In the latest episode of the Agile State of Mind Podcast, I sit down with fellow ProKanban trainer Benjamin Huser-Berta to discuss the visualization of flow metrics in Kanban. Our conversation reveals practical insights into improving predictability and system health that any software development team can benefit from.
We help you make sense of what we see on different metrics charts - cycle time scatterplot, throughput run chart, and estimation vs cycle time!
We discuss how to visualize metrics effectively, the significance of cycle time and throughput, and the role of service level expectations (SLE) in improving predictability. The conversation also highlights the importance of work item age and how it can impact team performance and system health. The episode concludes with a call to action for teams to embrace these metrics to enhance their workflow and decision-making processes.
This is a continuation of the Flow Metric podcast series. In the previous episode, I spoke with Colleen Johnson about why estimations are a waste of time. We unpacked Flow Metrics, how they save us from the never-ending estimation cycle, and where they show up in everyday life. We also explored the stages of grief teams go through when they first see the real numbers behind their workflow.
The Estimation Problem
The episode starts with a striking visualization: a scatter plot comparing story point estimates to actual cycle times. The revelation? There's virtually no correlation between the two. Items estimated at 21 points sometimes finish in just three days, while five-point tickets can drag on for weeks. This inconsistency undermines the very purpose of estimation - predictability.
"We should not try to get better at estimating, but use flow metrics and probabilistic forecasting instead."
Benji explains, capturing the core message of their discussion.
Why Should You Care About Flow Metrics?
If you’ve ever been asked, “When will this feature be done?” and had to rely on gut feeling or best guesses, you already know the pain of traditional forecasting methods.
Flow Metrics provide a data-driven way to answer that question with confidence. They help us understand:
* Cycle Time - How long does work take from start to finish?
* Throughput - How many items are getting done per unit of time?
* WIP (Work in Progress) - How much work is in progress at any given time?
* Work Item Age - How long has something been in progress, and is it at risk of taking too long? (Perhaps the most important yet least discussed metric.)
With these insights, the teams can see bottlenecks, adjust priorities, and make forecasts for stakeholders.
From Metrics to Action
What makes this conversation especially valuable is the focus on practical application. Rather than just collecting data, we discuss how these metrics change team conversations:
Instead of asking, "How many points is this?" teams can ask, "Can we complete this within our SLE of 10 days?" This shifts focus from abstract estimation to concrete delivery capabilities.
When aging items approach your SLE threshold, they can be color-coded to signal the need for intervention. This creates natural opportunities for teams to collaborate and prevent items from becoming outliers.
"If Work Item Age is the only thing you talk about in your daily, that is time well spent."
"There is this joke that, every time you start an item, you put the banana peel on that item. And then you see how it ages and it doesn't look good. It probably doesn't smell good over time either!" Benji explains with a memorable metaphor.
Breaking Free from Estimation
Perhaps the most liberating aspect of this approach is moving away from what Maria calls "the estimation mess." By focusing on flow and actual performance data, teams can make more reliable forecasts without the overhead and false precision of traditional estimation techniques.
"Plans based on average assumptions are wrong on average."
Maria quotes the book Flaw of Averages by Sam Savage, highlighting how conventional approaches often fail.
Watch the Podcast & Level Up Your Kanban Game
This episode is packed with real-world examples, practical insights, and a few laughs along the way. Whether you’re a Product Owner, Agile Coach, Team Lead or just someone who wants to make work flow better, you’ll walk away with actionable knowledge.
If your team is struggling with estimation challenges or seeking more predictability in your delivery process, both Maria and Benji are ProKanban trainers who offer hands-on training to help teams master these principles. Their approach focuses not on selling a "magical solution" but on providing practical techniques to improve your system's health and flow - check out the APK training here!
As we note in the episode, this isn't about achieving perfection but about becoming "least wrong" in an inherently uncertain environment. The journey starts with understanding a few basic principles that can transform how your team works.
🎧 Watch the episode now!
💡 Want to learn more? Let’s train your team in Kanban! Contact us for details!
Links to Benjamin Huser-Berta articles and flow metrics visualization tools:
* Using Flow Metrics in Your Scrum Events
* What does a Fridge have to do with Flow? - An Analogy to Explain Flow Metrics
* Using Probabilistic Forecasts for Feature Planning
* Here’s how to use Benji’s tools to do what Jira can’t do for you - visualize your metrics!
This is a public episode. If you'd like to discuss this with other subscribers or get access to bonus episodes, visit mariachec.substack.com/subscribe
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
How good do our estimates work compared to what is called cycle time, right?
SPEAKER_02Which is like, how long does it take from starting a work item? Let's say a user story, bug, task, whatever you have till it's done. What our assumption was, if our estimation works is that you have somewhat a linear line. So if things are estimated lower, they are also done quicker. So the cycle time is lower. Reality is that it feels very random, right? Because what we could see is maybe something is estimated with 21 story points, but it took only three days while something else is estimated
with five story
SPEAKER_02points and it takes 20 days.
