Send us Fan Mail CISSP Domain 3.9 - design site and facility security controls, built on a real data center power failure where every control in the building worked and the building still went dark. Start free: https://www.cisspcybertraining.com/free-cissp-self-study (360 practice questions, a Domain 1 diagnostic, weekly questions by email, and the slides from this episode) In October, a cloud provider's London data center lost its utility power. The batteries picked up the load exactly the way they were supposed to, ran for about five minutes, and then ran out. The generators should have taken over in that window. They never got the signal. Nobody attacked anybody here. There are no bad guys in this one. No ransomware, no intrusion, nothing for incident response to chase. It was a cable fault outside the building and a logic error inside it. HOW THE BUILDING WAS BUILT Start with the design, because the design was good. Two completely independent utility feeds coming in from the power company - they call them A and B. Google's own words for that are a 2N utility power architecture. Now listen to where that label stops. Behind both of those feeds sits one central bank of high-voltage generators, run by a dual-redundant controller, a PLC. Two of the thing coming in. One of the thing that was supposed to save them. And between the utility going away and the generators coming up, a battery system with about five minutes of runtime. That isn't a lot and it isn't supposed to be. It's a bridge. So when somebody tells you a site is 2N, the only honest follow-up is: 2N at which layer? Five days before any of this, they ran a quarterly load test on the generators. A real test, under load. And that test found a problem. So they did the right thing - they scheduled the repair. But to do the repair they had to physically open the breaker on feed B and lock it out, which they did properly: keyed interlock, locked out, tagged out. And that is the moment the building stopped being 2N on the utility side. For several days - Google doesn't publish exactly how many - that site ran on one utility feed. Google's own words for it are a temporary single-feed, 1N, bridged maintenance posture. Then the cable broke. An underground cable out on the utility network, outside the building entirely, developed a fault. And it was on feed A. The only feed that was live. WHY THE GENERATORS NEVER STARTED The PLC decides when to start the generators, and it decides it by sensing voltage. If the voltage goes away, start the generators. Simple enough. But those voltage sensors were wired upstream of the feed breakers. On the line side. And feed B - the one that was open for repairs - was still energized upstream, all the way up to that open breaker. The power company was still feeding it. It just wasn't connected to the building anymore. So the PLC looks at its sensor, sees voltage on feed B, concludes that a healthy utility source is available, and never issues a start command. Google's own root cause is this: a misconfiguration of the PLC logic that did not verify both an undervoltage condition and physical breaker position for both utility feeders. It checked whether there was voltage. It never checked whether that voltage was actually connected to anything. And here's the part worth a line in your notes. That PLC was dual-redundant. There were two of them. Both of them were wrong in exactly the same way, because they shared a configuration. Duplicating the box does not duplicate the judgment. That's common-mode failure, and it is the reason a redundancy count is not a resilience measurement. Five minutes later the batteries were done and the data halls went dark. TWO NUMBERS, KEPT APART About ninety minutes with the data halls unpowered. Six hours and eight minutes before the services on top of them were whole again. Both figures are in Google's report and they measure different things. According to The Register, the companies caught in that window included Lloyds, HSBC, Royal Mail and Revolut - Google published no customer list and no customer count. To their credit, Google published the whole thing: the timeline, the wiring, the root cause, and a list of fixes with dates on them. One of those action items is the most honest line in the document. They committed to making PLC code review part of facility commissioning - which tells you it wasn't. THE MANAGER'S TAKEAWAY Two things, and neither one is "test your generators." They DID test. The quarterly load test is what found the fault in the first place. What nobody did was look at the consequence: fixing that fault meant opening a breaker, and opening that breaker meant the building ran on one feed for days. As far as anybody treated it, that was a maintenance ticket. It wasn't a changed risk posture. And the second one, the one to carry into the exam room: an automatic control is only as good as the thing it can sense. The generator was perfect. The battery was perfect. The logic was asking a question - is there voltage? - at a place where it could not tell the difference between "the utility is healthy" and "the utility is healthy and no longer connected to us." Redundancy isn't a label on a drawing. It's a property of a system at a particular moment, and that moment includes whatever your facilities team happens to have open for repairs today. IN THE TRAINING BLOCK • The power chain end to end, and the fourth thing almost nobody reads - the logic that decides when to start, which lives on a controls drawing rather than a power one. • UPS runtime: battery in minutes, flywheel in seconds, and why five minutes is a bridge rather than a weakness. • Redundancy notation - N, N+1, 2N, 2(N+1) - and why N+1 survives one failure but not one failure during maintenance. • Concurrent maintainability versus fault tolerance: two different promises that candidates collapse into one. • The three states of a redundant system - designed, degraded, failed - and why failure almost never arrives on its own. • Every physical control has a sensing input: fire, cooling, water detection, door alarms, access control vestibules. • The 3.9 recall content, and the crossovers named out loud - change management is 7.9, risk acceptance is 1.9, resilience and fault tolerance is 7.10. FOUR CISSP PRACTICE QUESTIONS Set inside the real incident, so they are hard on the reasoning instead of hard on the reading. Common-mode failure; a FIRST question where the trap is the answer you are proudest of