During a visit to the Port of Leith, ESB head of offshore wind Paul Lennon talks about the status of the construction campaign for the 1.1GW Inch Cape offshore wind farm. He tells reNEWS Editor Stephen Dunne about the 18 jackets currently marshalled at the Scottish port, what the company has taken from building the troubled 450MW NNG project and how Inch Cape has got to the point of being on track for first power later this year.
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
SPEAKER_01Welcome to the Remuse Podcast with me, Stephen Don.
SPEAKER_00But yeah, there was a certain number of synthesis out there in terms of having a look at ranges of progress and then almost catastrophizing how we would go in the end. But ultimately with the engineering, it's done successfully, and it was just really way suitable.
SPEAKER_01Everyone was hello listeners, you join me as I'm on my travels again, this time in Edinburgh, where the city's inhabitants have recently been getting used to some interesting new neighbours. I am in the port of Leith, just a few miles away from the city centre, where huge jacket foundations have begun to appear over the skyline in recent weeks.
SPEAKER_01The structures are for ESB and Red Rock Renewables, 1.1 gigawatt Inch Cape offshore wind farm, which is under construction off the coast.
SPEAKER_01So I travelled to the Scottish Capital to walk among the foundations and talk all things Inch Cape and Offshore Wind with Paul Lennon, the head of offshore wind at the Irish Utility ESB. Here's how we got on.
SPEAKER_00Okay Stephen, well, welcome to Leith Port. This is where it's all happening at the moment in relation to Inch Cape, and it's a great day to be here and finally get to see all the hard years of work that's gone into getting the project at this point, anyway.
SPEAKER_01Thanks for having me for starters. I mean we're standing here and we're looking at I can't count them, but I think there's about a dozen or more. 18 jackets in front of us. Huge yellow monsters on the skyline of Edinburgh. Jackets aren't uh aren't as common now in offshore wind, but on Inch Cape they are. What what was the decision behind bringing in jackets on Inch Cape?
SPEAKER_00Yeah, so um a couple of couple of main reasons in terms of jackets on Inch Cape. Really, first one was down to uh ground conditions. So maybe just look at Inch Cape at a high level. Uh we have 72 turbines, so 54 of those are the monopiles which you just missed maybe from about four four weeks ago. The last shipment of monopoles went out there and talked about them in a second. Um, so 54 monopiles and 18 jackets.
SPEAKER_00Um, and the rationale, two main reasons: water depths and also just site conditions at the very across the site vary um a lot, um, and just in terms of the strength of the seabed. So, in certain areas we felt that um it was more jackets for a better overall solution.
SPEAKER_01The jackets here obviously you contracted in Asia.
SPEAKER_00Yeah.
SPEAKER_01Um what was that scope like? How did that work out with the fabricator? Jackets aren't the most straightforward a thing to fabricate, and over the years have always presented problems on projects, but here it appears certainly to the naked eye, you've got all your jackets here ready and they all look ready to go in.
SPEAKER_00Yeah, so in terms of the fabrication of all of the foundations, um we had three main fabricators, as you said, they're all all Chinese fabricators. So, in terms of the pin piles, which you can see just behind the jackets, there we have 54 pin piles and as I mentioned 18 jackets and they're all fabricated from the same company CFHI. Then in terms of the transition pieces, which you can see just in front of us here, we've two fabricators for the 54 transition pieces, so um CFHI and GWSHI, and then for the monopiles, we had two fabricators for the monopoles as well, two Chinese fabricators so Dajing and GWSHI.
SPEAKER_00Um, and a key I suppose benefit for this project was really having three different fabricators manufacturing all the foundation scope and just effectively um not putting all their eggs in one basket and having de-risking the overall fabrication um process for the foundations and we've seen in terms of time, terms of budget, uh in terms of quality, it's it's second to none in terms of what we've seen from from the Chinese uh fabricators here in particular, it's excellent, excellent finish.