SPEAKER_03For that, I also like to use a lot of this SLE because we define we should close items in 10 days or less. That's the most items, the 85%, right? And then we can aim for that. And that can be the very easy discussion of how we should split items. Will it take more than 10 days? We should split it. Is it like very small? Then it's okay. Don't forget that we both are pro Kanban trainers. We are happy to host a training in your company
SPEAKER_03Hi, everyone. I'm Maria Cech, and I have with me Benji. Hi, Benji.
SPEAKER_02Hi, Maria.
SPEAKER_03Welcome to Agile State of Mind. I would like to continue talking about flow metrics in Kanban. And after my recent conversation with Colleen Johnson, the CEO of ProKanban.org, where we talked about the flow metrics, how they appear in our everyday life, and also how Why estimations is a waste of time, like estimating and making a lot of emphasis on it is really a waste of time. Today, I invited Benji, who is a pro Kanban trainer as well,
SPEAKER_03to talk about not only the metrics that you know already, and we will do a short refresher, but also how to visualize them and how to get to this next level of using the metrics, making sense of how they appear and what they mean. and different ways of visualizing them. Today, I invited Benji Husserberta, who is a fellow, as I said, fellow pro Kanban trainer. He's also a trainer and a speaker at conferences where he puts a lot of attention to the metrics,
SPEAKER_03the probabilistic forecasting. That's how we met on the ALE, the, I always say ALE, the Agile Lean conference in Europe where we were together. I really like how you explain the deterministic thinking, which is we have an estimation and add a deadline versus probabilistic thinking, how to make predictions, forecasts, and how that can be a better way, maybe less violent way of communicating and sharing the forecast. So I would like to start with,
if you could explain what you actually do and how did you get to this metrics visualization?
SPEAKER_02Sure. So as you mentioned, I'm a trainer for Pro Kanban. So I'm doing this as well as I'm a former software developer or I studied software engineering. So I have some coding technical background. So I was mainly in the last five years, a scrum master in a company where I worked with different teams kind of day to day as well. And there I discovered some years back, kind of the magic of flow metrics and also probabilistic forecasting.
SPEAKER_03Yeah, and you actually started not only using the probabilistic forecasting, but actually tailoring it for your needs and for the team's needs. Could you explain? Because you even created your own company out of that.
SPEAKER_02Yeah, so we started to use the tools that were available for visualizing the different things, but also then trying to run forecasts. And as it is in real world scenarios, it was not perfectly matching what we needed at the time. So we started kind of playing around with, could we do it ourselves? And it turns out like flow metrics and forecasting, it's quite simple to do the things on your own.
SPEAKER_03It's good to know.
SPEAKER_02So maybe we get more into this in a bit. Oh, yeah,
SPEAKER_03we will, especially because, you know, when you use Jira, it would seem it must be so hard because Jira can't do it for you, right? So it must be like some science that few people can do. So I'm glad you say it's quite easy.
SPEAKER_02It's very basic math that we need. And it helps if you have a computer that can run it for you, but you could do it manually as well. So if you're not into coding or not into math, it will work anyway. So I'm confident that everybody that is interested can try these things out either by hand or by a tool or writing your own tool as well.
SPEAKER_03Great. And we will show that. So today we will be showing and Benji will be explaining what we see so that you can really get to see what can be done and how easily you can access all the data that, by the way, you already have, right? That's the beauty of flow metrics. It's not something that you need to start creating some calculations and filters in JIRA to get that data. You already have it. It's just to retrieve it. But then I also wanted to talk about one curiosity you shared with me.
So you are a Scrum Master, you were a developer, and you became a pro Kanban trainer.
SPEAKER_03Even though you have a professional Scrum Master 3 certification, which is like super advanced, how did it happen that you actually became a pro Kanban trainer and not a Scrum trainer?
SPEAKER_02Yeah, very, very interesting question. The PSM 3 is quite a tough exam, so I think not many people... And on my journey getting this, you really dive into theory of Scrum and you need a lot of real world experience that I had from working with my teams in everyday life. The more I... Sorry, yeah,
SPEAKER_03I think it's... I wanted to ask because I think it's not even like a quiz anymore because usually when you pass the exams, you just have like multiple choice questions. I think in the third one, you actually have to write like an essay and you are interviewed.
SPEAKER_02Yeah, it's like essay questions. So and an actual human is checking your answer. So it takes a couple of weeks to get the results. So and it's funnily enough, like you really need the experience because you don't have so much time to type all the stuff in. So you cannot think too long to answer a question. So you should have some real world experience. At least it was my experience from taking the assessment and preparing it.
SPEAKER_03Okay, so congrats. And what happened? What did you learn?
