Scott Sutherland, the project director of the proposed 1.3GW Codling wind farm in the Irish Sea, joins The reNEWS Podcast for a walk along the County Wicklow coast where he one day hopes to look offshore and see turbines spinning. He joins our editor Stephen Dunne, who hails from the area and walks the stretch every day, for a chat about the project, the challenges on permitting and grid connection agreements, as well as CfDs awarded in 2023. Sutherland also talks about the wider importance of Codling and other so-called Phase 1 wind farms for the country's offshore wind ambitions.
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
SPEAKER_01Welcome to the Renews Podcast with me, Stephen Dunn.
SPEAKER_00Without phase one's being delivered now in a timely manner, I don't know what that means for the rest of the offshore industry in Ireland. We need phase one to be successful to unlock the investment for the next phase. And if we don't, you might be in another Article One situation whereby there's another 20 years go by. Ireland can't afford that.
SPEAKER_02So welcome to a special episode of the Renews podcast. As listeners will know by now, from my accent, I'm an Irish man. That's meant sometimes delving into Irish matters, but it's rare that I get to mix the professional with the private and the personal, but today is one of those days. I'm currently walking a stretch of land north of Wicklow Town, my hometown known as the Murrah, where I've been born and raised, and I have the good fortune to walk this every day with my dog Dixie.
SPEAKER_02Today though, I have a special guest who I'm hoping will make a bit more sense than the dog, and that's Scott Sutherland. Scott is the project director of the 1.3 gigawatt coddling offshore wind farm, planned just off the coast here. Scott, you're very welcome to the Re-News Podcast, and I hope you brought your walking shoes. Yeah, thanks very much, Stephen. Thanks for having me. Now the reason Scott's on the podcast today is because, as I said, coddling is planned just a few kilometres offshore here as we're walking north from Wicklow Town.
SPEAKER_02It'll be quite a prominent fixture on the horizon, hopefully, in a few years. Scott, you've been with the project a few years. What have you learned about us Wicklow folk over those few years?
SPEAKER_00Yeah, no, so I've been on the project now four just over four years. And I think that what we see in Wicklow is just a great reception that we get generally. People are very supportive of the project. We've done a lot of studies and sort of through Window Energy Ireland, and I think the local support is over 80% in favour of the wind farm. The community engagement that we've had, the the engagement during the planning process, has just been brilliant, really, to be honest, and really welcoming.
SPEAKER_02The Mora here, which as I said, I've been walking on since I was a child. It's a coastal wetlands area that stretches from Wicklow Town up as far as Greystone's about 15 kilometres to the north. It's a special protection area apparently as well, and there's a number of sort of protection areas along the line here. What do you know about this sort of part of the coast and also what implications has it had to have sort of special protection areas like this close to the project?
SPEAKER_00So we're quite lucky and fortunate in the sighting of Codley. We we don't have any special protected areas in the array. As we come slightly further in on the export cable, which is going to go into Pullbeg, there is some SACs around. So we've obviously had to be very conscious and take into account those protections, make sure that we minimise the impact as far as possible. And that's what we've done through the planning process, the pre-engagement, and then the planning application itself. So I think this is a great stretch of area as well. We've had great engagement all the way from Wicklow up to Greystones. The sort of the project is sited sort of between the two, um, between sort of 13 and 22 kilometres offshore, sort of right slap bang between Greystones and Wicklow.
SPEAKER_00So um, yeah, I think it's a great area. Um, and the coddling site is great for developing offshore wind as well.
SPEAKER_02Before we sort of get into the project, maybe I wanted to ask you about the big picture in Irish Offshore Wind. We're we're walking here in September 2026. We've got the phase ones of being on the move for you know in a big way for five or six years. Obviously, a lot of those projects have been around for a lot longer than that. Um we had a successful CFD auction in 2023, but we haven't had planning decisions yet, although hopefully are due soon.
SPEAKER_02The prospects of getting any steel in the water in the next few years are looking fairly slim. You know, before we sort of get into the detail, what's your sort of sense of Irish offshore wind in general?
