In this episode, Jason explores a critical concept in Lean construction: understanding the difference between the waiting you pay for and the waiting you don't. He explains why pushing workers, adding extra crews, or forcing every zone to be active can actually create costly inefficiencies, while well-balanced flow and strategic pacing prevent unnecessary waste. What you'll learn in this episode: The hidden cost of "waiting you pay for" vs. natural gaps in work. How to balance resource efficiency and work efficiency. Why rushing, trade stacking, and overtime can hurt flow and morale. How to optimize production without overburdening crews. The Lean definition of success: fastest throughput, highest quality, lowest cost, and respect for people. Are your crews truly working efficiently, or are you paying for waiting unnecessarily? If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊). Also, here are links to our YouTube Channels: · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Hey there, welcome everybody out to podcast number 1635. I've got a killer podcast for you right now. This is, the title is gonna be Waiting You Pay For and the Waiting You Don't. If you're interested in that, please stay with us. Welcome everybody. I hope you're doing well and staying safe out there. I'm super excited to be on this podcast. I've been really behind actually. I went, where was I? I think I was at a bootcamp and
then, no, no, no, I know I was at a bootcamp. Then I went to El Paso for a week with a client. Then I had a couple of days off. Then went to Canada. And then yesterday I went to Yuma. And then today I'm headed to a recording. And so I haven't really been back in the mix for a little bit here. So I'm just getting caught up. And I appreciate everybody being patient with me. But this podcast topic is fire.
I think you're gonna love it. And it hit me the other day based off of lean principles. These lean books that I'm writing and researching are really doing a lot to solidify this knowledge in my brain. And I couldn't be more grateful. So the waiting you pay for is when you say, or somebody says with authority, I want every worker busy. I want extra crews. I want extra workers.
I want to work overtime. And I want every zone being worked on. I want everything being worked on. That, ladies and gentlemen, is the waiting that you pay for. What do I mean by waiting? I mean that people are waiting for information, for roadblocks to clear, for materials. And they're literally standing there. Or they're on treasure hunts. Or they're trying to keep busy. Or they're doing work-based planning, which a
project engineer or somebody else on staff should have been doing. Or, or, or, or. The waiting that owners are worried about is the waiting of a zone, or waiting, like I remember Brad Nelson one time coming back from an LCI training and saying, it's either workers waiting on work, or work waiting on workers. And workers wait in construction. This is not true for manufacturing. But one of those is worse than the
other. And there's, we've talked constantly about these concepts of like resource efficiency and flow efficiency. But really, there's a couple of extremes. Like flow efficiency, we should actually call it work efficiency. We should, instead of just, so Nicholas Modig does a great job. But he only has two definitions. He has resource efficiency and flow efficiency. But there's actually a third. There's resource efficiency, flow efficiency, which is right
in the middle. It's a balance of both. And then work efficiency. And if you have resource efficiency, that means that each piece of equipment might be optimized within themselves, sub-optimized, which hurts the overall flow. And then work efficiency is where you have all of the work being worked on so that each area can be efficient within itself, which hurts the workflow as well. What you have to do is merge. You have to match the pace and capability
of resources with the desire of the client. Meaning you have to match supply and demand. And so having a trade say, oh my gosh, I wanna be efficient, I want the whole building to myself and to stage, that makes me more efficient, is detrimental to production. But also saying every zone has to be worked on and every person has to be busy is false as well.
Really false, actually. And it hurts people. Because when you have everybody working at full efficiency inside of a zone, that means you get, on a project site, when you aggregate everybody together, you get trade stacking and trade burdening. And you get people, lots of people thrown at work that may not be ready. Like I tell people in conferences and in trainings, you could, every crew on the site
could get 10 additional trained people. And really not go any faster if the areas are not ready, if the system is not in rhythm, and if you don't have the materials or the information. So if you're in the TAC production system, and if you are, you will always have zones that are at some time or another not being worked on. And you will have people that are not at 100% capacity. And an owner opens their mouth and ignorantly
says that something should be done about that. You're into the waiting you pay for and the waiting you don't. And let me explain both. The waiting you pay for is where workers are waiting on those things and that work is not made ready, but you've brought out additional crews, you've told people to trade stack, trade burden, you brought out additional workers, you're working overtime, you're rushing and pushing and panicking. That's waiting you pay for. And it is expensive. The waiting you don't pay for is where
that zone may be waiting for a crew because there's a little bit of a gap or even an inefficiency gap. Or the trades are going maybe a little bit different paces. Or maybe you have had to crew down a crew to go the pace of the rest of the crews, right? You're not working at full efficiency, but you're not paying for it either. Because your project schedule, your production plan is still finishing it at the soonest possible point.
And you're not rushing and pushing and panicking. So you don't have additional labor. You're not paying for overtime. You're not paying for treasure hunts. You're not paying for walking around. You're not paying for the additional labors that aren't being able to be put to use. You're not paying double or time and half or double time. You're not paying for it. So if you go rush and push and panic, the people are waiting. But if you have a well-intentioned, flow -efficient plan and every now and then the
zone isn't being worked on, that is waiting, meaning a zone waiting on workers that you don't pay for. So we have to be very, very wise about what we do. So now, just so we're clear, nobody, Jason never said, work everybody at full efficiency, which is resource efficiency. Nobody ever said, which also will cause gaps in your schedule. Nobody said, let's go ahead and focus on work efficiency, which is where every zone is worked on all the time.
I said, match a beautiful, balanced plan between work efficiency and resource efficiency and get what Nicholas Motor calls flow efficiency. I don't have any problem with Nicholas's work, but because he doesn't do construction, he never pulled in the two ends of the spectrum and explained the middle. He just explained one side and the middle. So just to paint this out and make sure that everybody's clear. If you have every trade just doing what's best for them, that's called sub-optimization, it's
not good. Or if you have an owner say, there shouldn't be an empty zone, work overtime. I want people worked and I don't care if there's trade stacking or trade burdening, that's bad. We have got to be intelligent enough, educated enough to keep everyone in a flow and optimize for our shortest overall throughput time, best quality, but respecting people at the same time. That's the only way you win. I love the definition. Lean is about finishing a project or a phase at the shortest duration, highest level of
quality that takes care of our people at the lowest overall total project cost. And that is what we're looking for. So there's waiting you paid for and there's waiting you don't. Be wise about which one you choose. I hope you've enjoyed this podcast. On we go.
Avoiding the hardest problem rarely makes it disappear; it usually gives it more time to grow. In this episode, Jason explains why one of the best ways to improve projects, leadership, and even your own peace of mind is...
When estimating durations, people tend to drift toward one of two dangerous extremes: padding the schedule because they have been burned before, or promising unrealistic performance because they believe they can push...
You do not need authority over the entire project to start leading. In this episode, Jason shares a story from his own career to explain why the most effective way to lead from below is not to wait for permission,...
A three-week pull may look like Lean planning, but Jason argues that it can leave teams focused on what is directly in front of them instead of preparing the entire phase properly. In this episode, he explains why...
A great meeting should do more than share updates it should expose what is off track and help the team solve it. In this episode, Jason breaks down the purpose and flow of the Level 10 Meeting from the Entrepreneurial...