If you do that three months before, meaning you prepare. Actually, hold on.
So you prepare for the pull plan four months before the phase starts. And a phase is a geographical grouping of work with its own unique zones through which a train of trades or multiple trains of trades flow. Four months ahead, you plan the pull plan. Three months ahead, you do the pull plan, and you lock in the sequence. That is where you start vetting out the contractors and how participative they are.
This is your first ability to showcase any red flags, right? Like to saddle a different contractor, to get something heading in a better direction, right? 100%. Then the look-ahead planning starts to happen six weeks minimum. I would almost extend that. But six weeks minimum, you're starting to make work ready, asking trades if the materials are actually identified down to the day and to the zone.
I mean, the large procurement should be on its way, but you're starting to really get specific. You're working with trades to make sure that they have all 17 required items at that point. And you're looking for roadblocks, and you're going to identify, discuss, and solve the roadblocks. This is your second point to make sure that the trade partner is participating properly and that you have saddled the right horse. Okay, so I cannot stress enough the importance
of look-ahead planning. Now the pre-con meeting. If you do these well, there's very little in all actuality that you could probably fork up. Because you're going to go ahead and review all the plans and specs. There's no reason not to do this now, especially with AI. You're going to gather all of the relevant information from your AI brain, your AI project brain. You're going to review this with the foreman and the superintendent and the inspector if you have them. Anybody who's relevant to the task, owner, whoever.
And at the end of the meeting, you're going to leave with a single checklist or what we call definable feature of work board or visual or installation work package, according to AWP. And the bottom line is, you are going to know for a fact that that trade is ready to start and have all of the information ready for them to go with a burned-down checklist of things that have to be done before that activity starts. And here's what I'm going to say.
Yes, your production plan is going to get quite big. But any leftover item that has to be done to make that work package ready should go on, in my opinion, in the next three weeks on your actual production plan. If it's like, hey, we need layout for blah, blah, blah. That's the only thing that's not ready for that work package to start properly. Put the layout activity on the damn production plan. Let's get this going. So the way I think that we'll do that is that before the first work package
happens in the first zone, we'll have like a hammock activity, and then we'll add subtasks, lots of detailed subtasks, inside of that actual activity that need to get to be tracked before the actual activity starts. So that's super important. But the one thing that I don't talk about a lot, and obviously material procurement, but we're always on material procurement. And here's, oh, let me say one thing real quick. It's not just, is it here on site? And I'll make a point of that here in just a minute. It's, is it full kit, ready for the
crew, staged at the zone, ready to go, like IKEA? That is the ultimate end of all of our success. Okay? So the other two that I don't talk about enough, and I need to, I get to talk about it more often, is the morning worker huddle and the material queuing for the project. So the way this goes down is that no worker comes onto the project site unless
they are a part of the morning worker huddle, 100%, meaning that they're queued. They're queued 100%. They don't come in to the project site to work unless they have gone through that plan for the day, and they are completely aligned and ready to go from a behavior standpoint. That way I'm not out there babysitting anybody. The other thing is no deliveries come onto the project site until they have been inspected
and everything is pieced out the way it should be, 100%, for the project site. So this is how it's going to go. And if you do those things, installation should start to become the easiest thing you do because you're staying ahead of everything. So if somebody said, hey, right off the top of your head, pick the five most important things in construction from a planning standpoint, that is what I would say. Now, am I 100% right about this? Probably not, but I really believe that at
a minimum, these must be a focus. And if you do that, it'll save you most of the time. I hope you've enjoyed this podcast.
Avoiding the hardest problem rarely makes it disappear; it usually gives it more time to grow. In this episode, Jason explains why one of the best ways to improve projects, leadership, and even your own peace of mind is...
When estimating durations, people tend to drift toward one of two dangerous extremes: padding the schedule because they have been burned before, or promising unrealistic performance because they believe they can push...
You do not need authority over the entire project to start leading. In this episode, Jason shares a story from his own career to explain why the most effective way to lead from below is not to wait for permission,...
A three-week pull may look like Lean planning, but Jason argues that it can leave teams focused on what is directly in front of them instead of preparing the entire phase properly. In this episode, he explains why...
A great meeting should do more than share updates it should expose what is off track and help the team solve it. In this episode, Jason breaks down the purpose and flow of the Level 10 Meeting from the Entrepreneurial...