Data Centers, Local Resources, and Government Failure

Aug 4, 202644 minAudio
ShareXLinkedInFacebookWhatsAppEmail

In this episode, I examine the rapid expansion of data centers and the pressure they can place on local electrical infrastructure, water supplies, land use, tax policy, housing, and other community resources. While data centers are often blamed for moving into an area, the larger issue may be the decisions made by local governments that approve these projects, offer substantial incentives, and fail to establish meaningful requirements to protect the people who already live there. This discussion is not simply about opposing data centers or economic development. It is about responsible growth, transparency, and accountability. Local officials should carefully evaluate the long-term costs, require data center operators to address their impact on infrastructure and natural resources, and ensure that existing residents are not forced to carry the financial or environmental burden. Data centers may be necessary to support our increasingly digital world, but local governments have a responsibility to negotiate agreements that genuinely benefit the entire community - not just developers, investors, and short-term tax projections. Become a supporter of this podcast: https://www.spreaker.com/podcast/electrify-electrician-podcast--4131858/support.

Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.

Transcript

From the show. Tap a time to play from there.

Speaker 1Welcome to the Master of the NEEC podcast, the ultimate destination for anyone passionate about the electrical trade. Whether you're a season electrician, an eager apprentice, or just someone who wants to dive deep into the world of electrical work, you've come to the right place. Join your host, Paul Abernavi, a true authority in the industry with over thirty eight years of trade experience, as he electrifies your mind within depth discussions, expertips, and valuable insights that will keep you ahead of the curve. Each episode, Paul will illuminate the

Speaker 1complexities of the trade, decode the national electrical code, and share the latest industry trends, all while empowering you to take your electrical career to the next level. So gear up, plug in, and get ready to supercharge your knowledge because with the Master of the NEEC podcast, the power is in your hands. Now get ready. Here is your host, Paul Abernavis.

Speaker 2Whatever, everybody, Welcome to another episode of Master the NEC, the podcast where we talk about all things electrical, electrical contracting, things about the electrical industry, and just plainly answer questions you have about anything to do with being an electrician and things like that, hiring, firing, marketing, national electrical code, all those type of things. Now today's episode is a little different because it kind of touches me a little bit in order to give an opinion on something that

Speaker 2seems to be really going all over the country. And it's amazing since twenty twenty two, the rapid growth of the data center topic has really grown. And it kind of started about twenty twenty two when we all of a sudden had the explosive expansion of AI and everybody wants AI, everybody. And we'll talk about a little bit today about how it touches you. But you may think it doesn't. And so you know, there's a lot of

Speaker 2protesting about it, a lot of people blaming the data centers, saying they're not good stewards of the environment, they don't do this, they're being plopped down in neighborhoods. This is probably all true to that part, But the reality is you really can't blame the data centers. But I'm going to kind of do it and explain some things to you for those that are interested, those that are not piss off, you can move on by if you like.

Speaker 3You don't have to listen, but I'm going to kind.

Speaker 2Of explain to you where we're at and why things rapidly changed in twenty twenty two so differently, and how you know, how data today is much different than it was even again just in twenty twenty two and earlier. So let's kind of start this thing with the problem. So I live in Louisa County, Virginia, and we are very close to what they can see or the data Center Alley, which is Alloudin County, Northern Virginia rapidly becoming areas around Fredericksburg, Virginia, and all that Northern Virginia stuff

Speaker 2at Corridor is becoming, you know, per capita, it's the largest group of data centers. And you can say in the world, be honest with you, because the vast majority of data centers in the world or right here in the United States well over three thousand plus compared to other countries. I mean, so it's not an argument. Really, are we trying to beat China, for example, to the AI race.

Speaker 3No, we're strongly ahead of that.

Speaker 2That is not the case because again, you can be technology, but if you don't have the capacity to to scale it, then it just doesn't do anything for you. And I'll explain all that in a hopefully in an elementary way, not because I'm talking down, but because it just gets so confusing for people. I go on social media and I see next door here in the Louisa County area, we see.

Speaker 3TikTok.

