Tech teams often find themselves trapped in an endless estimation cycle, trying to forecast delivery dates with the precision of assembling a German car! “Shall we re-estimate the spillover? Or shall we close part of the story and open a new one for the new Sprint?” Those are the questions on the Product Owners minds during the Sprint Planning.
They are on a neverending quest to find the perfect estimate as if it were the Holy Grail
“One day we’ll find the perfect estimate and live happily ever after.”
Yet, as Colleen Johnson, CEO of ProKanban.org, points out, this obsession with estimating is often a waste of time. Instead, she advocates for a shift towards flow metrics - simple yet powerful indicators that help teams understand and improve how work moves through their system.
Chapters:
00:00 Introduction to Kanban and Flow Metrics 03:39 Understanding Flow Metrics in Everyday Life 06:02 The Importance of Work Item Age 08:04 Challenges in Estimation and Forecasting 10:15 Real-Life Examples of Work Item Age 13:02 Risk Management in Project Timelines 15:49 Changing Conversations Around Estimates 18:38 Flow Metrics Stages of Grief 21:32 Improving Communication with Stakeholders 24:39 Conclusion
Why Flow Metrics Matter
Flow metrics offer a pragmatic approach to tracking value delivery. Rather than endlessly debating over the estimates, teams can rely on four key metrics:
* Throughput - How many items are completed over a period.
* Cycle Time - How long it takes for a work item to move from start to finish.
* Work Item Age - How long an item has been in progress.
* Work In Progress (WIP) - The number of active work items.
These metrics already exist in any system - they don’t require complex calculations or additional tracking efforts. By making them visible, teams can shift from speculation to informed decision-making.
The Work Item Age Blind Spot
One of the most overlooked yet crucial flow metrics is work item age - how long something has been in progress. Many teams neglect it, assuming that if work gets delayed, it’s an anomaly.
But as Colleen points out, delays are not exceptions; they are part of the system. If a feature takes 30 days to develop but sits for another 200 days due to dependencies, that’s the reality of how work flows. Understanding work item age helps teams prioritize what to complete first and avoid accumulating stale work.
A simple real-world analogy is food expiration dates. When milk nears its expiration, you decide whether to drink it or not. Similarly, when work sits in progress too long, it should trigger a discussion: Why is this still here? What’s stopping it from getting done?
The Estimation Trap and the Illusion of Precision
Traditional estimation methods often focus on breaking work into smaller tasks, assigning points or hours, and refining these numbers. Yet, despite all this effort, work still takes longer than expected. That’s because estimations usually account only for development time, ignoring factors like meetings, interruptions, dependencies, and external approvals.
Instead of striving for a perfect estimate, teams should embrace probability-based forecasting using historical data. If past cycle times indicate that most tasks are completed within 15 days or less, this data is far more reliable than an estimate pulled from thin air. It also allows teams to provide stakeholders with a realistic likelihood of completion, rather than a rigid deadline doomed to slip.
How Flow Metrics Shift Conversations
When teams start using flow metrics, it changes how they communicate about delivery. Instead of executives demanding a fixed date and teams scrambling to commit, conversations become about risk and probability.
For example, instead of saying, “The bathroom renovation will be done by March 31st,” you’d say
“Based on past data, there’s an 85% chance it will be done by March 31st. However, if issues arise, that likelihood may drop.”
This framing highlights the % of risk and allows for proactive decision-making. You can talk about adjusting scope or prioritizing critical tasks, rather than waiting for a crisis when the deadline inevitably slips.
Overcoming the Stages of Flow Metrics Resistance
When organizations first confront their real delivery times, they often go through five stages of grief.
Flow Metrics Stages of Grief by Colleen
1. Denial - “This data must be wrong.”
2. Resistance - “The work is wrong.”
3. Refinement - “We need to clean this up.”
4. Acceptance - “Oh. This is actually useful.”
5. Action - “Let’s use this to improve.”
Many teams try to “sanitize” their data, ignoring delays caused by external factors. Colleen emphasizes that all delays matter because they impact how long customers wait for value. Recognizing and addressing these realities is the first step toward meaningful change.
