Railway Conversations with Doc Frank

Railway Conversations with Doc Frank artwork

#114 – Why a Year Late on Brownfield CBTC Is a Good Result, with Mike Palmer

Sep 23, 20261 hr 12 minAudio
ShareXLinkedInFacebookWhatsAppEmail

A brownfield CBTC project that lands a year late is a good result. Not a consolation prize. That is what the record actually looks like once you take the press releases out of it. Mike Palmer spent 29 years at London Underground, finishing as the user acceptance manager on the Jubilee and Northern line upgrades, where every operational decision on scope and functionality went through him and nobody else. He then crossed to the supplier side, and in 2014 Andy Byford brought him to the Toronto Transit Commission as Deputy Chief Operating Officer and later COO. He now works at Parsons. This conversation was recorded in 2024, and Mike speaks throughout in a personal capacity rather than for any employer or agency. In this episode: why eight contracts across three suppliers left Toronto Line 1 with no endgame, and what consolidating them to two actually fixed. Why he does not want a fully compliant bid, and what he asks for instead. What a reference site is worth, and why he flew his team to Mexico City and Panama to touch the system before committing. Why backup signalling so often buys risk instead of resilience. Why dwell times, turnbacks and traction power queue up behind signalling and take away the capacity you just paid for. And his top three golden rules for brownfield CBTC, with the same one at number one every time. If you get something out of it, tell a colleague. That is the only ask. If this conversation has got you wanting to go deeper, visit my training platform at www.docfranktraining.com. There you find the most comprehensive suite of online courses in advanced railway signalling anywhere. CBTC, ETCS, high capacity signalling, and more. All in one place, all vendor neutral. Check out my latest course addition, ETCS for Australia.

Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.

Transcript

From the show. Tap a time to play from there.

This is Railway Conversations with Doc Frank and his guest Mike Palmer. Mike, welcome to the show. Thank you for inviting me, Frank. It's good to be here. I wanted to talk to you for a long time, for one, because it's been absolute ages since we met the last time in Sydney. Seems like these days you are more often in Sydney than I am. But the other reason really was that you've got an almost unparalleled experience of implementing CBTC in at least two different countries, as far as I'm informed.

So why don't you start telling us a little bit about your career so far related to CBTC, please? Sure. Well, it's interesting you mentioned Sydney, because I'd forgotten you were at that conference when I was a keynote opening speaker, which was February 2014, from memory. And I combined a vacation and my last day was speaking at the conference. And for those that know me, doing a 7am breakfast workshop, which is highly unusual for me to be up that early. What can I tell you about myself? I joined London Transport, as it was, in 1982.

I failed one of my A-levels. I was going to be a teacher and I needed to retake the exam. A friend of mine worked for London Transport as a guard. And so I joined London Transport in September 1982 as a guard on the district line. And I spent two and a half happy years as a single man going up and down the district line five days a week. I always did 1pm starts around there so I could finish, go for a drink, go clubbing, go to bed and get up for my next shift. So it was a great kind of bachelor lifestyle. Two and a half years in, I got a lucky break and I went to work in control centres on a station manager two grade, which is unusual at the age of 22 to become a station manager two.

So there was lots of good pay there and promotion. And that was the start of my control centre career. So I did two and a half years as what they called an information system, where in the control centre I passed out cancellations out of turn, running delays to all the stations and made public forecasts and set the dot matrix. And then after four years and one day of service, I did my controller training, equipment dispatcher in the US or similar elsewhere. And that was unusual because I was the most junior person at that time. You had to have four years service to do the training.

And I started on my fourth year and first day of service. And so I became the most junior controller on the underground and there were eight lines in four divisions of two. And I worked for C division mainly, which is the district and the Piccadilly lines. And I had a very happy time between 86 and 89 being a line controller and really having my own train service. It was like having a model train service and I could send trains and divert trains and short change, short turn trains. And it's one of those jobs where you either loved it or you hated it. You had to have that mind of being able to retain information, recall it quickly and see this massively moving puzzle of 60 odd trains in service, all running late out of turn and maintaining service. And I did that until 1989.

I then went into a duty manager, kind of a mobile role for the Piccadilly member district line, which was troubleshooting trains in trouble, going to incidents, suicides, writing up reports on all sorts of stuff, interviewing drivers and guards for disciplinaries and so on. And then I became what they called a service manager. I was a shift boss for two lines up until about 95 on shift, but I was the most senior person on the two lines to make service calls. In 95, my real lucky break was to work on the Jubilee Line extension. So I was asked to help my then boss, Howard Collins, who is well embedded in Sydney, as you know, and that was to open a new control centre at Neasden for the jubilee line extension and the new yard control tower in Stratford in East London. So we opened that and in 2000, I got bored with a steady state railway, kind of like problematic things, things with a challenge. And so I moved out of there and I did two and a half years running a train division of drivers, which was probably the most thankless job I did in my 29 years at LU. In 2005, I was asked to go on to two projects. One was a seven car project for the jubilee line, where we increased the size of the trains from six cars to seven cars, which was an immediate uplift in 17% of capacity. And on the jubilee and northern line project was to re-signal both lines with brownfield CBTC. In fact, it was Alcatel who became Thales and now Hitachi with a SelTrack 40 system. I was what they called the user acceptance manager. So I was the lead operator and any operational decision around functionality scope front end came through me and no one else. I had to sign everything off.

And that was about change management, scope creep, the voice of the operator, a single voice. And we commissioned the jubilee line in 2010-11. And I left London Underground in 2011 on what they call voluntary redundancy. So London Underground paid me to resign. And I left with a shed load of money. And I took nine weeks off, which is highly recommended to anyone who hasn't had nine weeks off. And when I joined Thales, the company doing the signalling, but now on the supplier side. So I was now on the other side of the table looking after the interests of the operator. And I had a great time on a traffic management project where Network Rail in the UK, the infrastructure owner and operator, were going to consolidate 680 cabins down to 12 regional centres, initially 14. And those 12 centres over one life cycle of signalling would dispatch the whole of England, Scotland and Wales. And then in late 2013, I had a call from Andy Byford, train daddy to some, of Sydney and New South Wales trains alongside Rob Mason, the TTC, NYCT, London, and so on. And he asked me to apply for a job he had posted for Deputy Chief Operating Officer at the Toronto Transit Commission. So I applied, I got the job and I moved here to Toronto in April 2014. And I had just under four glorious years working for Andy, initially as the Deputy Chief Operating Officer and then the COO. So I was effectively a shared number two in the company. And half of my day job was to run the railway and maintenance of buses and streetcars for a while and revenue collection and infrastructure. But the other half was projects. So that was bringing in one person train operation as a prototype, because Toronto still has guards on trains on only one of the lines now. So I opened the TYSSC extension and to help rescue the ATC project, the CBTC brownfield project on line one. So I'd say probably half of my time was spent day to day improving service, reliability and infrastructure. And the other half was on projects. The TTC are not known for their projects, essentially line one had been extended, but it stood still technology wise, other than the rockets, which came along, I think in around 2011. So that's my background. Andy left in December 2017. I left in April 2018. And I now work for Parsons, one of the engineering consultancies. I'm one of a few operators there.