Speaker 2Social media is everywhere, and everybody's bashing these data centers. They're protesting, and again they they deserve some of the blame, but no more of a blame than we the consumer. So let's kind of take it back a little bit. So the normal reason that we scale up so quickly is because originally, when it comes to data, it was warehoused and servers all around the country, and it was kind of dumb. Data means that when we would type something into Google or any of the search engines, it

Speaker 2would go up into the cloud. So it leaves you, goes through your fiber, goes to your switching gateway, then it goes out to wherever it goes. It gets broken into tokens. Those tokens are numbers. Those numbers is what they pay for. Kind of think that as widgets, it goes out and then it goes through the data center and it just spits you back information that was already out there. So when it comes to the old days when we're just searching for something in Google or being or anything, we're really we were pulling information that already exists,

Speaker 2whether it's in somebody's book, whether it's articles I've written, or whether or not it's articles.

Speaker 3Other people have written.

Speaker 2That's pretty easy because that's just pulling stored data from a collection of intertwined servers. That's not really power intensive to do that. It's just really a regurgitation of information.

Speaker 3That's already out there.

Speaker 2So when people say what has changed in order for us to have this massive growth in data centers, what's changed is how we want the information. So if you were just simply typing in something and you're trying to pull back something on a topic without it being original, it's basically just pulling it from published data that gets uploaded into this net network of interactive servers that is your network, that is your cloud, but it is based

Speaker 2on physical information that somebody has created. That's easy, and we've been doing that for nearly twenty thirty years since the Internet's been around. Okay, so really what's happened is the technology of the chips. Ok And what we're asking now servers to do is create very complex calculations, be very freethinking in how they develop stuff in order to.

Speaker 3Help us in our daily tasks.

Speaker 2You know, today you cannot go and get any app that's online, whether it's your banking app, whether it's whatever. They all have an AI tool, they all have an AI model. Okay, there's a bot involved. Now, this is a freethinking opponent and it has to think about it and give you a response very quickly. That is far different than simply regurgitating information that's floating in the Internet. Now,

Speaker 2the growth of the data centers clearly started in Really the growth started in twenty twenty two when the AI started ramping up, and then again the chips became much more powerful and the things that it could do. Now, I'm not gonna lie I in full transparency. Most people know that I own trade Hog. Trade Hog is an AI tool that's designed to help electricians in the field, but also plumbers mechanical, it doesn't matter. It's designed to

Speaker 2pull up relevant codes, so it looks for data, but how it compiles it is very intelligent, and we're constantly feeding that data so it's not just a copy and paste. It's the way it presents it is very intelligent. Now we're connect did to and this is no secret. Most people know that there's the data centers that create the AI interaction like open AI, things like at X and XAI and all this kind of stuff Microsoft and Meta

Speaker 2and so these data centers will think about what the response is intelligently and it will create it. Now, I've used AI to create letters, to proof things, to write articles, and then I go through them to make sure it's accurate. Because I don't trust it. I have to go through it. I can't help it. I've used it to do certain tasks for me, create software, create websites, web web pages. I've asked it to do a lot of things. So

Speaker 2organically it creates these things and it has to be an intelligent component. So there's the chips started integrating this AI capability. And again we can grow, moaning, grown about it, but you're not giving it up. You can say you don't want a data center in your backyard, you can say that I don't want to see it, but you still are using the technology. If you're listening to this, this podcast was uploaded in a data center somewhere and you're requesting it from that data center to listen to it.

Speaker 2It's you're contributing to the problem. If it's a problem, you're helping create it. So you can't really you can whine about it, you can moan about it. I don't like it. I wouldn't like one right across from my house. But the reality is we've created this beast, and we created it because we want things quicker, faster, more intelligent, more accurate. We wanted all these things, and so we want that our banking online is quicker, more accurate. We

Speaker 2want all of our search results to come back more quicker and accurate and more detailed. And we don't just pull up documents anymore that are just pre done or pre loaded. There's an intelligence behind these documents. There's an intelligence behind these responses, and that takes computing power. So the first thing we'll kind of talk about is the electricity, the grid, the power. So currently the power grids cannot handle the rapid growth that it's expected of these data centers. Okay,

Speaker 2the megawatts and the gigawatts of power these things are consuming has to come from somewhere, and a lot of times they bid for this power, which ultimately means that in your jurisdiction, your power costs. It might be twenty cent per certain number of kiloot hours, but it's going to go up because it's a bidding process.

Speaker 3And they have to allocate this power.

Speaker 2But the trade off is that you're getting all of the benefits of the AI. You're getting it whether you like it or not. Now you might say to yourself, don't have that, I don't want it.

Speaker 3Well, then you're gonna have to go back to the stone ages.

