Co-chair of the Offshore Wind Industry Council Adam Morrison speaks to reNEWS Editor Stephen Dunne about his belief that the UK sector has the strategic fundamentals to thrive despite challenges on the horizon. Morrison outlines his hopes for AR8, how delivery risks must be dealt with and why he believes offshore wind costs must be back in play.
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
SPEAKER_00Welcome to the Re News Podcast with me, Stephen Dunn.
SPEAKER_01Listen to the media models that are far greatly having in the past. So we're asking for more transparency over that. We need to make sure that the garrisons that we need to do problems that we know about them and that they're acted on quickly in the government as the hill.
SPEAKER_00So I'm joined by Adam Morrison, the co-chair of the Offshore Wind Industry Council. Adam, you're very welcome to the Renews podcast. Yeah, thanks for having me, and Edinburgh has managed a sunny day for you to visit. Well that is rare having been here just a few weeks ago to see the jackets out at Leight. You're just over a year into your role as co-chair of OWIC. How's it been?
SPEAKER_01Yeah, it's a year that's really raced by. It's probably for others to say how it's going. But um I may mean maybe to start, in case any of your listeners aren't familiar with OWIC Offshore Wind Industry Council as a joint industry government council, very well established now, more than 10 years old. Well-established platform to engage with government, and we have you know very very very good engagement through that channel. But the real core of OWIC is the work programme, which I'm always keen to call out, that's run by the OWIC team, so made up of multiple work streams and a lot of, as well as a staff team, a lot of industry contribution to that, looks very deeply at issues we've got and opportunities.
SPEAKER_01And I mean something that's been mentioned to me a lot, particularly in the last last six months, as I've got my feet under the table a bit, is just how effective OWIC is, and it's a it's a reference point in terms of how industry councils can operate. And I I share that view, looking at it from the industry side. Um I think it's something we're really fortunate to have. Um, and it's nice to be able to play a part in it. I really enjoy being involved in it.
SPEAKER_00Well, you've got a lot of work streams, as you say, and a lot of work to do, and you know, you're that reference point for the industry and working with government. We're sitting here, the summer is coming to an end, we're looking into a really interesting six months or so with AR eight, we're coming off the back of what has been branded a successful AR7. You know, the industry seems to have turned a couple of a corner in generally at the global level.
SPEAKER_00What is it that you put top of your priority list uh as the co-chair of OWIC as we head into the autumn and winter period?
SPEAKER_01I'll quickly avoid the question just to take the chance to um talk about the big picture that you you sort of introduced around whether we've turned a bit of a corner in the UK sector, because I I I think we have. We had an OWIC delivery board um at the Global Offshore Conference in Manchester recently, and we always take that opportunity each year to do a bit of a recap. And when you look at the projects, including those recently awarded in AR7, we've got about a dozen offshore wind farm projects in execution phase at the moment in the UK market.
SPEAKER_01Most of those are in active construction now, onshore and offshore. And when you consider that each of those is a multi-billion pound capital investment, there aren't many markets that can point to that level of activity going on in offshore wind, and there aren't many sectors that can show that level of economic activity and that level of investment in in the UK. Um so I think I think actually, although we've had some uh some tough times, particularly around uh around AR4, AR5, we've got a lot in execution phase now, and that that that's a tremendous opportunity for us.
SPEAKER_01And away from the projects and the megawatts, um I also think we're on the cusp of seeing some of the industry efforts uh which OWIC has led, bearing some fruit. So, for example, from AR7, we've got the first projects paying into the Industrial Growth Fund and with the idea that that will sort of cascade into supply chain, uh supply chain investment and supply chain delivery as these projects come through. And so I expect that to generate a string of positive stories in our supply chain.
SPEAKER_01I'm really hopeful about that. We've put a lot of effort into getting it into place. Um and then looking even further ahead, we've got another leasing round being brought forward and good early dialogue with the Crown Estate on that. So the fact we're still talking about new leasing, we've got a big development pipeline still in the UK, but we're talking about new leasing, that shows there's appetite and still a lot of resource in the UK market as well to go after. Um, so in the big picture, I'm I'm I'm very positive actually about how the last the last year or so has gone.
SPEAKER_00And yet, offshore wind is and renewables in general are probably at the tip of the spear when it comes to the political debate in the UK at the moment. You see politicians from the right being quite critical of offshore wind in particular, largely on cost grounds. Obviously, you've laid out a positive trajectory for the industry, but there's still a challenge, isn't there, to you know, tell the offshore wind story and to counter those claims that it's high cost and unreliable.