And just to remind everybody, I'm speaking tonight in a personal capacity, even though Parsons has given me permission to do the podcast, because these are my personal views. They're not views of Parsons or any agency that we work with. That's exactly how I like it that you give me your own personal views. What's interesting and why I'm so interested in especially your knowledge of CBTC is that I've been doing trainings on CBTC for 10 years now. In all honesty, without having done a CBTC project back to back, it was just when I started dealing with CBTC, I had a very hard time learning that stuff. Information was extremely scarce. If you looked it up on Google at the time, the first thing that came up was the Cardiff Business and Technology Center as an explanation of CBTC. So that was kind of the level of information that you got. And once I learned about CBTC, I thought I want to make it easier for other people to learn about CBTC. So I developed a training course, which was very successful since 2014. And what I like doing when I have the opportunity is to basically compare notes with experts who really walk the walk like yourself. With regards to Toronto, I don't want to go too much into detail there, but you said you had to rescue that project CBTC on Toronto Line 1. What was, in your view, the biggest issue there? I have an idea what it is because I'm using Toronto Line 1 actually as a case study in my trainings. But what was the biggest problem that needed resolving from your point of view? So I'm going to come back to something you said about the history of CBTC and its origins, because I have knowledge and a view on that. In terms of Toronto, they started out with one contract back in 2008 for three interlockings, but it's the original three interlockings when Line 1 opened in 1955, which was Union, Bloor and Davisville.

And that was fine, replaced three interlockings with three new CBIs at life. And then another six contracts came along, and I'm going from the list so I do it correctly. In 2009, they commissioned Alstom to do CBTC and 39 trains, which is what they had at the time. 2011, another contract for another 21 trains to be fitted with CBTC car-borne controllers. In 2012, they put tender out for more interlockings, CBI interlockings. And also in 2012, they gave the contract for the TYCC extension interlockings. In 2013, they asked for another 10 trains to be fitted because they kept increasing the order of rockets by another 10. And in 2014, another contract for the final 10 trains making 80. So all 80 rockets were fitted with CBTC.

The early trains came with no on-board equipment because the contracts were not aligned. But the later trains arrived with the Alstom car-borne controller and all the wiring, the tachometers and accelerometers and some of the power supply already installed. There was an eighth contract for the yard at Wilson, which was given to Thales. So when I arrived in April 2014, there were seven mainline contracts with three different suppliers. Well, eight in total with Thales doing the yard. In August 2014, I travelled to the US to a centre of excellence for the third supplier, doesn't matter who it is. And after that visit, I came to the conclusion that we couldn't carry on. And there were three reasons, two very relevant to this conversation really, which was about reliability and speed and capacity.

But the third one was that the interlockings provided by this third supplier were not compatible with the Alstom CBTC system. And what I think probably happened is that the commission thought, well, they will be in time. And the supplier said, yes, they're compatible, which probably meant no, but we've got five years to work it out. And so one of the main drivers was there was no end game. We could commission the interlockings, but the ATC overlay would not work with these brand new interlockings. And so at some point very quickly, I'd be ripping them out, perhaps only a year or two old. And so what I did when I got back was I spoke to Andy Byford, my COO, and we decided to consolidate the contracts on the mainline from seven to one.

And for the yard from one to one, two contracts instead of eight. But it meant that a supplier had to fall by the wayside. And so I terminated reluctantly in February, March, 2015, one of the three suppliers. And we reset the contract on the 30th of March, 2015, one supplier for the mainline, one supplier for the yard. And that simplification of the project meant that there was an end game and suddenly it was much easier. And so my director of ATC, Pete Tomlin, who's worked with me in London and in Toronto, and I've known him since the nineties, was my project director.

And we moved forward on the same schedule and the same cost as the original contract. And so we had the test track open within 18 months of the notice to proceed with Alstom to do the mainline CBTC in full. We had within the 18 months, the first shadow section and the test track both going. And we opened our first section temporarily just to get drivers familiar in probably mid 2017, early 2017. Two, two and a bit years after we signed a contract and we started again from scratch, ripping out old interlock, well, brand new interlockings as it turned out.

And then the first proper section went into service in December, 2017. And that was TYSSE. So it was one Greenfield section, the rest was Brownfield. And we persuaded the TYSSE management team to let us re-signal it. But it's going to be this weird scenario, the brand new extension having old signalling and the old line having brand new signalling. And that just didn't make sense. And so Pete and I took on the extra section and we delivered it to within one second of time on the promised day. On the Sunday morning at 7am, two trains were due to meet at a station called Private Pioneer Village, going north with the city coming south with North York. And so kind of a Glasnost moment as all the celebrities and VIPs and politicians from the two municipalities met on the platform and shook hands. And we delivered it on the day we promised. And the trains arrived within one second of each other in ATO with the doors opening.

And that was really the start of the success, which turned line one successful. We did slip about a year. And that's because taking on the extra section took its toll. And the first section was new from Mr. Trudeau was opening it on a Friday morning. But I think the project was completed after I left. And it was probably about a year late. And for me, a year late in Brownfield CBTC is world class. It's not at the bottom, it's near the top. Because, you know, a lot of ages bite your arm off to only be a year late in CBTC and all of its challenges when you're trying to run a railway Monday to Friday, at least. I think there are several important lessons to be learned from that project. You mentioned the complexity by the sheer number of contracts with the different suppliers. And you also explained quite eloquently how things got better very quickly once you had consolidated those contracts and you had a single supplier that is clear what needs to be done.

So to me, in hindsight, it looked like a series of sensible procurement decisions, which, however, were not coordinated. So I'm pretty sure when they gave the. In isolation of each other. Yeah, for sure. Yeah. Yeah. So when they let the initial interlocking contracts, I'm pretty sure they did proper due diligence on the suppliers and they chose what they thought was the best interlocking supplier. And then only a year later, they did a different procurement and chose what I'm sure they thought was the best possible CBTC supplier based on a promise of the supplier that the interface, as you mentioned, between interlocking of one supplier and CBTC of the other supplier could make to work. And and that was the missing link that that never that never happened. And I think you said that was the outcome from your meeting. There was one of the suppliers that you basically came back and said that that interface will likely never work. And.