The Path to Predictable Delivery
Flow metrics provide a clear, actionable way to manage work without falling into the estimation rabbit hole. By tracking and acting on data that already exists, teams can improve delivery times, reduce uncertainty, and build trust with stakeholders.
Instead of promising unrealistic deadlines, they can communicate risk and negotiate trade-offs, leading to better planning and fewer last-minute surprises.
The real magic of flow metrics isn’t just in understanding work better - it’s in changing behaviors to make workflow faster. And that’s a conversation every Agile team needs to start having.
Looking to dive deeper into flow metrics? Check out the latest tools and resources at ProKanban.org and start making data-driven decisions today. You can also grab a copy of The Kanban Pocket Guide for more tips from Colleen Johnson and Prateek Singh.
Want to know more about Kanban and Flow Metrics? Contact me to run Applying Professional Kanban Training in your company:
This is a public episode. If you'd like to discuss this with other subscribers or get access to bonus episodes, visit mariachec.substack.com/subscribe
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Whether you're doing it in points or hours, I don't care what estimate process you're using.
SPEAKER_02I think it's all a waste of time. And so full metrics are really intended to be kind of the simplest approach to understanding how value is moving through your system. There are four key flow metrics. It's throughput, cycle time, work item age, and work in progress. We have a tendency to try to dismiss certain parts of our data to be like, oh, well, that's an anomaly because that had dependencies. Well, if your system is set up in a way where work is getting stuck in the system because it's done in development, but can't be deployed because of some other kind of dependency, whether that's an internal or external dependency,
SPEAKER_02that is the reality of the system that you work in. So that data is still valid, right? And it's still taking you more than 200 days to deploy a feature. even though it might only take you 30 days to do the development work, right? How long have we been making an investment on this work without seeing a return on that investment? And so it's kind of shifting the way that we're talking about work item age to kind of that, the monetary side of it, right? The cost of doing business and the cost of sitting on that undeployed work. A lot of what we're trying to do when we talk about flow
metrics from a Kanban
SPEAKER_02perspective is understand what action we should take based on the data. And so we're trying to simplify that for the teams, make that data visible, but then also help it drive better decision making every day.
SPEAKER_00So I would like to talk about the flow metrics that Pragmatic implementation of Kanban in how we can leverage it with our teams, how we can help get things done and use the probability it provides to say when it will be done, the most important question of our work lives. Hello everyone, it's Maria and we are back in the Agile State of Mind podcast and today I have with me Colleen, Colleen Johnson. Hi Colleen.
SPEAKER_02Hi Maria, hi everyone.
SPEAKER_00It's lovely to see you. Colleen, if you didn't know Colleen, she's a CEO of ProKanban.org. And a co-author of the Kanban Packet Guide. We work together in Pro Kanban. Since I'm the Pro Kanban trainer, it would make you my boss, right? I don't know about that. Yeah, I would never think about Colleen as a boss. It's like a sort of oxymoron. Yeah, but we do collaborate together. And we met last year for the first time live in Dallas on Agile 2024.
And I loved your talk about 12 ways of how flow metrics show up in everyday life. So I really like how Colleen puts everything into pragmatic everyday use.
SPEAKER_00So we feel some parts of Kanban or flow metrics are kind of enchanted. And this is how we can make it. No, no, no. Let's see how we. Anyway, use it in everyday life and how we can make it easy and accessible. If you want to learn more about Kanban and the way we talk about Kanban, because this is also the prokanban.org and the Kanban guide. And I really like the approach. So I will just make like a short introduction because for me, it's very simple.
SPEAKER_00It doesn't have many rules. It's more about how to make the flow consistent. go in a more optimal way through the workflow. So I like to make things simple and Kanban Guide makes Kanban really simple. You can learn more about it if you go to prokanban.org and also if you grab a copy of the Kanban Packet Guide. It's available on Amazon and you can have like a real book now. I would like to start from what are flow metrics and why are
they so important?