spotting; a MOST DIRECTLY question where the trap is the biggest answer on the list; and a control-class question where the trap is the governance gap the episode itself spent ten minutes describing. CHAPTERS 0:00 Two power feeds, and the generators never started 1:56 The whole thing in thirty seconds 3:36 A spare, or a complete second path 4:44 How the building was built 6:09 The load test, the open breaker, the cable fault 7:40 Why the controller never issued a start command 9:00 Two controllers, one mistake 10:18 The manager's takeaway 12:33 Free Essentials, Accelerator, Pro and the Cohort 15:51 Domain 3.9 and the power chain 19:03 Redundancy, and where the label stops 22:01 The three states of a redundant system 23:37 Every control has a sensing input 29:17 Question 1 32:20 Question 2 - the one that gets people 35:23 Question 3 38:31 Question 4 41:43 The pattern across all four LINKS Free CISSP Essentials - 360 practice questions, a Domain 1 diagnostic, weekly questions by email, 8+ hours of rapid review audio and video, and the slides from this episode: https://www.cisspcybertraining.com/free-cissp-self-study All episodes and the written walkthrough: https://www.cisspcybertraining.com/podcast CISSP Sprint Cohort - for people with a test date on the calendar: https://www.cisspcybertraining.com/cohort-sprint-page SOURCES PRIMARY - Google Cloud's own incident report for europe-west2, Incident Xs2XTHzAVC9YnafnPyzj. Every figure above comes from here unless stated otherwise: https://status.cloud.google.com/incidents/Xs2XTHzAVC9YnafnPyzj SECONDARY - The Register, 5 November 2026, Simon Sharwood. The four customer names come from here, NOT from Google: https://www.theregister.com/off-prem/2026/11/05/when-datacenters-lose-power-generators-should-kick-in-that-didnt-happen-for-google-in-london/5307739 Gain exclusive access to 360 FREE CISSP Practice Questions at FreeCISSPQuestions.com and have them delivered directly to your inbox! Don’t miss this valuable opportunity to strengthen your CISSP exam preparation and boost your chances of certification success. Join now and start your journey toward CISSP mastery today!
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
SPEAKER_00Welcome to the CISSP Cyber Training Podcast. We provide you the training and tools you need to pass the CISP exam first. Hi, my name is Sean Gerber. I'm your host of the Action Active Format Podcast. Join me each week as I provide the information you need to pass the CISSP exam and grow your cyber security knowledge. Alright, let's get started.
SPEAKER_01Good morning, everybody. It's Sean Gerber with CISSP Cyber Training and hope you all are having a beautifully blessed day today. Today is Monday, and as we do every Monday, we go over some great things related to the CISSP exam. And our goal here is what? Yes, to help you pass the CISSP exam the first time. So today we're going to be going over some different aspects. We have an article that we get into, then followed up with some training, and then we full rolled into some CISSP questions. And today's topic is going to be over domain 3.9, right?
SPEAKER_01So domain 3.9, designing site and facility controls. So I know you all are thinking facility security is a domain that most people skip because it's not IT, right? It's the one people figure they'll figure their way out and it's all good when they deal with it in the test center. Not a big deal. Well, this is why you shouldn't, because a major cloud provider had a data center in London lose power to its data halls for about an hour, hour and a half, and it took six hours to get the services back online.
SPEAKER_01So again, two independent power feeds, a whole bank of backup generators, all of it built and all of it working, ready to go. But yeah, the generators never started. Not because they were broken, not because someone forgot to put gas in them. They just never started because the thing whose job it was to notice the power, and again, it's a thing, it's an idea, that its purpose was to look at this aspect and notice the power had gone out was wired wrong. And it was not correct.
SPEAKER_01And because of that, yeah, they had an outage. And you know, if you're dealing with an outage of a large data center, yeah, that can be pretty problematic. So we're gonna get into that, and then we're gonna get into the various aspects around physical security, followed on with four CISSP questions at the end. And again, you're gonna love all of these because the goal of this is to just highlight the fact around the CISSP so that when you go in for the exam, you see these different questions, and you then are ready to take the test and you're ready to pass it. Again, I try to try this home.
SPEAKER_01Memorizing gobs and gobs of questions isn't going to help you. It's gonna be extremely challenging, and honestly, you're never gonna get there. So the goal is understanding the content, really diving deep into the content, but also in the same time knowing how to understand the questions and answer them in a correct fashion. So here's the whole thing in 30 seconds, and then I'll get back to what we're gonna get into. Is in October, a cloud provider's London data center lost its utility power. The batteries picked up the load exactly the way they were supposed to do it.
SPEAKER_01And this ran for about five minutes and then they went dead, right? The generators should have taken over in that window, and we've talked about this a lot at CISP Cyber Training that your battery backups are not designed to basically run your data center. They are designed specifically to allow you to have a good shutdown or for the generators to kick in. So there are two numbers and you need to keep them separate. About 90 minutes with no power in their data center. Six hours and eight minutes before the services on top of them were basically brought back online and whole again.
SPEAKER_01And according to the register, the companies caught in that window included Lloyds of London, HSBC, Royal Mail, and the Revolute. All of those were caught in this outage. Now nobody attacked it anywhere. There was no bad guys or girls involved in this whatsoever, no ransomware, no intrusion, nothing for instant response to chase and go after. It was a cable fault outside the building and a logical error inside it. And we've talked about this numerous times is that those stray backhoes, not necessarily in this case, but those stray backhoes can cause a significant problem.