SPEAKER_01There's a big debate obviously at the moment in the industry around you know the influence and the involvement of Chinese companies, maybe more into turbine OEM space, but obviously they're here and and active in the steel fabrication space. What's your sort of sense of that? We hear the European fabricators say there should be tariffs on this finished steel coming into Europe. The Chinese guys say we're competing on a level of playing field as it is. What's your read of it?
SPEAKER_01And having gone through the experience of dealing with them, you know, how do you find it?
SPEAKER_00Yeah, I think from well, I can only speak from our own experience on HCape here, um, and uh in terms of as I mentioned, in terms of quality, in terms of um safety on the site, and in terms of trying into different sites, we had over 50 people out on across the three fabrication sites just looking, checking quality for safety for health and safety and just supervising over the period that the the foundations were manufactured. So all I can speak of is from our own perspective, we've seen the quality being second to none, and and the proof is here in terms of all of the foundation infrastructure landed in Scotland on programme and with very very little uh defects or any additional amendments needed.
SPEAKER_01We'll talk about the monopoles in a minute which are already in the water, about what 40 kilometres out at sea here, maybe?
SPEAKER_00Or is it a bit less, no no, it's it's it's only about I think in around 20-25 kilometres from from shore.
SPEAKER_01So when will we start seeing these jackets um loading out and and going for installation?
SPEAKER_00So, first thing we'll install those pin piles so you can see that as I mentioned, the pin piles behind the jackets there. So we have a pile insulation frame, so that's coming, that's up in Invergordon, so that's coming down um over the next couple of weeks. And the Seaway 7 vessel, which you can see over there, the alpha lift, um, so that's gonna once it's finished the transition pieces. So we have 54 transition pieces to go on top of the monopiles. As we stand here today, we have 34 transition pieces installed.
SPEAKER_00So you can see it's coming in for those six. It's gonna load up those six today, hopefully get back out in the field. And by early August, we should have all the transition pieces installed. Then the Alpha Lift is going to come back and commence the insulation of the pin piles. Um, so it's gonna take on board the pile insulation frame or PIF and the pin piles as well, and it'll get I think it's around nine pin piles or three um jackets uh foundations at a go in terms of the installation of that, and then once that's done, the jackets will will be installed probably from September onwards.
SPEAKER_00That's the plan, anyway. September, October onwards.
SPEAKER_01You still have the scars from NNG and drilling in the seabed there for jackets. What's the approach to pin pile installation here? And you know, we're not a million miles away from NNG. Do you do you think you may have some seabed issues on jackets?
SPEAKER_00Well, touch wood, um, never say never. Um I think all the design, the engineering, the validation, the revalidation, um the geotechnical work, all of that groundwork that we've put in would like to think that we shouldn't have any issues anyway with installing the pinpoles. We had um in effect no issues associated with installing the the monopoles, and if just put things into perspective, those monopoles were about 110 metres long by 10.5 meters in diameter, um, and each one of those what went in went in well into the North Sea.
SPEAKER_00So you can see the pin piles are a lot smaller in around the 40 meter mark and maybe in around 3 meters in diameter. So the we'd be confident based on all the engineering, based on all of the work that's gone into today, that we shouldn't have any issues with the the pin piles, but it is an important consideration.
SPEAKER_01So go going back to that monopile installation job, which started I think just before Christmas uh last year, you know, again talk about NNG. You came here and had a difficult job, difficult seabed, big water depths, massive monopoles. Yet it appears you knocked them in in I don't know what record means, but in some sort of quick quick order.
SPEAKER_00Yeah. How exactly did you achieve that? So the the Les Alise came in, I think it was in around the 20th of December, loaded up um the first four uh monopoles and went out in around Christmas Day or day after Christmas Day. So um and we got the first one in, I think, within a couple of days of being out at sea. For the following eight weeks, we got a further two monopoles into the into the into the seabed, and that was a mixture of um just terrible seabed conditions, metoting conditions at that point.
