Ep.1660 - What Happens When Your Production Plan Is Missing?
7 minAudio
In this episode, Jason explains why a complete production plan is essential for reliable construction flow. Without the right milestones, pull planning, buffers, look-ahead planning, and day planning, projects quickly become reactive. Jason breaks down how the Macro Level Takt Plan, collaborative pull planning, six-week make-ready planning, weekly work planning, and daily planning work together as one production system. What you'll learn in this episode: Why the Macro Level Takt Plan is critical for setting accurate milestones and project duration. How pull planning creates the right sequence, line of balance, buffers, and optimized system. Why six-week make-ready planning removes roadblocks before they impact committed work. How weekly work plans and daily plans keep trade partners aligned around reliable handoffs and execution. Does your project have a complete production plan from the Macro Level Takt Plan all the way down to the daily plan? If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 馃槉). Also, here are links to our YouTube Channels: 路 Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg 路 LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt 路 LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured 路 LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Welcome everybody out to podcast number 1660. At least I think that's the number. Yeah, that's the number. Okay, I'm super excited to be with you. I'm gonna talk about what happens if we're missing a production plan. If you're interested in that, please stay with us. Welcome everyone, I hope you're doing well and staying safe out there. Exciting news, just shipped out our first tact simulation and the other ones are in production.
We have four printers going full-time, super exciting stuff. And I recorded for the first time at the office, at the Lean Logistics office. In fact, just got the LinkedIn site up and running. YouTube will be up and running soon. And it's so interesting how much more fun Lean is when you have an actual physical space. Every single day I find something to 3S and then go find a waste and then
make a before and after video. Really cool stuff. So anyway, I'm gonna be talking today about what happens if a component is missing, and meaning the production plan. When I say a production plan, that means a macro level tech plan that sets proper contractual milestones. It means that we then do a pull plan, and a collaborative pull plan with the trades. And through that effort of zoning it properly and sequencing it properly, we gain buffers.
And then we're able to do a six week make ready look ahead and a weekly work plan, and then a day plan. Well, I know it sounds simple, but if you're missing the macro level tech plan and you have something like a CPM schedule, you will not have proper milestones and you will not have a proper overall total project duration. And so you will enter a crash landing most of the time, I won't say all of the time unless you, like if people
have done a CPM schedule well, it's probably because they accidentally overshot the milestone by some miracle and they relied more heavily on their look ahead plans to build the workout in the field with flow than anything else. But anyway, but for the most part, if you don't have a macro level tech plan, you won't have accurate milestones and you will not have a correct overall total project duration. If you don't have a pull plan, that's catastrophic.
If you don't have a good pull plan, the first thing to do is absolutely freak out. I mean, you should be devastated. And when I talk about being devastated, what I mean is you will not have a proper sequence, you will not have a proper line of balance, you will not gain buffers. And almost all known constraints, constraints, system constraints will negatively impact you because they have not been observed and analyzed and optimized.
When we look at the root cause of most constraints and roadblocks, it really comes down to a pull plan, a improper look ahead planning and not doing pre-construction meetings. Like literally those are the main root causes. So if you have a production plan and pull planning was the start of it basically or is a part of the overall process and you do it well, you will have a correct sequence, a correct line of balance,
the proper buffers, and you will have an optimized system. See, when we talk about constraints or roadblocks, they're two very separate things. Constraints are system problems, roadblocks are things that are in the way of the train of trades. All constraints should be, all system constraints should be known, analyzed and optimized by the end of the pull plan. If you don't have that, you won't get that done. The other thing is the production plan with buffers.
If you don't have a production plan with buffers that has really beautiful trade flow, is well articulated in a time by location format, like I said, with buffers according to a risk analysis, then you won't have a basis, a visual basis from a schedule standpoint. You won't have a plan that you can use to target excellence and productivity in the field. And then you won't have the ability to do six week, make ready, look ahead planning and weekly work plan.
The six week, make ready, look ahead plan is where you look anywhere between three, I prefer to do six, but three to six weeks out, and you identify, discuss and solve roadblocks before they impact you on the weekly work plan. And the weekly work plan, if you don't have that, then you won't have committed handoffs and buy in from the trade. So it's a huge problem. And then if you don't communicate your day plan every day, or make your day plan
every day in the afternoon foreman huddle and communicate it in the worker huddle, then people will all be going in different directions. And that's more detrimental even than low crew productivity or not having enough people. So these are big, big problems. You must have a production plan in construction if you wanna do well. And if you wanna have a target that intersects all of the varying things that have to come together at the right time, tools, materials, equipment, space, permissions, the whole nine.
So those are the consequences if you don't have that. So please implement the TAC production system with a complete production system all the way to a day plan. I hope you've enjoyed this podcast. On we go.
Avoiding the hardest problem rarely makes it disappear; it usually gives it more time to grow. In this episode, Jason explains why one of the best ways to improve projects, leadership, and even your own peace of mind is...
When estimating durations, people tend to drift toward one of two dangerous extremes: padding the schedule because they have been burned before, or promising unrealistic performance because they believe they can push...
You do not need authority over the entire project to start leading. In this episode, Jason shares a story from his own career to explain why the most effective way to lead from below is not to wait for permission,...
A three-week pull may look like Lean planning, but Jason argues that it can leave teams focused on what is directly in front of them instead of preparing the entire phase properly. In this episode, he explains why...
A great meeting should do more than share updates it should expose what is off track and help the team solve it. In this episode, Jason breaks down the purpose and flow of the Level 10 Meeting from the Entrepreneurial...