SPEAKER_01Now, here's why we're talking about it in a physical security episode. Every control in that building worked. The generators were fine, the batteries were fine. What failed was what the automation could see, and that's the issue. Okay, so let's back up and let's show you how this actually occurred and what actually happened in this situation. So how the building was built, it's one piece of vocabulary first because nothing after this really makes sense without it. There are two different ways to build backup systems, and both of these things, they will people, most people will call them redundant.
SPEAKER_01The first is a spare. You need three units, so you install four, right? You have a spare one sitting there. One can die, and guess what? You're still hopping and you're running. The second is a complete system, not a spare part, a whole duplicate path from top to bottom. Either one can carry the entire building itself. Okay, again, different promises, very different money. And you can only guess the differences in those. Okay, so I want to talk about the industry shorthand for these systems, and we're just gonna quickly move on. A spare is an N, as in November, plus one.
SPEAKER_01A complete system, a second system is a two N. Okay, these are gonna be slides on this later as we go through the training, but those are some things for you to keep in the back of your mind. So let's start with the design because the design was good, and that's the part where people get wrong in this story. The utility side, the facility had a complete second path. Two completely independent feeds coming in from the power company. They call them A and B, each one able to carry the whole building on its own. Great redundant systems, that is a great design.
SPEAKER_01Now listen to where this potentially stops, right? Behind both of those feeds, since one central bank of high voltage generators, so each bank had a high bank of high voltage generators, run by a dual redundant controller, a PLC, a programmable logic controller. Two of the things coming in, one thing that was supposed to save them both was this PLC. So they're run by a dual redundant PLC. So in between the utility going away and the generators coming up, a battery and a battery system, about five minutes of runtime.
SPEAKER_01That isn't a lot, but it isn't supposed to be. It's designed to be a bridge. So between the utilities going away and the generators coming up online and having a battery backup system in place, this is about five minutes of runtime, which isn't a lot, right? We're taking not a lot of money, or not a lot of money, a lot of battery power to do this. There's a lot of battery power, just not a lot to be able to take care of it. But what this was designed for was specifically a bridge, like we've mentioned, the ability to shut down or the ability to bridge you up to your generators.
SPEAKER_01Now here's where this starts to go sideways, and it starts with something very good, actually. Five days before any of this, they ran a quarterly load test on those generators. A real test under load, and that test found a problem. So they did the right thing. They scheduled the repair. But to do the repair, they had to do physically open the breaker on feed B and lock it out. So they shut down feed B, which they did properly, keyed the interlock, locked it out, and tagged out. Again, that all happened, not a problem.
SPEAKER_01And that's the moment the building stopped having a complete second path. So you understand what I'm saying? They basically went through and they did the physical open of it. They gone on feed B, they went to lock it out, they did it all properly, right? All that was good, but then they didn't have that second path. So for several days, Google doesn't publish exactly how many. That site was running on one utility feed. Google's old ones words for it were a temporary single feed maintenance posture. There's a lot of big$10 words there to say we had one feed.
SPEAKER_01Now, does this happen a lot? Yes, it does, and people work through these things. But as we've always talked about on CISSP Cyber Training, when things are gonna go wrong, they're gonna go wrong at the most inopportune time. So again, one feed, no second path, and it was on as a schedule, not on everybody's wrist register. So again, they knew it there, but they didn't document it. Then, guess what? Like we mentioned, the cable broke and there had a problem. An underground cable out on the utility network outside of the building entirely developed a fault.
SPEAKER_01It wasn't a stray backhoe, but things break. And it was on feed A, the only feed that was live. Now the building has no utility power at all. So what happens? The batteries pick it up right on cue. Five minutes, the clock starts, and then the generators sit there. So the question is why did they not start? The PLC that we talked about decides when to start the generators, and it decides it by sensing voltage. If the voltage goes away, start the generators. Simple enough, right?
SPEAKER_01But those voltage sensors were wired upstream of the feed breaker. So they're up line of that, on the line side, and feed B, the one that was open for repairs, was still energized. So there's still voltage. All the way up to the open breaker, the power company was still feeding it. So it thought there was power. It just wasn't connected to the building anymore, but it had power. So the PLC looks at the sensor and it sees voltage on feed B and it goes, I'm healthy, right? Even though downstream it's gone.
SPEAKER_01So it concludes that the healthy utility source is available and it never issues a start command. So Google's own root cause is this a misconfiguration of the PLC logic that did not verify both had an under voltage condition and the physical breaker position for both utility feeders. It checked whether there was no voltage, it never checked whether that voltage was actually connected to anything. So here's the part and that that's worth noting when you're trying to think about this. That PLC was dual redundant.
SPEAKER_01We talked about that. There were two of them, but unfortunately, both of them were wrong in the exact same way because they shared the exact same configuration. So duplicating a box does not duplicate the judgment. That's called common mode failure. And this is the reason redundancy count is not a resilient measurement. And let me strike that back again. Resiliency measurement is not when you deal with you have a multiple redundancy count. So five minutes later, the batteries were done and the data center went dark.
SPEAKER_01And to their credit, obviously Google published the whole thing. And that's amazing because it is. It's good that they say that they have a challenge and they address it and they deal with it. The wiring was the root cause and the list of fixes with the dates on them, including the validation of the PLC configurations at the other sites with a similar topology and the same controller vendor. And to their credit, they published the entire thing. The timeline, the wiring, the root cause, the fixed dates, all of those things were incorporated into this overall plan. They are basically saying all of it.