SPEAKER_02Awesome. Yeah, this is a great topic, and I think it's an important one. And what you said is so true, Maria. I think so many organizations get really caught up in, like, they have maybe too much data or so much data they don't know how to use it or they don't believe it. And so full metrics are really intended to be kind of the simplest approach to understanding how value is moving through your system. There are four key flow metrics. It's throughput, cycle time, work item age, and work in progress. And they are all pretty simple metrics. You probably have them all now, which is also really beneficial, right?
You don't have to go through this process of trying to baseline your data or gather new data when you're starting this process of looking at your flow metrics because
SPEAKER_02it's data that already exists for how you're working. Now, all of that being said, where the idea came from about the 12, you know, your question about where did the 12 ways flow metrics show up in everyday life? So if you're looking at things like work item age and your standup, hopefully that's helping you figure out as a team, what thing is the highest priority item for us to organize around? And in most cases, hopefully it's the oldest item on your board instead of going to pull something new, right? That's the kind of behaviors we're looking for.
SPEAKER_00Yeah, I would like to stop you for a moment because work item age is like the metric that when you learn about Kanban and you learn about the flow, you understand it's probably the most important metric. Yet, I don't think many people know it exists and many people know what it means. And I was actually, it was today, I was asked by a team to come and talk with them about their workflow because they are not
SPEAKER_00typical team. It's not a development team, it's a technical knowledge team. And we were talking and I was talking to them, you know, you could think about the sprint goal, what's more important, because they were asking me what we should refine first, you know, like what should be the most important, how do we even prioritize? And I'm like, well, you probably have something that has a day, due date or, you know, and I was trying to do the same thing I usually do with the teams, like, oh, if this is your sprint goal, that's probably the most important thing, but why do you even do the rest?
SPEAKER_00And then they were like, yeah, but everything is important. And I'm like, happy, great. Everything you do, you actually want to finish. So maybe you should look at what spends more time in being in progress, right? Maybe your prioritization should go towards... Is there something that spends here, sits here for a long time and nobody pays attention? And it's actually something that if we finish it and we start finishing those items
SPEAKER_00that spend already a long time in our work, in our work in progress, in our system, then we could really see the change how quicker and more productive our work is, right? So... And they were so happy. They were like, oh, we never thought about this. And do you see that as well? How is it possible that the most important metric is the metric that we never look at?
SPEAKER_02Well, I think there's a couple of reasons, right? I think it's easy to, you know, like I was in a conversation yesterday, for example, where somebody asked about, we were looking at work item age of features. And for this particular board, it had, they had over 50 features in development.
SPEAKER_00And,
SPEAKER_02you know, I started asking some questions about like, okay, well, let's, let's take a peek at how old each of the features are that are currently in development. And there was a couple that were over 200 days old. And for this particular organization, they were doing the quarterly planning cycle where they were figuring out what features to pull in every quarter. And I was like, well, it looks like there's stuff in here that's more than a quarter old just in the development column. So let's talk about what's happening with those. Why are they stuck? And when we started digging into it, it was like, well, there's dependencies and there's things they're waiting on.
SPEAKER_02And the first question I got was, should we move these to like a holding column or a waiting on something column? And I was like, well, no, because... You're still investing in those things and they're still not deployed. Right. They're still not delivering any value to your customers or giving you any feedback about what the customers like or don't like about what you're working on. And so I think that I think for a lot of organizations, it's like, well, we're trying to track track active time or we're trying to track how, you know, this one piece works. contributes to that overall cycle time.
SPEAKER_00Right. And then also there is this part that you mentioned before that in the end, all those metrics, they're very easy to have. You don't have to do anything like any calculation, mathematical to get them. You can look at the past work and get those metrics from that work, right? But if you have those items that sit there forever, They won't be really important, like they won't give you the real value because it will say that you,
SPEAKER_00on average, on average, we don't want to talk about averages, but you seem, you can get to like 200 days. You don't want to go to your product manager and say, hey, we do stuff in 200 days or less.
