First, we speak to The Indian Express’ Dheeraj Mishra about why the Mumbai-Goa highway remains unfinished nearly two decades after construction began, the companies and political connections behind its most delayed stretches, and whether the latest April 2027 deadline can be trusted. Next, we speak to The Indian Express’ Nikhil Ghanekar about why citizens protesting Delhi’s worsening air pollution were stopped before reaching the Environment Ministry and what their experience reveals about the Capital’s continuing public-health crisis. (18:15) And in the end, we look at the Election Commission’s response to claims about religion-wise voter deletions in Uttar Pradesh and the wider gap between the state’s projected adult population and its electoral rolls. (30:16) Hosted by Ichha Sharma Produced and written by Shashank Bhargava, Niharika Nanda and Ichha Sharma Edited and mixed by Suresh Pawar
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Speaker 1In today's episode, we look at Delhi, where citizens protesting worsening air pollution were stopped before they could reach the environment ministry. We also take a look at Uttar Pradesh, where the election commission has pushed back against claims about religion-wise voter deletions, saying it does not record voters by religion at all. But first, we talk about a highway project that began nearly two decades ago but remains unfinished. Hi,
Speaker 1I'm Ichha Sharma and you're listening to 3 Things, the Indian Express news show. In September this year, Union Road Transport and Highways Minister Nitin Gadkari made an unusually candid admission about the Mumbai-Goa Highway.
Speaker 2This road is part of Mumbai-Goa. In my opinion, He said he was ashamed of the delay and would not attend its inauguration when the project was finally completed. And there is a reason for that frustration. Work on the Mumbai-Goa section of National Highway 66 began.
Speaker 1In October 2007. The government initially promised to complete it by December 2018. That deadline was later pushed to 2021. And now, nearly 19 years after construction began, the latest target is April 2027. According to Ministry of Road Transport
Speaker 1and Highways, around 99% of the project is finished. Just 8km of work remain across 5 stretches in Maharashtra. And when an investigation by the Indian Express examined government records, company filings and the contracts awarded for these five delayed stretches, it uncovered a complicated trail of construction companies and political connections. So to understand why has this highway remained incomplete and who should be held accountable for the repeated delays and
Speaker 1mounting costs, we speak to the Indian Express's Dheeraj Mishra, who led the investigation for the newspaper. Dheeraj, we understand that this Mumbai-Goa highway is an important road connection. But for our listeners not from this stretch, could you explain why does this highway matter so much?
Speaker 3So it's one of the flagship project of Ministry of Road Transport and Highway. And it was conceived for a very key purpose because this highway, it is a National Highway 66. So earlier it used to be two lane highway. So now the government planned it to make it to the four lane highways. So four lane highway and this highway goes all the way to the Kanyakumari. So, it's a very key economic corridor. So, the highway, it is connected to some of the very key terminals of Mumbai like GNPT Jawaharlal Nehru Port Terminal and apart from that,
Speaker 3there is Dighi Port. Apart from that, there is the Agad Danda Terminal and a shipyard in Raigad. So, the highway passes through very key areas of the Konkan region. The highway is also connected to very key tourist area like there is this Muru Janjira Fort. Apart from that, there is Padma Durga Fort. Then there is Divya Ghar, Golden Ganesh Temple, Hari Harishwal Temple.
Speaker 4All of these temples, these are in Konkan region.
Speaker 3And the highway passes through areas like Raigad, Ratnagiri, Sindhudur, Lanja, Nivali, Kante.
Speaker 4These are the key areas. And apart from.
Speaker 3That, the highway also connect to the Navi Mumbai Airport which is.
Speaker 4Near to Panvel.
Speaker 1Recently, the highway was in the headlines after Nitin Gadkari made a rather extraordinary admission that he was ashamed of the delay in completing the highway. So what does that tell us about just how troubled this project has become?
Speaker 4So you're right.
Speaker 3I mean, the project is one of the most delayed project of the ministry. So this entire highway to expand it from two lane to four lane was conceived as back as in 2006 when there was a UPA government. And work started on one of the section which is near to the Goa border. It started in 2007 and was completed in 2013. And after the new government, new NDA government came in power and Nitin Katkari has been the Minister of Road, Transport and Highway since 2014. The
Speaker 3completion of Mumbai-Kovar Highway was one of the key projects that he outlined at the beginning.