SPEAKER_00I think there's definitely a lot of support for offshore wind. Things have been slower than we would anticipate, and even I'm sure the government would have anticipated, but I think we have to take into account this is the first time this has really been done at scale. Arcla 1 was built in 2004, so 22 years ago. That's the only time there's been any sort of real marine planning for offshore wind. So everything's being redone, sort of reinvented, if you like, and all the legislation and policy has been put in place, but then it needs to be implemented. And it's just that implementation is just taking longer than we anticipated. But that's not for the hard work of both the projects, the government, and also things like the regulators and ACP.
SPEAKER_00Um, what we want is obviously an expedited process, but we also want a consent that we can stand behind and actually go and build as well. So it's a trade-off there. Um, but we're hopeful we'll get our consent sort of early next year. Um, we'll be out for consultation on the further information. Requests will start on the 10th of September. Uh, that's an eight-week process, and thereafter, uh ACP have given themselves a timeline of four months to determination uh after that. So um, all being well early next year, we should have hopefully a positive determination.
SPEAKER_02So give us a sense on the project, maybe let's get into it in terms of give our listeners a bit of a walkthrough about the high-level details of the project, and you've obviously mentioned planning there, but what are the main work streams on the project right now and for the rest of uh you know into next year?
SPEAKER_00Yeah, so we if we walk back in time, this site was actually identified by Fred Olsen in 1999. So Coddling has been around in different guises for a long time. I was only a boy. Exactly. Um so high-level facts and figures. So Coddling is 1.3 gigawatts. We were successful in Orez in uh 2023, which was great. Um looking between 75 and 60 uh turbines, as a connection, three circuits back into Poolbeg, so right near the demand centre, that's where Air Grid wanted us to connect into. So in the Poolbeg Peninsula, connecting into the new ESPN substation there.
SPEAKER_00Um it's about 125 square kilometres of the array, about a 40km export cable. Um and yeah, so for the sort of the remainder of this year and into next year, the main concentration will be on electrical systems design. So we have a feed contract being awarded at the end of the month, and that'll then run us into 2027 where the interaction with AirGrid around sort of uh feed design and then into detail design will happen. Elsewhere, we're doing a lot of work with AirGrid to try and get the connection agreement and the asset purchase agreements over the line, working alongside CRU as well.
SPEAKER_00So that's a big work stream, and then the consent side responding to the further information, making sure that we're on the right foot to actually take that determination and go forward is kind of the big step for the project.
SPEAKER_02So you mentioned uh earlier, we'll get into the grid picture in a minute, but you mentioned earlier about the planning situation. I was looking back this morning before I came down here, and I think it was two years. Um it's about two years.
SPEAKER_00It's almost two years to the day, actually. I think it was about the 8th or 10th of September, 24. We submitted.
SPEAKER_02So you submitted the application two years ago. Last year, the phase one projects all received requests for further information, which uh from speaking to one of the phase ones the other day resulted in a pagination of 80% uh of what they actually submitted originally. So really hefty requests. We still haven't seen any consent decisions, although there is hope that the first of the projects, which would be the Oriol project of County Loud, could come out in the next few weeks before maybe even this podcast is released.
SPEAKER_02But you know, I'm interested to know. Obviously, you've said it's taken a bit longer, the whole process. How do you run a project during that phase and what does it mean for trying to staff up and staff down and just manage the whole process, not knowing you know how long this consent process is going to take and what ultimately it'll be the outcome?
SPEAKER_00It's definitely a challenge, and I think it's great having two supportive shareholders from Codling, an EDF and also Fred Olson, that we've sort of had that support from them. We've been able to staff the project accordingly. Yes, we've had to have shifts because things have gone slightly longer, but the commitment is still there, which is really really helpful. And also, I think as my old technical director coined a phrase, it's almost hurry up and wait. Because in Ulres, we've obviously got milestones that we have to deliver. So from clean consent, we now have two years to take FID. So, what we can't do is just wait for that determination and then start the work because there's certain works that are going to take longer than that period.
SPEAKER_00So we're we're in a balancing act of okay, what needs to be done now in order for us to be successful in taking FID within that two-year window, um, and that's how we prioritise the project.