SPEAKER_00In particular on cost, like what will we see in ARA, do you think? And what is industry trying to do to counter that that that narrative?
SPEAKER_01Yeah, there's a lot in all of that, and that that's obviously something that in industry a lot of us have been grappling with over the last the last couple of years, and I we'll probably return to the topic of how how we tell our story and whether we can tell that story better. But just going going on to the cost point first. Um for AR8, I'm going to avoid laying any numbers down, anything I predict will be totally wrong. So but if you look back at there was analysis published, commissioned and published around AR7, and even with upward pressure we've had on cost of energy, I think we're still able to demonstrate value for money as a technology in offshore wind.
SPEAKER_01And alongside that pace of deployment is a really unique combination that Big Wind has of I feel demonstrable value for money for customer and ability to deploy quickly at scale. Um, and I think that was recognised by government in AR7 when you look at what was done with the budget. So obviously, we hope that government recognises that again in AR8, that we can demonstrate it and that government recognises that when decisions are made around AR8. I mean what you can definitely say, away away from um specifics on uh on cost is that we're taking a very high quality pipeline into that auction, whether it's projects in existing hubs that can benefit from synergies, and I think really importantly demonstrate sustained economic development in areas where there's already been a lot of offshore wind development and operation.
SPEAKER_01Um that's an important thing for us to be able to show in those areas and to those communities, or projects that are bringing opportunity to new areas of the country where there hasn't been offshore wind construction and operation to date. We're taking a high-quality pipeline into the auction so there will there will be a good level of competition, which is what government wants to see, but some really high quality projects going in. So I think the ingredients are there for it to be another success story as with AR7. So I I mean in summary, I hope that we can make the case on value, that's on that's on industry to show to show value and then secure backing in uh backing in AR8.
SPEAKER_01Um, there's an opportunity there to create an incredible pipeline of delivery projects, given we've already got the dozen that I I mentioned earlier. Um creating nearly 10 years worth of execution pipeline in front of us.
SPEAKER_00I think you mentioned Manchester. I think the energy minister Michael Shanks challenged industry to cut costs in Manchester. He really put it up to the industry in his speech. You know, you you obviously chair or co-chair a large group of developers. Is that community of developers ready to answer Michael Shanks' call to action on costs?
SPEAKER_01Yeah, sure. I mean I I think that industry is actively happy to have that discussion. It's something that we decided to do with you know with um with government using OWIC as a as a forum for it. Um we shouldn't be afraid to do that. There was a cost reduction task force for offshore wind in the past, I think it predated OWIC, if I remember. Um and the context is pretty different now, but I don't think we we should be afraid to be uh talking about the subject.
SPEAKER_01If nothing else, it's a valid objective to have a good understanding between industry and government on where we are with with cost of energy and what drives offshore wind cost of energy. So that that's part of it, is just making sure that there's a reasonably common understanding. Then there are some macroeconomic factors which there's maybe limited amount of things we can do about those. Um, but no large-scale generation is immune to that. Inflationary pressures on supply chain, upward pressure on cost of capital, for example.
SPEAKER_01So there are some things that we have were limited in our ability to mitigate, but again, common understanding between industry and government on those is uh is a is a good objective in itself. But I think um, you know, and I I think others in the OEC group would would agree with this that there are some quite specific factors related to offshore wind cost of energy, um, which we should double down on looking at. Um and you know, I could I could reel off a lot of those and maybe we can get into some of them.
SPEAKER_01We will. But but it's I think it's a it's the right time, it's the right time to look at kind of structural components of the of offshore wind cost of energy and where and that I think there are levers that are in government's hands to to help with some of those.
SPEAKER_00We will get onto them in a second. Just before we do, on the big piece around costs. I mean, you know, we've taught we've talked about it a lot for a long time around the offshore wind industry is coming off a challenging period where costs got out of kilter, projects failed, uh developers walked away, and so on. You know, I think that correction that has been taken place is still going on in some parts of the industry.
SPEAKER_00Is it a bit risky to start putting costs back on the table, so to speak, um, given a lot of the challenges are still ongoing?