Speaker 2Because the phone that you're using connects to data centers and has an AI component. Nearly half the things in my house is connected to the Internet and has a smart feature on it that's understanding, that's always learning. So, whether you like it or not, this is where we're going. Okay, So the electricity is the first component. And so in our area, for example, we have the nuclear power plant. Well, the nuclear power plant is only able to put out

Speaker 2a certain amount of power and you can't just definitely add additionals to it. It's not like the plant is growing. Okay, So the Lake Anna nuclear power plant has a certain amount of capacity. There's other power plants, they have certain levels of capacity. So this is why all of the data centers have these massive generators for that time when the grid can't handle it. Maybe they're waiting for that

Speaker 2one day that the grid goes messy. They can still power it and preserve the information and keep the Internet flowing, keep the AI flowing. Okay, and in many of them will actually run these generators, and this is why you hear them because the grid in that area cannot handle their capacity and so they have to supplement it with these generators, and that is very costly for them. But it generators do generate noise. It is what it is.

Speaker 2But we as consumers have helped create that. Now you might be saying some people will say, well, that's fine, as long as they build somewhere else. Well, this is where the problem begins. And it's even before we have to worry about water consumption and taking natural resources and all those type of things.

Speaker 3Before that, it has.

Speaker 2To do with the luring of these data centers to certain areas geographically that are close proximity to readily available power and resources that end up being wooed there by your local government. Now, it doesn't hurt that a governor, a governor of a state, may or may not make it more advantageous for a data center project to come to your area. I mean, data centers are in business

Speaker 2to make money. They're not lying to anybody, they're not telling anybody. They're just here to be good stewards of the community.

Speaker 3Dude.

Speaker 2They're a business no different than John's mom and pop down the street, or you know, Susie's clothing store. They're no different. You may not like them, but they're no different. And yes, they do create a massive opportunity for employee growth hiring jobs, whether they're aminable or not, or just because of the buildout or whatnot, but they do create this in the community.

Speaker 3You know.

Speaker 2Obviously, some of that wanes as it's complete and it becomes online and they get normal number of people that they need per CPU, and that's a whole factor they do. But there's a there's a real reason why data centers are expanding so rapidly, and the real reason for that is the numbers. It's basically scale scalable law means that if one facility has to run it mass capacity, then it's inefficient to run. If you branch it out and

Speaker 2spread it across a network, then the cost of operation come down. So the reason they're opening up so many is because the demand is so high that the scalable law means that they spread it out amongst other data centers so that it's it's manageable. Whereas you can't simply do this, the capacity would not work with one facility. Now, some people say, well, why don't they build them out in Arizona. Well, they're building them in Arizona out and the deserts and stuff. But again they need resources as well.

Speaker 2And I know that might sound good for you because you don't want it in your backyard, but you still grab that phone. You still want the technology, you still want the AI. You want it, you know you want it. You just don't want the repercussions from it. And I get it. So this takes me back to where we were talking about the government local. So the problem with it is that a lot of times, and again by no means of I an expert on data centers. Let me make that up front. You know I'll get my hate mail. I always do. This is my podcast. I'm talking.

Speaker 2You choose to listen. If you don't, you can move on. But The biggest issue locally is the incentives that are given to the data centers. Now, granted, they will pay large amounts of money for the area to be able to build these So if your local government or your state is giving such tax break, that and in many cases they're saying, look, you don't know any property tax for five years just to come to our locality. Well,

Speaker 2that's the problem we have locally with Louisa Fredericksburg area or whatnot, is that the council members and everybody that's voting is being lured by the prospect of money, teacher raises and other things that they don't see the other issues, and that is not holding the data centers accountable. In other words, you know, first of all, I'd never run for office. I hate politics. I hate politicians in general. It doesn't matter whether you're a Republican or a Democrat. I think they're all crooks. I trust some more than others.

Speaker 2But at the end of the day, anybody that gets in and runs more than one term or two terms or not in it to help the community. They're in it for a career and I'm just against that. But you know, people that sit in the these offices for thirty years, forty years. I think that's you know, that's just I don't agree with it. But anyway, that's neither here nor there. I'm not gonna We're not creating a situation where it's one party versus another.

Speaker 3That's not what this podcast today is about.

Speaker 2We're talking about the fact that you can even listen to them. Let's say the city of Fredericksburg, talk about why they do it. If they don't do it, somebody else will. We want to bring that into the area because it brings in the revenue, that's great, But if the revenue is not structured properly, then everybody loses and the resources suffer. So luring them to your area by giving them so many tax breaks and so many incentives without holding.