SPEAKER_02You've mentioned your shareholders are supportive. I'm not asking you to speak on behalf of the other projects, but in general, like the other phase one shareholders and people involved in the offshore wind sector, you know, nobody expected it to take this long, and you know, there we've already had Coryo walk away from the Scared of Rocks project on the west coast for a number of different reasons, not all because it's taken so long, but you know, at what point will it become untenable for these big utilities to hang around here and wait for uh us Irish to get our acts together?
SPEAKER_00I think that's a it's a difficult question, probably up to each individual sort of organisation, but I think we do need to start now seeing progress. So there's a lot of work gone into it. The the t-shirts clearing house is helping and supporting and being able to feed back that information to shareholders that we are still progressing. But I do think that the first award, hopefully being Oriol in uh in a couple of weeks' time, will be a real measuring stick for the industry. And if that's then the case, we can start having a bit more hopeful predictability as to when our consent will come out, which will then give further comfort to the shareholders as well.
SPEAKER_00But you're right, the investment is difficult these days, like people are really targeting where they're putting their money. Um and luckily, right now, Ireland's still a target market for a lot of utilities, but it is competing, and Ireland in general is competing with the rest of the world for that investment. Um, and I think the government have taken that on board and they understand that. Um, and now it's about delivering through the other regulatory bodies and being able to see these projects into fruition.
SPEAKER_02Well, I don't know about you, Scott, but I didn't expect the weather to be quite as nice as well. The sun on your back, yeah, very warm. And you know, speaking of raising the heat, let's talk about grid. Um you mentioned grid process. Obviously, the phase one projects with Orez contract CFDs have been given grid connection agreements. Over the last few years, there's been a lot of back and forth between the phase ones and the transmission system operator AirGrid over the specs, the designs, the costs, the timelines, the OM phase, because ultimately the TSO will take over the grid assets in a similar way to you know other jurisdictions.
SPEAKER_02They'll be built by the developer but handed over to AirGrid. It's the first time AirGrid has ever done offshore wind connections. The latest earlier this summer was in Dublin at the Wind Energy Ireland offshore conference where it was quite clear that the grid connection agreements were still not of sufficient standard for the developers to bank. Can you give our listeners a bit of a sense of what's been going on in that process and you know what needs to happen now to ultimately get these grid connections to a to a stage where you can bank them?
SPEAKER_00Yeah, so probably worthwhile talking about that. There's two different agreements that we're currently working on with AirGrid. One is called the the offshore connection agreement. So that's your your typical grid contract, how you're going to connect, what the grid connection is and availability and everything else. And then you've got the asset purchase agreement, is where we then sell the assets back to Air Grid, sort of COD plus 18 months. Um so those two agreements are very, very key, both from a bankability perspective and a delivery perspective. So over the last year, almost two years maybe, we've been in negotiations with AirGrid around sort of what those agreements look like, what the obligations and liabilities are, and we're at a position now whereby the um offshore connection agreement is it's almost there.
SPEAKER_00We've still got quite a they've got a few fundamental issues still, but we're we're getting there. I think CRU are now opining on that agreement. But I think it's AirGrid have been in a difficult position, so I will give them some credit here in relation to this is their agreement, this is their liability, but they're also then responsible for negotiating with us. We want one thing, they want another thing. We'll get to a position probably whereby we we will need the CRU to step in and sort of give in a direction both for AirGrid and for the developer. Because AirGrid's a state entity at the end of the day.
SPEAKER_00For them to take risk, they want to make sure that CRU are comfortable with the risks that they're taking at the same time. So it's not without its challenges. We we've got good collaboration and cooperation with AirGrid, but there are a few fundamental issues that we still need to go over before these agreements are ready to sign.
SPEAKER_02The regulator, the CRU, has already come down hard on AirGrid last year over a lot of this. Um you're saying that it'll probably need another intervention, will it, by uh the CRU to get this right?
SPEAKER_00Not necessarily an intervention, more direction uh from CRU or from the department itself in relation to where risk and responsibility sits between the contract, between the developer and air grid. Um that that's kind of what they'll what we'd be looking for, is for that direction to be given.