Speaker 4And even initially, the.
Speaker 3Highway was planned to be completed by 2018. Later, this whole timeline was again revised to 2021. And it was kind of the timeline that, you know, by 2021, it will be completed. And then again and again, whenever reporters ask to the minister that when it will get completed. So you may find many stories over internet that in 2023 he is saying this will complete by December. Again, he said in 2024 that it will complete by December. Then again, I mean, he has to say he has to go on and on. And I can understand his frustration.
Speaker 3That why did he say that I'm ashamed I will not join the inauguration of the project? Because he himself had set this deadline many, many times and it never got completed. And it is yet to be, I mean, the entire project now is scheduled to be completed by April 2027. And if everything goes well, then it will happen. I mean, it might happen by April 2027. But again, if there is another problem, props up. So this project might get more delayed.
Speaker 1Right, and Dheeraj, could you help us understand the timeline of the project? Like, how did a project conceived in 2006 remains unfinished even in 2026?
Speaker 4So there are many reasons of the deal here.
Speaker 3Number one is the entire, the way the projects were awarded in this National Highway. Number one, a lot of projects were awarded and then after that land acquisition started. So what happened after you awarded the project to a contractor, after that you are starting a land acquisition. So land acquisition, again itself, it's a very complex process where a lot of aggrieved party, they go to the court, they file claim for higher compensation. They file cases against the, you know, ministry, the concerning department and everything. So this kind of took
Speaker 3a long time to complete the land acquisition process. Apart from that, there was this problem of the clearances because the highway passes through some of the key forest area also.
Speaker 4And then there was a problem of utilities shifting.
Speaker 3So you would have seen that along the national highways, there are different kind of things. Let's say there is a, you know, electricity wire going along the highway.
Speaker 4There might be some pipeline going along the highway.
Speaker 3So before construction, all of these things had to be shifted to a different location. After that, construction can be started on a highway project. After the contractors started their work, so now the delay comes on the part of the contractor. They defaulted on loans and then because since they defaulted on the loans, there was a problem with the cash flow and sufficient money was not coming in for the project and then this further led to more delay of the project. A lot of contractors were filed against them.
Speaker 3Insolvency petitions were filed against them in the NCLT. So contractors had to stop their work. And there was local protest as well. So this highway has been a very key center of politics as well. You would have noticed that before the Ganesh festival, this issue of non-completion of Mumbai Go Highway pops up again and again because people have to travel to Konkan region and they face a lot of problems.
Speaker 4During this movement.
Speaker 1And Dheeraj, the government's claim that the highway is now 99% complete, with only about 8km remaining, that sounds like a relatively small amount of work left to be done. So why is this final stretch proving so difficult?
Speaker 3So, I mean, that is true that, you know, not much work is left to be completed. But these eight kilometers of the work are very key section of the highways. Like there are some flyover, there are some bypasses, there are some key hill cutting area. Let's say there is a hill cutting where two sides of the road had to be connected. But if you do not complete the hill cutting, then it doesn't matter that either.
Speaker 4Side is completed by 99%.
Speaker 3But there is a mean something which link either side of the road is missing. So even the 99% would not mean that much because people had to face problem to cross that particular section.
Speaker 1Then during your investigation, you closely followed the companies and individuals who behind these five unfinished stretches. So what did you uncover about the contractors?
Speaker 3So we look closely in the project and let's see that, you know, who are the people involved in the project, who are constructing it. And it was very important to see because we had to hold all the involved people accountable because, you know, those people who are implementing the project are the people responsible for the daily of the project. So when we looked into the most delayed section, which is the five key section, and we found some interesting thing behind it. And the investigation reveals that, you know, I would say these are the heavyweights. These are very powerful people who are involved in the construction of this
Speaker 3most delayed section of the project. So one of the main section from Indapur to Wadpal is around 27 kilometers section. It was earlier being constructed by the joint venture of Chetak Enterprises and APCO Infratech. And Chetak company is owned by Udaylal Anjana. So Udaylal Anjana is a senior Congress leader and he was a minister of cooperative in Rajasthan government, the last Congress government in Rajasthan between 2018 and 2023. Now, because of the consistent delays in the project, the project
Speaker 3was terminated in 2023. in 2025 and the balance work was awarded to another company which is Jaipur based. The company name is LNA Infra Project. The another company involved in this in the Putu Wadparle section was App Apco Infratech. Apco is a very famous company from Uttar Pradesh. It's a Lucknow-based company and it is run by Anil Kumar Singh. He's a very known and powerful industrialist from UP. So these are the two key names in the Puttavad Police sanction.