SPEAKER_01No, I think it's almost the reason to do it. Because if you look if you look back to AR4 and AR5, AR5 is used as the the reference point because of what happened in that auction, but actually some of the ingredients were there in AR4 already. You see there what can happen if there's if there's a lack of kind of common understanding of where we are with with cost of energy and cost pressure. So it's not only a case of talking about cost reduction, it's also a case of talking about how certain macroeconomic factors drive our cost of energy and influence auction outcomes.
SPEAKER_01So my my view is no, it's not too soon to talk about it, it's almost um the the reason why it's something that needs to be on the on the table.
SPEAKER_00I think Wind Europe, I was looking reminding myself this morning last year, put out a paper saying that they could cut offshore wind costs by 30% by 2040 if they were given a you know stable pipeline of of CFDs. You know, in the UK, what you know, is there any ballpark figures being kicked around, any sort of roadmap towards cost reduction being kicked around at this early stage? And can you give us a sense of you know what it what it what's the brass tax here when we're talking about cost reduction?
SPEAKER_01Yeah, well we have a work stream uh running now. Um in in general, I think it's important to have honest discussions about where we're placing risks, where uncertainty is being created, and how that uncertainty, for example, policy and regulatory uncertainty impacts costs, how we invest in and support the supply chain and provide them with pipeline continuity. Um so we're looking at it across themes broad broadly, um, broadly in those sort of areas.
SPEAKER_01But it's maybe more interesting to get into some specifics underneath that. So, for example, when it comes to grid and offtow, things have changed a lot since the early days of the offshore wind sector, the scale of network build-out that's going on and also the time that's passed since the offtow regime was first conceived. It's the right time to look again at all of that. RUK led some really good work on that. And you know, there's a question there about whether the where the risks are placed and as a result priced creates the right outcome for the consumer.
SPEAKER_01Network charging needs to be resolved, of course, that's a very long-running issue. And then, you know, I said I would do specifics, it's not exciting to come onto a podcast and talk about tax, but that's another area that we're we're looking at. There are trade-offs, of course, but by government could refine certain aspects of the tax regime and benefit the electricity consumer as a result of that. And I think it's a sign of a mature industry that we're talking about topics like uh like like that.
SPEAKER_00If you were to single out one of the specific factors, I appreciate there are many and you know it's very complex and it's a constantly moving picture. But if you were to single out one key ask, if if the energy minister was to be sitting here and we were to co-chair a meeting as we head into AR8, what would be the industry's you know, key ask of government to pull that lever to help it reduce costs?
SPEAKER_01Um I'm gonna avoid your question, I'm sorry. But that there is a reason, which is that actually when you look at the range of projects that we've got around the country, they're all affected differently. So they would all have their own top one or top three, and what we're trying to do is gather all of those. Um so I I think if I single one out, I'll end up singling out the one that I prefer. But um the reality is that the that the projects we've got in the pipeline are affected differently.
SPEAKER_01Some of them are carrying really big lease option fee burdens, for example, the leasing round four projects. Um have got pretty significant environmental compensation costs, um, others that are more affected by grid connection risk and uh grid connection costs into NUS. So there's a range of different impacts, but that you know, again, that's the reason to try and capture them all within a work stream.
SPEAKER_00You are listening to the Renews podcast. For breaking news or to access our exclusive market intelligence on the global renewable sector, subscribe at renews.biz. Now, back to the show.
SPEAKER_01One thing that I that I could draw together though that that industry across developers and supply chain would would argue for is that we've you know we've got the makings of a bit of a strategic plan, including on the industrial growth side, um in this sector, and we need to stay the course on that. And I think that's a that's definitely a key ask that everybody would get behind as there's an opportunity for us to, with a very strong pipeline in this country, to stay the course, make sure those that pipeline is successfully executed.
SPEAKER_00Maybe before we get on to that, just stay in on some of these you know key factors. I mean you you've mentioned half a dozen really significant challenges there, some of which in isolation you could class as project killers uh on s in certain areas. Um some of those are obviously government initiatives and you know that that they've ultimately added cost on to the developer. Is the government receptive to dealing with some of these issues around you know grid charging, uh tax, for example, things that it has is in its gift to deal with?
SPEAKER_00Are they casting a critical eye over this and and willing to help?
SPEAKER_01I I believe so. I I think it's just a few months in the making, really, this work that that we're doing, but that's where you get the benefit of having a joint industry government council, laying some of these things out fairly transparently. In a lot of cases there are there are trade-offs. I again tax is an easy example to choose. You've got a trade-off between tax take and electricity price impact. Um, so in a lot of cases it's about presenting the trade-offs. But I you know, I think if you zoom out, we we have as a technology we've kind of gathered cost, not only due to things like inflationary pressures, but things that we've we've chosen to do.