Speaker 3Them accountable is the problem. Now, you and I.

Speaker 2Both pay property tax. Remembering in Virginia here, property tax is difference in real estate tax, right property tax. So some counties give your break on property tax, not real estate tax. They don't understand that, but they give you on a property tax. Okay, Well, and the reality is when you give a company that is literally you know, when you buy a computer for a business, you have to pay property tax on it. You buy equipment for your business, you pay property taxes on it. You have to pay these things as a business, Okay, annually. If

Speaker 2you take something that is essentially a massive building with nothing but equipment in it, like computers and servers and whatnot, that should generate a massive amount of annual property tax, massive just in that alone.

Speaker 3They don't want to pay that.

Speaker 2The data centers don't want to pay that, so they construct it in some other way to say they're giving incentives to the community. But they say this cleverly, and I'm not saying they're openly being dishonest.

Speaker 3I'm just saying there's a clever way they do it. They have great lawyers. I'm sure.

Speaker 2The problem is the council members fall for the easy money. In my they fall for They make decisions based on whether it's going to look good for their constituents by saying, oh, look, we're gonna pay.

Speaker 3More teachers' wages.

Speaker 2But paying more teachers' wages doesn't offset the cost of the people that aren't teachers. Yet everybody else has to understand that there's going to be burdens involved in that. So if you give somebody a tax incentive to come to your area because you want to lure them here, and you read district land, you change land use around so that they can be there, especially if they're near a residential community. You're doing it for one reason. You're doing it because of the revenue, because there is no other reason you do it, especially as a locality, there

Speaker 2is zero reason you would do it, So you do it. But then you give them tax breaks and incentives that encourage them to pick your community over somewhere else. So I think the problem is like when I tell people in business, you can work for yourself, but if your expenses outweigh your income, then you're not going to be in business a loan. So when a community offers so much incentive to bring something here that their consumption, their

Speaker 2use is so much greater than what benefit they bring to the community, that's a problem, and that's going to continue on for twenty years or more. So I think that the real problem is not so much the data centers itself. They're a business. They're just trying to do a business. And I've talked before of how data centers can benefit the trades, and obviously they're gonna get built we can't stop it. You can protest all you want,

Speaker 2but hold in your hand how many times a protest has actually caused a project to really stop and see where we're at.

Speaker 3Okay, here in Louisa County.

Speaker 2Alone, there's like three or four data centers going up and they get protested. Guess what, they're still getting built. You're not going to stop it. The only way you stop it is if you make it an issue with your local government. And even then you need to hold them accountable. If they vote a certain way, and they vote and make stupid decisions, then they need to be They don't. They don't get a free pass. You take the Charlottesville, Virginia for example. Charlottesville used to be such

Speaker 2a wonderful city and then they got administrations in there to just tore it up and did not make good decisions for the community and the growth in the origination of Charlottesville that they've ruined it.

Speaker 3And that's my opinion. You can disagree. I'm just giving my opinion. I understand it.

Speaker 2The people that'll be disagreeing with that, that's fine. Where's your facts, Paul, dude, I'm giving you my opinion. If you don't like it move on. But the reality is unless you start taking back and holding your elected officials accountable and being vocal about that rather than protesting the data centers themselves, then that's going to be You know that that's a problem. You have to hold them accountable. Now, how could we hold a data center accountable? Okay, I'm

Speaker 2not going to give you all the ways that I would do it, but I'm just going to tell you how I would hold a data center accountable. First of all, you want to come into my area. I'm not giving you any tax incentive. If you want to come in and he said, well, they'll go somewhere else. If we don't, well, then I'm going to weigh the tax incentive. If I give them a tax incentive, I'm going to make sure that it offsets by what they're giving me the community. So they should not come in here and win, because if I'm not getting anything for it, if I pay one thousand dollars for something and I'm giving you a

Speaker 2thousand dollars, break and ultimately I'm not making anything but just putting you here.

Speaker 3And you say, well, they'll.