SPEAKER_00Um so we were we were concerned to be honest with you in relation to just the rate of progress. Um but then once the weather picked up um and just to be honest with the professionalism of the the staff on the Les Elyse and Yandonol and all of the work that again has gone in between the the Incate project team and uh Yandanol, that was a seamless activity, and we towards the end there we were getting one monopyle in per day, and just with with obviously the right weather conditions and everything, but we um we look you make your own look, so they say, in terms of in terms of all that goes with it, but we really put in a lot of effort again in terms of just a whole geotechnical campaign looking at the design, significant amount of engagement between the the Inch Cape team and Yandonol just in terms of the seabed, and we had external consultants appointed as well just to keep the checking and the validation going in relation to the seabed conditions, and ultimately came down to I'd say good design, proper engineering, and a very professional crew on the LED Alize, a very competent crew because we had the not only do we have each of the monopoles but for 44 to 54 locations we had a pile follower as well, which was effectively a steel tube that went on top of the monopoles, and the hammer used to hit the the follower which then would pass the force through to the monopyle during installation.
SPEAKER_00So that again was a further complication on top of everything else, but all of that went according to plan again. We ultimately caught up in programme just given the rate of progress during particularly May and June.
SPEAKER_01Was there ever a point during that eight weeks where you you know started to started to worry or started to get concerned? Because I you know I know the vessel Les Elise is obviously a charter that from RWE and that only had a short window, and there isn't a lot of those vessels lying around the place that can handle these massive monopoles. Did did um was there ever a point there where you felt we're we're we're gonna be tight on this?
SPEAKER_00Yeah, personally, you're looking at this pretty much every day in terms of checking progress, the rate of progress, you're looking at the the marine traffic to see if we've moved, is it likely that we're gonna move um within the day, within the week? So there was a period of time there in March where looking at contingency planning and what what could we have done had we um gone beyond the contracted period in terms of the vessel? Um because as you mentioned, Stephen, there's there's only a few vessels in the world I'd say that can carry um monopoles of the weight that we have here in terms of about 2,300 tons.
SPEAKER_00Um so ultimately we got there in the end, but yeah, there was a certainly a number of sleepless nights there, I'd say in around March time, in terms of having a look at rate of progress up to that point, and then almost catastrophizing how how we would go in the end, but ultimately with the engineering done and done successfully, and it was just really waiting for uh suitable weather windows, um which we did get there.
SPEAKER_01I know NNG is a different side, and you you know it's a little bit like comparing apples with oranges, but you know what is it that you took from NNG into this operation and into this campaign that has maybe helped achieve the progress to date?
SPEAKER_00There are different projects. We with different obviously different different different teams, different joint venture. Um a lot of learnings from an ESB perspective went into Inch Cape, particularly in relation to, as I mentioned a while ago, maybe multiple fabricators looking at trying to eliminate any amount of drilling in the particularly in the North Sea. Um that was a key consideration for us at an early stage in Inch Cape is to make sure that we we limited the amount of drilling in the North Sea.
SPEAKER_00Um that meant having effectively at the time, I don't think it is now, but at the time the world's largest hammer um hammering hammering in the monopoles and to the point where we felt that we couldn't hammer in the final 18, we went for a jacket structure instead of looking for a drilled monopole. So at all times we wanted to ensure that we limited the amount of drilling effectively to zero here on this on this side where on energy there was a significant amount of um drilling.
SPEAKER_00You mentioned the jackets.
SPEAKER_01I mean we're we're we're walking along here and I'm looking at at a line of as you say 18 huge jackets that have come all the way from China on the back of a ship, which I don't quite understand how they're able to achieve that, but nevertheless they're here. I mean, talk us through the size of these animals and uh you know how they compare. I mean, they look, I've seen some jackets in my day, but these look pretty much up there in terms of size and scale.
SPEAKER_00So these jackets, if they're not the biggest in the world, they're certainly in around the biggest in the world. So um the largest jacket here we have here is about 83 metres tall, so you can see even just standing up there, they're they're huge. Um and we're putting on the 15 megawatt Vestas turbine as well, which is the largest turbine in the world. So um seabed depths here are in around 55 metres, you know, plus or minus. So that's that's why we're ending up with the jackets given this the size that they are, um the scale that they are, but they're they're impressive structures uh nonetheless.
