In this episode, Jason continues his before-phase planning series by sharing practical methods teams can use to test and strengthen a construction phase before fieldwork begins. He explains why every phase must be planned as a coordinated flow of trade trains moving through zones between clearly defined milestones. What you'll learn in this episode: How experienced outsiders can stress-test a phase through a fresh-eyes meeting. Why teams should assume the phase failed and work backward to identify potential causes. How to assign risk owners and mitigation strategies before problems occur. How 4D models, physical mockups, and paper sequencing reveal issues that schedules may overlook. Why simplified installation work packages make the plan clearer and more reliable for field crews. Are you validating every phase before work begins, or are you relying on crews to uncover planning problems in the field? If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊). Also, here are links to our YouTube Channels: · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Hey there, welcome everybody out to podcast number, let's get the number 1644. This will be the second podcast where I talk about before-phase planning. If you're interested in that, please stay with us. Welcome everybody, I hope you're doing well and staying safe out there. I love this topic because every phase, like the phase in a construction project is the core of everything. It's the core of advanced work packaging. It's the core of last planner system.
It's the core of first planner system. It's the core of the tech production system. A phase of work, meaning a train of trades, at least the pace setting train of trades with other trains flowing through zones in a phase between a start and an end milestone is the core of everything. By the way, I have to say I'm super disappointed. I'm just going to have to say this as a data standpoint. I shout out Marco, Dr. Marco Vinegar and Dr. Janusz Lewy all the time and talking
and they just will not stop trolling posts or content or intact about multi-train. There was a comment that was posted the other day that's so disappointing. It said, well first of all Janusz one time said, where's the tack time in this when I showed a multi-train tech plan that was very appropriately done and finished ahead of schedule. I want everybody to know. I had to respond to him and no
response back, like totally cold shoulder. The other thing is recently there was a trolled comment on intact that was like, hey that's not a multi-train. That's the same train going different speeds and I was like, oh my gosh. The problem with tacting is that it's so myopic. They force you into one tack time. They call a phase a train, which is incorrect. They don't understand the analogy.
They have myopically focused on one aspect of tech planning, which actually excludes 95% of the industry and brings everybody back to, oh you can't tack something that's not on rhythm. They ignore the research and the advanced concepts that are coming out of the tact world and they are misleading people and trying to really force people into a single tech time, which is wrong because it will force crews
to abnormally stretch and flex, and I'm just going to say bastardize their sequences and their durations, unnaturally when they didn't have to do it in the first place. It's totally unnatural. It's totally inappropriate and it's totally sick and the comment, that's one train going different speeds. I'm talking about the concept, not the person. How dumb is that? Have you ever seen a train with wagons go different speeds?
That's so dumb. I've never heard of anything dumber than that. There's such a lack of thought. I know there's not a lack of intelligence, but there's such a lack of thought when they say that and it's so disappointing because it's so misleading and a concept that everybody could get around, which is tact, and our industry could drive forward. We have tact influencers fighting about things that don't even make sense. No, a train has engines. They used to have a caboose and they
definitely have wagons or boxcars that are all linked going the same speed, the same distance apart within the train, and if you have wagons that are going a different speed, then what you'll find is that they have their own engine and it's a separate train. It's multi-train. It's very well researched. It's very well thought out and I'm so tired of having to explain these things just because somebody accidentally, hey tacting, I'm sorry that you all like accidentally programmed your software the
wrong way, but that doesn't mean you should confuse an industry and make everybody else's life a living hell. Like we've got to get past this and literally grow up. Like it's time, it's time for lean influencers to grow up and stop worrying about money and stop worrying about being famous and stop worrying about their one little thing that they understand and it's time for everybody to understand everything about tact, last planner, and the Kanban method and these systems like first planner that
really help projects to win and if you don't understand it, great, then say that. Don't go around confusing people. So that's my little rant. I'm literally so annoyed that this keeps coming up. Like it has to stop. It has to stop. It's so irresponsible. It's so unintelligent to say that it's the same train going different speeds. How ridiculous is that? Okay, on to the topic. The before phase system. There's a couple of things that I want to talk about that you can do in addition to the things that I mentioned in
the last podcast to actually make sure that you're doing proper before phase planning. Okay, so a couple things. Fresh eyes meeting. You not only, not only can you do a fresh eyes meeting for the overall project, but you can do a fresh eyes meeting for the phase and so you grab experienced outsiders who are not attached to the plan and you stress test the phase on paper. That way you can make sure that the phase, even if you've already done a fresh size meeting for the whole project, you can
make sure that the phase is going to go well. Another one is a pre-mortem and a risk register with pre-assigned mitigations, meaning assume the phase failed, then work backward and find out why. And in fact, this will get everybody out of the wish thinking and out of their rose colored glasses and then what you can do is get people in the mindset. Once you've got them in the mindset, log each risk and pre-assign its mitigation and owner now, like meaning assign them the mitigation
strategies now so that the response to it can happen real time right away. You already have a plan. It's like Patton in the Battle of the Bulge. All you had to do is say play ball and his units, his commanders already knew what to do. 4D sequencing. This can happen with styrofoam. It can happen with kinetic sand. It can happen with blocks, Legos. It can happen with printed simulations. It can happen actually in 4D. By the way, I love 3D and 4D. It's just not fast enough.