SPEAKER_02Ultimately getting the grid connection right is you know probably more so than permitting or maybe even the root to market element is is critical, particularly on an island nation like this with a small system. You need to be confident that it's going to operate the way you know it needs to to ensure your revenue flows and and no hidden sort of issues. Are you confident that this is going to be sorted out in time in the next? I think at the Wind Energy Ireland conference, an AirGrid representative said hopefully by the end of the year.
SPEAKER_02You know, are you confident that it'll be sorted out along that timeline and that it will deliver what the developers need?
SPEAKER_00I I'd be very hopeful that the the connection agreement uh can be done by the end of the year uh with the will and uh the direction of the regulator and the department uh along with the collaboration with AirGrid, I'd be hopeful of that. So that's just one piece of the puzzle. The next piece will then be the asset purchase agreement, which you've got a longer runway on. The the main focus has been on the connection agreement to start with, and now the focus will shift into the asset purchase agreement as to how that mechanism is going to work, what we're gonna build, how we're gonna build it, and how Air Grid are actually gonna purchase that off of us.
SPEAKER_00So, yeah, and it is a critical document. I think the will is there. Uh, the the agreements aren't quite in the right form yet, but I'm hopeful that we can get that done by the end of the year and both parties can be comfortable with um with the agreement going forward.
SPEAKER_01You are listening to the Renews Podcast for breaking news or to access our exclusive market intelligence on the global renewable sector. Subscribe at renews.biz. Now, back to the show.
SPEAKER_02We're looking north here towards the point, as we call it locally, which is basically playstones beyond the point there. Your project's gonna be out to the right of us here to the certain northeast. Uh, your grid connection, as you mentioned, is into Pool Beg, up north into Dublin. Um, it's not as straightforward maybe as coming straight in uh from Codling into land. You've got to go north, you've got to connect into a busy, a busy location, uh an industrial location.
SPEAKER_02What's the challenges with that grid connection and you know what sort of sort of early engineering work have you needed to do to try and get that right and work with the system operators on it?
SPEAKER_00So, yeah, as I say, the grid connection into pool bag it has its benefits and its challenges. The benefit being obviously Dublin being the largest demand centre on the island. So when it comes from a constraints perspective, that is a great position to be in in Pool Beg, straight into the demand centre. Challenge if you got it's obviously quite a long export cable route. We've got some deeper burial areas, like we're going past Dunleery Harbour, so right the entrance to the harbour. So we need to make sure we take into account shipping lanes and maybe bury the cable slightly deeper.
SPEAKER_00Then in Pool Beg itself, it's a rather constrained peninsula, if you like. Um so one of the big challenges there actually is although we only have about 900 meter stretch from landing on the peninsula to Pigeon House, where the um substation will be, there is so many services in that Shelley Banks Road area that we're actually having to build a tunnel. So that's one of the unique sort of the the onshore connection itself is almost an infrastructure project in itself. So we're looking at sort of a 20-meter deep, four-meter diameter tunnel, sort of from the landfall site, popping straight up into our substation site, of which is quite constrained itself.
SPEAKER_00It's probably half the size we'd want, it's about uh just over a hectare and sort of land. When you look at a compensation compound for 1.3 gigawatts, you probably want at least double that. So we're having to build sort of a multi-sory substation. But again, these are the challenges that we're willing to work with, obviously, for getting that grid connection. We had other options with air grid where we're looking at carrick mines, uh, where I think Dublin Array are going to connect into. They all have their challenges and their benefits, but I think um we're comfortable with Poebag now, we're getting more comfortable.
SPEAKER_02We'll turn around because if we keep walking, we'll end up in Greystone. But it strikes me as you're talking there about the grid connection, and we just talked about the planning delays and things taking longer. A lot of offshore wind projects now are are front-loading all their grid works well before their offshore campaigns on their arrays for loads of different reasons, partly due to the complexity of system upgrades, partly due to the late delivery of you know backfeed and go live on your grid connection. What you've just outlined there is a really complicated, tough infrastructure challenge.
SPEAKER_02At the moment, you can't place a firm contract because you haven't got planning permission and you haven't got that bankable grid connection. How are you going to I suppose de-risk the grid build? Um, because you'll need to get onto that pretty quickly, won't you, in order to deliver the project?