SPEAKER_02Also, let's say I still like Scrum, so I'm not against this. And I think it works pretty well together with Kanban. What happened when I dove into the details of Scrum and what is it really... suited for I just noticed that it may not be useful for the problems we are having right now in the company I was with at the time so the main problem was how can we get more predictability because the company was kind of bidding for projects and then it was like okay you won you need to deliver this and this
by I don't know
SPEAKER_02soon uh 25 and these are these are the specs and it included like five different products of our company that then had to be ready right at this point in time otherwise you might get fines for every week or month you're late so okay so you've
SPEAKER_03got some hard deadlines yes Okay. And did it, so you noticed that the way we, well, actually, I think it's this problem that we try to use Scrum and Kanban, especially when we don't know either interchangeably, right? As if it is one or the other. And there was always this, should we do Scrum? Should we do Kanban? Maybe let's do Scrum ban. And then, yeah. And then I think it's, as I see it,
SPEAKER_03it's more like a complementary solutions, not one or the other. and actually that's the thing like scrum doesn't give you a lot about flow management and predictability it's not there at all it's even estimations and story points that people consider is part of scrum is not there so so yeah i think it really makes sense to use it as complementary right and even though and not getting caught up by okay i'm doing scrum it has to be perfect maybe we don't have to do
SPEAKER_03perfect scrum we just have to do something that's good for our teams that responds to the needs. And your needs are different than mine because I never have such a cemented deadline. Of course, it's not seen with happy eyes if somebody says, we are missing the deadline, we will deliver in maybe we need two more weeks and then two more and so on. It's like, okay, not great, but we can live with it. But in your case, I see that. So that it was a problem and you had to know where something
will be done.
SPEAKER_03So what was the first step? If you have such a deadline, what do you do?
SPEAKER_02So maybe I can take you on that journey with me. And also we didn't say I went to the Kanban training. Now let's throw out Scrum and do Kanban. But actually we just started looking at what is the first problem and maybe I share my screen. If you could also explain a bit the flow metrics that we can see so that it's a refresher as well for those that already forgot the four flow metrics that we have. Yeah. So I will start with some other chart, which is I would say one of my favorite charts,
SPEAKER_02which looks at cycle time and estimation and compares kind of how well the estimation was compared to the cycle time because this was as mentioned we wanted predictability and we were using story points at the time and then i was reading some of the work from dan vakanti and looking a bit into his podcast yes with pratik singh and i realized oh there there might be this other thing that we should check out and One of the things initially we were doing is,
SPEAKER_02okay, how good do our estimates work compared to what is called cycle time, right? Which is like, how long does it take from starting a work item, let's say a user story, bug, task, whatever you have until it's done. And that's also the importance of Kanban to actually define those points, right?
SPEAKER_01Yes, exactly.
SPEAKER_03It's interesting how different, if you even ask different roles in your team, they might consider different points true for start and end. So as a team, we first agree, where is the start? Where is the end? And that's what we will measure, right?
SPEAKER_02And once you have this, you basically have all the data you need for all the metrics we were going to show and explain to you.
SPEAKER_03Yeah. And that's a great news. And I love it. I think it's also the part of, we are so used to story points and estimations. And it's hard to say, you know, whatever you do, you just can count the number. Like you have the cycle time here, but then we will talk about the throughput. So it's so good to have this comparison so that we can really see what works best. So please go ahead. So here what you see or also for the people maybe just
listening and not seeing the screen is like on the x-axis you see our estimation which was in story point it could be ideal days or man hours or whatever things you use or i don't know potatoes or whatever measure you're using and on the y-axis it's the cycle time like how long did it take to complete this item and what our assumption was if our
SPEAKER_02estimation works is that you have somewhat a linear line so if things are estimated lower they are also done quicker so the cycle time is lower reality is that it feels very random which is kind of or it did explain why uh we're not predictable uh in terms of if we use the the estimations and try to create the project plan based on this right because what we could see is maybe something is estimated with 21 story points,
but it took only three days while something else is estimated with five story
SPEAKER_02points and it takes 20 days. So it's not really useful then to base your plans on this data. And that was kind of where it's like, okay, I think we should not try to get better at estimating, but maybe try this flow metrics thing and then probabilistic forecasting instead. So that was kind of the trigger. And it's very interesting because in Every team we tried and did this chart, it basically looks similar always. I haven't seen yet a team where you really get more or less a
linear line.
SPEAKER_02Maybe it's just the teams I worked with. So feel free to prove me wrong. But this is something I encourage everybody to try it out because it's quite eye-opening. And that's a tool that we can just take and use with our existing tracking tool,
SPEAKER_03whatever we use. If it's Jira or Azure DevOps, so we can just plug it in, right? And see this.
SPEAKER_02Exactly. So like maybe I can mention I'm showing the tool that I created. There are others around. Maybe you can also share. There was recently a blog post from Pro Kanban sharing a lot of free, really available tools. So yeah.
SPEAKER_03Yeah, yeah, definitely. I can share it in the description, but I also want to share yours because I really see this is like, for me, the first point we should do with the teams. And then we can have a conversation. And I really encourage people, now we have spring. And it's like a perfect time to say, hey, what if we do a spring tidying up our spring cleanup? Right. And like, you know, let's see what we have and let's see, because sometimes it's hard to say about, we will get there probably like,
SPEAKER_03oh, shouldn't all the items be the same size if you only want to count the, well, how is that working? But what happens here is like, you can ask like, what do you think is happening? Maybe you actually, the story that you had 21 points, well, that's actually the outlier, but maybe you had a story that you only had three points, but it took many days because you were blocked. Something happened. You couldn't keep going. There was a dependency, right? And it's really hard to take that into consideration for everything.