SPEAKER_01So, and one of those action items is the most honest line on the document. They committed to making PLC code review part of the facility commissioning, which tells you, yeah, it really wasn't at the beginning. Now I'll just be honest with you on all of this. This is something that every company deals with. I had many situations where we thought everything was good and we even did tabletops. We did all of those aspects, but until you have a problem where your stray backhoe or some other situation occurs, it is when you don't really realize maybe you had a bit of a problem.
SPEAKER_01So what I say on this is this is why it's so important for you to have tabletops as well as different types of playbooks that you have in the event something goes sideways. Because guess what, guys? Yeah, it's gonna go sideways. And as a CISO, these are things we dealt with all the time. So from a manager's standpoint, okay, let's look at this from that perspective because this is where it turns into exam content and why it's so important. So there are two things here, and neither one of them is to test your generators. The first one is did they test?
SPEAKER_01Yes, accordingly to load test, it was found the fault in the first place. So they did that. Testing worked exactly as it's supposed to. What nobody did was look at the consequence. Fixing the fault meant opening a breaker, and opening that breaker meant building the building was running on one feed for days. So as far as anybody was treated, it was a maintenance ticket. It didn't change their wrist posture. But because you're down to one feed and you don't have dual redundancy, yes, your wrist posture should change.
SPEAKER_01And that is something of, especially for a data center, of significant value to an organization. So you need to ask yourself when people take half a redundant pair out of service, does anybody decide whether that is acceptable or not? Or do they decide who schedules it? Or at the same time, is is that's just an IT function and they don't worry about it? Do they communicate this up the chain to senior leadership? And the second one is this I want you to carry this thought process when you go in and sit for the exam.
SPEAKER_01And automatic control is only as good as the thing it can sense. The generator was perfect, the batteries were perfect, the logic was asking a question, is there voltage? And when it came right down to it, yes, there was voltage, but it didn't say whether it was connected or not. So again, redundancy isn't a label on a drawing. It's a property of a system that's set for a specific moment, and this includes whenever the facility is potentially open for repairs. I cannot stress this enough.
SPEAKER_01We had very specific windows when you did this. This, but this happens a lot in a physical environment. People have really good controls. But do you have those same levels of controls when you're dealing with IT? So again, domain 3.9 does not ask you to list the fire suppression types. It asks you which controls this facility in this configuration, right specifically now. Actually, requires whether or not anybody even owns this specific situation. So you need to think about that. Those are the questions that a manager is going to want to ask is who owns the risk for this facility.
SPEAKER_01Okay, so this is domain 3.9, site and facility security controls. Again, redundancy is not a property of design, it's a property of the system at the specific moment. Well, before we get started in what we're gonna talk about today, I wanted to do a quick shout-out for CISSP Cyber Training. If you all know, I'm just kind of hitting this right hard at the right at the beginning. My cohort is starting in about eight days. Okay, so again, November 17th is when it's kicking off. We are almost ready to begin the cohort.
SPEAKER_01We have two specific times. We have 7 a.m. and we have a 7 p.m. For all of those that are listening in different parts of the globe, pick one that works best for you. Just had another person in cohort two pass the CISSP exam, did it in 100 questions. And I'm not saying that that's because we are amazing, but I'm saying that that person took the cohort, loved what we did, and took the time and the energy and studied really, really hard to be successful on the CISSP exam. So again, CISSP cohort starts in about eight days.
SPEAKER_01And I'm gonna be also honest with you, my early bird special ends in two days. That's when the price goes up to another 100 bucks. So you need to get on this as fast as you possibly can. The thing is filling up very, very quickly. So before you know it, it's gonna be to the situation where I'm gonna have to do like I've done before, and they'll be sold out, and you'll have to wait till January. So take advantage of it now because it's starting in about eight days. So I've got three different ways to study with me. It's the accelerator,$19 a month. I have my pro version, and that's available to you as well.
SPEAKER_01And then I have the live cohort. If you're not ready for any of that, fine, not a problem. Head on over to CISSP Cyber Training and you can sign up for my CISSP Essentials. You just need to decide which one of those three programs is best for you. The accelerators for those that really want to do self-study on their own and they just want to get at it. My pro version is for those doing self-study, but also want to have some interaction with myself during this entire process, which we have an office live coming up uh next weekend, or I should say next Monday. And then we have the sprint cohort, which I already talked about.
SPEAKER_01So go check those out at CISSP Cyber Training. Okay, so what does domain 3.9 actually ask? So it does not ask you about fire suppression types, like I just kind of mentioned, right? It gets into the situation where is this your system? Is it in place? What is the risk? What does it actually require, and who is in charge of it? So when you're dealing with utilities and power, you have different feeds, power feeds, you have UPSs, you have interrupted power supplies, generators, transfer switches. These all control are controls that are out there when they're last resort, when everything else is fine.
SPEAKER_01You have utilities in HVAC, this is where you have power and cooling, humidity, water detection. This is where equipment will fail on temperature far more often than on anything that an adversary may do. Fire prevention and suppression, this is where you have different detection types, types of agents, where the people are at is usually when you're dealing with fire prevention. Again, these are life safety decisions. Then you have secure areas. This was where your wiring closets, server rooms, media event storage, and then restricted work areas. And then finally, your environmental issues, where you have natural and man-made issues, floods, seismic activities, weathers, uh tornadoes, all of those things right there.