Well, it will work. You know, they admitted that it wouldn't be compatible with the Alstom system. So in a sense, I had no choice. Yes, yes, yes, yes, yes. But I mean, the original promise was that the interface would work between one suppliers interlocking. And I'm trying to avoid the names here, but I mean, you already slipped one. So the the the other thing I think here, and that's also related to procurement, is really the due diligence of suppliers. And I thought from your from the pre-discussion we had and from your email you sent me afterwards that you've got more to say about that. To basically ask a question like, will your interlocking be compatible to a CBTC? The client meaning somebody else's CBTC, possibly the supplier saying yes, on the basis, well, yes, if it's our own CBTC, surely it will work. So so so let's go into due diligence of suppliers for for a moment. What would you think there is a good way to make sure that you don't have any nasty surprises down the line? So certainly in Canada and definitely in Toronto and Ontario, you're obliged to take the lowest compliant bid. And so it's a two stage process, the actual bid and the second envelope with the price. And you should never open the second envelope unless they're compliant. You should just shred it and you'll never know what the value was. And I've seen projects here where they did open the second envelope and were swayed by price rather than compliance to the to the contract. And so all of the bidders were the lowest compliant price. And I think with the the interface between the two, it would be a reasonable assumption to believe that the outputs of an interlocking in terms of switch position and point position could be interfaced. And what I think probably happened was they said yes, rather than no, but we've got five years to think about it and work it out, which I would probably do as well, because you've got that time, but time is the enemy. I also think that the only similarity between the old system and the new system is the controller switches. Nothing else is the same. New signals, actual counter secondary detection, radio based communication for train positioning, the only subsystem that both both systems shared was control of the switches and either the old or the new could be in control, not both. And so I think, you know, that assumption was flawed.

And because there was no endgame at the time, I'm sure had they had time, they would have worked it out. That's not the point. You know, we hadn't commissioned anything. And we've resisted commissioning for a year, 18 months, you know, and the first couple of interlockings were ready. But I just couldn't pull the trigger, because there was no endgame. There was no solution at the end of it. And just that streamlining, we did due diligence and the bids were compliant. But I think there's no point in pointing the fingers at suppliers, because they were bidding against the contract set out. I think what often the problem is, is that the client, which is the railway organisation, has an interest in the procurement process to get multiple compliant bids. So their best interest is that all the suppliers are compliant.

So when they ask a question like... You see, I disagree with that. Okay, non-compliant. So if you put out an RFP for a new CBTC system, it is highly unlikely that any supplier is going to be fully compliant with what you put in your RFP. And a lot of RFPs are too long. I think good RFP is probably between five and ten pages. You have to describe what you want. And then it's for the supplier to tell you whether they're not compliant. Any supplier that says they're fully compliant, I kind of think, are you sure about that? And so I don't want them to be compliant. I want them to tell me what the differences are, so we can then have a basis for discussion and see whether non-compliance sits and whether I could live with that. And if I can't live with it, they're going to change their baseline system, which I'm against, because I want to buy something that's close to the baseline as possible.

And I don't want to be an early prototype of a new system. British Airways, useless fact number one, only buy aircraft construction number 100 or above. They are not interested in buying, being the launch customer for the Dreamliner or a Max or anything else. And you saw the headlines for both as to why you shouldn't be it, because they want a stable product. And I'm the same. I want a stable CBTC system, which is cute and innovative, but it's not brand new. And I'm not the guinea pig for a supplier to see how it works.

Well, yeah, that's the thing. I mean, you've been on the supplier side as well. I'm not sure whether you were involved in bidding process, but if you work for a supplier, you try to win a bid and you come up with what could be seen by the client as problems, i.e., well, we're not fully compliant. Let's talk about this. But then you may have a competitor which basically says, yeah, yeah, yeah, it will all be fine. We will sort it. We will sort it out.

So by being honest with you, they may put themselves in a disadvantageous situation regarding winning the bid by saying, well, these guys seem to be less compliant than the other guys. So we just go with the other guys. And then only, I don't know, three years later, you find out that they have kind of hoodwinked you or put wool over your eyes or so. By which it's too late and you've fallen for the naivety of a supplier saying, yeah, we can do that and we can do that and we can do that. And I don't want them to. I want them to tell me what they can't do. And then you meet in the middle. You either go off piste and do something bespoke or you accept it's non-compliant, but it still does the job. So I didn't actually, when I worked for Thales, I didn't work on any bids to do with Transport for London, but I did work on a bid for another small subway somewhere in the United Kingdom. And it was very prescriptive from the agency, a small agency, never done this before since probably the 70s.

And so we were asked if we would put in a code, you know, some sort of functionality where the system would know when to wash a train. And my response is, yeah, we can do that. It's an algorithm which knows when it was last washed and so on. I said personally, I'd look out the window and if a train was dirty, I'd wash it or I'd have a whiteboard in the corner with the dates of all the times the units were last washed. And so agencies in asking for this stuff were going into unknown territory and it's scope creep and it's money for the suppliers. And actually I push back on things like that, saying, are you sure you really want that? Because I'm not sure about standard. It might be a great idea in your head, but do you really need it?

Yeah. Yeah. That's the risk, see, that clients think they get a proven product, but by definition of their own requirements, they enter territory where they will be the world first for certain features, not for the entire product, of course, but for certain features. And that may cause them more trouble that it actually brings them benefits. So by you from a client position saying you don't want to be the launch customer, what you would probably ask suppliers during a tender process, well, firstly, you would get suspicious if a supplier said, yeah, yeah, we are fully compliant because he said, yeah, that's probably not 100% true.

Yeah. So let's, let's find out what the real deal is. And, and then secondly, you will probably ask a follow up question. Well, have you done this before? And if the answer to that is no, then you know that you would be the launch customer. You would be the world first. And then you could still decide whether that requirement was really that important or whether you said, ah, you know what, I rather take something off the shelf to the extent possible. That's, that's been proven elsewhere and, um, and do away with that. For example, the train wash feature that you, that you mentioned. So, so in North America, generally these days, an agency will ask for three reference sites where you've done similar work within North America, preferably as recent as possible. And in some ways that's good because it's evidence based that shows you've done it before. I think it also shows up the, the problem of the consolidation in the same industry where, you know, you're down to three or four main suppliers, uh, the usual Siemens, Hitachi, uh, uh, Thales, well now, well, Thales before it became Hitachi and perhaps a fourth one, um, in the US with some overseas one as, uh, overseas one as well.