When you estimate, you basically estimate the time coding and not the time waiting, right? And maybe the one that was estimated 21 story points and then was done in,
SPEAKER_02I think, three days, maybe there the team said, well, if all four of us work on this together, we have a better chance of getting it done. Right. Which is exactly the conversations we want to have. But then we don't need this extra step of estimation for it. Right. So it's more. But we will get there. Exactly. But cycle time can be really useful for this.
SPEAKER_03Okay. Yeah, let's continue.
SPEAKER_02Maybe just one addition here, like as you mentioned, a tool would work with Azure DevOps and Jira, but also with like CSV input. So many tools, you can just export it into a CSV file and then generate your charts to get started. That may be the easiest way of trying it out. Oh, that's great. Before you invest a lot in connecting your tools or you need some special permissions maybe. Yeah. So a CSV usually is easy. Like I said that we are this enterprise level company in our systems and maybe I
SPEAKER_03need like security team to clear it for me. So then it's easier to just, okay, I don't connect anything to my data. I just export the data and check. Yeah. Okay.
SPEAKER_02And the cool thing is you only need like this. When was an item started? When was it finished? And maybe some kind of ID, but it's quite anonymous, right? So whatever you see here is like random numbers as labels, right? But you cannot really infer what it is exactly.
SPEAKER_03Okay, so let's continue because you have more than this. So this would be great to start to really have many conversations of what happened and how it might not be the best tool.
SPEAKER_02And you can just try this out, right? There's no harm. Like you don't even have to ask anybody. It's just like, let me check this out and maybe once share it within a team just to see, hey, somehow this estimation thing might not work. And it's a good kind of kickoff to think about other metrics. Like for example, cycle time. So this was what we concluded then instead of estimates. What if we would use cycle time instead or in place of
estimations and try to focus
SPEAKER_02on this a bit more? So what do you see Maria here on this picture?
SPEAKER_03So I see a lot of dots. And as you say that for those that don't see, we have on one axis, we have the cycle time in days and on the other one, we have the calendar days. Yes. And then we have, this is actually, I think the only chart that you can somehow get in JIRA. It's the scatterplot, right? They have a similar chart where you see the dots reflect your user stories and we
SPEAKER_03can see how long, when they were finished and how long it took for them to get done, right?
SPEAKER_02Exactly. And so what you also have is like four lines here that are these percentiles. So you can see, for example, the 50th percentile means 50% of all the items were done in this many days or less. And the other 50% took longer than this amount. So here it would be six days. So this means if you start some item today, there is like a 50% chance that this item is done within the
next six days.
SPEAKER_02But there is also 50% chance that it takes no longer. So this is kind of your... risk level associated to get it done in six days, one single item. And also here you see those lines have different colors because the bigger risk,
SPEAKER_03the more highlighted, right? So red is like 50% risk and then you have the less risk, the more green it becomes.
SPEAKER_02Yes, exactly.
SPEAKER_03And here you have the legend so you can see which means what. And this is interesting. So how does this change the conversation about when will this be done?
SPEAKER_02Yes, so you can use these percentiles. I think often people use 85 or maybe 70th percentile. I think somebody started once with 85, but it's not really set in stone. So think about how risky can you be, right? Because even 70% is still... quite certain that you manage. So maybe think about using this. And in this example, 10 days is kind of the number where we get 70% of all our items done. So you can think about, A, is this fast enough?
SPEAKER_02Is it maybe too fast? Maybe we're optimizing too much just to also bring in, if you have some process that you can just deliver something every two months, maybe you don't need to be as fast, right? So you might be optimizing the wrong thing. Just to also look a bit from this angle, because usually it's just faster, faster, faster. But you can talk about this with your team. Would we be happy with this? What I often see is if you run, for example, a two-week sprint and your 70 percentile is 18 days,
SPEAKER_02that's already strange, for example, right? Because it means most likely you have to start before your sprint starts to get your items done in this time. So, I mean, again, I cannot judge. Maybe your sprints are too short, but more likely maybe you can think about how to get this number down.
SPEAKER_03Exactly. You are starting to talk about the SLE, which is like the service level expectation. That is a very... It's not... flow metric but it's a very important metric or tool to use when you want to establish how long it takes for you to deliver stuff and could you just explain a little for the sake of clarity because what I saw recently we had some conversations about SLOs and different things and do you count
the weekend do you
SPEAKER_03not so how does that work so if I work in a scrum and I have two weeks sprint, my SLE would be 15 days or 10 days. So if you could just explain a bit how that works.
SPEAKER_02So I would always use just regular calendar days because The whole idea is that you look back, right? How did you kind of perform with your team in the past? And then you can use this for predicting the future in a sense. So I would argue you had weekends in the past, so you also have weekends in future. I sure hope so.