SPEAKER_01These are the ones you have to deal with that happen to you. These are not decisions, and you can't retrofit to these situations. You have to plan for these thought processes. So, again, today is the one, the first topic we're talking about. Everything on this list has the same shape. A control that is only as good as what it can sense. So we're gonna be getting into the utility, UPSs, and generators. We have the normal supply, two independent feeds in this situation that were coming in. It's a common design that people have. In case you have the stray backhoe that comes in and takes out one of those feeds accidentally, you have a backup and redundant system that's set up, especially for high-risk environments such as a data center.
SPEAKER_01But in many ways, you'll want to have two power feeds coming into your facility. Independent means a separate physical pass, not just two breakers on one path. And I mean it. I was working and I had a manufacturing facility in many of my manufacturing facilities. We had paths coming in, one power provider here and another one over here. They came from separate power providers. They weren't the same company and they came in in separate lines. Now the battery is the bridge. This gives you minutes, right? This gives you just a brief moment and it allows you some time to be able to migrate, either shut down the system in a logical, professional way that doesn't cause breakage or until something else starts.
SPEAKER_01Again, the one thing that happens though is battery age. If these batteries, again, if you don't test them, you don't use them, they you can be asking and waiting, going, hey, my battery's gonna kick off when the power goes down. But if you didn't do the proper maintenance on these things, your power goes down and your batteries will fail you. And that's a bad time for something to happen. Generator, this is your sustained supply. This is where it's sized for full critical load. It's fueled for a staged number of hours, and in many cases, most generators need to run for a period of time.
SPEAKER_01If you are in a regulated industry, you will have to test this and provide evidence that you did test this. Then you got to make sure you have the fuel. Do you have the diesel? Who's managing the diesel fuel if that you're running a diesel system? Most likely most generators run off diesel. Um, again, all of those pieces around sustain supply. So we'll walk through again what happened in specific order. A, the quarterly generator load test failed A on a specific vault. So, what did they do? They opened up the breaker, they locked it out for repair, and then days go by.
SPEAKER_01Now, the question is why did days go by? Don't know. Maybe they didn't have the part, maybe whatever that might be, but days go by. It's considered just a maintenance thing. And you know, the sad part is in many cases, what ends up happening is you go, this is not gonna happen to me. And so what do you do? You go, it's good, it's all good. We've never had a problem. But yeah, the one time when you think you're not gonna have a problem, you have a problem. So a cable fault outside the building, again, key killed feed A. The UPS carries the load for about five minutes, and then the plant controller sees the voltage on feed B and does nothing about it.
SPEAKER_01Finally, the batteries are depleted, and the overall data center goes dark. So, again, this happened very, very quickly, and it's one of those situations where you're now everybody's scrambling. So, let's talk about redundancy. So, one of the things you're gonna see in the exam is you're gonna notice about redundancy notation. So, n, n plus one, two n and then two n plus one, or two and then brackets n plus one. Let's get into that. So, if you're looking at the screen, you'll see this. And n is exactly what you need.
SPEAKER_01It's full capacity, no spare, one failure is an outage. You're done, right? Now, n plus one is a spare component. Four units where they carry the load, one serve one fails, right? And then you still have the other three to bring it up line. So that's where you have a spare. You have a redundant system. So you have your N, N plus one. Now you have a complete second system. Now you have two independent paths carrying the entire load. This would be a 2N, okay, two November.
SPEAKER_01And that is a complete second system. Now, if you have two systems, each with an N plus one, which basically means you have two separate systems, each of them has one extra component, that would be a two brackets, N plus one. So it's got full duplication and a spare inside each path. The two N plus one, again, that is an important thing. If you really truly want to have that availability. Now, the question is though, in this situation, because of where the PLC was at, it really didn't matter. Now, we're going to get into some different promises here.
SPEAKER_01You're going to deal with concurrent maintainability versus fault tolerance. And you'll hear fault tolerance a lot, but concurrent maintainability is something that you may not hear you, but if you're going to see it, you don't want it to be the first time you see it is on the exam. So the concurrent maintainability is any component or path can be removed for planned maintenance without impacting the critical load. So again, you can pull stuff out for planned air quotes maintenance, and because you have multiple things in place. This problem is about scheduled work, right?
SPEAKER_01It says nothing about what happens if something also fails when the work is underway. And I again I try to stress this. If you're working on anything that's critical to your organization, always have a plan for when it fails, because, like I said before, it's going to fail at the most inopportune time. Now, fault tolerant is when the facility survives an unplanned failure of any single component while it's in normal operating configuration. Now, if you had a situation where you were doing a down maintenance and then there was a failure, okay, that it would be a planned event because you planned it already.
SPEAKER_01So that wouldn't be fault tolerant. Fault tolerant is unplanned. So again, this is a promise about surprises. So the facility in this incident was delivered on the typology, a path was removed, and the route to the power remained. Again, this classification was awarded against design. It was set up just fine. Everything was good. However, it degraded quickly, and then again you had a significant problem. So you have three states of a redundant system. You have designed, degraded, and failed.
SPEAKER_01Design is that every path is available. The state the drawing shows, the state of the certificate of supplies, the state everybody's pictures, all of it is as designed. It's operational, things are good. Degraded is when there's one or more paths out of service. You have maintenance, repair, failed components. That is a degraded state. Failed state is when there's no path available, the one everybody plans for, the one that is almost never arrives on its own. It arrives while usually you're already in a degraded state. And what I'm saying that is that you design it so that if all of a sudden something happens, we can roll.