SPEAKER_00Yeah, for sure, and that's where where I talked about sort of the just earlier around what we're doing in the sort of latter end of this year and start of next year. That feed engineering on the electrical system is just the big part. So what we've done is that because of that and because of the way the contracting structure is, and we're not going to be able to place a tier one contract until we have some more certainty, as you're mentioning, around planning and around grid. We've taken that front engineering in-house, so we're going to do that independently of a tier one contractor to allow us to sort of unlock that process without having to overcommit it this time and then gain more confidence in that feed design going into then detailed design.
SPEAKER_00So that's kind of what we're doing right now. So that contract will be awarded hopefully by the end of the month, and that'll enable us to firm up our thought process around that grid connection and how we develop it going forward.
SPEAKER_02So moving on, I mean we're at the end of an interesting summer in Irish Offshore Wind. We've had a lot of debates and discussion around the 2023 Aurez contract awards. As readers of Renews will know, there's been a number of updates to that. Some phase one developers have asked the government to improve the terms of the Aurez contracts because of the delays that have resulted in changed economics on the projects.
SPEAKER_02The government has publicly said in a statement to ReNews that they've declined that request. Before we get into the sort of the detail on it, like what's your overview sense of this debate and conversation in general rather than specific on the project?
SPEAKER_00So I think in general, just looking at the offshore industry as a whole, it's a challenging environment at the moment. We've seen sort of since 22-23 a significant increase in CapEx, whether that be on turbines or foundations or electrical systems. And that has had a hit on, I think, probably every project's economics. And it's how do you manage and sort of take that forward? I think the one thing we did sort of negotiate with the government and we we dealt with them quite thoroughly on this, was the milestones in Orez. So that was actually a change that happened three or four months ago now.
SPEAKER_00What that's done is it's relaxed the NTP, so the notice to proceed milestone, which originally was one year from clean consent. Again, not knowing when that clean consent comes, it's really difficult then to manage a project and your spend. So that's now been expensive. Extended to 24 months. So that gives us some breathing space on the project to allow us to sort of develop in time with more certainty on the project. So that was that was great, and it was a lot of sort of discussions with the department, and it was great that we managed to get that over the line.
SPEAKER_00Elsewhere, I've seen your article in Renews before, we're working with the government constantly in relation to the viability of everything. And some projects maybe not, some projects maybe are. We'll see in the coming weeks and months how that develops. But at the moment, from coddling perspective, our shareholders are committed to coddling. They're committed to Ireland. EDF side, we have some onshore projects and we have some solar as well. So I think that's really good for us as a project.
SPEAKER_02So from what you're saying and what others are saying, the government has helped where it can. It has made some tweaks to the process, but clearly, you know, on the bottom line, if you like, they're they're holding firm on those awards in 2023. The ORES contracts aren't fully indexed, which is a big issue and is something that's being debated in the German sector right now, where they're talking about CFDs, and Berlin just the other day decided to introduce some sort of indexation.
SPEAKER_02Is that the critical issue here in that the the contracts haven't moved with you know the times over the last three years and that they haven't provided that protection against inflation which continues to impact the global economy just as much as offshore wind?
SPEAKER_00Yeah, I think the nuance of the ORES contract is that we do have indexation protections to a degree, uh, and up until uh FID we have sort of 90% HICP and then we have 10% steel. The steel's actually quite a big factor at the moment because steel's actually reducing in price. So it's kind of offsetting that inflationary pressure by the steel reducing as well. So that's a bit of a nuance, but as I see it was a competitive auction. Uh the four projects were successful. There's three three of us left now with scared, um, sort of no longer here.
SPEAKER_00We we all have different economics, we all have a different price, um, and we all have different challenges. And I think the the work that we've done with the government and the continued dialogue that we have, it just shows that there is the willingness from government, that there's a willingness for this offshore sector to be delivered. And I've said it before, I think without phase one's being delivered now in a timely manner, I don't know what that means for the the rest of the offshore industry in Ireland, to be honest. So I think we need, and this is not just me talking about coddling, but I think Ireland in general, we need phase one to be successful, to unlock the investment for the next phase and then the phases beyond that.
