At WindEnergy Hamburg 2026, the German onshore and offshore wind sectors have sounded alarm bells about future growth. Hear from the fair from reNEWS senior editor Sian Crampsie, who outlines the onshore concerns her reporting has revealed. Offshore wind editor Paul Stephen meanwhile brings listeners up to date on the offshore news from the show, including a chat with Orsted chief construction officer Patrick Harnett about the newly-inaugurated Borkum Riffgrund 3.
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
SPEAKER_02Welcome to the Renews podcast with me, Stephen Don. As you know, Wind Energy Hamburg 2026 is taking place this week among the largest events on the calendar for the European wind sector.
SPEAKER_02And I'm pleased to say I'm joined on the line from Hamburg by Renew senior editor Shan Cramsey. Shan, you're very welcome to the podcast, your debut.
SPEAKER_00Yeah, thanks very much for having me.
SPEAKER_02You've been on the ground there for the first 24 hours. What are you picking up? What are you hearing from the European wind sector?
SPEAKER_00Well, um, as you can expect, it's uh it's very busy here. Um week I think they're going to be expecting about 40,000 visitors. But overall, I think the the vibe seems to be fairly positive, um, especially for the onshore wind sector. Um I think people have been talking a lot about how much permitting has improved over the last few years. So they're very happy. But there's a large pipeline of projects to work on. They've got a fairly clear route to the market.
SPEAKER_00So, in some respects, business is pretty green.
SPEAKER_02As you say, the German sector in particular is in road health right now with construction activity, you know, really high levels. Yet, from some of the reporting, including your own, that's appeared on renews.biz, there appear to be some clouds on the horizon. What's the industry saying about this, Sean?
SPEAKER_00Well, I think uh at the moment, main concern among investors, and then of course the supply chain, uh mainly around upcoming regulatory changes. So, um, of course, in Germany the government has um published recently uh draft update EEG regulations that kind of govern the whole of the onshore uh renewable sector, and then they put forward also a proposed food package.
SPEAKER_00Um EEG main objective is uh bringing in a new CFD support mechanism. Um, and then the grid package will mean quite a few other changes, um a lot of regulatory changes around uh how the grid is used. So that will affect uh asset owners and particularly concerned things like in dispatch. So the problem with those at the moment is that developers aren't really sure exactly how these uh proposals will look in practice when they come in.
SPEAKER_00Um ideally they'll come in early next year. They don't know exactly how they'll be implemented, but uh what they've told me is they're pretty sure that uh these changes will change the business case for onshore wind. So um speaking to the developers at ISP over the last couple of days, they've told me that what that means at the moment that is that investment and capital flows into the sector are already slowing down. Um banks are pretty nervous about how the CFDs are going to work, they're not very happy or they're they're not really sure about um PPA market in Germany, that's something that's relatively new for them.
SPEAKER_00So everyone's kind of ground to a halt, but everything's slow down as people are kind of taking uh away from CFOs. There's a lot of frustration, I think, because the sector has got itself into quite a good place. There's a lot of investment in the supply chain, and now it looks like the winds that are gonna slow the market down.
SPEAKER_02Do you detect there in Hamburg any response to this from government? Is our officials responding to these concerns and uh addressing any of the issues that developers are bringing up?
SPEAKER_00Well, there are conversations, I think, the two and being associations such as um the German Wind Energy Association Association and the uh BDMA power systems, they've they've both said that they're talking constantly to government and lawmakers about these proposals. What they have said as well is that there didn't seem to have been much stakeholder engagement, so government hasn't really necessarily been listening to other stakeholders, and the the associations really feel that they're trying to almost educate the government on what the impact of these changes will mean on financially for the industry.
SPEAKER_02Politically, of course, Germany is in flux at the moment given the electoral success of the AFD party. How is that going down in Hamburg? How will it affect renewables policy at all? And what is the industry's response to this changing political landscape in Germany?
SPEAKER_00Well, I think uh there are definitely some concerns about political stability because obviously um risk aspects of that's not good. And then, of course, the the sort of rise in popularity or the current rise in popularity of the AFT uh could have some implications um for renewable energy. But at the moment, I think the policy uncertainty around changing regulations of the animal are more at the forefront of mind.
SPEAKER_00Um developers today and yesterday they've all said that of course these state election results don't um impact the makeup of the federal government. So uh they've emphasised that their focuses on continuing to work at the municipal level with local governments, uh, and they say acceptance within the energy has actually improved over the last few years. So they're taking a kind of a business as usual approach to the situation, um, but I think the political landscape is certainly back there.