But if a North American agency says I want three reference sites in North America, you've either done or you haven't, you could say I've got one or two. Some have none, you know, and there are signalling suppliers who are not from North America trying to enter the market have a real problem getting in there because of this, this block of three reference sites. But I think it's still a good test of how solid your product is. And I would always talk about touching and feeling it. So you, you, you, you touched on choosing your supplier when we terminated the supplier in February, March, 2015, I took my ATC project director, Pete Tomlin, and a couple of my team along with some Alstom guys, and we visited Mexico city line 12 and Panama city line one, because they were the nearest Alstom Urbalis 400 reference sites to Toronto. So Toronto was the first US Canadian project for Alstom with Urbalis. And it was their first brownfield, I think worldwide. And so we were working with a supply new to what Pete and I were used to. And we had a mad 72 hours flying on a Monday morning, spending Monday night in Mexico city, we left at 6am Tuesday to Panama city and we left Panama city Wednesday afternoon and got back at midnight Wednesday night. I mean, we did thaw out after kind of minus 20 in Toronto for two nights, but we were absolutely shattered and we did loads of miles. And one of the things, one of the reasons I took my team was I wanted to touch and feel Urbalis, which I hadn't been able to do before, but also talk to Mexico city transit agency and Panama city agency. And we had private sessions sessions with them away from Alstom where we said to them what I asked them like to deal with what problems we had with them and so on. And we were shown around their line and their interlockings. And so we got to see it and touch it and feel it and, and actually talk peer to peer and what they found. And I have to thank Mexico city as a transit agency, because they stay behind on a Monday evening to spend an hour and a half with us, which is very generous in terms of their time. But at the end, we asked them what's the one thing you would do differently as a user of Urbalis on line 12, what would you do differently? And their, and their response, which I treasure to this day was we had too elaborate a backup. So the backup was signals, train stops, block joints, every a hundred meters mimicking fixed block, but it was a backup to Urbalis. And they admitted that it was expensive. It drove up risk and it was never used because these days, the fastest way to recover your system. If you have a zone controller failure is to restart the zone controller and move your trains to safety rather than fiddle around with the backup to get trains into platform safely. Cause while you're moving trains, you can't restart the zone controller because it gets confused if trains are moving as it tries to reestablish positions. And so that was a really valuable lesson and we did it intentionally. So we went into replay, you know, replacing the contract, resetting it with Alstom with our eyes wide open about what we were walking into.

Yeah. Yeah. Backup is another interesting thing that that's often, I think, miss, mishandled or misunderstood by, by the client. Normally they introduce CBTC to raise capacity on the system beyond what's possible with conventional signalling, but then they introduce a backup system for the sake of having a backup system and the backup system has to be conventional signalling. But the backup system will not be capable of handling the capacity that CBTC gives you. So, so when you operate CBTC and you pump say 30 trains per hour through the system, and for whatever reason, you have a very rare system failure, you're left with a backup system that's only designed for, I don't know, say 20 trains per hour, trying to handle 30 trains within one hour that you have in the system. So, so you, you will always have problems with that from a performance point of view. You probably also can tackle only very limited selected failure scenarios with that backup system. So, so, so all up I'm, I'm with you that it's, and I think meanwhile it's best practice in the industry to focus on making the primary system, the CBTC system as reliable as possible so that you, you minimise your downtime in the first place and you are able to bring it back into operation as quickly as possible and then run your normal service again after the disruption, of course. So I, I, yeah, I, I have a different view of backup to a lot of people. You know, when we started visiting other networks, we went to Docklands Light Rail in London, which we weren't benchmarked against, you know, that wasn't our baseline system. And they talked about this special feature they had in the middle of the room, which is this separate terminal, and it was essentially a station control emergency gateway.

And they said to us, we're the only ones that have got it and it gets us out of trouble. So if your system goes down, a zone, a zone control goes down, it, you might have a fifth of your trains all EB-ing simultaneously, losing communication with the mothership. We have to restart the process and enter them. That was designed to get trains into platforms. And so your worst scenario from a safety point of view in an underground system is trains stuck between stations. With the power off, hundreds of people, it's very hot. You want to move that train into platforms. If it's plain line to the next platform moving forward, or there's one just behind you, you can do that. Since you have switches, you've got to somehow get trains over switches which are locked. And so the station control gateway was designed for you to go into the back door of the station controller and move switches manually, and then the train can move manually into stations. I've never seen a backup as an alternative to running CBTC. It's your get out of jail card. We went to Hong Kong, and we went to West Rail, and we looked at West Rail, and they had this thing in the middle. And I said, so what is that? And they said, oh, it's very special, only we've got it. Yeah, right. It's the station control emergency gateway. So London Underground and Tube Lines, who were the infrastructure P3 partners said, we want that. And so we had what we call degraded mode control, which is very similar, moving the switches. Now in London, there were no signals, there were just signs, stop signs, replacing semi-automatic signals.

And so all your moves were done under rule, but you could still move the switches to secure a route and know it wouldn't move. But it was never used in London, because by the time you'd moved all your trains into platforms, you were itching to restart the process, which you couldn't do while trains were still moving. So you had this really stark choice. What's the fastest way to recover? And the fastest way to recover is to restart the zone controller and re-enter trains, however quick that is, and you can cherry pick. But it was to stop trains being stuck underground with facing switches that couldn't be moved. When it came to Toronto, we took a piece of middle ground that was really for engineers' vehicles, work trains, which weren't initially going to be fitted. And we changed the contract so all work cars that could be would be fitted with CBTC. And I think that's the norm now. Any supplier that says no, you would have to question as to why they weren't prepared to fit CBTC equipment to work cars, not for ATO, but to drive manually with a target speed and target distance. The big thing is to know where your trains are, not how far you want them to go, because you can always authorise a driver to go so far and so fast. But if you don't know where they are, because you don't have a backup secondary train detection, that's terrible. And, you know, Vancouver Skytrain don't have a secondary, you know, their diagram at night is blank. There could be 10 work trains out there, but they don't know they're there. They have a whiteboard and they write them all in and they send them out behind each other with the furthest ones going first, because once they stop and work, they block everything beyond it. And that's fine, that works for them. But the other thing you said was about reliability and availability. And the reality is that CBTC has high reliability and high availability, way, way larger than conventional systems. The only downside is it's a bit all or nothing. It either works, or it doesn't. And when a zone controller goes down, or, you know, when the train control system, the SMC for Thales, SelTrac, goes down, you're busy, but it quickly recovers. And the capacity is, what, 30, 33, 36 trains an hour? Before the Jubilee, when it was limited to 24 trains an hour, and it's now 30, 32. So that increase in capacity is tremendous.

But then you have to think about what are the other constraints, because what happens is things overtake each other. So you buy a new signalling system, great, but you don't have enough trains to really, you know, harvest that extra capacity, you run out of trains. Or if you have enough trains and new signalling, your terminal stations are not designed for high speed run-ins. And so you have trains going across diamonds at 15 miles, 20, 25 miles an hour. And that slows you down because you can't physically get 30 trains in and out, even at that speed, because it's just so slow. And then you need more power. And so all these things come together, and you have to consider them all in your, in your signalling renewal. Otherwise, the worst constraint will always hold you down. And I think that happens a lot.

If this conversation makes you wanting to go deeper, I run what I believe is the most comprehensive portfolio of online training courses in advanced railway signalling. CBTC, ETCS, High Capacity Signalling and more. You find them all at my own training platform docfranktraining.com. That's docfranktraining.com. And everything is right there waiting for you. But now back to the show.