SPEAKER_00And if we don't, you might be in another Arclo 1 situation whereby we there's another 20 years go by. And I don't think Ireland can't afford that. The energy security, the the sovereignty of energy. I was looking at an article the other day. Ireland spends, I think it's a million euros an hour on imported fossil fuels, which is 9 billion euros a year, and 80% of it comes through, I think it's a single pipeline from the UK. That is not a really secure way to see for your energy. And then also on top of that, is unlocking the other potentials in Ireland.
SPEAKER_00There's a great industrial sector in relation to pharmaceuticals, but now the data centre and AI, those data centres need a lot of power. And what your electrical consumers don't want is their price to go up because they're trying to power a data centre. So you need alternative forms of energy to do that as well. So I think that's the real benefits that offshore wind can give Ireland.
SPEAKER_02And yet it comes down ultimately, despite all of those obvious drivers for offshore wind in Ireland, ultimately it comes down to you know brass tacks, right? So the Orez contracts were awarded in 2023 at around uh averaging 86 euros per megawatt hour. You know, in for a comparison, even though it's hard to compare, the AR7 contracts for offshore wind last year were awarded at around 100 euros, give or take.
SPEAKER_02Yeah, I think it's about 91 pounds or whatever that it's compared into Euros yet. And they are fully indexed, unlike the Orez contracts in Ireland. So there's quite a gap there, although I appreciate it it may not be quite as wide when you actually do the proper calculations. This is the back of a beer mat sort of uh thing here. But nevertheless, those AR7 prices are gonna be a challenge for the UK, an established market, but they're more attractive than the ones over here where it's a new market.
SPEAKER_02We just talked about all of that policy development, all of the delays, the development capital that's being spent. Is it really realistic for the phase one projects to be built out under these contracts?
SPEAKER_00I I think so. I I I do, I'm very sort of hopeful and optimistic on that. We have our challenges for sure. We we need to be smarter in the way we engineer and design our projects within the parameters and the bounds of the planning application, better and smarter at how we procure and what supply chains that we foster. So as I say, I'm I'm hopeful and optimistic that these projects can be developed under the under the current contracts, but there's headwinds in the way at the same time. And I think there's things that the government can do, there's things that we can do ourselves to sort of enhance the viability of these projects.
SPEAKER_00I can't talk for the others, but that's that's where I am on Coddling.
SPEAKER_02Oriel, we mentioned all eyes on the planning decision. What sort of signals are you looking to get from that in the next few weeks, hopefully?
SPEAKER_00So yeah, I think it'll be great if that if that comes. I think it's due the 21st of September. I think if that keeps on that timeline, that just really helps investor confidence, first of all. But secondly, what we'll be really looking at is the the conditions. Well, we're I'm hopeful they get a positive decision in the first place. But then we will be looking at the conditions that ACP are going to impose on that determination because then we can start getting a bit better view as to what conditions are going to be in our consent as well, and where we can start working towards how do we satisfy those conditions, what are the general conditions that they have, what is an entity need to do to be put in place to be able to satisfy the conditions.
SPEAKER_00So I think that's going to be the big thing for the industry as a whole. This will be the first determination, hopefully positive, and that conditionality within it is going to be key.
SPEAKER_02Speaking of about coddling, then you're hoping for a consent decision early next year. Yeah. Obviously, in the consenting realm, everybody's concerned about the litigious nature of Irish society and that the case some of this might end up in a judicial review. We're a million miles from courthouse in Dublin, so we won't go into that. But what does it realistically look like for Coddling in terms of that high-level timeline of getting your consent?
SPEAKER_02And once you have your consent, you've got your ORES, you've got your grid connection agreement hopefully sorted out, you've got your consent. The three main things you need for a project. When like as early as possible, can you hit FID? And what could we see in terms of a construction program and COD?
SPEAKER_00So it is really dependent on that potential judicial review and whether that's received or not. I think the good thing about the the way the process is working now, we've seen the courts actually they're fast tracking these decisions. Um so whereas before it was kind of a bit of a finger in the air as to how long a JR potentially could be, there's a bit more predictability around that. But if we get our consent next year and we're luckily enough for that that consent stands, we would be looking to take FID towards the the back end of this decade and then construction at the front end of the next decade.