SPEAKER_01But it's usually when things go sideways and you're like, oh, I'm dealing with this issue, and then kaboom, it goes dead. So again, think about all of those aspects. Now every physical control has a sensing input. And what does that mean? So the control, let's just do backup power. So you're in this situation, the plant controller was sensing utility voltage. This senses the in this situation, it was on the wrong side of the breaker. But you need to consider that. Where should it be? So if it would have been on the right side of the breaker, when you flip the breaker switch, the voltage would have gone down, generators would have come online.
SPEAKER_01They put it on the right side because they're like, well, if we're flipping it off, um we don't want the generators to go on. So that would be in the situation there. Fire suppression is it's sensing smoke, heat detection, and it's often set between multiple zones. If in the where this would potentially fail is if the detector is in the wrong airflow path, right? So if you don't, maybe it's in the area where it's going out of your air conditioning, your return valve, and it's sucking all of the smoke away from your sensor, and the sensor never goes off, but you actually have a fire, that could be a problem.
SPEAKER_01Cooling is temperature and humidity sensors. Do you have the sensor at the top of the rack? When but the heat is all at the bottom, that would be a problem. Water detection, where are your moisture sensors at? Are they on top, above, or are they under the floor? So again, again, many cases the floor tiles are lifted up during work and then they're never ever replaced. Door alarms, this is where you have a contents contact sensor on the frame. But if the door is propped open and the contact is basically intact, the alarm stays silent.
SPEAKER_01And I've seen this where people will pop it open, they'll put something in place where the alarm is at, just so the fact is that they can keep the door open. And it's brilliant, I know. But yeah, I see people doing it. Access control vestibules. This is where it's based on occupancy. Is there somebody in there? Is there a weight in there? Is there optical sensing? But is the weight enough for somebody carrying gear, right? Or someone who passes a second small person. One area we got around this was we just did that. We knew that the cameras weren't watching.
SPEAKER_01We knew the fact that we could get into a vestibule. We had access for one person. And so what we did was is we'd have one person and we would get someone who's relatively lighter, most times it was a female, would jump on our backs and we would go in. We would beep in, and then now we have two people in a facility, not just one. So again, those are areas to think about when you're dealing with setting up security. So we're gonna talk about fire, water, and air. So fire, the four different classes you will run into with fire. A is ordinary combustibles, B is flammable liquids, C is electrical, D is combustible metals, and then K is cooking oils.
SPEAKER_01Again, those are the four classes A, B, C, D, and K. Suppression follows the class and the room. A clean agent where people where electronics are, those are different aspects. You're not gonna want to have electronics, you're not gonna wanna be putting in normal water, right? That's something you don't want to deal. So a wet pipe is the standard. You'll see that where there's water in the pipes and it's there. Dry pipe is where freezing is potentially possible. So what that means is there's air in there and the situation comes in. If there is a fire and it releases, then at that point in time the water is released.
SPEAKER_01But it's air inside the pipe. A double interlock slash preaction basically needs two events detection, needs to detect it, and the loss of air pressure in the pipe, which is why it belongs in a data center. Single interlock needs detection alone. Now, air and water is where you deal with positive pressure, pushes smoke and contaminants out of a secure area. Humidity, it's too low, gives you a static discharge. Too high gives you condensation and corrosion.
SPEAKER_01So those are important parts when you're dealing with water. Hot and cold containment is the availability control, and the sensor placement decides whether it's working or it's just installed. Always remember this. Life safety outranks asset protection all the time. Dealing with the exam question, they're gonna always do that. If you're dealing with life safety, that is it. The systems can burn to the ground. It's more important that somebody is taken care of. Now, secure areas and who actually owns them.
SPEAKER_01You have wiring closets, server rooms, media and evidence storage, and restricted work areas. So wiring closets are the most underprotected room in many, many buildings. A network tap in there beats any perimeter. And guess what? I did that a lot. We would get into various different wiring closets and I would put all kinds of systems in those, and nobody ever knew. They didn't typically go back and even look at them until after an event occurred. Server rooms, these are have layered access. They're logged and they're separate from the rest of the floor. They're very challenging to get in, and I never got into them.
SPEAKER_01I really didn't. I would try, but in most cases, you get you also don't like getting into them because once you're in, you're kind of like a rabbit that's stuck and you can't get out. So they're kind of iffy. But wiring closets, oh yeah, those are awesome. Media and evidence storage, this is where you have chain of custody and environmental controls. If you need to have that in place, not just some lock that's there. Because if the lock, most locks, especially those keypad locks, they're like one, three, five, and click, you can go in. If you don't have chain of custody and you have a strong lock, that will then say if you didn't do chain of custody, you wouldn't even know if something was missing.
SPEAKER_01And then restricted work areas. These are defined by what happens there, not by what is stored. So again, these are important parts that you need to understand related to physical security. When you're dealing with facilities, it's really important to understand who has decision rights with this. And this is why when you're dealing with a question that might be tied to facility controls, it most likely is not IT, right? It's somebody else has facility access. So I would work in many cases with my facility folks to kind of walk through the different security controls to put in place.
SPEAKER_01I highly recommend you do that. And from a managerial standpoint, that is one of the questions you could potentially could see is how are you working with the facilities managers? Okay, so five key takeaways for you to think about here. A control includes a sensing input. Again, what is that controlling place? How are you sensing it? Is it logs? Is it a PLC? Is it what is sensing that control? And then it enables that control. Redundancy is a state, it's not a label. Again, you need to understand just because you have something that's 2N or 1N on a drawing does not mean it's actually redundant.