That's, that's such an important insight for brownfield drivers, especially where the, the railway wants to introduce CBTC for improving capacity. And they hear these fantastic things of CBTC running. Reliability. Yes, yes, yes. That, that, that's a, that's a side effect, which often proves to be even more impressive than, than the capacity increase. But with regards to capacity, you mentioned a couple of very, very important points. One is you really need to look at the entire service cycle. So if you can run 40 trains per hour on the, on the open line, but your turnbacks can only do 24, you're stuck at 24 because you can't just turn around enough trains that, that you get into the terminus. You're right. But you're supposing that all the service goes end to end. So on the larger lines, and the Elizabeth line in London is a good example, they've got auto reversing at Paddington. And so a turn back at Paddington, which goes into one of three pocket tracks beyond the station, but before the Network Rail boundary going out towards Reading and Heathrow airport, the driver sets the train in auto turn back and they depart the train and they then walk through the train while it drives itself to a turn back and back into Paddington station on the other platform. By which time the drivers walk nine cars and they're ready at the other end. What a lot of agencies do is short check. Well, they have a shortage of trains and the Jubilee line is a good example. Trains are short-turned at both ends of the line because their focus is a higher core TPH through the centre of London. And so there are always sacrifices to make. And if the most important thing for an agency is a high capacity through central London, then you're going to short turn at the north end and the east end.

But then you get delays at those places. So a train has to get all the people off. The driver has to go back and check the train, then it goes into the siding. And by which point you've got two trains stuck behind it. And so in a way you're picking your poison as to what's most important, but also how the agency deal with it. If you had six station staff at a turn back and each did one car and the driver wouldn't have to leave the cab, you could be out of that station in 30 seconds. But if they're not there, because there's no business case for it, and the driver has to check the train, which is correct, because people could fall in between, then you're negating the benefit of a short turn, even if it gives you a high capacity going in the other direction.

And it's because, you know, people think if you buy a new signalling system and on new trains, your problems are solved. And often they're not. Yeah. And that was in fact, the second point that I wanted to make that for improving capacity, people focus or tend to focus on the tightest constraint, which is normally signalling. And then they often make the additional thing, well, if I want to run more trains, I need more trains. So they get a new signalling for higher capacity. They buy themselves more trains. But often what happens is that other capacity constraints that were lurking in the background or hiding behind the signalling constraints are suddenly in the limelight.

So it could be that you don't have enough traction power to run the trains that the signalling system would allow you to and all the trains that you that you bought and you don't have enough traction power. So that certainly becomes your constraint or it's the turnbacks or it's the the processes how to change ends with a train and basically from entering this terminal station or a turnback to being able to pull out again in the other direction, stuff like that. So I think your point is what I wanted to emphasize, really, to look at the entire system and not just are we fixing that one signalling constraint with a high capacity system and now overnight we will have a high capacity railway. And that's just not the case.

Right. So I think most of the things you've mentioned you can mitigate against. So if you're talking about fast turnarounds at the end, you step back, you have a spare crew. And so the driver gets off, another driver gets in the right end and it can depart in 20 seconds. And then that driver changes ends. There are things you can double end trains in and out of sight and put spare crews on and take it into the side and back out again without an interruption. You've missed the most important actually one and there's evidence of this from Canada and London, that is dwell times.

So modelling is rarely accurate and modelling assumes, say, a 20 second dwell at a station. And I know a line, it doesn't matter where, where roughly it takes eight seconds from train stop to the door being fully open in ATO and the same for a door to close. And that's 16 seconds of your 20 second dwell where people aren't actually getting on and off the train. And so I think one of the issues, particularly at busy stations, is the inability to maintain dwell times. If you have a 30 or 40 second dwell on a 120 second headway, you're not going to achieve it because 40 seconds, one third of your headway is taken up with people getting on and off. And so the running run out times and the wheel start to wheel start means you're never going to achieve it unless you improve your throughput. You could argue that with more trains, your boarding and alighting should be more efficient and so on, but that's not always the case. But fundamentally, if you want to operate 30 trains an hour plus, you can't be having 40 second dwells at central London stations because you can see the trains losing time. In Toronto, when I arrived in April 2014, I resisted going into control centre for a couple of months because of my background. I didn't want to revert the time and go into my comfort zone. And I just said to my deputy at the time, how late are we? And he said 40 minutes. And I went, what? And he went, oh, that's pretty good. That's normal from Monday to Friday. And what had happened is for a number of years, perhaps 10 years, the run times and dwell times have never changed, even with new trains and with more people using the system. And so it was normal for trains to run 40 late in the morning peak and then just with none of them all at the crew relief point. So they're back on time, despite the fact that journey times were longer and you missed all of these north to south because of, you know, short tripping is cancellations. It's lost kilometrage. And there was an acceptance that that was normal late running, which I found bizarre.

And so your schedule and your dwell times and your run times have to be accurate and fit the purpose. And that goes back to the modelling and the accuracy. And what I would call operational biased optimism. You think everything's going to be fine. Your modelling shows it to be fine. You've got all these plans. You still don't achieve it on the day. Yeah, the thing is, with modelling, you often only have dwell times from basically wheel stop to wheel start, assuming that the dwell time would actually be equal to your actual passenger exchange time. But as you just mentioned, that's often very, very different, especially when platform screen doors come into play, because you do have technical times required from wheel stop to the actual opening of the doors, including the coordination between the train doors and the platform screen doors. And then at the end of the dwell time, you've got the same process for closing the doors and securing that they are closed, confirming that they are closed before the wheel can start rolling again. So there's a technical aspect of dwell time control, but there's also a human aspect of dwell time control where the station staff basically can't just keep up with the old ways. Ah, there's a granny with a pram coming with the grandchild in it. We're just going to wait until she has boarded. And if you've got like 30 second dwell time, the trains got to leave after 30 seconds. And if you come from a brownfield in a brownfield railway from a legacy system where the staff gave a bit more leeway to delays from allowing passengers to board passengers with disabilities or with a pram or whatever, it's a huge cultural change, both for the staff and for the passengers as well.

So there's an old saying, which I don't fully agree with. It says people wait for trains, trains don't wait for people. And in a way, that's right. You know, if, if, you know, it isn't the station staff, they work really hard to dispatch trains on time. They see the signal is clear or the indication we put on JNUP for station staff could see the driver had a target speed to depart. And people kept running for the train, people kept blocking the train doors. So actually, I think the station staff do the best they can. But the reality is, if you're 30 seconds is too long, right? You know, if you want to do 120 seconds, you're assuming that you've got 90 seconds only to run in, run out and let the next train reoccupy the platform track.

And that's probably not possible. But if you can get the trains around 20 seconds, the next one is sitting outside waiting. And you can see it on TV to see like, Young in Toronto, probably Baker Street or Canary Wharf on the Jubilee line, probably Kenny Waterloo on the northern line in London, you can see people running for the train running for the train. And what they should be doing is shutting the doors and getting out because the next train, you see the headlights of the next train, you know, behind you in the tunnel, and yet people still run for that train, because they've got to get that train. And it's a badger runner where people block the doors and try and get on. Yeah, yeah, yeah, yeah, yeah.

Set of problems with train dragging and so on. Yeah, their five seconds of playing Superman, yeah, that they can, they can, they can squeeze the doors open. Because you've just delayed their service by five extra seconds. And by the way, the next station, that's seven seconds of worth of extra people. And that train then start to lose time over time. And people wonder why ends up five minutes later at the end of the line, because one person blocked it for a few seconds. Yeah, it's it's it's devastating the impact in the peak in particular. Yeah, I don't know. So the station staff do really well in trying to get the trains away the drivers try and do well. If you've got people running for the trains with different entries on the platform, there's no good time to shut the doors, you've got to pick a sweet spot, which might be a split second. And by the time you press the door close, and the door starts to close, you'll be on that spot and people are running for the train again. And so I don't know what the answer is truly.