SPEAKER_01So the funding that our projects provide to the Industrial Growth Fund, that that will deliver a resultant benefit, of course, and it's an active decision which I'm very supportive of, but I think it's it's the right time to step back and set all of that out and look at where we've where we've made decisions, either government or industry has made decisions that have structurally driving our cost of energy and and reassess all of all of those.
SPEAKER_00You know, industry has a role here too. I mean, you know, developers bid into AR4, uh, you know, that nobody forced them to bid at those prices. You mentioned the round four lease fees. I mean, again, that was uh that's a sort of a mess, a little bit of industry's own making, right? Um, you know, what what is it that industry can do to uh you know, it's very quick to ask government for things sometimes and ask for changes, but like industry has a role here too, right?
SPEAKER_00So like where is it focused on this uh cost-cutting drive and and how can it sort of deliver going back to the question around uh Shanks's demand and call to action back in Manchester? Yeah, that's a fair ask.
SPEAKER_01Um I think the first key component and and I I I start with this because actually th this was a key factor in helping us originally significantly reduce the cost of energy and offshore is keeping focus on execution in construction and operation because if we successfully deliver projects that gives confidence all around, whether that's confidence to those that funded the projects and made the investment or confidence of the supply chain that are doing the work.
SPEAKER_01Um if we keep successfully executing, then it helps us keep contingencies down. Um so I think it's important that we have that on the table at an OWIC level. It's in our collective interest that every project that secures a CFD goes on to be successfully executed. So where we find execution issues, we have to tackle them quickly, escalate them quickly. Um so that that that's the first one. Again, that that was a key factor in us driving down the cost of energy in offshore wind originally.
SPEAKER_01So keeping focus on execution is really key, I think. Um looking further afield, I think the work on future leasing is important. We've got a really good resource in the UK, and if we find and enable the right sites, then we'll be able to keep demonstrating value, we'll be able to keep bringing forward projects that are at a good cost to consumer. And then the final point to probably return to here is smooth pipeline. We talk about it all the time, but it is a key ask of our supply chain. I think that's that's where our supply chain can really help us to deliver low-cost projects.
SPEAKER_01Working as an industry with our supply chain and with with government to maintain that pipeline, take advantage of the high-quality sites, keep projects moving into execution and into operations, stay that course. That that's something that we can do as industry.
SPEAKER_00Execution is something that's come up on the podcast before. I was uh in London with Ben Sykes at the start of the summer, and we had an in-depth chat about, you know, what are the key challenges that are stopping projects from reaching from getting from CFD to FID. Uh, you know, and and Benj was pointing to particularly to the Grid Connections reform process as being something that's potentially slowing the process. We had AR seven results in January. We haven't seen many contracts be placed uh out of that uh so far and and no FID decisions just yet, although it's still relatively early doors to be fair.
SPEAKER_00The execution Uh picture is tough right now for projects even with CFDs. What are the issues that you know you're dealing with at Owick and engaging with government on to try and you know manage and and help DOS developers that that have DOS headaches?
SPEAKER_01Yeah, it's a good question. I'll maybe first mention that RWE would probably would probably point out that Norfolk Vanguard from AR7 is already in execution mode. So so there's one of them at least is is uh is moving forward pretty rapidly. In general, what we're doing is trying to put this perhaps a little bit more in the spotlight because when you've got a dozen already in execution phase, whether that's pre-construction or in full-blown construction, and then more to come through AR8, then making sure that we give that enough airtime.
SPEAKER_01Perhaps in the past have been biased towards looking mostly at development phase risks and issues. Um we've got really well-established work streams looking at that that I think are really effective. But making sure we're giving enough airtime to where all of the execution projects are, what their issues are, and where there's opportunity for industry government working to alleviate some. So that that's the sort of approach in general is to make sure they get the airtime and that we don't assume that CFD award equals immediate immediate success.
SPEAKER_01But I'm being too general, so I'll I'll I'll go more specific. I I think Grid is talked about all the time, every conference you go to, so it's it's a much discussed topic, I know, but I I think when you look at it in an execution context, you know, we've we've got projects now, generation projects that are dependent on lists of enabling works that are far greater than they generally have been in the past. So we're asking for more transparency over that. The network operators have got a lot to build and we're rooting for them.