SPEAKER_02For example, that's probably more a symptom of the system than of the time it takes to do the work. So that's a great example where I think that there's an urge, I think, for a lot of organizations to clean the data and be like, oh, well, that should only be 30. We only spent 30 days developing it. It just got stuck for 150 days waiting for this dependency. But that's the reality of the system that you work in. That time is still real time where a customer is waiting for that feature. I think, you know,
we talked a little bit about that post I put on LinkedIn of like the stages of grief,
SPEAKER_02flow metric stages of grief, but it really is true. Like there's this first reaction when we start looking at the data to be like, oh, that data is not right because of all these reasons. And then, oh, maybe those work items aren't right because of all these reasons, right? But those are the reality of the system that you work in. And like you said, all of that data that you have right now is indicative of maybe delays in a system that could be improved or breaking the work down in a different way that could be improved. But it's the reality of how long it's taking you to deliver.
SPEAKER_02And sometimes that number is really ugly. Yeah.
SPEAKER_00Yeah, that's definitely true. I have here a few topics that came to my mind to dive into. So one is from the everyday metrics, if you could give an everyday example of a work item age. And second would be to talk about the stages of grief and how really... How many there are circumstances and everything that is surrounding the team, the meetings they have, everything of that has to be taken into account when you want
to give a forecast.
SPEAKER_00And I think so many times we just... We just think, oh, well, I will imagine that I just do this thing and I have all the time in the world. And then that's the forecast that we usually give. So that's the other one. But yeah, let's start with how would you compare this work item age to some real life examples?
SPEAKER_02Yeah. Well, so I think there's a couple. And I think like we were talking about with that particular talk of how flow metrics show up in everyday life, it's more than just the metric itself. It's understanding what decision you make based on having that data available to you. One of the examples we used in Dallas was expiration dates on food, right? So you have an idea of how many days a jug of milk has been in your fridge. And when it's nearing that expiration date, you're going to make a decision about whether or not you're willing to How much risk is associated with how old this milk is?
SPEAKER_02So that's kind of one that I think we make decisions about every day. One that I think is kind of an interesting driver of behavior or driver of action is looking at the time that something's been in process. If you have drive-thrus at Starbucks or drive-thrus at fast food restaurants, you may not be able to see this from your car. Sometimes you can, but they have a timer inside of the drive-thru windows that are telling them how long a car has been in the queue. And they have targets that they have to hit about how long that
car takes to get
SPEAKER_02through the drive-thru process. And if it exceeds that time limit, This is an SLE, right? We're talking SLEs now. They can see it starts making noise and like flashing behind the thing that that car has been in the drive-through for too long. So that's driving behavior on their part, right? They probably have some kind of metrics and drivers that they have to report to on what's causing those delays internally. But that's a way that they're saying that this car has been in process in our queue for too long without receiving their food and being able to
drive away and then
SPEAKER_02serve the next customer. That's another example of where that work item age is driving behavior because there's a kind of a threshold in place, that service level expectation of how long things should take. And at some point, maybe that work item age is exceeding that threshold. So that's another place where that's driving some action. But our goal here with all four flow metrics is really how are they helping drive action for both the teams and decision making, whether that's prioritizing capacity, prioritizing new work,
or understanding what to do next.
SPEAKER_00And also how they are connected to all the other metrics, right? So the longer an item stays in our queue, the longer the queue will take, the little law. And then we also have the part of, okay, is this the cycle time? Is this the SLE that you mentioned? We can say with some probability that items will take this amount of time in our process. And this is very helpful for forecasting. If we start having these items that are getting blocked or
something happens to
SPEAKER_00them and they stay in our process, creating a long queue, then we are directly impacting all the other items. And the predictions that we probably already said that this something will take 20 days or less and we are still there, right? So it is, for me, very interesting how everything is connected. So if you spend too much time in this queue, then everybody else will be impacted.