Platform edge doors are strange. When the Jubilee line extension opened, we had some incidents where the driver got a door close visual. So they proceeded, but a ped door was stuck open. So very quickly, we had to put an additional wayside indicator, because the peds didn't talk to the signalling system, because it was manual driving and fixed block initially, they had to check the wayside to see the ped doors were closed as well. And only the doors closed and ped doors closed in the tunnel where they allowed to depart. Otherwise, you had a ped door left open and people, you know, potentially injury.

I would like to talk to you briefly about the culture change, because you worked on brownfield projects, all the CBTC projects you worked on from memory were brownfield projects. Three brownfields, but Toronto line one hadn't had one section, which was greenfield, which is interesting in its own right. Yes, yes, but the majority of the operations, so it was an existing railway for the majority of the lines. So basically the whole system, both from the railway staff point of view, also from a passenger point of view, were used to the old world of lower capacity. And now you're introducing CBTC, a high capacity signalling system, but what's really required is a culture change of the entire railway system, including the passengers to a high capacity railway. The signalling system itself just doesn't cut it. And we just established that. What, how did you perceive this need for a change? And how problematic did you, did you find it to reeducate the passengers that it's no longer necessary to basically run for the train, squeeze the door open because the next one will follow in a much shorter period of time than previously in the old system before you had CBTC or, um, I don't know, educating your station staff that the dwell times are now measured by the second and not by the minute and the departure times are now on a per second basis and so on. So, so what can you say about culture change and any challenges there?

So firstly, I would like to congratulate you on the longest ever question I've been asked, taking over 90 seconds for one question. So I'm going to rewind a bit and unpick it. I don't blame customers. Customers don't know there's a new signalling system. They might be aware because of all the closures, but from the customer point of view, nothing changes on the surface, even though over time they might perceive it's a better service, faster service. Don't forget with CBTC, you can run faster. So your interstation journey times are shorter and so you can get the same number of trains working harder and delivering you more trips per hour. In terms of a change, I partly disagree, I'm afraid again, because it's the same railway, it's the same passengers, it's the same staff, it's the same trains, it's the same stations. The only thing that changes is the signalling. One of the things I did get wrong in London was I thought the change to the rule book would be this big, this whole new rule book, massive, because of the way CBTC or TBTC in London would change it. And in fact, in reality, the rule book was that big and it was just an appendix. Because a lot of the signalling function actually doesn't change how you deal with a suicide or a wrong directional move or a signal overrun, or a platform overrun. You know, have your existing processes that get you out of trouble and resume the service. And so what I would say is you really have to consider what the delta is between the old system and the new system.

And it's one thing, well, two things, signalling and automatic train running, because generally under fixed block, you don't have automatic. I mean, you do, but it's a clunky version because it's fixed block. And so I think you have to keep both feet on the ground and really focus on the things which are different for the CBTC line, faster trains, faster journey time, shorter dwells, turnbacks being quicker, but they're all signalling related. It's that impact the signalling has on them that makes them easier, harder or faster or slower to do.

And their impact is more felt under CBTC. You know, I always say that if you're dispatching or controlling a CBTC line, you have to be really fast. You have to be so fast. You have to get in really quickly and shut the door. Number one rule of controlling, I learned in London Underground, is shut the door. If you're in trouble, you stop trains entering the affected area. You do code reds, whatever you want to call it. You put signals back at danger. You do general message, you know, on the radio. I remember I was caught, you know, back in the late 80s, I would get a driver call and say, mayday, mayday, I've got one under Green Park West.

I immediately shout to all of the dispatchers in the room, one under Green Park West. It's all I had to say. And all these dispatchers would start putting everything into push button. They put signals back at danger. You know, I would do anything they could to stop trains because every train that was stuck between stations, particularly near the suicide train, was another monkey on your back you had to sort out. A train full of people you had to walk out and you walked them out, because if you start walking them, you can't stop it. I mean, you're ready to move the body, but you can't because people are on the track somewhere else. And so the thing I learned the most, stop trains entering the affected area. The turnbacks either side, and then you can start to do the service either side. And then people in control centers get fixated by the suicide. You know, the person under a train, all the cameras are on it. They're looking at it thinking, oh, hang on, I think we get someone out. And I used to walk into my control center and turn off the cameras and say, don't worry about that. You can't do anything about that. The fire service are there.

You know, the operating managers are there. The only thing you need to know is when they're ready to run again. And meanwhile, you should be doing focusing on these services, not having a good look at the CCTV, because you know, you can see the blood and gore. But CBTC railways are fast, you have to get straight in, you have to have to deal with it. If you dilly dally for a minute, you're gonna have two more trains stuck one in each direction, because the capacity on that signalling is so good. That trains will just keep leaving and leaving and going into, you know, a dead end. And then you've got more problems. Yeah. So I think, sorry, go ahead.

I thought you just confirmed what you said you would disagree with me that that the whole organisation, the whole system needs to speed up because of your high capacity signalling. And this is a culture change. Yeah. And it includes, believe it or not, it includes the passengers. Yeah. The example that I keep coming up with is Sydney. When they introduced the first line of Sydney Metro, the terminus of the Sydney Metro line in Chatswood is a shared station where on the same platform, on the one side, you've got the existing Sydney Trains services on the North Shore line. On the other side, you've got Sydney Metro trains terminating.

And between the two sides of the platform, you see huge differences in how the trains operate. One side has platform screen doors. The other side doesn't. How passengers board the trains and how trains close the door and just leave automatically, whereas on the other side, there is still station staff trying to keep the passengers out from boarding the trains. So so the the differences between a legacy system, as I call it, and a high capacity system is is tremendous. And it affects a lot of stuff, not just the signalling people, but the train controllers, the drivers, of course, if you still have drivers, the and and the passengers.

Yeah. The the the passengers that you have on a on an established high capacity railway, if you take, say, Singapore as an example and you compare them with passengers on a legacy system, it's hugely different. The passengers are faster. It's just between a city, a busy city and a town. The people move faster. They. Yeah, it's about the population and the culture of that country and that city. So if you go to Singapore, go to Hong Kong, if you go to places within Asia, you know, customers don't disrespect the system.

They wait for the next train. They don't throw up on a train. They don't throw litter. They don't throw cigarettes on the track. They don't tell us. Yeah. Culture of the country. And I think it's very difficult to re-educate people. I used to reply to customer complaints when I was more junior. So I'm sorry about train and wait for you. But it couldn't wait because the next train was two minutes behind and you have to wait for the next one. If we hold that train for you and delay it, you're delaying everything downstream. And that's not acceptable either. So I agree with that. I agree that staff need to be more, you know, more on the ball. If you take SelTrack as a system, the driver gets a dwell countdown from when they open the door. They could have a value in seconds from a minimum to a maximum dwell and the minimum maximum be varied. And at nine seconds, the target point advances. So the driver nine seconds before departure could say these train doors are now closing. The door might close the doors and press start on zero. And if I press start on zero, the train will arrive at the next station within one second of time. But what the SelTrack system does, it sees a journey from one end to the other as a series of small journeys.

