In this episode, Jason explains why so many construction activities suffer from constant two-to-four-hour delays. The root problem is often simple: teams are reacting in the field instead of choreographing tomorrow's work in advance. Jason breaks down how delays around forklifts, cranes, layout, deliveries, trade coordination, and access can compound throughout the day. He explains why the afternoon foreman huddle and day-ahead planning are essential for locking in logistics, resources, handoffs, and responsibilities before crews arrive. What you'll learn in this episode: Why reactive construction creates repeated delays throughout the workday. How day-ahead planning helps eliminate waiting for equipment, information, access, and coordination. Why "figuring it out" should happen during pre-planning instead of in the field. How the afternoon foreman huddle helps choreograph the next day and create more predictable production. Are you choreographing tomorrow's work today, or are your crews still spending hours waiting for the project to react? If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉). Also, here are links to our YouTube Channels: 路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg 路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt 路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured 路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Hey there, welcome everybody out to podcast number 1683. In this podcast, I'm going to talk about construction has no choreography. If you're interested in that, please stay with us. Hey there, everybody. I hope you're doing well and staying safe out there. I have really been thinking about a certain concept and observing it. I've been doing a lot more field walks lately. The main way to scale operational excellence is
to have an operating system, and we have that complete in our books now. Training, which our SuperPM boot camps are just out of this world now. And then monthly field walks to support and help. So um, that is the pattern and we're getting paid a lot more to do the field walks because people want to take it all the way. They don't want to wait years for their lean transformation. They want it in six months, eight months, 10 months, which is super, super possible by the way.
If you do, if you follow that scaling system, it's really quite remarkable. Um, and as I'm, as I'm doing more field walks, I'm noticing something that's absolutely, uh, absolutely a pattern is probably the way I want to say it is that everything in construction has at least a, and I'll, I'll be, I'll be generous. I'll be generous and say a two to four hour delay, a two to four hour delay. If a trade has a question, a two to four hour delay. If you want the forklift, a two to
four hour delay, if you want the crane, a two to four hour delay, if you want to meet with a foreman on site, a two to four hour delay, if you call somebody a two to four hour delay, uh, if you have, uh, a issue that might stop the train and need to talk to other trades around you, a two to four hour delay to get this logistics item, uh, so that you can actually mobilize into the building, a two to four hour delay. You're probably getting annoyed at me by now, but this is, I'm, I almost want that
because I want you to like hate it in your soul. A two to four hour delay. Um, if, if you, um, want that layout from the field engineer, I could just keep going on and on and on a two to four hour delay for everything because we are reactionary instead of proactive. And there's, uh, a couple of reasons why the human brain does this. And I'm not a, I'm not an expert at this by any means, but I do attempt to research this as much as I
can, that the human brain has got to be able to envision why something is important or why, or be able to envision the risk to do the pre-planning effectively out ahead. And it has to be important enough for the human brain to choose it in the moment. And most of the time we choose to go figure things out in the field instead of, uh, preventing problems from happening in the first place. And like people pride themselves on that.
I just, I, there's a huge misconception. Like I always believe in figuring things out. I am a figure it out kind of guy. In fact, like when I, uh, I'm a super judgy by nature, nurture, accident, or behavior. I don't know. But, uh, if I'm judging somebody's performance, um, if they can't figure things out, if they have to be spoon fed everything all the time, I'm like, I don't, I, I don't really have any use for that, but I'm never talking about figuring it out in the field. I'm never talking about figuring it out after
the fact. I'm never talking about figuring it out in the moment. I'm talking about figuring out in the pre -planning, figure it out in the pre-planning, figure it out in the pre-planning. Let me say it again, figure it out in the pre-planning. I don't expect anybody to go figure it out as victims and to get used to that and get good at that. I expect us to figure out through proper research and diligence, how to prevent problems from happening in the first place. So we have this problem. We're all trying to react, uh, but we
have this two to four hours, sometimes six or eight or sometimes days delay, but it's probably actually about a four hour average delay that we're dealing with all the time. And I want somebody, somebody to tell me that it's not the most annoying thing. I told you the other day about, uh, waiting for that project manager who didn't have anything ready when we had, uh, flown somewhere to do a certain project. And it was like, Oh, you know, I don't really have it done, you know? And it was like, Hey, let me just go firefight and feel significant in the moment.
And it just one instance left such an impact on me that I'm still mad about it. And yeah, you can call me emotionally immature and I'm super fine with that. But like one time and I, it crawled under my skin. It ruffled my feathers. It was like, it was, it was so annoying. It was so annoying. And the fact that the person didn't have any acknowledgement of what was happening was so frustrating. And people tease me all the time in the United States.
Oh, afternoon foreman holes. I going to do it the morning. Oh, that's what the lean builder said to do. Blah, blah. And people are arguing with me, arguing with me, arguing with me. But if we don't want the four hour delay on average, then we have to start pre-planning out ahead. We have to start looking at least a day ahead. We have to make sure everything's locked in for tomorrow. We have to make sure all deliveries are scheduled for tomorrow. We have to make sure that everything is mapped so that we know where it goes tomorrow.
We have to know when the forklift is available for tomorrow out ahead. We have to make sure everything is locked in and ready. And I hate this stupid rule that meetings can only be a certain length. That foreman meeting is however effing long it needs to be to where the next day is as predictable as possible. And if we don't do that, we are signing up for four hour delays all throughout the day. In addition to the already hard work that
we had to do. And it's not fair. And my main point is, if I got annoyed and got my feathers ruffled the other day because of one instance, how in the world does a trade partner not want to just hurl themselves off a damn bridge every day, waiting for the forklift, the crane, the hoist, somebody to move something out of their way. There's a pile of dirt. Somebody parked their truck in my way. Like how annoying is this?
We have to stop it. Everything in construction has a four hour delay. And if you want to get rid of it, you have to start locking in the plan the day before. I hope you've enjoyed this podcast.
Avoiding the hardest problem rarely makes it disappear; it usually gives it more time to grow. In this episode, Jason explains why one of the best ways to improve projects, leadership, and even your own peace of mind is...
When estimating durations, people tend to drift toward one of two dangerous extremes: padding the schedule because they have been burned before, or promising unrealistic performance because they believe they can push...
You do not need authority over the entire project to start leading. In this episode, Jason shares a story from his own career to explain why the most effective way to lead from below is not to wait for permission,...
A three-week pull may look like Lean planning, but Jason argues that it can leave teams focused on what is directly in front of them instead of preparing the entire phase properly. In this episode, he explains why...
A great meeting should do more than share updates it should expose what is off track and help the team solve it. In this episode, Jason breaks down the purpose and flow of the Level 10 Meeting from the Entrepreneurial...