SPEAKER_01I mean I've been I've covered offshore wind for a long time and covered jacket projects for a long time, and as I said earlier, jackets have had a checkered past in terms of their quality and delivery. One thing I often would see at ports like this when jackets arrive is a is an army of cherry pickers in to fix welding and to repaint and to snag up and so on. Everything looks pretty quiet here. These jackets were delivered well.
SPEAKER_00Yeah, no, they were top class, it was really, really top quality um finishes. We do have um a local company that are looking at some of the painting, some of the welding, but to be honest, it's it's it's bits and pieces, it's nothing substantial. They're really a first-class job coming from actually well in the case of jacket C F H I in terms of top quality coming across from from China. Um so we've had very, very touch wood now, thankfully, we've had very few issues in terms of touch-ups.
SPEAKER_00Well that's that that's what it has been, just touch-ups and a little bit of paintwork, but nothing substantial at all coming on the jackets or the transition pieces or even the monopiles.
SPEAKER_01So, which vessel now we talked a little earlier on about installation, which vessel will be in for these? And you know, when you look out to the rest of the programme Fringe Cape, is this now the last sort of big ticket program you would imagine in terms of where things where the risk lies?
SPEAKER_00Seaway 7 Alpha Lift will um install the jackets and the pin piles as well before before the jacket. So, my own experience is that below sea level is usually where the risk is. Um, and so so for this phase it is absolutely the biggest risk until we finish this phase, and then it'll be getting the wind turbines in over the course of um November, starting in November, and over the course of Q4, Q1, Q2 of next year. Um but that's just the scope here out offshore.
SPEAKER_00We obviously have the onshore substation as well, which is own scope with its associated risk. But um based on I suppose my own experience and looking at NNG, it's really getting out of the water will be a huge um it'll be a huge moment for the project for ESB as a company and just for for everyone working and involved in the project.
SPEAKER_01You are listening to the Renews Podcast. For breaking news or to access our exclusive market intelligence on the global renewable sector, subscribe at renews.biz. Now, back to the show. You mentioned the onshore side projects in Scotland. I think the last number of projects have all had difficulties with their onshore grid connections and late delivery from the grid side of energization backfeed, whatever you want to call it.
SPEAKER_01I think you guys have experienced a little bit of that as well, perhaps. Although obviously you took a decision early on to go really far ahead on the onshore scope in the event that you might find an energisation delay, and it looks like that's gonna that's gonna stand to you even with the delay from the grid side. Can you talk us through what the situation is with that at the moment and whether it will have any impact on the programme?
SPEAKER_00Clearly the right decision to do at the time, but back a couple of years ago we took a decision between uh ESP and Red Rock to commence the onshore substation well in advance of financial close, and for that exact reason, Stephen, it's usually a long lead item in terms of the overall construction of a project of this scale, um, and we want to try to get ahead of it. So we we we entered into contract with Siemens for the onshore substations and the offshore substations, and we also entered into a contract with Ningbo for the export cable between the offshore substation and the onshore substation.
SPEAKER_00So commenced that over two years ago now at this stage, and it is it is it's ready, it's ready to be commissioned. Scottish Power are working are working on their side of the grid connection. Hopefully, we will have um we'll have energisation there in early August so that we can start the commissioning of the overall um grid infrastructure. So we we it's it's not on the critical path at the moment. Uh we want to keep it off the critical path. We want to keep that that float we have between energisation, doing all the pre-commissioning, getting the turbines in here installed from October onwards, and then ultimately having power to commission the turbines and export before Christmas, first power before Christmas.
SPEAKER_00So that's our that's our overall plan. But for us to be able to do that required um significant decisions back a number of years ago when the overall you know business case and the overall outlook for the project was not as well understood, maybe as it is now. But that's I suppose that that's the inherent risk that comes with offshore wind when when grid connections are usually on the critical path.