Speaker 2Bring you know, they'll bring jobs, and they'll bring visitors and people don't go visiting data centers, by the way, folks. So that's not really what's going to bring income streams to your community. Okay, it's not like we're going to have all of a sudden the restaurants are going to be booming. But that is not how it works. Okay, don't be a fool. There ain't that many people inside these data centers once they're up and running. Yes, during the construction phase, yeah, that'll bring local revenue. That'll bring some people things like that. But other than that, once

Speaker 2it's done, that's pretty much going to scale back and there'll be limited jobs to the community. Limited jobs, but most of the you know, people understand that their people come from other states to do electrical work on these data centers.

Speaker 3They make great money.

Speaker 2I saw a report the other day that some make anywhere between thirty five hundred and forty five hundred dollars a week a week as an electrician.

Speaker 3No wonder there.

Speaker 2If they're young, travel around from data center to data center, Dude, you can stack some money away. Remember what I always say, You work your ass off in your twenties and thirties, and so you can reap the benefits in your fifties and sixties. Absolutely, Okay, So you know it's it's just one of those those things. If I was a damn young electrician again and I was doing the data center, dude, I'd just buy me a motor coach, put my family in it. Home, my wife homeschool a kid, and I would just live out of a travel trailer. Well, I

Speaker 2would probably buy a nice one because at thirty two hundred dollars a week, I could afford one, and I would just park it somewhere at a camp, at an RV park or whatever, and just pay there, you know, stay there and tell the project and then get in my motor home and then go wherever the next project leads. I'm just saying, stack that money, That's all I'm saying. So anyway, different strokes for different folks. But the reality is you have to understand that if you're not going

Speaker 2to you cannot give so many incentives to bring them to an area. And then if they threaten to not come here because the incentives aren't good enough, you have to be willing to walk away from the table. And that's the problem with our local governor government, the governor everybody, is that they don't want to walk away. This is why Northern Virginia is the data center corridor, right, It's they don't walk away, and they're putting them right into subdivisions,

Speaker 2just blatantly doing it. And if you're not asking your politicians why you're allowing that, and then you say, well, I don't care where it goes, I just don't want it in my neighborhood, then you're part of the problem because you're the one using the data.

Speaker 3You're the one that has a subscriptions.

Speaker 2Dude, in my house, I've got a washing machine that's connected to the Internet. I have all of my TVs. Six of the TVs in his house are connected to the internet. My tesla is connected to the internet. My computers are connected to the internet. My employa monitoring systems connected to the Internet, my HVAC systems connected to the internet. My phones are all connected to the internet. What else, My Elixa devices are all connected to the internet. Everything is connected to the Internet. Okay, so at the end of the day, you may not have that exposure, that footprint,

Speaker 2but you picking up that cell phone, you're contributing to it, whether you want to like it or not. And if you say to yourself, I know I want these things, I just don't want it in my neighborhood. Then you're a hypocrite. And it's okay, I get it. Nobody wants to stare one down. But the reality is it's ingrained in our life at this point. So the reason that this grew in twenty twenty two is because of AI.

Speaker 2AI is connected with everything today because we as people want things to be quicker, easier, more efficient. My time is money, help me out make things easier. So that is what's happened, and it's not going anywhere. So I would say to those out there that want to protest data centers, if you think that that's going to change the data center, that's not This is not going to

Speaker 2change the data center. Now, we can push for certain things that local government can write in to the prospect of an agreement with these data centers. One, they could demand that they use closed loop water cooling systems, they can demand it. They can demand that they create their own on site power plant. They can demand that they create their own water towers or own water, and that they do not pull from wells. They can demand a lot of things, and if the data centers say well,

Speaker 2I can't do that. We know that you can, because there are data centers out there that are closed loop systems and things like that, and there's other technology.

Speaker 3It's just expensive.

Speaker 2And the reason is expensive because in these things are legitimately energy hogs that you have to wrangle. You have to make sure that you control them. One processor of these new modern data centers a server. One processor produces about a thousand watts of heat inside of one of these racks. You could have hundreds of these processors all putting out one thousand watts of heat from one little

Speaker 2chip the size of a postcard.

Speaker 3I'm not lying.

Speaker 2Google it, okay, And if you do google it, you'll be using data centers. So think about it. So this heat has to go somewhere. Well, back in the day, it used to be that air, like a normal air conditioning system could remove this heat efficiently.

Speaker 3It cannot do that anymore.

Speaker 2These these these these racks now that are clustered, and the things that are size of a refrigerator with multiple servers in there, many of them costing more than your house per server, are so smart, but they run so hot that the air movement cannot cool them.

Speaker 3Anymore.