SPEAKER_01But we need a bit more transparency over that. We need to make sure that if there are issues with any of the big network projects that we know about them and that they're acted on quickly and the government acts to help where it can. So that's the natural, obvious one to choose. There are lots of other details under the surface, of course. Like we we talked earlier about the issue that emerged with marine workers' visas. Um, but as a headline, you know, it's clear that we're gonna have to stay very focused, and I think government is to give them give them credit, very focused on the network build-out and the dependencies that all of the generation projects have, transparency, urgency where there are issues, that's gonna be critical for the next five years or so.
SPEAKER_00So do you think in your role as co-chair then of OIC that you're that that the government is is really grasping this and and that NISO is at the table as well here and really, you know, giving that transparency and and giving that certainty where issues are cropping up? In short, yes.
SPEAKER_01With whether I mean of course of course different projects are affected in in different ways, so I'm certainly not gonna claim that it's perfect, but I think I I definitely see w willingness at ministerial level to be in the detail of this. I think it's understood how critical a success factor it is. You know, the there needs to be pressure on that network build, but also support where it's where it's needed support and intervention. But I I think there's a collective recognition of the criticality of that, yeah.
SPEAKER_00Obviously, the Labour administration has been you know really supportive over the last number of years towards renewables. We've had a change in the administration in in the department with a new Secretary of State. You know, in the last few weeks we've seen big political debates crop up around system costs and you know the best way to build out uh the energy system in the UK. Do you have any anxiety that renewables, which was the poster child, if you like, of the Labor administration, that that sort of positivity towards the sector is starting to diminish a little bit?
SPEAKER_01Yeah, I think all of us in industry feel that very keenly and feel pressure to act in one way or another. You know, I'm sure I can speak for others on that. But I don't feel defensive. It it's maybe even a sign of a mature sector. Um true, it's nice to be nice to be a poster child, but the reality is that we're we are at the backbone of the UK's energy system now. So it's it's a sign of a mature sector that we're under scrutiny on whatever grounds that is. I mean we've talked a lot about cost here already on an industrial footing.
SPEAKER_01I think as I mentioned, it's important that we stay the course because I think there's a lot that we will deliver that we can signpost really diverse regional benefit that our sector offers that a lot of the time isn't visible. And so for sure I think we feel the pressure to showcase that a little bit more and make sure that it's recognised that we've got a lot to offer. But I think it's a sign of a mature sector that we'll be challenged on those those things. So I'm not I'm not defensive about it, but you know, we we definitely feel the pressure to to keep making the case for the value that we're bringing.
SPEAKER_00You mentioned you know staying the course. Um at the big picture you would have to acknowledge that the strategic vision is there now for the build-out of renewables, whether it be the you know, the strategic energy plan that's coming, you know, network planning and the advancement of of grid, the industrial growth plan, and you know, attempting to to really build out the UK supply chain. The the fundamentals are there.
SPEAKER_00Would would you subscribe to that view?
SPEAKER_01Yes. I mean I I think there's a fair amount of debate and discussion about the SSEP, and we're yet to see the output of of that, and so you know, under understandably there's some concern around it, but overall I'm I'm positive about the concept of of being much more strategic. Because all of these things are interconnected in the end, you know, what what we plan to do with our generation is interconnected with it with what we need to do with network build-out, and if we really want to achieve industrial growth and sustained industrial delivery, then the whole thing has got to the whole thing has got to hang together.
SPEAKER_01We can't get caught in the headlights and and and flip-flop. So I am positive about the the intent that's behind all of that. But I I think that the the next 12 to 18 months working through SSCP outputs and then establishing what a post-AR8 plan looks like, then that applies not only to offshore wind, of course, is really really important, but I think it's the right thing to have embarked on trying to be much more strategic about all of this.
SPEAKER_00So staying the course, you know, in industry, that message you could argue may not quite have got through in offshore wind. We're seeing, you know, a number of big developers pivot a little bit towards grid build-outs and network build-outs, reduce their exposure to offshore wind in the short term at least. Although the strategic plan is there for the UK and the messages stayed a course, no, industry hasn't quite got on board fully with that message, yes.
SPEAKER_00Would you agree with that?