SPEAKER_01We might go back to that in a minute, maybe focusing on construction and installation. Obviously, you've mentioned a few times it's Vesta's 15 megawatt turbines. First deployment in UK waters? First deployment in UK waters, yeah. Vestus hasn't had it easy. I mean, they've publicly disclosed. This in terms of having to set up a manufacturing footprint for this new turbine? They've had a couple of delays on the early projects in terms of pushing out nacelles and blades and so on.
SPEAKER_01Where does it sit for you guys? And are you confident that the equipment will start arriving into Dundee? I think, is it before first loadout in October, November time? And what's the interaction with Vestus being like on this new model?
SPEAKER_00Within the project team, they're actively working with VESIS, within the package managers there and within the Inchcape team. So everything's going to plan on programme from a risk perspective as a as I suppose a shareholder in the project in terms of ESB, we see limited risk within VESIS in terms of the fabrication of the components and transport to Dundee over the next number of weeks, actually, at this stage.
SPEAKER_00So that's that's that's on programme, and we'd be confident that we'll make the timelines there in relation to the wind turbine side of things anyway.
SPEAKER_01All going well then. When will we see first power? And do you think the winter will have its say in any of this like it did in the monopyle installation campaign?
SPEAKER_00Yeah, so winter always has its say. We have factored that into the overall programme for Inch Cape, so the we're working towards a commercial operation date of August of next year, and we're confident in delivering that date. First power, we are forecasting for the end of this year, so end of November, early December. We would hope to be exporting before Christmas. That is our that's our plan, that's what the project team are working towards. We have a very motivated project team there under John Hill that are working hard to get the substations energized, get the obviously finish the marine works and the foundation works and commence turbine installation towards the end of October and first Mar before Christmas.
SPEAKER_01You're in deep into the campaign now of delivering Inch Cape. I think I mentioned to you on the way down here. Inch Cape has been mentioned always as a project that might never get built. It's gone through many different hands, it's bid into many different allocation realms. You eventually secured an AR4 deal projects in that auction, never got built because they were I think it was Boreas at the time because the the prices didn't didn't work.
SPEAKER_01You had another bite, I think, in AR6 and got you know uh a slightly higher CFD and a better business case for part of the project. Still, Projects Horn C4 wasn't delivered out of that at a similar price. This is a really tough project, deep waters, challenging conditions, tough seabed, all of that. Scotland, the whole shebang. How have you actually managed to get to this point?
SPEAKER_00It's a great question, Stephen. Um and when you stand here and look at what we have in front of us here in terms of the transition pieces and the jackets, it's uh it speaks to the resilience of the of shareholders, project team, um, and ESB as a company. And there were times that you would you'd think back maybe maybe we wouldn't have got this far without um people. Ultimately, people have got us to to to where we are today. Um but maybe yeah, just to recap, the reason I'm standing here and the reason ESB is involved in offshore wind is um is really around what we can we feel it can do for Ireland ultimately, but also in terms of um delivering to the UK's um renewable targets as well.
SPEAKER_00But uh less than 10 years ago we didn't have a presence in offshore wind, and we started in 2017 with a small stake in Gallipur just to literally get our feet wet to develop to develop our own understanding of offshore wind to build the capability but also build the credibility in the sector. And what I've seen is that it comes down to credibility as a developer, as a as a utility, as an offshore wind company. You really need that credibility with the OEMs, with the vessel suppliers, with the foundation fabricators.
SPEAKER_00So from there, as we've just mentioned, we moved on to Nart Negrija, and moving back earlier in the development cycle. So we went into that project at Financial Close with with EDF, and I know you were speaking to Matthias a number of months ago, and he got he got a full um I'd say debrief in terms of challenges there. Um but again that that was part of learning and just um understanding different aspects of offshore wind, and then where we are now in terms of Inch Cape, we we started Inch Cape in 2020, so we acquired a 50% stake in the project from uh Red Rock Power.
SPEAKER_00And as you mentioned, at that time I think Inch Cape had just missed out on allocation round three by could have been a pound, maybe even less than a pound, um in terms of the clearing auction or in terms of allocation round three. And I, like you, would have heard of Inchcape at conferences and just meetings in terms of it being a difficult project, like a good project, but a project that's never got away and maybe never will get away. But at the point in time that we got into the project, it was in around a six to seven hundred megawatt project and looking at maybe eight megawatt turbines, eight or ten megawatt turbines.