SPEAKER_03Right. It doesn't work all the time, but that's also the beauty of those metrics. We just have it as it is in life, right? We don't try to say. That was a weekend, so we shouldn't count, shall we? Those conversations are out. They don't bring any value. Our life has weekends. We usually don't work on them. That's what we have. And then we are just free of those. We're removing waste as well, right?
SPEAKER_02Exactly. You don't need somebody that takes care. And we were jokingly saying at times, it's been like four or five years since we filled in an Excel spreadsheet where we track like who is off when because, well, people are sick, people are on vacation, there will be public holidays and so on. And if you look just back in your history, this happened in the past, so it will happen in the future. So you don't need to take any action there, which is the nice thing.
SPEAKER_03Okay, so you don't even measure that, but isn't it that, for example, there will be days that it's a bit different, like in the summer where people take more holidays than usual, or I would say that maybe August would be a bit like December, but not as much as February where there's no bank holidays and people typically don't take holidays. Isn't that like a different?
SPEAKER_02Well, you're not in Switzerland where people go skiing in February.
SPEAKER_03Right.
SPEAKER_02Well, I mean, I would say you should take this into account. It's a great example in the chart here because you could see it's actually December and January and you see towards the end of December a bit left of the center of the chart. There is a bit of a hole, right? Because most people were off during Christmas because this team most likely was mainly based in Europe where I think it's usually days off. in this period. So there are some items kind of on top that were getting done in this period, but you could see they aged a bit more.
SPEAKER_02But just take this into account when you plan, but you don't need to like overthink this, right? So there's maybe it's still good to have a human look at these things and interpret the data. So and this is why you don't want to maybe watch just the numbers, but visualizing this will give you clues. So you spot patterns, right? So you might see, hey, there's something here that is a bit blank that looks odd. And then you look at the date and maybe you find an explanation or You just ask the team, what are they seeing here is something strange,
which like the visuals can really help because it's quite simple what we're seeing, but then you can interpret and there's like often different interpretations.
SPEAKER_02And that's great kind of to involve your team. Don't just look at this in isolation, like trying to optimize without even asking the team. But another example might be, oh, sorry.
SPEAKER_03No, no, yeah, I agree because we can be the best people to know all about the metrics, but if we don't include the team and don't include their buy-in and also their understanding, because, you know, on the other hand, we also have this, what gets measured gets managed and then you start to game the system. But if you just show it as it is, not a blaming reality, but like, oh, what can we learn from it? Are our sprints, do our sprint make sense?
SPEAKER_03Do our user stories make sense? Maybe we need to split them in smaller. Maybe we need to do something like, right? There is this conversation that we can use. So just to come back and finish the one about SLE. So SLE is a great thing, great tool for us to be able to define how long it takes with everything that's included in our system, all the interruptions, everything that happens, not just the coding, how long it takes for us to deliver something. And then we can base it and then we can use it as a benchmark
to forecast as well, right?
SPEAKER_02Yes, for individual items. So if you want to just forecast when they will this bug that somebody just reported be done, you can use this or basically your cycle time data with the percentiles. Also, and I think this ties a bit into what you said before about gaming the system or smaller items. So one thing I always thought, it's great if we game this, because if it means we're bringing cycle time down in a somewhat controlled manner, and this is where I felt as a scrum master, I should make sure we're not taking numbers,
SPEAKER_02but we're actually kind of doing something that is meaningful to get the numbers down. That is a good improvement. So what we did in our team, for example, would be SLE is we want to get 85% of all items done in 10 days or less. And then we would look at the cycle time scatter plot, look at the percentile. See here right now it's a 12 days, so we have to improve a bit, right? So that might be okay over the last month. It may be explainable due to Christmas,
SPEAKER_02for example, no need to panic here, but just to, you can track this if you hold your commitment to this expectation. And what it helps us doing is we can replace the estimates, right? So instead of estimating how many points do you think that is, you can ask, will we get this done in 10 days or less? Like, is it possible? And usually what we did is there is like very clear yes. Then we don't need to have a further discussion.
SPEAKER_02If the team is confident, then no need. There is maybe like it could be doable, but might be tight. Then we may have another discussion about, okay, what do you need to get this done in 10 days? Like what if two people worked on it together, for example?
SPEAKER_03Exactly. So then there are also a lot of techniques, which we usually, when we teach the applying professional Kanban class, we explain a lot of techniques, what you can do to make this happen. to actually unblock the items. And there are a lot of things you can do to just improve the way you work, which means also improve kind of the health of the system, right? We don't want this big outliers like we have here because then they will
bring the whole cycle time for the whole system up if there are such a big outliers, right?
SPEAKER_01Exactly.
SPEAKER_03Okay. Let's see another one. So this one is scatterplot. As we see, those are like scattered balls scattered all around. The easiest explanation.