SPEAKER_01I I'm not sure I would I the you of course you're right that you're seeing some capital be diverted into network regulated network build out. We need that, so you know I'm very pleased to see that the three TOs in the UK are in CapEx mode at the moment. That's necessary. There's 10 years of catch-up to do there and and more. So some some of that capital being diverted is actually something that you know we we we needed as an enabler.
SPEAKER_01I think my other counter would be that you've you've still got a pretty healthy sector in the UK. We've got a great pipeline that I talked about, but a lot of developers involved in that. Um in that pipeline, we've got a lot of members of OWIC. I should know the number, but I don't know off the top of my head. We you know, we've we we've got a lot of members around the table, developer and supply chain members around the table. So I I think it's still a very vibrant sector. I think perhaps where there is something to be challenged in all of that, though, is the risk reward balance that you see on the generation, non-regulated generation side versus the risk reward balance that you see on the network side, including OFTOs.
SPEAKER_01It's the right time to look closely at that, and you know that that's a key topic within the work that's being done and the engagement that's being done on the OFTO regime right now. So definitely that is worth that is worth challenging. We've got to make sure that the incentives are right so that you continue seeing generation projects being brought forward and that developers and operators are are appropriately incentivized and rewarded to build out on the generation side.
SPEAKER_00I remember talking to you a number of years ago up in NIG when you were building out Murray West, and this risk reward element came up back then. You know, I know we're talking with your OIC hat on here, but that risk reward profile for developers who you represent through OIC, is that out of kilter still a little bit in terms of providing the incentives to go ahead and build out, or is there just too much risk still in in at the party?
SPEAKER_01There are definitely areas where there are uncertainties that then flow into our cost of energy that that we need to put on the table with government and we need to challenge. And again, that's a sort of key part of the work we're doing, we're doing on cost, is look at whether some of the risks that we're asked to carry should actually be sitting with us and whether that's in the best interest of the electricity consumer, which is ultimately paying whether that's through CF through CFD prices or otherwise. So the short answer is that there are definitely issues in a number of places there where I think we you could have some relatively quick wins, make some corrections that would be in the interests of the consumer.
SPEAKER_01But we need to have them on the table, which is why why we're doing that work.
SPEAKER_00The other risk, I suppose, on the horizon is politics and changing politics. Uh you know, we we've seen it in multiple markets where new uh administrations have come to power and and ripped up the playbook, uh not least the US. Um what is in the what what is what are you hearing from the OIC members about this issue? All big utilities with long-term views.
SPEAKER_00Are they concerned about the direction of travel in UK politics in the sort of medium to long term around the next election, or is it something that they're you know that that they're not too worried about?
SPEAKER_01Yeah, of course, we all feel it really keenly. But but at the same time, I think we've got an incredible track record, and we can put the industry in a very good place. AR7 has made a contribution to that with the volume that came through that allocation round. We can put the industry in a very, very good place on a clear path to delivering industrial content. We can showcase the high-quality jobs that that already exist in coastal communities around the country.
SPEAKER_01Um so I think that we've got the opportunity to put the industry in a in a strong position. Um and then again, it's this sign of a mature sector if we come under scrutiny and come under a bit of test. But I you know I'm still completely convinced that we can show that we can show value on a number of fronts, value to consumer, but also really important economic contribution.
SPEAKER_00Well, on that note, Alan Martin, thank you very much for being on the Renews Podcast. Thanks. The Renews Podcast was produced and edited by me, Stephen Dunn. Click subscribe wherever you get your podcast to make sure you never miss an episode. For more exclusive market intelligence on the renewable sector, see renews.biz.
Northland Power and ORLEN are in the final stages of commissioning Poland's first offshore wind farm, the 1.1GW Baltic Power project. In this episode, Northland's international executive vice president Toby Edmonds...
Ireland has big ambitions in offshore wind with a 5GW target for 2030. While few believe that is possible due to grid and permitting delays, it is expected that projects will enter construction in the coming years. So,...
Reporter Michael Lee-Murphy joins the reNEWS podcast from Taipei where he is attending this week's series of flagship energy events. Lee-Murphy reports on the current health of the island's offshore wind market and...
A dispatch from the RenewableUK and Scottish Renewables Floating Offshore Wind 2026 conference in Aberdeen. Hear Scottish First Minister John Swinney's view on what the UK government must do to unleash offshore wind...
At WindEnergy Hamburg 2026, the German onshore and offshore wind sectors have sounded alarm bells about future growth. Hear from the fair from reNEWS senior editor Sian Crampsie, who outlines the onshore concerns her...