Speaker 2So they either have to be liquid cooled designed into the chipset or maybe back end radiator systems, but they have to be designed in a way to move this heat. And it would take tornado force winds to move that heat quick enough. And that's not how it's going to work in a data center if you've ever been in one, and I have. Okay, So at the end of the day, the only way to do it is to use liquid cool because liquid cooling is way more efficient efficient than air. Right,

Speaker 2Why do you think your car does it a certain way? Why do you think vehicles?

Speaker 3You know?

Speaker 2It makes sense, right, And then of course you could submerge it into a non conductive liquid that is also expensive, and that is what we may be going to. But it's still liquid of some type, non conductive, but it's liquid. The point of the matter is you could ea even pushed for purple systems or purple water systems or recirculatory systems or whatever. But you have to think about these things in your community. So before I offer to anybody a tax break, as a community, what your counselmen and

Speaker 2women should be doing in saying, look, I'm going to give you these incentives, but this is what I want in return. I want to know how you're going to manage your water. I want to know what the amount that you're going to take and how you're going to deal with it.

Speaker 3And I don't care what the cost is, you're not going to take it from the community.

Speaker 2Secondly, I want to know what incentives you're going to give us for giving you incentives, because I'm not giving you incentives for me to lose money as a community. We're giving us incentives, but essentially you're deferring the benefit that's going to come to us. What is the benefit to us? In my constituents, these are the conversations that have to be held, and these to be open conversations. A lot of times these councils will do these closed

Speaker 2door deals or things that really, oh, they're sneaking in an agenda that nobody knows about, or it's the data center people, or everybody talks in such circular terms that nobody can really understand what the shit's going on, when it should be just a simple question to them and saying, so where are you using, where are you getting your cooling, how are you doing your cooling, what's your thoughtful power. Are you going to have to run generators all the time because you know the grid can't sustain it. Dude, we're ten fifteen years away from full sustainability, and that's

Speaker 2even further than that because I don't think the grid could catch up. This is the reason that Microsoft is trying to or paying to start up Three Mile Island again for the nuclear power plant that melted down one of the reactors years ago, kind of sat in moth balls, and now they're paying a certain number of billions of dollars to refurbish that thing and get those reactors that didn't melt down back in service.

Speaker 3Why Why Because they need the power. It's simple. They need the power to run these things.

Speaker 2So we have through Louisa County, there's this prospect of running a new high power line in every and there's a lot of people against it. Well again because it's gonna run through people's land and nobody wants to look out and see these big ass tower.

Speaker 3I get it.

Speaker 2But the reality is without that line, you're gonna pay the price because you're gonna be bidding against power that's used, for example, from Lakena and other power plants. You're gonna be bidding against that, and it's gonna raise your price. If you allow this to come in, then it's probably gonna help in terms of offsetting the increase that it would be to you the consumer, because then they would be buying this high power directly from another source, and it actually would help your area. But we're so focused

Speaker 2on what it would look like. Well, I get it, Paul. You don't want a tower running through your backyard.

Speaker 3I wouldn't. But here's the deal. It's not going away.

Speaker 2At some point a palm will get greased and something will happen. Because the data center growth is not going anywhere. It's gonna happen. You can protest it. All that energy is great, and I'm all about you know, protesting, you know, doing it peacefully, YadA YadA. I I don't have a problem with that. The moment it gets violent, that's I gotta have a problem with that. But reality is it's not going away. So your your biggest focus should be rallying around elections, are rallying around putting people in government

Speaker 2that in your local And again I would focus locally. I think too many people focus on bigger things like the presidential election.

Speaker 3Election elections in Congress and Senates.

Speaker 2I think that one of the biggest things that people lose sight of is the importance of your low local elected officials and what their positions are, because they're the ones when the rubber meets the road. They're the ones that are making decisions for you at council meetings that you may or may not like. And if you're not informed and you're only focusing on a bigger issue like government wide, statewide, or even national, then you're missing and

Speaker 2things are getting slidden in the back door in your local jurisdiction that you're going to have to be saying, well, how the hell did that ever happen? I blame the governor, I blame the president, or I blame no, you need to blame your local government and what they were sold as them thinking that it was good for the community, when in fact it's not good for the community. Now again, I have nothing wrong with data centers. People say, Paul, you're just so pro data center. That is not true.