SPEAKER_02Exactly. And it's cycle time. So it means you basically see it for all the items that are done. So, and the other thing that you see on all the things that are done is like, this is the throughput. So what your throughput is, is how many items did you close or get to done in a certain period of time? So it can be per day, per week, per sprint, per month, per release, whatever you choose. normally visualize this is we look at on each day,
SPEAKER_02how much did we get done on this day over a certain period? So here you have again, the dates on the X axis at the bottom and how many items did we close each of this day? And here you can actually quite nicely see the Christmas break, right? So there is like a gap where you didn't get anything done, which is explainable. And you can somewhat spot the weekends in between as well, especially in December. Every few days you have like a two day where nothing was closed, which is a good sign for...
health of the team that they didn't feel like they needed to work on weekends.
SPEAKER_03Definitely the good culture of the company as well. And then we have some outliers, right?
SPEAKER_02So you have outliers kind of in both directions. Like the obvious ones is where you didn't close anything, but even outliers on days where it's like we have four or more items closed on the same day while normally it's more one or two that is interesting right because like what happened there was one day where we closed seven items like why did this happen and if you look at the whole thing there is like almost two weeks i think where we closed one item and then we have like quite a lot of items closed at the same time.
SPEAKER_02So that's quite interesting. Wondering what happened there was systems down was, I don't know, a QA engineer not around. So things were stuck somewhere. And in our, like, we will not dive into probabilistic forecasting, at least not today, right? But for a good forecast, you don't want these outliers also not kind of upwards. So you may think because seven items one day, that's great, which Yeah, it's not bad. The question is more, why did we not kind of better flow before?
SPEAKER_02Like, why were we waiting that long? And this is a pattern you like in certain scrum teams, you can see when they start sprints and when they end because there's like nothing closed for one and a half weeks and then everything gets closed in the end, kind of rushed in. And then again, you don't see things getting closed again. And I think what we're aiming is more continuous flow rather than the rush towards the end of the sprint, for example.
SPEAKER_03Yeah, true. And I remember also to see not only that, but also, for example, there will be a sprint that's not many things closed, but a lot of things open. And then the next sprint suddenly so many things closed because they closed the previous, the spillovers, right? And then again, there will be less because we started opening new ones. And then again, another sprint. And then you would have like those And this is so many patterns we can see in those teams because we never look at, okay, how we can improve the flow and how we can actually make our system.
SPEAKER_03I'm like obsessed with this health of system. In Scrum, we are never taught about this. And then you learn Kanban and then you learn how important it is to understand what we can do to ensure that health of the system. For that, I also like to use a lot of this SLE. Because we define, we should close items in 10 days or less. That's the most items, the 85%, right? And then we can aim for that. And that can be the very easy discussion of how we should split items.
SPEAKER_03Will it take more than 10 days? We should split it. Is it like very small? Then it's okay. We will keep closing items every day, right? And that's where we want to go. And you don't need to worry so much about that they are not equal. It's just not to break the threshold that we put for ourselves, right?
SPEAKER_02Exactly. And maybe just a link to throughput and predictability. Like one thing is, let's say you look at the throughput over 30 days, if you just have a number, not the visual number. You might say we closed 30 items in this 30 days. It doesn't give you more input. If you now see this run chart, you can see, is it evenly distributed or is it kind of, you had four days where you closed all those items and the other days nothing was closed. And that's quite a different conversation you're having.
SPEAKER_02Just theoretically, like a perfectly predictable team would close exactly the same amount of items every day. So for example, you close one item every single day within 30 days. And the very unpredictable team would close 30 days on one single day, right? Those are the two extremes. Most likely you don't have them because again, weekends and so on. But our goal to link back to the beginning and my story was more predictability. So if you look at this is How can we get the large bars down and limit the workdays where
we have zeros, right? So kind of how can we even it out more and then we will have a more predictable system.
SPEAKER_02And I would say one way to do that is, as you mentioned already, kind of get your cycle time under control. So trying to lower this, look at your percentiles there, really discuss it with your team and define a meaningful SLE. Like if you're right now at 25 days, it doesn't help if you say it should be three days because probably that's a bit stretched to go there. Even if it may be your long-term goal, but kind of setting small steps where you can reflect on like
on a certain cadence,
SPEAKER_02are we getting better as well?
SPEAKER_03And this also shows how wrong we can be if we only talk averages.
SPEAKER_01Yes.
SPEAKER_03Yeah, right? Exactly. It's like forbidden. If you do Kanban, you're forbidden to use average as anything. And I'm just laughing now, but there is a book that's called Flow of Averages, and you can check that. I love this line from it that it says, plans based on average assumptions are wrong on average. Because that would happen, what you say. And we so many times not only use estimates that we know
already are not really
SPEAKER_03reflect how long it takes to do something. And somehow we decided to decouple it from the long, how long it takes, right? So create this very philosophical discussions of humanity. You know, in the end, you have to tell when it will be done. But no, in the meantime, we will just focus on thinking how it's a complexity and not time. And it's like your head explodes and you still are no closer to really predict something.