And so when it arrives in a station five seconds late, it will look for a run time for the next station that makes up that five seconds in five-kph increments. And it will say, well, the nearest one is this and it'll get there two seconds early. So I'm going to increase the dwell by two seconds. So if the driver then presses no on time, it will still arrive on time at the next station, having made up time or losing a bit of time to schedule. And so getting that into the drivers, you'd have to wait for zero to close, you know, like you wait for a signal to go green. You can preempt departure because you can see your target point advance at nine seconds.

In a busy interlocking, it's about seven because several switches want to be called on plain line at nine seconds. You get the departure. There's nothing to stop you leaving up to nine seconds early. I mean, you could preempt it at 15 seconds. You could close up and at nine seconds when you get the target point, press start. But then you're going to arrive at the station, next station nine seconds early. The system's going to pull you back nine seconds because all he wants you to be is right time throughout. And so the drivers can't beat the system over the length of the line. And so the systems are smart like that. But you need to train the staff to be confident that as you approach zero, press the start button and off you go. And if you have an unimpeded run to the next station, then you're right within a second of time. And that's really cool. Bearing in mind that some subways only time to the half minute or the quarter minute, some of the suburban rail times the nearest minute and may always round up. And so you think that's interesting. What is the actual run time? What's the dwell? And in London, they used to have a different dwell for the peak and the off peak. So you could see the run time vary in the peak being lengthened because the schedules team recognised it would take longer for a train to get from one end to the other in the peak purely because of dwell times. Big change all around. There is one big chunk of stuff that I haven't even addressed yet where I definitely wanted to go. You told me in the pre-talk you've got a top 10 of do's and don'ts for CBTC projects. And I definitely would want to go into this rather than a separate episode or in this one and maybe I cut it in half or something like that. So yeah, your top 10 of recommendations. Well, I want to go for 10 now because I'm going to take a while and rather than just give them to you, there needs to be some context and some justification as to how to reach a conclusion. What I would do is do the top three.

And I think the top three, we can talk about now and we can enlarge on that because actually my next presentation will be the top 15. And in October at the NextGen Train Control Conference in Baltimore this year, I'm doing a top 10 operation and maintenance considerations with Pete Tomlin, who now works for Kiewit, where we're taking the project management, the maintenance and the operating and giving our 10 shared golden rules for Brownford CBTC. But the top three, and I think I've got them in order, the third one is practice, practice, practice. You need to get control room staff, mechanics, signalling technicians, drivers as your test train operators working under test rules under the instruction of a lead tester, driving the trains, dispatching the trains, because those staff then learn about the system up front. It's not like suddenly you give them the car keys and you think, well, you know, what am I going to do with it? And it's for people that will make the project work. The other, number two is actually migration, migration, migration.

I'm doing this from memory, so I apologise if they're wrong. And basically, you can look at a network. I mean, if anyone listening to this was to bring up now, say, the BART network in Oakland and San Francisco, or the Ramarta network in DC, you'll see five or six lines, services, interlinking in all sorts of octopus tentacles going out in all directions. And so if I gave you a start point, say for BART, and said you start at Millbrae, which is one away from the airport, and you can go anywhere you like, and then you follow the trunk section on the split, you can go this way or that way, and when you get to the next, you can go this way or that way. And there are probably 40 different ways of migrating. Some are better than others, and some are not so good. And you wouldn't want to start with a short first section. Get your first three or four stations right before you spread the chaos, potentially. And then migration, as you increase each section, gets shorter and shorter between the sections, because as Pete Tomlin always reminds me, it's just a bit of extra code. It's more code of the same thing. You know, you're familiar with the trains are humming, the signalling's humming it's just more guideway with more data about points and switches and so on. And so I think getting the migration improved will improve your chances. But the number one golden rule is it's all about the people. You can have the most magnificent CBTC system, buy the best supplier in the world, really efficient, but it's the people who make it work. It's the people from the agency, the drivers, the maintainers, the station staff, the control room staff, the scheduling staff who write the timetables. It's the signalling supplier and their talented teams, often not in your city. And in our case, you know, for Lyman, we were dealing with Paris and Rochester and New York State, London Underground, we're dealing with Toronto. And so we have people embedded, but it was the people, it was the clever people. And those less clever bats, they had operational experience who made it work. Without the people, you're always going to have an uphill struggle. So you need to get them on board, you need to incentivise them, you need to have fun.

And one of the reasons I left JNUP was I stopped having fun because doing the Northern line off the Jubilee line was actually respectfully quite boring, because it was just more of the same. And you know, we got burnt on the Jubilee and we're able to build all the lessons into the Northern on a rebaseline contract. We delivered it early on a pain share gain. So both Thales and London Own benefited from the later stages being commissioned early. But it's the people, it's your contractors, it's your people you bring in to set up protection, it's your work car operators, it's your test train drivers, it's everybody at the agency pulling together will make a difference. If I flip that argument, you could have the most cruddy, crappy, I'm not allowed to say crappy, but there you go, CBTC system. But it's the people that will make it work and make the best of a bad job and can sometimes do really well. And unless you have the people on board, and you empower them, and you give them self belief, and you let them make some mistakes early in time, and you correct them, you will deliver your CBTC system. It's all about the people and I will never change that as my number one. Yeah, yeah, yeah. And then I can probably add from a supplier's point of view, that it's, it's a big misconception sometimes by the client, by the railway organisation to assume that the supplier at large is an expert in CBTC.

And that's just not true. I mean, like in every organisation, you've got some people that are particularly good. And then you've got a lot of people that are kind of okay to average. And then you've got some people that you don't really want on the project, if you can avoid it. So the key, I believe, is really to make sure that you have access to the real specialist within the supplier organisation. That doesn't mean that they can work full time on your project, because in most cases, they're just not possible. If you look at a big supplier organisation, you may find that the real gurus, the super specialist on that CBTC technology, there may be three or four worldwide.

And, and you can see if the supplier has like 25 projects worldwide, they can't possibly have three or four of them all working on your project. Yeah, especially if you are not a top tier railway organisation, but you are somewhere in the backwater like Australia, you can't expect the A team being on your project 24/7, that just not working. However, if you run into projects, you want at least to be able to tap into those specialists just to troubleshoot. And then the project team can keep running with it. So I think agencies are just as guilty, they think they know what to do with a CBTC, having never done it. And so they go in their own direction. I wish them really luck, you know, if you can crack it different way, then knock yourself out. I don't like singling people out. But if you go back to JNUP, Walter Kineo from Thales, who's now the VP for innovation, Steve Kelly, who is an SMT expert, you know, these were heroes to us, they got it, they listened to us, they made the changes. So I agree with you, there are specialists on both sides, operators as well maintainers who should be listened to by the other side, I'm going to leave you on this might be a good thing to finish on with a little anecdote from the summer of 2017.