SPEAKER_02Elsewhere at the conference, I mean we've seen some big uh news come from the turbine OEMs, both Vestus and Nordx have launched new models with giant rotors for the European market. We've seen some of the Chinese OEMs also launch turbines. I mean, particularly from the European OEMs, they're the first variants we've seen in quite a while from them after many years, where they've probably clipped their wings a little bit due to financial headwinds.
SPEAKER_02How have these new turbine variants gone down and what will they mean for developers?
SPEAKER_00Um well, I think I think actually first there's been a bit of surprise in the sector about the the launch of the new variants. I think certainly in the case of Nordecs, it was kept really under wrapped uh until the very last minute. Um and also, you know, in the onshore sector for quite a long time there's there's been a narrative that um onshore models, especially in Europe, wouldn't get any bigger um because the industry didn't need some logistics more to be classically.
SPEAKER_00Um I think uh talking to investors over the last couple of days, I think uh they're really positive towards the new goal. Um I think especially very often the prospects of an increase in AEP um energy complex and um that you're looking at around the 6% increase in A2 compared with uh other magic models. So that's really positive on the when you're in a mark margin for being raised uh increase in A3 is really welcome.
SPEAKER_02Thanks for your time. We'll let you get back to the conference. You are listening to the Renews podcast. For breaking news or to access our exclusive market intelligence on the global renewable sector, subscribe at renews.biz. Now, back to the show. I'm now joined from Hamburg by Paul Stephen, Renews' offshore wind editor.
SPEAKER_02I understand you've been along to Orsted's inauguration of the Borkham Rifgun Tree Wind Farm over there in Hamburg. What did the Danish giant have to say about what is its flagship project in German waters?
SPEAKER_04Well, hello Stephen, from me here in Germany. Uh yes, I was very pleased to go along to the event which was held just a short distance from here uh in the centre of Hamburg. Uh many of the great and good of the industry also went along to hear speeches and discussions, uh, not just from Osted Chief Executive Rasmus Erbo, but also senior representatives of the many companies and organizations involved in the um successful delivery of the 83 turbine scheme. That included Siemens Gemita and of course tenant for the grid connection.
SPEAKER_04Um as you can imagine, everybody's been very proud of the wind farm, which uh which could supply enough power for up to one million German households. Um it brings the developers' offshore installed capacity in Germany to two and a half gigawatts. Um although what was also clear is it hasn't been without its challenges.
SPEAKER_02What were some of those challenges, Paul, that Orsted outlined? I am familiar with the grid connection delay, having visited the topside up in Norway a couple of years back, which didn't get offshore on time. How are initial operations going on the project and what did Orsted say about how it managed those challenges?
SPEAKER_04There have certainly been uh several hold-ups, some of those um COVID-related and perhaps inevitable. Uh, a lot of them do relate to uh to the connection side, which which grid data suggests is ongoing as as Tennet continues to undertake maintenance. On the Dolwyn 5 link and also the Epsilon uh converter platform, which brings power to shore. Uh Orsted did seem confident these issues were close to being fixed, however. For more on this, I spoke to Orsted Chief Construction Officer Patrick Harnett on the sidelines of the event.
SPEAKER_01The wind farm um obviously it's one of the largest wind farms that we have in the North Sea. It's nearly a gigawatt, it's a um it's the largest that we have in uh Germany. And of course, with that size and scale uh comes enormous challenges. Well a number of the challenges have been as a you know as a hangover a bit from COVID. So, for example, uh the tenant's platform had was delayed because of COVID. That obviously has knock-on effects on other elements of the program.
SPEAKER_01There were there were challenges with the fabrication of the monopoles, and we work very, very closely with the supply chain there, with CS Wind and BLAT in order to uh overcome those together and actually make it a success overall and get the to get the monopols uh into the ground. The installation method that we used for the um for the monopols was challenged because one of the key key tools was delayed again by COVID because it it hadn't been completed in the uh in the COVID years in China.
SPEAKER_01And again, the team managed to overcome that. So it's a case of each and every challenge that was thrown at the team. Um they've overcome and then managed to deliver this enormous fantastic wind farm that creates a million uh enough uh electricity for a million homes in Germany.
SPEAKER_03How have they done that? Because a lot of these things are outside your control. The platform is tenant and the uh monopoles and uh construction in China, so the it's not within your gift to um No, so what you're not measured by the challenges that you have, you're measured by how you overcome them.
SPEAKER_01And so, you know, adaptability, flexibility, the competence and capability of the teams at all are second to none. And we were able to um adapt and overcome the challenges as they arrived, and you know, delivering commission the fantastic wind problems we see today.