SPEAKER_01You have to understand the state and do you have the controls in place for that? Do you have the ability to do that? Degraded is the normal state. Failure almost never arrives on its own. It usually happens in a degraded position. And then a certificate describes capability. It says what the design can do, but only somebody exercising it tells you what the controls actually do once the path is gone. So you say, I've got a certificate, this is happening. Yes, it's great. It talks about the capability that happened, but did you actually test it?
SPEAKER_01Again, that's where tabletops come into play. And then facilities is not your team. Do you not understand who owns the facilities and who owns the risk associated with that? So you need to kind of walk through all of those and think about it from a perspective of a person who is managing these systems. Okay, so we've got four CISSP questions. We're gonna get into question one the data center's generator plant starts automatically on a decision made by a redundant pair of controllers. During an outage, neither of the controllers commanded a start, and the critical load was lost when the UPS reserves were depleted.
SPEAKER_01The post-incident review establishes that both controllers were powered, available, and healthy throughout, and that both evaluated the same inputs and reached the same conclusion. And then it ended up being that both were commissioned from one shared configuration, which no second party had reviewed. Which characteristic of this design best explains why the redundant pair provided no protection? A, the standby controller had no means of detecting the active controller that faulted in taking it over. B, the pair had a common cause failure, so duplicating the controller duplicated its defect.
SPEAKER_01C, the pair was built as an active standby pair rather than a voting group, so agreement was treated as confirmation. And then D two controllers were not separated into independent physical locations, so a single event could reach both. Okay, so what one is it? And the answer is B. A pair had a common sense failure, so no duplicating, so co-duplicating the controller duplicated its defect. Again, redundancy protects only against independent failure.
SPEAKER_01These two failures were not independent. They were one specific failure. So now the trap would be D. The controllers were not physically separated. A candidate would look at this, you might look at this and go, well, they weren't separated. So that would be the logical one. And you go, aha, that's gotta be it. If I separated those, that would be the problem. But again, no event ever reached this specific controller, and that was in the question. Both were powered and healthy the entire time. So slow down when you read the question. Okay, next question.
SPEAKER_01You are the security manager for a facility that has just entered a planned maintenance window. And we know dealing with a lot of different maintenance aspects, those are typical. To repair a fault identified during a generator load test, one of two independent utility feeds has been physically opened and locked out. The work is expected to run for several days. Routine planned maintenance notification has already gone out to the service owners. The engineer on the crew has raised a concern that the plant's start logic may sense voltage upstream of the feed breakers.
SPEAKER_01No assessment has been raised against the change. Which action should you take first? So let's look at this from a different standpoint. You got a security manager for a facility. Again, IT does not own this, and this is a planned maintenance window that they have already scheduled to repair the fault identified during a generator load test. So you have one of two independent utility fees, which we have talked about, and the work is expected to run for several days. Now, some key points. Routine planned maintenance notification has already gone out to the service owners, so they know this is happening, but it's a planned maintenance notification.
SPEAKER_01The engineer of the crew raised the concern, and now but no assessment has been raised against the change. So what should you do first? A brief the tenant service owners in person on what to do if the remaining feed is lost during the window. B. Reconfigure the start logic to evaluate breaker position in addition to voltage before the window proceeds. C. Call an immediate load test to confirm the generator plant will start while the facility is in on one feed. Or D record the reduced redundancy as a change in the risk posture requiring an assessment.
SPEAKER_01Okay, and there qu and the answer is so there's a big factor here. This one that you could bite off on would been B, right? Record reconfigure the start logic first, which we talked about. So you're reconfiguring the start logic to evaluate the breaker position in addition in addition to the voltage before the window proceeds. That's a technical response. And everything that we have talked about in this episode has been around the evaluation of the breaker position, right? Baker positions, we're dealing with the PLC, we're dealing with voltage. Those are all technical concerns.
SPEAKER_01But the one reason the one D is correct is because you reduce the redundancy as a change in risk posture. And then it requires an assessment. Because you know it's going to be down for a couple days. You just know that. So you should be doing an assessment to ensure that what do you have in place is sufficient for a situation where it goes down. So again, recording it and having this change in place is an important piece. The trap would have been reconfiguring the start logic first.
SPEAKER_01Again, that's a technical response to a question. And because we've been talking about this, you think it would be an easy one to jump onto, but it was the incorrect answer. The correct answer is D. Next question. The post-incident review establishes the following. Again, post-incident review. The facility's two utility feeds are genuinely independent. The generator plant is size for a full critical load and was never sent the start command. The UPS performed two specifications, and the plant's automatic start logic did not command a start.
SPEAKER_01It read the isolated locked-out feed as a healthy source. So which control would most directly have prevented this failure from occurring or reoccurring at this facility? So again, most directly. A require the start decision to confirm that the feedbreaker is closed. Not only the voltage is present. B Extend UPS runtime so the critical load can be carried long enough for the operator to start the generators by hand. C. Require the facility owner's signature on the maintenance waiver before any utility feed breaker is open.
SPEAKER_01Or D add a third independent utility feed so that losing one source during the maintenance does not leave the facility in a single feed. So which one do you feel is correct? And the answer is A. Require the start decision to confirm that a feedbreaker is closed. Not only that the voltage is present. So now when you look at all of these different ones, you're talking about, again, this is a technical measurement, this is a technical aspect. However, because there was no other answer that kind of went along the risk side, it did have to, you did have to have a decision to confirm that the feedbreaker is closed.