Speaker 2I'm pro data center because I love data. I can assume it. I have everything that I have is consumed with data, and I get it, and you might let me quit it to this way. I heard somebody say to me, says, Paul, my footprint is so little. I still don't think it's fair. And I'm like, if you throw a cigarette butt out of your window, you're littering. If you throw one plastic straw into the ocean, you're littering. Littering is littering. If you convince yourself that your impact

Speaker 2is so small, then you're the same person that won't go out and get involved in local elections because you think your voice doesn't matter. That the mentality we have to change. So I am all for holding data centers accountable. We need them. They're not going anywhere. The reason they open so many of them is again, scalability means their cost to run comes down as they Expand I know that sounds hard to believe.

Speaker 3You're thinking, well, they got a look.

Speaker 2It might cost them two hundred billion dollars to build one, but if it makes them five hundred billion dollars in a year, then that's profitable.

Speaker 3Okay. The more you have, the less resources.

Speaker 2It is based on a single location and it's allocated now across the network, and that makes operating costs come down. And if you don't understand that scalability and a scalable law. I can't help you. I'm not here to educate you on the understanding of that type of concept.

Speaker 3But it is a real deal.

Speaker 2And the fact of the matter is, this is why they expand, This is why the US per capita has the most data centers.

Speaker 3It's scalability putting them out there.

Speaker 2Googles, Amazons, Amazon's probably the biggest one out there.

Speaker 3They're everywhere. Yeah, they're under different code names.

Speaker 2You have to go digging into the deep web to find them, or look at some of the holding companies and then look them up and see who's holding them or what LLC and then go back. Yeah, you got to do this little patchwork right, because they all love to use these code names. Tell me how you know how I know because I work for a large wire and cable manufacturer that surprised a lot of wire and cable to these data centers. And you can't always find the name of these damn things because they're under code names. And a lot of it has to do with proprietariness. One data manufacturer comes up with technology, they don't want

Speaker 2to share it with somebody else, and then so they kind of keep it all private. I get it. The fact matter is I don't care about any of that. I really don't. What I care about is if they're going to come into a community, then I'm going to hold them accountable. I'm going to say, dude, I love the data, bring it. But if a locality is going to rezone things or allow them to be in certain areas and simply because of revenue, but ultimately they end up giving them huge tax breaks to come here in

Speaker 2the first place, that's a problem because ultimately, no no business in a city is a business. Okay, running a city is a business. No business is sustainable. If your expenses outweigh your income, it's just not it's just gonna fail. Now, in the terms of a city, if you're giving such incentives to a data center and you're not taking care

Speaker 2of your community, then that's a problem. If you have one county that's got three data centers, there should be no dama, especially as small as like Louisa. There should be no damn way that anybody in Louisa has to pay property tax, real estate tax. Should I would venture to say they shouldn't have to pay sales tax. But the end of the day is you make the data center pay it. Well, that's not fair, sure it is.

Speaker 2If you're using our resources, you've been given incentives to come here, then I want something back. What's the point of giving so much incentives and tax breaks that you don't make anything from it for your constituents, your people in your community who are not benefiting from it, Well, they bring jobs, No, they don't, not that many. In fact, a lot of the electrical jobs which they do bring are remote from other places. They do create jobs, but then the jobs tend to go away and they start

Speaker 2to level out. Yes, there'll be some local stuff, but at the end of the day, it's a good opportunity for electricians, plumbers and mechanical but there is a time when that's going to balance out and it's good for restaurants. Yeah, dare in construction, it is, but then once it's finished, it's not like a data center is going to employ two thousand people.

Speaker 3It's not. So why sell yourself for a short term game for a long term headache.

Speaker 2The only way you make this viable is to convince your local officials to scrutinize these contracts, in these agreements and come up with the way that benefits your community. Everybody feels the impact of it. Also come up with areas that allow this type of thing that doesn't impact the residential folks so much.

Speaker 3But if you.

Speaker 2Force them to worry about sound, if you force them to orbe put up walls around it that kind of blocks the sound out, rather than just sit the generator there and try to put some trees along the lining of it, that's not going to block the sound they can create. You've seen interstates with have the sound barriers right along the interstate and then you get on the other side of it and you can hardly hear the interstate. There's things that they could be forced to do. They could have closed loop order systems, they could have their own power production forced into them, or submit a plan

Speaker 2for how they're going to do it that doesn't affect the local community. You can force them to do these things, still can give them incentives, but you have to force these things, and you have to hold them accountable for it.