SPEAKER_03We've heard glowing tribute to uh everybody involved in the project. Um, does this make this a template for future Austin projects?
SPEAKER_01Absolutely. I mean we we've developed um incredible capability in Germany with our local team. Um we have now have extensive experience in the market. Um we've proven our sonic technology on both projects and we look forward to looking for opportunities to uh to use that technology again. It's an attractive the German market's an attractive market, and we hear positive um news positive thoughts around you know contractor difference, which I think is we think is what the industry needs at the moment in order to build in a sustainable way.
SPEAKER_03Yeah, I mean there's a lot of debate um around the the offshore wind act is there and calls for the government to go further and faster. Is there anything else you'd like to see from the German government?
SPEAKER_01Uh we would we would like to see regular auctions so that it's a consistent build-out and you know, sustain CFDs that are a level that allows um you know the correct value to be created from the wind farms that we we're looking forward to building.
SPEAKER_02So, Paul, where else has your reporting taken you while you've been in Hamburg?
SPEAKER_04Well, sticking with this part of the world and in neighbouring Denmark, in fact, uh the traditional home of wind power, there's been some interesting calls from the trade association there to let uh Danish seabird be included in German auctions. But the argument goes that if um if those wind farms export their power mainly to Germany, which looks increasingly likely to be the case via interconnectors and other planned links, um, then it makes sense for them to be eligible for for German CFDs.
SPEAKER_04This would clearly require some international cooperation, uh, but would be an industry first as far as I know, and and is certainly uh an interesting idea.
SPEAKER_02Did the Green Power Denmark folk have any suggestions or any indications of whether that proposal uh or how that proposal is going down in Copenhagen or indeed in Berlin?
SPEAKER_04No, I get the feeling that it's at early stages. Um Germany is in the process of some quite wholesale reform uh to auction design, including bringing in CFDs, this would clearly add uh it's another element, um, another complication. It's perhaps not a burning priority. Um it's clear that bringing in power from non-domestic wind farms is part is definitely part of the longer-term plans, as we've reported recently with federal authorities beginning to plan uh for increasing amounts of power um to come in and contribute towards its long-term renewable energy targets.
SPEAKER_04Um so this could be an idea that goes somewhere, but uh but I'm not sure it's an idea for today.
SPEAKER_02As you say, the German government is looking at overhauling its tender regime. It's planning to introduce CFDs for next year, and recently we saw that Berlin is considering the introduction of indexation, which is something the industry has called for for a long time, not just in Germany but across Europe. Has that come up uh in Hamburg this week and what are the main developers saying?
SPEAKER_04It most certainly has uh been a big talking point. It was a major theme for him when I was here two years ago, but largely uh due to the absence of CFDs um and measures including indexation. Uh we of course we see it come as standard in the UK. Um the German government is currently looking at this um as looks to bring in two-sided CFDs from next year. As might be expected, this is definitely a hit with uh developers and the supply chain for tackling cost inflation, uh particularly in that tricky period between CFD award uh reaching FID and then going into construction itself.
SPEAKER_04Um RWE had quite a lot to say about this, um, the merits of not just doing it in Germany but but also seeing it uh more widely rolled out in other European countries.
SPEAKER_02Well, Paul, a busy few days for you there in Hamburg. We hope to read and hear more from you after the event. Thanks for joining the Renews Podcast and enjoy the next couple of days. The Renews Podcast was produced and edited by me, Stephen Dunn. Click subscribe wherever you get your podcast to make sure you never miss an episode. For more exclusive market intelligence on the renewable sector, see renews.biz.
Northland Power and ORLEN are in the final stages of commissioning Poland's first offshore wind farm, the 1.1GW Baltic Power project. In this episode, Northland's international executive vice president Toby Edmonds...
Ireland has big ambitions in offshore wind with a 5GW target for 2030. While few believe that is possible due to grid and permitting delays, it is expected that projects will enter construction in the coming years. So,...
Reporter Michael Lee-Murphy joins the reNEWS podcast from Taipei where he is attending this week's series of flagship energy events. Lee-Murphy reports on the current health of the island's offshore wind market and...
A dispatch from the RenewableUK and Scottish Renewables Floating Offshore Wind 2026 conference in Aberdeen. Hear Scottish First Minister John Swinney's view on what the UK government must do to unleash offshore wind...
Scott Sutherland, the project director of the proposed 1.3GW Codling wind farm in the Irish Sea, joins The reNEWS Podcast for a walk along the County Wicklow coast where he one day hopes to look offshore and see...