SPEAKER_00So all your items will be impacted. And this is very important to understand. And it also, when I'm thinking about it, as you said, it's like, yeah, we have the expiry date already. On food, that's the SLE, that's how long we should... It's also sometimes it says best before, right? It's like, it's best that you eat it before this date. It's best that you finish it before this date, right?
SPEAKER_00Then our process is stable because I think... We don't understand many times how important it is that the system is stable and that we don't get to those, oh, suddenly something takes very long and it will mess up all the metrics and we will not. It will be hard to recover from there. So I was talking to the teams as well. And because we have this big problem of when it will be done and we track in JIRA, you can track the GA date or the due date,
SPEAKER_00whatever you want to track. And then you can see how suddenly two weeks before the date, the date gets moved, gets moved, and then it gets moved. And then it's like, until we never know. Whenever we have conversations around it, it's all about this perfect estimate. Like, oh, one day... we will know the estimate will be perfect. And we focus on getting to this perfect estimate. So we will probably need to, maybe those story points is getting better.
SPEAKER_00Maybe we should use not Fibonacci. Now we will use the normal. Maybe we use ours, you know. And it's sometimes I feel so, it's like a useless conversation. Totally. Yeah. So much time and many times we are asked, right? Like, how can we get, how can we estimate better? Right. it's all wrong.
SPEAKER_02It is, it is. And we're spending energy kind of on the wrong part of the conversation. I think when we're looking at that estimating, whether you're doing it in points or hours, I really like, I don't care what estimate process you're using. I think it's all a waste of time. Um, because I think you're spending so much time trying to discuss and, and, and determine how you're going to do the work in order to provide that estimate without just getting in there and getting your hands dirty in the code to figure out what you need to do. And, um, And so that's taking time, right? All of that's taking time away from doing the actual work.
SPEAKER_02But here's the other part of it. Nobody's trying to give shitty estimates. Everybody's really trying to do their best job of giving the best estimate that they can come up with. But we're all thinking about the part that we're contributing and our hands on keyboard. So if I tell you that this piece of work is going to take me two days, I'm thinking about the time that I need to sit here and code is going to take me two days worth of work. But I'm not factoring in meetings and sick time and all the bugs that pop up and all the other things in my system that are going to contribute to that two-day
SPEAKER_02estimate turning into a four-day estimate. But it really might be two days of work. And that might be the perfect, precise estimate for that particular work item. But all the other things are going to make that into four days or six days or whatever when it needs to move from point A to point B through our process. And that's why using that past data becomes so important. It already reflects all of those things. If I'm a team that deals with a high amount of interrupt driven work or production support tickets, that's reflected in my cycle time and throughput already.
Or if I'm a team where maybe we're constantly getting pulled off in different
SPEAKER_02things or we're getting pulled into estimation meetings, right? Or we're trying to do architecture for a future project. And that's pulling my time away from doing development work. That's all going to be reflected in my cycle time and throughput from the past. And so that's where using that past data as a way to predict the future becomes far more accurate. And then we want to make sure that we're continuously re-forecasting those things as new data is coming in. And you know what? You have new data every day. Did I get something done? Did I not get something done? Every day is a new data point that you can start to blend to
that forecast.
SPEAKER_00Yeah. And so many examples come to my mind when I'm thinking about it. And one recent example is when, because I'm doing renovation of my house and now I am on this other side. I am this customer that comes and I'm like, I'm just redoing the bathroom. Can you tell me an estimate? And, you know, it's like, you made, you did so many bathrooms. Come on. You know how to do it. You don't need to see my house. And then you start working and then you, they scrapped all the things from the bathroom and they saw
that the wall was super wet.