The technology's got to go faster. So tie the schedule to the model and watch the phase build itself in time. Clashes, access conflicts, and crane or lay down collisions, all of these things can really come to light. And then the biggest thing is you're gaining human intelligence. They're actually seeing this and coaching you along the way. Okay, the other one is if you can't do 4D sequencing, do what I call advanced sequencing on paper. So go through the drawing sheet by sheet and walk through the order of the project,
the path of construction, the path of flow, the path of critical flow, and you'll actually feel whether basically things that you're scheduled can't show you. And I like to do this on paper actually. I just print a whole bunch of logistics plans. I print a whole bunch of zone maps. I print blank sheets of paper and I'll just say, okay, here's our proposed sequence and I'll literally just draw it out and I'll be like, oh, there's a gap there. Oh, there's an overlap here. Oh, this can't happen until that.
Let me give you an example. One time, a job site and I was a field director and I was checking the job site's plan and they had a plan to install the tower crane foundation at a certain time. But when I did the overlay, I found that the basement layback actually cut into the foundation and they couldn't install the tower crane foundation for another six weeks. And I was like, okay, we need to go back to the drawing board. Okay. I've already mentioned the foam, but advanced visualization
means sometimes we got to go buy a whole bunch of foam core boards, styrofoam, kinetic sand, or whatever we got to go do and literally just sequence it ahead of time. I've already told you about Jeff Stewart, Southern California, Hensel Phelps. He had his field engineers build the entire building. It was a 400, I can't imagine what it would be now, probably $850 million, but it was a $480 million, which turned into a $620 million high school at the Ambassador
Hotel. They took down most of the Ambassador Hotel and built the Ambassador High School. Anyway, it was really cool. And they built the entire thing and he actually planned the whole thing intact, they call it SIPS, before the project ever started. And it worked out beautifully, wonderful project. Another thing that you can do, which I'm also always telling our people, is to create more detailed installation work packages. Not detailed like it's more complex, but simplify it. Break the work down into packages a crew
can finish in a known short window, which is your talk time, with everything attached. The finer, meaning the more simpler the package, the truer the plan and the earlier that roadblocks will reveal themselves and the better the crew will be able to do. Why not spend more time making the kits and the information better for the crews? There's so much to this, I think I'm going to break the next one into another podcast. So I'll leave this one the way it
is, and hope you've enjoyed it. And I'll say on we go.
Avoiding the hardest problem rarely makes it disappear; it usually gives it more time to grow. In this episode, Jason explains why one of the best ways to improve projects, leadership, and even your own peace of mind is...
When estimating durations, people tend to drift toward one of two dangerous extremes: padding the schedule because they have been burned before, or promising unrealistic performance because they believe they can push...
You do not need authority over the entire project to start leading. In this episode, Jason shares a story from his own career to explain why the most effective way to lead from below is not to wait for permission,...
A three-week pull may look like Lean planning, but Jason argues that it can leave teams focused on what is directly in front of them instead of preparing the entire phase properly. In this episode, he explains why...
A great meeting should do more than share updates it should expose what is off track and help the team solve it. In this episode, Jason breaks down the purpose and flow of the Level 10 Meeting from the Entrepreneurial...