SPEAKER_00So we with the project team at that point looked at uh reconsenting the project for what we have today, um, almost 1100 megawatts of offshore wind and looked at increasing the grid connection as well. Um that was one of the first activities that we undertook as part of the uh I suppose the new joint venture. We worked hard in relation to the bidding for allocation round four and at the time of allocation round four, I'm sure like other other allocation round four uh competitors, we we we had a strong project at the price at the clearing price at that point.
SPEAKER_00But little little I suppose did anyone know what was going to unfold between the the Ukraine war and just the cost, the cost of materials, the cost of fabrication, the cost of vessels, the cost, the cost of everything went up significantly. Um I think on Inchcape we might have the overall capital expenditure maybe increased by 30 to 40 percent over the course of 12 or 18 months. Um so you had that additional cost on one side, and then on the other side, in terms of the financing side of things, I think in tw in 2022 alone interest rates went up something like 300 basis points.
SPEAKER_00I think they went up closer to maybe 450-500 basis points between 2022 and ultimately when we got to financial close. So you had those two significant um issues on one hand, and you but on the other you had an allocation around four contract. Now you were benefiting as well from um inflation. Inflation was high as well, so that was increasing the allocation around four price as well. So but ultimately that led to a very, very challenging business case. So we had to look at our options around how we um how yeah, how how we look to improve the the business case for the project.
SPEAKER_00So one of the the things that we looked at was the inchcape CFD contract, the allocation round four contract. We've actually three separate contracts and we look at other options around well, whether there's a market for corporate PPA, whether we could uh look at alternative routes to market um to try and really uh optimize the business case at that point. And we did um and actually one of our colleagues no longer with us, Shawan McAdam, um she she worked hard on the allocate the actual rules of the CFD contract, and we we had the ability, like all allocation round four winners, had we had the ability to hand back up to 25% of our contracts and um rebid those into uh effectively what was allocation round six at that point um in 2024.
SPEAKER_00So we did that. Um so we had a very active engagement, uh honest engagement with LCCC and DESNES in relation to the options there, and ultimately within the within our contracts that we had we had the ability to hand back 25% of our allocation round four contracts and rebid that into what was allocation six at the time, and that that auction cleared for for for the allocation four projects. It cleared around£54, which which was uh just about what we needed to improve the business case to a point where we could take it forward for a final investment decision both ourselves and Red Rock there um towards the end of 2024.
SPEAKER_01You've just described you know a really lengthy, challenging, difficult process that a lot of developers are now facing in offshore wind. And a lot of people question the economics of offshore wind and say it's not really deliverable at scale because of exactly what you've outlined, because of what we're looking at here and the scale of the steel work required. I mean what's your sort of sense of that now you've gone through this process and what is offshore wind out of the woods now and and sort of back in the clear, or is it still a really challenging environment to actually go through everything you've just sort of talked about there?
SPEAKER_00I think it's a lot better than it was back then. Uh I don't think it can be any more difficult to be honest. Um, and the difficult part, certainly for the allocation around four projects, and just using Inc. as example was not everything happening uh in terms of the interest rate increases in terms of the capital expenditure increases. It was more we'd locked in on the um allocation around CFD contract side of things, but everything was varying on the interest rates and the capital expenditure.
SPEAKER_00Now parties can bid in those those changes insofar as you can, but there's certainly less volatility, I would say, in terms of the capital expenditure side of things. Um interest rates have stabilised also in the interim. So there while it's still volatile, there's less volatility and there's a greater, and I'd say developers as well are pricing in a certain element of risk within this within the CFD auctions as well to cater for that volatility. So it's it is I'd say it's more well known now and perhaps less volatile, but the the challenge for us on Inch Cape was we locked it in at a very benign, let's call it quote unquote now, a benign time in terms of market conditions for both interest rates and and and the price of materials to something that went chaotic almost overnight, and you had the fixed CFD contract on on one side and a very variable uh interest rate environment and a capital expenditure environment as well.