SPEAKER_01So again, it's not just IT making the decisions, that there was a decision had to be made to ensure that that feedbreaker would be closed. Now, when it comes to the trap, add a third independent utility fill. Now, this is probably one of those aspects where people go, hey, if two is good, three is better. And it it does answer something that is true. The site really did spend days on a single feed. But spending a bunch of extra money on another feed isn't most likely the right answer. And so that's one of those aspects where you go, well, hey, if one is good, two is better.
SPEAKER_01Two is great, three is amazing. And that one would be wrong. Last question. For several days, the facility operated with its one of two utility feeds isolated for repair. Throughout that period, the automatic start logic would have started the generator plan because of where its sensing, its sensing was taken. The post-incident review finds that nothing in the facility was positioned to surface this. The maintenance self was recorded, approved, and communicated in an ordinary way. So some key concepts there.
SPEAKER_01What nobody held at that point in those days was the fact that an automatic start had stopped working and the configuration of the building and in the configuration the building was in. So which class of control was absent? A. A keyed interlock making it physically impossible to open the feedbreaker while the facility carries production load. B. A standing instruction that facilities staff notify security management before reducing the redundancy. C. Check the reestablishment whether an automatic start still works in the configuration now in force.
SPEAKER_01Or D. Staffing the generator plant for manual start for the period of the feed was isolated. Okay, so we got a couple different questions things going on here. And what should you think about? So the maintenance was recorded and it was approved and communicated in an ordinary way. That's a key point. What nobody held at any point during those days was the fact that the automatic start had stopped working. And the answer is C. A check that reestablishes whether automatic start still works in the configuration now in force.
SPEAKER_01Now I will tell you that you probably all were thinking it's B. It's gotta be B. Make the facilities tell security before reducing redundancy. Now that's in a one that you're like, yeah, we've been talking about this. There's a gap. This thing has a gap that you've got to talk to your security people. But if you go back and look at the question, okay, for several days the facility operated with one of its utility feeds isolated for repair. Throughout that period, the automatic start logic would have not started the generator plant because of where the sensing was taken.
SPEAKER_01However, the post-incident review finds that nothing in the facility was positioned to surface this. The maintenance itself was recorded, approved, and communicated in an ordinary way. So what it means is when you say make the facility security aware before reducing redundancy, they were aware. They were part of the whole process. So this is one that would be incorrect. But as we talked about this whole episode, we know that there was a gap here. And so therefore it would be a really easy way for you to bite off on that.
SPEAKER_01So again, read the circumstances, read them quickly, and but also make them take some time when you're going through it. Because if you're reading these questions and you're taking your time, odds are high you will correct you will select the correct answer. But what happens is if you feel like you're getting in a hurry, that is when most people make the mistake. Okay, so that's all I've got for you today. Again, go check me out at CISSP Cyber Training. I've got three ways you can study with me. If you're looking to take the CISSP here in the next couple months, the live cohort is for you.
SPEAKER_01I guarantee you, I mean it. If you want to get this thing done over the holidays, this is the time to do it. And what's even better about what my cohort has set up, hey, guess what? You guys have life, right? You have time with family. And you may be going, I don't want to take my exam right now. Or, you know, I don't want to go sit in an actual course over the holidays. Not a problem. I have all of my uh cohorts, my weekly cohorts are recorded. So you will get a recorded copy of this and you'll be able to do go ahead and continue studying.
SPEAKER_01You can also reach out to me and I'm gonna help you with it. Again, a live cohort. That's the option. You can do the accelerator or the pro, depending upon how you want to do your self-study. And then finally, if that doesn't interest you, none of these interest you, great, not a problem. Go check out my free CISSP essentials. And it's basically it's C ISSP Cyber Training, free-s CISSP dash self-study. So free CISSP self-study, it's all there for you. All right, I hope you guys have a wonderful day, and we'll catch you on the flip side.
SPEAKER_01See ya. Thanks so much for joining me today on my podcast. If you like what you heard, please leave a review on iTunes. I would greatly appreciate your feedback. Also, check out my videos that are on YouTube and just head to my channel at CISSP Cyber Training, and you will find a plethora or a conocopia of content to help you pass the CISSP exam the first time. Lastly, head to CISSP Cyber Training and sign up for 360 free CISSP questions to help you in your CISSP journey. Thanks again for listening.
Send us Fan Mail CISSP Domain 4.1 - apply secure design principles in network architectures, built on a joint federal warning about internet-reachable refrigeration controllers. Start free:...
Send us Fan Mail CISSP Domain 2.6 - data security controls, compliance requirements, and the three states of data, built on an AI hosting exposure that encryption could never have reached, because the data was exposed...
Send us Fan Mail A company found a concealed recording device in the room where its executives meet. They pulled it, imaged it, reviewed the camera footage, went through the employee's internal tool usage, found a...
Send us Fan Mail A “boring” GitHub Actions workflow file should never be able to empty your secrets vault, yet that is exactly what the Ghost Action campaign shows. We walk through GitGuardian’s research and the real...
Send us Fan Mail 495 organizations woke up and could not get to their servers. Railways. A prefectural police force. A food logistics company that could not receive or ship goods. All on the same cloud provider, all...