SPEAKER_00That's not something that happens on every house, right? It is my typical case. And given this, we have to rethink and do the new forecast because now there's something that we uncovered or, you know, it was raining for many days, they couldn't come, something happened with the car. So... I think that what you said is just so true that we have this context and the circumstances that we are in and we cannot take the work out of
them and just say
SPEAKER_00in this perfect world, mathematically speaking, where everything is perfect, we don't have any... Anything that's influencing that calculation, this is what it's going to take, right? That's why looking at the past data, and for me, it's also so liberating because looking at the past data, you don't really have to do any of this, like stretching your thinking hard. If it's a five or it's an eight, right? You just look at the past data and you see,
SPEAKER_00okay, within all the circumstances, all the different things and new... requests that come all the time, we can say we have this SLE, right? This cycle time or we can do something. And then we also can work on the levels of risk that we want to take when it comes to forecasting. Could you elaborate a little bit about that? Well, yeah.
SPEAKER_02And let's go back to your bathroom example here. So I think what often happens... is what you said right we just keep changing the date every two weeks something else happens there's some other piece where now your contractor is going to come and say because of the water in the wall it's going to be two weeks later and because i couldn't come for two days because now this overlapped with a different project that i was supposed to start now it's going to be two weeks later than that A lot of times what happens when our default is to always change the date is we take the conversation about options off the table. So if we go back to your bathroom,
let's say you have guests coming, right? Your guests are coming at the end of March and now there's water that's discovered
SPEAKER_02in your wall, but you need that bathroom back before your guests come. So let's talk about what options we have. Maybe you have to cut back on the tile design. Maybe you have to... Skip painting so that the bathroom is usable for your guests, right? But now you can have a conversation about what the options are instead of the only option being you can't have your bathroom back for two weeks. And so when we think about risk and how risk plays into this conversation, that's really what we want to start to focus on. So if there's an 85% chance that you get your bathroom back at
the end of March, And now I come to you and say there's a 60% chance you can start to have a conversation here about what things could we do or could we change that might give
SPEAKER_02me the option to have my bathroom back in usable before my guests come. So that's really where all of those things start to tie together, where instead of it being one date with 100% certainty that we're going to have your bathroom done on this specific date, we want to talk in terms of the likelihood. What's the likelihood of hitting that date? And as new information comes to us, Is that likelihood increasing or decreasing so that we can make different decisions about how we're working and what we're working on?
SPEAKER_00And that's great. And because this also changes the way we talk about it, the conversation changes, right? We suddenly talk about, hey, we know that we can do this with 85%. So we already give the risk, like there is 15% risk that we will not. be able to do it within the timeframe that we gave, which means we will be updating you constantly and then you will be able to make
SPEAKER_00some decisions, to take decisions. And do you, how is this conversation usually in practice? So my question is, okay, you go, you know, from the moment of, hey, we will have this deadline and you have this deadline, you have to do it, I don't care, to Hello, we are now talking about risk and we will tell you how, like, I think it gives the team and the people responsible for giving
those estimates so
SPEAKER_00much more tools and ways to communicate in like nonviolent communication. Yeah. Like you really have to, you don't have to just shout at them like, we cannot do it. Or, you know, it's also very violent in a way when you say yes, yes, yes, yes. And then you know it won't be a yes, but you just prevent the fight. Like the fight will happen later. Let's live carpe diem we are in today. Today I'm not getting this fight. Yeah. How do you see those conversations change and especially how
those executive people
SPEAKER_00that are expecting a date react when they hear about the risks? Well, I think the good part is the conversations that come out of that, right?
SPEAKER_02Like I said, I think, you know, if we go back to the beginning of our conversation here about flow metrics driving behavior and driving action, that's exactly what happens when we start talking in terms of risk, right? And so if we know now that there's a 60% chance of having the bathroom done before March 31st, we can weigh different options. And that's often not part of the conversation with stakeholders, right? It is usually just changing the date. And one of the things I think I see the most often when we start communicating in terms of risk is what happened,
SPEAKER_02right? Why did the percentage go down or why did our likelihood decrease? And a lot of times it's because they were told to start work on something else, right? So WIP increases and now our likelihood of hitting that original target starts to tank. Our risk is increasing. And that usually drives a really important conversation with stakeholders about what's happening. Like you said, how are all of these connected, right? So we went from 85% likelihood down to 60% likelihood because we started work on another feature that you said was really important for us to start on.