SPEAKER_03And then you, on top of that, use an average for it. Yeah. what can go wrong right exactly like i don't know we probably don't have time to go too deep into this but more or less you could assume that maybe your average is as good or even a bit worse than like your 50 chance right so it's well but you communicate it as this is when we will be done and not there is a 50 chance that then it will be done that would already change the conversation i think but
SPEAKER_02Yeah, it's a bit the issue of using averages.
SPEAKER_03At least you give that percentage of risk. And when we give the estimate, and we say every time, like, this is just an estimate. This is just the hands-on coding. It's still, you just turn around and it's becoming a deadline for the team, right? So it is funny. But as you mentioned, we don't have much time, but I would love to just go to see the the work item age and how you have a chart for that and why
it's important because that's like the work item age is a flow metric that's least talked about and probably the most important one and somehow the message doesn't get there so we will skip over work in progress so that's for another time which is also important
SPEAKER_02okay of course all of them are Work item age is my favorite metric and we have a chart for it. But I think you should see your age in whatever tool you're using in kind of if you're using Jira with boards, for example, or Azure DevOps with a board or even a physical. bored, if you're all in the office, I think that's where you should see your age. So as soon as you start working on an item, like that's my favorite way to visualize it.
SPEAKER_02So I'm encouraging you exactly that. If for example, you're doing dailies or whatever you're calling it, that you look at this and you just look at the oldest item and think about How can we close this today? Who is needed? What is needed? And how can we kind of progress with this one? And if this is the only thing you talk about in your daily, that is time well spent.
SPEAKER_03Oh, you're revolutionizing the daily now.
SPEAKER_02So like there is this joke that you can, every time you start an item, you put the banana peel on that item, right? And then you see how it ages and it doesn't age or it doesn't look good. It probably doesn't smell good over time.
SPEAKER_03I love this one. Yeah, makes sense. So work item age is basically the time that this elapsed since the work got started until the moment we look at it. And those are our outliers, right? Those are the moments where we see, oh my God, this is already getting out of hand and it will increase the cycle time for the whole system. That's why we also don't love the columns that are like blocked column,
right?
SPEAKER_03Because it's like a trash bin a bit. We put something in the block column and our brain is great in just... It's over there. We don't have to. What do we don't need? So it's there. We don't have to look at it and worry about it. And then you go and you have so many items there. And some of them, it's like, do you even need to work on them anymore if nobody asks?
SPEAKER_02Yeah. Yeah, it's funny when you look at this data and you have items that are in progress since 1,215 days. And it's like, if nobody asks about it, I guess we don't have to spend more time on it. But who am I?
SPEAKER_03Exactly. But we still spend time. We have to spend time asking, spend time doing something about it. So it is taking from our time. And we are not using this time to bring value to the customer. So it's basically wasted time. So, yeah, and here we see again the calendar days and the time the issues spent in progress.
SPEAKER_02Yes. So there are other tools like there. You also see maybe your workflow, like the different columns here. It's really just in total, how long has it been in progress? But again, if you have the way, and I think there are ways for Jira and Azure DevOps to visualize it on your cards, that's usually the best because you should really look at this one every day and to link back to the SLE. So if you have an SLE, let's say of 12 days, What I would recommend is once you're getting closer to that SLE, color it orange.
SPEAKER_02Let's say if you hit nine days, you're quite close already to like that it takes longer than your SLE. So you should really focus on this. And once you are at or over your SLE, then maybe it's becoming red or whatever color you prefer. Because this is like, okay, what are we doing with this item? How can we close it? What is stopping us from closing it? Because we're... breaking our commitment in a way so like and this is really then the goal that Like this helps you getting into the flow, right?
SPEAKER_02And if somebody is working on an item that is two days in progress, maybe we can just ignore that for a day or two. Like that may not be ideal, but it's still better because we can afford the time like that this item waits a bit. And instead that person may help to get the other thing to the finish line or over the finish line. And that's really a great conversation starter. And it gets you out of this Yesterday I worked on stuff and today I work on stuff and I
also have meetings.
SPEAKER_02So yeah, whatever. And getting to actionable discussions and making it useful, right? For the team members as well.
SPEAKER_03Yes. And I love this part because it's not like, oh, we're just selling you. And I love in Spain, they have the saying of I'm selling you the motto. You know, like just trying to sell something for you. So we're not just selling you the magical solution that if you use the flow metric, suddenly your life will be so much easier. No. We... show you the different way but we also show you techniques and questions and ways
that you can ask yourself every day how can i improve my flow and improve my system so that i can really trust the metrics that i see and they can become a good and to
SPEAKER_03help to get where i want and to my commitments as well so it's not just oh you know like we get caught up on this perfect estimate one day one day in our life we'll get the perfect estimate no that's that's the fairy tale here it's okay Hands on, you have this system. We give you all the tools and you please go manage the work, right? And I love that saying of manage the work and let people self-organize around it.
SPEAKER_03If you teach them well, if you educate them how to use the metrics that they see, they can make best decisions on their own. And you don't need to be the manager that just says there and like, why aren't you tackling that big item each item?