And the UITP World Congress was in Montreal. And I went to a workshop on CBTC and three suppliers, two of whom I was familiar with, and one I wasn't. Each gave a presentation on CBTC. And then a fourth consultant did a kind of a benchmarking of cost per kilometre of different cities and systems. And at the end, it got to the Q&A. And I was in the back row, often as a COO, you want to be in the back row slumped, unrecognisable, because every consultant and every supplier wants to talk to you about how their system is going to solve everything. So I was in the back row, with a supplier, just keep my head down. And the first question went to a signalling engineer from a company I may have mentioned, who said, the problem is operators don't know what they want.

If they just listen to us, we would tell them what they want. And if they let us get on with it, we deliver a project. And it kind of went on for about 30 seconds. And I just saw red mist, which I rarely do. I never lose my temper at work. However much I come home and I don't know, smash a place up. And so when he ran out of steam, I just tapped him on the shoulder and said, my turn. And I went, I'm Mike Palmer. I'm the Chief Operating Officer, Toronto Commission. And I do know what I want. You don't listen to what I want. And I know what I want. And I've done it before. So I do kind of a 20 seconds. And then he makes the mistake of coming back and answering, kind of honing it down a bit. And after he'd done his second bit, I did my Obama, drop the mic moment. I said, listen, we can fight this out in the bar later, which is always a good idea. But this is how it works. I'm the customer, you're the supplier. If you don't give me what I want, I won't give you the work. And I walked away from the mic. And what it made me really think about, and it's the topic of my paper at the IRSE convention in Toronto next month, 26 to 30 August. And the President, Jane Power, has invited me to do this presidential lecture on the role of the operator in signalling projects, specifically CBTC. But it really gave me thought about, do we know what we want? And the answer is not always. We don't always know, or it might be wrong. But at least hear us out and give us a good reason why we shouldn't do it.

But that exchange, which was probably two minutes in total, just really made me think about, I mean, I've been blessed. I've worked on three projects. That experience is probably fairly unique in the world. But it makes me quite opinionated, as you might have noticed in this podcast. But it's because I've done it, and I've seen it, and I've got burnt, and I've learned from it. And I've been able to hone my ideas on it. And I think sometimes suppliers forget that, and they just think they can, you know, treat you as a mug and rip you off, which is unfair on most of them. But for some, I think there's some validity. And to be across the table, you know, from the Mikes and the Doc Franks, you know, is daunting. Because we might actually know what we're doing. And we've done it before, not once, not twice, but I've done it three times now. And I'm helping agencies in North America go about it the right way. And that's kind of quite exciting, even in my older years.

Excellent. Well, Mike, thank you very much. I had a blast. I hope the listeners had as well. And I am carefully looking forward, if you're game to bring you back later on to listen to your top tips, number four to 15. Maybe after you've done the presentation in Philly, so not to steal your thunder there. Well, it's actually in Baltimore this year. We've changed city. Ah, Baltimore. Okay, good. Well, whatever. By the way, if you give me the link to that conference, I will probably do a plug for it in the show notes.

It's 17th and 18th of October in Baltimore. And Pete Tomlin and I will be doing a joint paper on 10 or 15 operational maintenance and project considerations for Brownfield CBTC. And the other thing is we've talked about me appearing in your next World Congress convention for CBTC. And I'd love to speak at that as well for you. But I think people would disagree with things I've said. And that's fine. I'm not the Oracle, but definitive on this. But hopefully some of what I've said resonates with people. And I think, yeah, you know, Mike might have a point there. And that's fine. And I'm sure people will reach out to me.

And I always like a good discussion, normally over a beer, which is not possible necessarily online. But, you know, we're all very different. And I don't want to upset anybody. I'm very respectful of the suppliers. I'm very respectful of the agencies. I'm respectful of consultancies. And I'm respectful of people who know what we're doing and more cautious about those who don't. Excellent closing words. Mike Palmer, thank you very much. And hopefully I get you again on the show soon. Thank you. Well, thank you very much. I would just point out it's 74 degrees here and I'm wearing a shirt. I've got shorts on which you can't see. At least I made the effort to dress up with my cufflinks and everything, Frank. But it was great to talk to you. We go back to that conference in February 2014. And it's been a blast. Thank you very much. Thank you. Bye-bye.

Bye. Have a good morning for you. Good evening for me. And I'm off to have a salad. Hi, it's Doc Frank again. I hope you enjoyed this conversation. If you like the content, then the best way you make sure that you don't miss out on any of the future episodes, just subscribe to the channel. By doing so, you also get access to all the previous episodes, which I'm pretty sure there will be many that are of interest to you. Another thing that you can do to help not just your own environment, but the entire industry is to share this episode with friends and co-workers because it helps more people in our industry to get educated and an educated rail signalling industry is a better industry. With that said, thank you very much. Hope to see you again soon. And bye for now.

Open the transcript file

Hosts and Guests

Nobody is credited on this episode yet.

Credit the people on this episode

Be the first to rate this episode

More episodes

All episodes
  1. #115 — 55 Years in Rail, Driverless Trains and Talent Drain, with Stephen Allday

    Nov 18, 20261 hr 1 minAudio

    What links Toby the Tram with a train control seminar in Beijing and the age profile of today’s rail workforce? Stephen Allday, who joined the railway 55 years ago and marked the anniversary in China. Stephen grew up in...

    Credit the people on this episode

  2. #113 – Why ETCS Is a Change Program, Not a Tech Project, with Cara Cohen

    Sep 9, 20261 hr 2 minAudio

    Fit the locomotives, commission the trackside, write the rules, and ETCS can still stumble on the day a driver decides the old way was better. The technology is the measurable part of an ETCS introduction. The people...

    Credit the people on this episode

  3. #112 – Why More Review Comments Make Railways Less Safe, with Andy Petrie

    Aug 26, 20261 hr 9 minAudio

    Twenty people comment on a document. Nineteen of them have no expertise in it. Every comment has to be answered, and the two that mattered get lost in the noise. Andy Petrie has spent thirty years watching this happen...

    Credit the people on this episode

  4. #111 — Fitting ETCS to a Freight Railway, with Craig Evans

    Aug 12, 202655 minAudio

    Freight is where the ETCS business case really gets tested. Many freight locomotives were built long before anyone drew a European Train Control System (ETCS) fitment design, and there is no factory fit to fall back on....

    Credit the people on this episode

  5. #110 — Why Digital Signalling Never Got Cheaper, with Andy Harrison

    Jul 29, 202636 minAudio

    Twenty years ago the promise was simple. Digital train control would get cheaper, and ETCS and CBTC would become the default for every new scheme. Neither happened. Costs keep rising, and the system knowledge keeps...

    Credit the people on this episode