In this episode, Jason continues his before-phase planning series by focusing on how to prepare, evaluate, and align trade partners before they enter the critical production phase. He explains why participation during pull planning, look-ahead planning, and preconstruction meetings is a strong indicator of how a trade or foreman will perform in the field. What you'll learn in this episode: How early participation helps identify reliable trade partners and foremen. Why visiting crews on other projects reveals how they are likely to perform on yours. How verified production rates and labor commitments support reliable phase planning. Why onboarding, workable backlog, safety planning, and quality planning must happen before critical work begins. Are you evaluating and preparing your crews before the phase starts, or waiting until production problems appear in the field? If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊). Also, here are links to our YouTube Channels: · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Welcome everybody out to podcast number 1647. I'm going to continue talking about before phase planning. I really want to turn this into something that people can utilize and use, and I'm super excited about it. So here we go. Before phase planning, stay with us. All right, here we go, team. This is going to be a normal six, seven minute podcast, but we're going to talk about crewing the train. Here's some options. Identify non-participating trades. This is a big one. One of the key things that you should
do in pre-con, first of all, is only select and go out to participating trades. But if you have a new trade that you've never worked with, your four month mark of asking a trade to participate in a pull plan, and then any subsequent interactions with the trade partner preparation process are an indication of how that trade is going to perform. And if they are not participating, then you, you switch that trade. You do not let that defect pass on to the field crew.
You have so many opportunities to make sure that we have great crews participating trades, um, showing up on the job site. If you have non-participating trades, they won't show up on time. They're not participating in the meetings. You don't have a good pre-construction process or probably a good pre-construction department. Um, visit trade crews on other sites. This is another thing you can do. How they're, how that crew that's about to come to your project into that phase, how they perform on other job sites is how
they're going to perform on your job site. And do like Toyota does, spend most of your time with your trades and your vendors before they come to your project site. Um, and, and, and, you know, at Toyota, they'll spend 10% at their own factory, 90% with vendors. You don't have to have that ratio, but supers and project engineers, especially can spend at least 10% of their time with, uh, the trade partners, queuing them up and making sure that you're evaluating them before you, they ever get to your project site.
Another one is verifying production rates. Don't go with guesses. Don't get, go with human estimation. Don't go with, I think literally go take the time to dig in and find out what the actual production rates are for those trades before they come to your site. So you can verify that you can actually finish on time under the proper circumstances. Um, another thing with that is according to the production rates, verify labor commitments and that they're able to ramp up. This is something that I did at the bioscience research laboratory for our most critical trades.
I did it with mechanical electrical plumbing. And I think, uh, the exterior traits and it worked out beautifully. They were like, this is how much labor I need to accomplish what's on your macro level attack plan. And it worked out and they had the labor and they were able to ramp up. So do these verifications ahead of time. Um, another thing is trade on boarding, um, trade on boarding. If there's training that's needed, if there's queuing that's needed, like I said, I'm never going to run another project where I don't queue
the people, the trucks and the materials. They're not, nobody's getting through that second gate until I verify that everything's broken out. The trucks are clean five S and that we've got people that are aligned and oriented. Um, the other thing is we need to make sure that we have workable backlog on the project so that we have swing capacity. And so we can start these trades and start to evaluate them on the site with workable backlog and not the critical production work that we're really, really, really worried about.
Here's a big one. You're going to be evaluating the foreman and, uh, in the pull plan and in the look ahead. And then, uh, all of the, um, subsequent meetings that you have for like the, the look ahead and the pre-construction meeting and the weekly work planning meeting. If you have a foreman that's not participating, you got to replace them right away. Now I love foreman. There's nobody I love more than foreman, but I've never seen a foreman of non-participating foreman situation ever get better.
If you've got a non-participating foreman, you're always going to have, I don't even know why that's the case. I'm talking like over a hundred examples of this in my career. If you need to replace a foreman and I'll also say a trade, you need to do that before they ever hit the project site. People say, Hey, I can't supplement. Yes, you can. You're a general contractor. You are a general contractor, right? The contracts to where the foreman in the trade has to be, has to participate in before phase planning. And if they don't, they can, it will
be, they can be supplemented and the materials must be turned over to the general contractor for management. A hundred percent. This has to be, um, the way we approach this so that we don't allow, we don't catch chaos and allow enemy behavior onto the job site. We prevent it from ever coming to the job site in the first place. Um, and then the other thing we can do is really great pretest planning. We can develop our AHAs, our JHAs, our site-specific safety plans, our site-specific quality
plans. These are some really cool things we can do before the phase. Sorry about the background noise here. I apologize. They don't give me that option on the Waymo, but anyway, these are some things that you can do with the crew specifically. I hope you've enjoyed this podcast and on we go.
Avoiding the hardest problem rarely makes it disappear; it usually gives it more time to grow. In this episode, Jason explains why one of the best ways to improve projects, leadership, and even your own peace of mind is...
When estimating durations, people tend to drift toward one of two dangerous extremes: padding the schedule because they have been burned before, or promising unrealistic performance because they believe they can push...
You do not need authority over the entire project to start leading. In this episode, Jason shares a story from his own career to explain why the most effective way to lead from below is not to wait for permission,...
A three-week pull may look like Lean planning, but Jason argues that it can leave teams focused on what is directly in front of them instead of preparing the entire phase properly. In this episode, he explains why...
A great meeting should do more than share updates it should expose what is off track and help the team solve it. In this episode, Jason breaks down the purpose and flow of the Level 10 Meeting from the Entrepreneurial...