SPEAKER_00So it was that was that was a challenge. But so that I'd say is uh it's certainly less volatile now.
SPEAKER_01Is it possible to make a profit in offshore wind? I mean ultimately that's what it's about, right? You know, it's about big utilities like ESB, building big power stations, and you know, providing that power obviously, but also uh keeping its shareholders happy. Um I'm standing here in Leith, I'm looking around at unbelievable amounts of steel, I'm looking at cradles, is that what they're called? For the monophiles, the grillage for hold just holding the monophiles, big giant pieces of sort of semicircular steel that are one-off, specially fabricated.
SPEAKER_01That's a pile, that's a pile follower there as well. All unique. You you mentioned the pile um template.
SPEAKER_00The the pile installation frame.
SPEAKER_01It's a one-off that's made especially we're looking at a huge vessel coming in across the horizon that's been specially built for offshore wind, and I I assume isn't cheap. Yeah. So bringing all that together, is it possible to make a profit in offshore wind and is it a sustainable business right now?
SPEAKER_00Well it is a sustainable business for us. Well, just well, just before, um we are looking at reselling a lot of the equipment you see here in terms of the pile insulation frame, um, the pile followers, the grillage. So, as part of a kind of a circular environment, we see that um these aren't single-use. Um we have an up-ending tool for the monopiles as well that we uh hopefully we will be reselling over the next number of months as well when we're finished with them.
SPEAKER_00So we see that other projects, considering it is a Vesus uh turbine, and as you can see here, the jackets and monopiles are quite similar to other projects that hopefully will get true consent and into construction across GB and Europe over the next number of years, that there is the ability to reuse a lot of the equipment that um we've been using here in on Inc. But in terms of the overall business case, well the overall business case has to stack up or other otherwise um otherwise companies like ESB and other utilities and developers won't won't can you know won't continue with with offshore wind, and just as as a country in terms of GB and also Ireland, um both countries see offshore wind being almost a centrepiece of the renewable energy net zero strategy.
SPEAKER_00And if I look at Ireland um itself, we're looking at uh 5,000 megawatts by 2030 or a little thereafter, um, and offshore wind being a significant enabler of Ireland reaching its net zero targets by 2050 and the ESB reaching its own net zero targets by 2040. So um it has to work, it is um it is challenging, there's no question about that, but there are opportunities out there, um, and that's why we're developing the experience and the capability to be able to look at refining that um that overall model to ensure that we can provide a sustainable power source ultimately for for Ireland and concrete Great Britain's kind of candidates as well.
SPEAKER_00Well, Paul, there's a lot of work done and a lot more to do.
SPEAKER_01Thanks very much for being on the Renews Podcast, and thanks for having me over here with me. The Renews podcast was produced and edited by me, Stephen Dunn. Click subscribe wherever you get your podcast to make sure you never miss an episode. For more exclusive market intelligence on the renewable sector, see renews.biz.
Northland Power and ORLEN are in the final stages of commissioning Poland's first offshore wind farm, the 1.1GW Baltic Power project. In this episode, Northland's international executive vice president Toby Edmonds...
Ireland has big ambitions in offshore wind with a 5GW target for 2030. While few believe that is possible due to grid and permitting delays, it is expected that projects will enter construction in the coming years. So,...
Reporter Michael Lee-Murphy joins the reNEWS podcast from Taipei where he is attending this week's series of flagship energy events. Lee-Murphy reports on the current health of the island's offshore wind market and...
A dispatch from the RenewableUK and Scottish Renewables Floating Offshore Wind 2026 conference in Aberdeen. Hear Scottish First Minister John Swinney's view on what the UK government must do to unleash offshore wind...
At WindEnergy Hamburg 2026, the German onshore and offshore wind sectors have sounded alarm bells about future growth. Hear from the fair from reNEWS senior editor Sian Crampsie, who outlines the onshore concerns her...