SPEAKER_00So seeing steel in the water in the early 30s, that is the that is the goal. What have you learned on a personal level?
SPEAKER_02You're a proud Scotsman, obviously. Uh you've uh become an Irish man over the last few years. What have you learned about the process and about you know how the country has responded to offshore winds and and what ultimately looks like success for you when you get steel in the water and you get the project built?
SPEAKER_00I think that the first thing we've we've learned really is patience and perseverance. That's the key in Ireland here at the moment. And again, we have to take the fact that we are the first. We are the guinea pigs, the test bed for Ireland. And what we do now, I think the the proud nature of it is what we do now will hopefully stand the industry in good stead going forward. So that's a bit of pride that you take in that yourself. But what looks good, I think the government have that they are willing and they are sort of supportive of the industry, and that that is really good to provide investor confidence, shareholder confidence.
SPEAKER_00I think what we're seeing now is that that is now starting to trickle down into the other parts of government, into regulators, into decision makers. And we're seeing that push, the clearinghouse has unlocked it as well. The teacher at Mayho Martin has come out and said that this is one of his national priorities is developing offshore wind, which is great. We just have to have a bit of patience, a bit of perseverance, and we will get through it and we will get these projects done. You believe that, do you?
SPEAKER_02Because there is a sense in some quarters that offshore wind in Ireland is on a knife edge, in that, as you said yourself, if the phase one projects aren't delivered, where do we go from here? You know, we've gone through all of the issues, whether it be uh an uncertain consenting process, um a slow and cumbersome grid connection agreement process, uh a challenging business case under the ORES. There's still a lot of square pegs and round holes.
SPEAKER_02Do you do you do you firmly believe that Ireland and the developers and the government can deliver these projects?
SPEAKER_00For me, I I'm still confident that these projects will be delivered. Whether they're all delivered or not, I that's not for me to say, but certainly from a coddling perspective, I I'm confident that coddling can be delivered, the size and scale of coddling, the significant importance of coddling and the power. We're talking almost a million homes that coddling will power. That's almost half of all Irish homes. So it's it's of national importance and significance in my opinion that it is built. And I think there's the willingness to build it, there's the shareholder willingness to get it done.
SPEAKER_00So I I am so confident.
SPEAKER_02If you had one final message, you know, if the Tae Shuk was here with us on this walk and had his dog with him, uh, what would be your uh what would be your message to him uh from the offshore wind industry right now?
SPEAKER_00Support. Yeah, I think we we are getting it, but that support and the continued support of himself and the government and the department in unlocking the challenges to the projects. It it's coming through, but we could be a bit faster, a bit more predictable.
SPEAKER_02Well, Scott, this has been the most special of all the 20 re news podcasts I've done because I've been able to walk where I walk every day with someone from the industry. Thanks very much for being on the re news podcast, and I think it's only right now that I bring you for a pint in the local hospital. Sorry, thanks very much, obviously.
SPEAKER_01The Renews Podcast was produced and edited by me, Stephen Dunn. Click subscribe wherever you get your podcast to make sure you never miss an episode. For more exclusive market intelligence on the renewable sector, see renews.biz.
Northland Power and ORLEN are in the final stages of commissioning Poland's first offshore wind farm, the 1.1GW Baltic Power project. In this episode, Northland's international executive vice president Toby Edmonds...
Ireland has big ambitions in offshore wind with a 5GW target for 2030. While few believe that is possible due to grid and permitting delays, it is expected that projects will enter construction in the coming years. So,...
Reporter Michael Lee-Murphy joins the reNEWS podcast from Taipei where he is attending this week's series of flagship energy events. Lee-Murphy reports on the current health of the island's offshore wind market and...
A dispatch from the RenewableUK and Scottish Renewables Floating Offshore Wind 2026 conference in Aberdeen. Hear Scottish First Minister John Swinney's view on what the UK government must do to unleash offshore wind...
At WindEnergy Hamburg 2026, the German onshore and offshore wind sectors have sounded alarm bells about future growth. Hear from the fair from reNEWS senior editor Sian Crampsie, who outlines the onshore concerns her...