Now that's decreasing our likelihood of hitting this date for this original feature
SPEAKER_02that we were working on. So I think the big thing here is that it starts to drive discussion about the patterns and the behaviors that are contributing to the risk increasing or decreasing, and then gives you a really solid conversation around what action to take to improve that. All of these things are kind of about awareness and how do we have a better conversation sooner? And I think that this is a great tool, especially with stakeholders. If you're having a hard time, you know, selling anybody on the idea of WIP limits,
SPEAKER_02which I think is a very hard thing to sell to most organizations, having a conversation about risk and dates and the impact then on what those decisions are doing to that likelihood is a better place to start.
SPEAKER_00Okay. Yeah, I have, before we go, because we are coming to the end, I have two thoughts about it, what you just said. So first one is exactly those conversations change. We don't talk anymore about this, like you have to fit it and do everything you can and that's it. Because we are starting to really have a conversation. It's not unidirectional. Like I'm telling you and you just say yes and you go and you try to squeeze the team. It's more like,
SPEAKER_00okay, so you would like to do this, but we are already having this in progress and we know how long it will, we said that it will take. What would you like me to move, right? So then we can say like, this is... I can do it in 30 days. I can do it in this many days. How would you like to fit it? And then you kind of reflect back to people. So like, you are giving me more work, but help me prioritize then, right?
SPEAKER_00And this way, the conversation is so much different than, okay, okay. And then you are to blame because you took all of this in and promised that it will be done. Right.
SPEAKER_02Yeah. And I think it creates this cycle of fear and blame, honestly, because when we see that pattern, it's like nobody wants to give a date because they're going to be held to it no matter what decisions get made that might impact that date. And then they're the bad guys when the date changes. Right. So we end up in this pattern of trying to buffer things. And it's like, oh, well, you know, we said it would be March 31st, but we're always wrong. So let's just plan for April 15th. And now that's the date. Right. Regardless of what happens or what decisions they've made that impact that, that we're holding everybody to. And it's just this awful cycle where I think it can all be really broken,
broken loose a little with better communication and that concept of communicating
SPEAKER_02likelihood and risk.
SPEAKER_00Yeah, yeah. And then it also gives you so much more confidence when you face those C-levels or those executives because you are backed by the data and you're talking about very easily. You can explain why, right? Otherwise, it's like, oh, yeah, we made this. Nobody trusts anyone anymore. And it's really hard. But then I have, going back for a moment, just too close to those grief, because I love that. And I was reading about it. And I thought,
because I'm creating now a training for the teams to go from this deterministic
SPEAKER_00thinking when you are saying this is the... the estimate that we have to like more probabilistic and taking into account everything that we know and I'm thinking what will happen so I'm already planning a second like a follow-up training for when you realize what are those metrics you will realize how long it will take to get anything done and What then? So when I saw your post yesterday, I was like, okay, this is perfect.
SPEAKER_00This is what will happen. And I'm already bracing for that, that we see and the data must be wrong. Like it cannot be. We cannot be this slow, right?
SPEAKER_02Yeah, I mean, I think that's the first stage is usually denial. Like this data can't be right. Things can't be taking that long. That's not correct. Like I said, I think one of the things that we see the most is, well, sure, that's been in progress for 200 days, but it only took us two days to make the change. But we still haven't deployed it yet, right? So how long has it been sitting here? What's contributing to the fact that... it is stuck. Because I think that that's kind of the next piece here is like, what's happening to the work? Why is the work getting stuck? Do we have dependencies? Are they too big, right?