Speaker 3You have to hold them accountable for it.

Speaker 2And there's nobody to blame at all but your local government. Don't blame the data center because you know damn well when you go out and buy a car, or you go out and buy something. You want the best deal you can get, don't you. You ain't no different. Somebody comes to do work for you.

Speaker 3You always FoST on Facebook, Instagram, everywhere you go.

Speaker 2I want somebody that's cheap and affordable. Do you not think the data centers don't want that shit too? I mean, come on, let's stop being blind here anyway.

Speaker 3So that's the deal. I say.

Speaker 2You have to hold your locals accountable and get involved that way. Protesting a data center itself is not going to do you any good because they're just going to push you out of the way and they're going to complete it. Because when it's done, it's just one building.

Speaker 3It's sitting there. Who gives a shit?

Speaker 2If you're standing at the entrance, nobody gives a shit because retail is not going in and out of it.

Speaker 3They don't care.

Speaker 2They're still gonna run, and you just wasted your time. Your time is better served trying to hold your local officials accountable. That's my thought on the process.

Speaker 3Folks.

Speaker 2I hope you enjoyed something today. Again, if you don't agree with what I have to say, that's fine. You're entitled to your opinion, I've just given you mine. Till next time, folks, Stay safe, God bless and we'll catch you on the next episode of Master the NEC.

Speaker 1Thanks for tuning into another electrifying episode of the Master THENEC podcast. We hope you're feeling more powered up and ready to tackle the electrical world with the knowledge and confidence you need to succeed. Remember, in the electrical grade, knowledge is power, and we're here to make sure you stay flogged into the latest insights, tips and code up dates. If you enjoy today's episode, don't forget to subscribe, leave us a review, and share the podcast with your fellow like atricians and industry pros. Until next time, keep your

Speaker 1tools sharp, your circuits clear, and you're my focused because here at the Master of the NEC podcast, we're all about sparking your success. Stay safe, stay smart, and keep mastering the trade. From all of us here at Electrical Code Academy, thank you for all your support and we will see you on the next amazing Master of the NEC podcast episode.

Open the transcript file

Hosts and Guests

Nobody is credited on this episode yet.

Credit the people on this episode

Be the first to rate this episode

More episodes

All episodes
  1. NiteNerds™ — The Future of Permanent Outdoor & Landscape Lighting Is Here!

    Nov 12, 202631 minAudio

    NiteNerds™ - The Future of Permanent Outdoor & Landscape Lighting Is Here! What if your home could look absolutely stunning every night of the year - with the touch of a button? Welcome to the world of NiteNerds™, where...

    Credit the people on this episode

  2. MASTER THE NEC PODCAST | E81 | Electrical Code Knowledge and 2026 NEC Updates PT 3

    Oct 18, 202655 minAudio

    ⚡ MASTER THE NEC PODCAST 🎙️ Hosted by Paul Abernathy Master Electrician | National Electrical Code Expert | Electrical Educator ⏱️ Episode Length: 55 Minutes ⚡ ABOUT THIS EPISODEWelcome to Episode 81 of Master The NEC,...

    Credit the people on this episode

  3. MASTER THE NEC PODCAST | E80 | Electrical Code Knowledge and 2026 NEC Updates PT 2

    Oct 18, 20261 hr 23 minAudio

    ⚡ MASTER THE NEC PODCAST 🎙️ Hosted by Paul Abernathy Master Electrician | NEC Code Expert | Electrical Educator⏱️ Episode Length: 1 Hour, 23 Minutes ⚡ ABOUT THIS EPISODEWelcome to Episode 80 of Master The NEC, where...

    Credit the people on this episode

  4. MASTER THE NEC PODCAST | E79 | Electrical Code Knowledge and 2026 NEC Updates PT 1

    Oct 18, 20261 hr 4 minAudio

    ⚡ MASTER THE NEC PODCAST 🎙️ Hosted by Paul Abernathy Master Electrician | NEC Code Expert | Electrical Educator ⚡ ABOUT THIS EPISODEWelcome to another episode of Master The NEC, the podcast dedicated to helping...

    Credit the people on this episode

  5. What The HECK? Do you have a 2026 National Electrical Code Course?

    Oct 3, 202641 minAudio

    The National Electrical Code is a minimum standard - but what does that actually mean? In this episode of Master The NEC, Paul Abernathy takes a deeper look at one of the most misunderstood concepts in the electrical...