SPEAKER_02And this is cool because like, let's say you're doing retrospectives like in Scrum or you have some other improvement meetings and somebody has an idea. This is an hypothesis, right? And now you have the metrics so you can say, oh, we would like to decrease our cycle time. Let's try to do more programming, right? Maybe that brings it down and maybe that works, maybe it doesn't, but you have the data now. So if you try it for two weeks, four weeks, and then you look at your metrics again, you can confirm your hypothesis or maybe it didn't change anything.
SPEAKER_02And then you can say, well, we tried and sometimes things don't work out, which is perfectly fine. But at least you have some data to like look back, like did our experiments work? And it's not just like that feeling, but really concrete data to base your decisions on which It's nice, like doesn't mean we should ignore gut feeling completely, but there is some combination of gut feeling and does the data also support my gut feeling or am I just seeing what I want to see now because I don't know, I like that way more and I want it to be better,
SPEAKER_02even though it may not be.
SPEAKER_03Definitely, because what you say and what Colleen said on the latest episode, she said that we will pass through those stages of grief.
SPEAKER_01Yeah. Yes. You see the metrics and at the beginning you will probably not like them because
SPEAKER_03that's not what we wish for. And that's not what we tell the client. And then we have to like undo what we said because sorry, from what we see, it will not be as fast as we thought. But then you get all those tools and then you can base and make the experiment. As you say, like add your gut feeling, use the tools, see if it works. If it didn't, well, next time we try again. until we get there. And it will never be perfect as well. That's not what we aim for. It's just to, first of all, be more predictable.
But second of all, as well, give this part of risk that there will always be risk.
SPEAKER_03It's unpredictable, really. It's uncertain. The work we do is very uncertain. And there's a lot of interruptions and things that really influence how we do. And it will never be perfect. But at least it's Least wrong. I don't know if that's a good finish line that we will never be perfect but at least we we can be more I think really reliable or predictable right somehow yeah I
would say so yes and yeah again I think it's it's not about perfection because if you're suddenly perfect then most likely somebody's gaming the metrics or or the
SPEAKER_02tool like what some people ask is how can I exclude outliers it's like Yeah, you don't. That's exactly the point that you look at outliers and think about them. Don't try to fake a chart here because then it will not be useful. And I think this is the hard part that maybe for a scrum master or team coach or whatever, like this is also where you can really help the team and deliver value to your team and organization, right? Thinking about how can we bring these numbers down or up if it's throughput,
SPEAKER_02for example, or what can we do with it? Yeah, then what would we need to do to be able to do probabilistic forecasting in a more accurate way? But that's kind of the hook for maybe another conversation in the future.
SPEAKER_03Yeah, thank you so much. This really helps. I think we are doing like a small tutorial for, okay, we have the scrum team and now we want to start looking at the metrics. Where do we start? This is what we already did. And I think it would really work to have another session and talk about probabilistic forecasting and Monte Carlo and how we can use that to predict and show forecasting and this way we have like the whole site i think that
will be that was my journey at least as well and then you you never really look back from there and you can still do scrum or you can choose to to not do it anymore that's up to you but i think whatever you're doing like if you're in
SPEAKER_02software development these metrics can really be a game changer and Like having a way to visualize them in one way or another and look at them with your team. I highly recommend this to everybody that works in this space.
SPEAKER_03And don't forget that we both are pro Kanban trainers. We are happy to host a training in your company. Actually, we could do it together, right?
SPEAKER_01Yes, exactly.
SPEAKER_03It would be really cool because it really is a part of this... like liberation that we don't have to try really hard. We just need to understand a few basic rules and everything flows. And from there, you just try to improve the flow. You focus on one thing and not trying to see how best to do the poker planning. So I'm really hoping it's like, let's liberate people from the estimation mess.
Thank you so much for joining today and for taking the time and explaining your tools.
SPEAKER_03I will link in the description the link to your metrics, how we can leverage that and everybody can use them. And yeah, let's see you on the next episode. We already said it.
SPEAKER_02Yeah. Thanks for having me. Looking forward to this already.
If you’ve ever heard terms like DevOps, SLOs, SRE, or platform engineering and thought, “Wait, what are these exactly?” - you’re not alone. That’s why I’m excited to share this new episode of Agile State of Mind with...
We talk endlessly about technical debt - the shortcuts in code that eventually come back to bite us. But there's another kind of debt accumulating in your organization right now, silently strangling productivity and...
"Planning isn’t about predicting the future. It’s about preparing for it." Most teams still try to plan with a single number: “We’ll be done in 3 sprints.” But real work doesn’t behave like that. Some work flies, some...
Are estimates the comfort blanket of the corporate world? Like trying to predict the weather five days from now while standing in a hurricane. But hey, at least you feel in control while the roof flies off. I recently...
Tech teams often find themselves trapped in an endless estimation cycle, trying to forecast delivery dates with the precision of assembling a German car! “Shall we re-estimate the spillover? Or shall we close part of...