So then the resistance usually moves from the data to the work items themselves of,
SPEAKER_02you know, we're not carving them up in a way that's valuable or they're too small or they're too big, right? There can be a million reasons, but Then we start to look at the work items themselves. And then I think once we've kind of uncovered the data and then the work, the next piece is, okay, let's clean it up. And I usually call it JIRA hygiene, but pick the tool flavor that you're in. And it's really just like, are we moving the tickets across the board on time? Is everything actually visible here so we can understand how much work is in progress and the impact that's having on our cycle time and throughput?
SPEAKER_02Yeah. Because a lot of times the first part of this is like the data doesn't reflect the work. The work doesn't reflect all the actual work that's in place. And so the next piece is like we need to get better about tracking what we're doing so that we have good data and that all that work is visible. And then I think you circle back to like, okay, well, what is the data telling us? How long are things taking us, right? And so it's like, first we have to have, we have to see the data to want to clean up the work and then want to track the work better. And then once we kind of get through those phases,
I think then there's a lot more confidence that the data is correct in telling us
SPEAKER_02where we have issues in the system that need addressed.
SPEAKER_00Great. Yeah, this was very powerful. I think it's great to see this in this way because it's also the part of don't stop when first you have the resistance. It will happen. It's natural. We always wish for better life, right? We wish for better outcomes and then we see the reality and it can be scary, but let's not stop. Let's continue this work. Let's see what we can do to improve this flow.
SPEAKER_00And there are many techniques, right? So we have the techniques. Let's concentrate on that. Small steps and then suddenly we will see how much better everything life is because we don't have to spend our time estimating and quarreling about like, yeah, again, we didn't do it as everybody expected us to do it. So I think it's like... It will be a bit hard at the beginning, but then the liberation will be worth it. Definitely. Totally agree.
SPEAKER_00Great. Thank you so much for joining. Really interesting. And I think, yeah, I really wish we can spread this word around and also liberate people from this estimation loop because you get into a loop when the estimation is kind of a king and you have to just make the best estimates as opposed to like, forget about that, start new and just focus on what you can really influence.
SPEAKER_02Absolutely. Yeah, I love that, Maria. And I think getting started is often a lot easier than you think. We just actually put a new blog post out on the ProConban site that highlights a bunch of free tools that are out there to help you get data out of whatever tooling you're using at your organization. Because I think that's usually one of the first barriers we hear is that we can't get the data out. We can't get it out of JIRA. We can't get it out of ADO. We can't get it out of Rally. Take your pick. But you'd be surprised how many amazing brains in our pro Kanban community have gone out and built their own tools to do exactly that.
SPEAKER_02And they're willing to share them. So if you check out that tools blog, it lists out a bunch of free tools that you can go get access to. So you can start to get your hands on this data and see where you're at.
SPEAKER_00Great. I talked to Benji as well recently. So I know some of those. So, okay. I will share the link in the description so everybody can grab the link and start using it. Because really it's, yeah, it's about starting and then it's really easy to keep going. So thank you so much. Really appreciate it. I'm happy that we could meet today here in your state of mind. And yeah, hope to see you soon on one of the agile conferences.
If you’ve ever heard terms like DevOps, SLOs, SRE, or platform engineering and thought, “Wait, what are these exactly?” - you’re not alone. That’s why I’m excited to share this new episode of Agile State of Mind with...
We talk endlessly about technical debt - the shortcuts in code that eventually come back to bite us. But there's another kind of debt accumulating in your organization right now, silently strangling productivity and...
"Planning isn’t about predicting the future. It’s about preparing for it." Most teams still try to plan with a single number: “We’ll be done in 3 sprints.” But real work doesn’t behave like that. Some work flies, some...
Are estimates the comfort blanket of the corporate world? Like trying to predict the weather five days from now while standing in a hurricane. But hey, at least you feel in control while the roof flies off. I recently...
In the latest episode of the Agile State of Mind Podcast, I sit down with fellow ProKanban trainer Benjamin Huser-Berta to discuss the visualization of flow metrics in Kanban. Our conversation reveals practical insights...