Speaker 1Reharan, moving to the Panvel Indapur section, you highlight how the original contractor ran into serious financial difficulties and eventually even lost the contract. So how did those financial problems affect the construction?
Speaker 3So, let's say the highways start from Panvel. So, Panvel to Indapur section, it is 84 km long section and it is being implemented by NHI, National Highway Authority of India. And rest of, out of 472 km in Maharashtra section, 84 km is implemented by NHI. Rest of section is being implemented by Ministry of Road Transport and Highways in collaboration with State PWD. So this, the only section which is with NHI is Panvel to Andhapur. It is yet to be completed. This particular section was earlier awarded to
Speaker 3Supreme Infrastructure as back as.
Speaker 4In 2011 in UPS period.
Speaker 3So both the section, entire 84 km, but this project could not be completed. completed it is very much delayed i mean it is yet to be completed initially it was awarded on the basis of bot so it is called build operate transfer i mean the contractor had to first build it operate it for the some time and then transfer it to the government interestingly supreme infrastructure later defaulted on loans it went into nclt and it was on the top 100 bank defaulted list of the RBI in 2019. Later, the project was scrapped. I mean, it
Speaker 3was the contract was terminated from the supreme infrastructure and was divided into two packages, Panvel to Kasu, Kasu to Indapur. Panvel to Kasu has been awarded to J.M. Matre Infra Private Limited. It was awarded in 2023. It's run by a politician and businessman called J.M. Mahatre.
Speaker 4He's a very influential person in Panvel. And he is.
Speaker 3Currently under an ED, Enforcement Directorate investigation for alleged fraud involving a forest land. The second section was awarded to Kalyan Troll Infrastructure. It's an Indore-based company. And many people would have heard of the Kalyan Group. So it's also a very famous and influential company in the road sector.
Speaker 1And Dheeraj, perhaps the most cost escalation is on the Parshuram Ghat Aravali section. Like the cost of the package has increased from 983 crore rupees to more than 2200 crore rupees. So that's approximately 126%. So what happened at that stretch?
Speaker 3So, Parashuram Ghat to Aravali, it is a 34.45 km long section which is yet to be completed. There is 1.8 km of Chiploon flyover in this particular section which is yet to be completed and is a very important flyover. So, like I said, to connect either side, this flyover has to be completed. So, this section is being currently built by Chetak Enterprises. Like I said to you earlier, that was involved in another Indapur to Wadpley section, which the company could not complete it in time and it was
Speaker 3terminated by the government. So, it's a joint venture of Chetak Enterprises, which is, like I said, it is run by Congress leader Udallana Njana. There is another company in this section, Eagle Infraindial Entry. So Eagle Infra India Limited is also a very influential company in the Maharashtra who is involved in a number of the road projects and it is run by the Rup Chandani family in Maharashtra.
Speaker 1And the last section is the Rawli Kante stretch which is 95% complete. So what delayed this stretch?
Speaker 3So this section was earlier awarded to a company called MEP Infrastructure Developer Limited. In joint venture with there was this Spanish company San Jose Indian Infrastructure and Construction Private Limited. So what happened in this particular section that MEP infrastructure defaulted on loans and there is this problem of cash flow and the company was later taken to the NCLT and this company is still undergoing the.
Speaker 4Insolvency process in NCLT.
Speaker 3And this particular section, so MEP, it is also a very famous company involving a very powerful and famous group, famous family, which is called Mahiskar Family. So they have many companies, they are involved in many road projects. So this company is also from that family. And when after they defaulted on the loan, the project was awarded to a company called Hazur Infra Project Private Limited. So, Hazur Info Project is a subsidiary of the Hazur MLT Project Limited.
Speaker 3It's also a famous company from Maharashtra. Interestingly, the chairman and managing director of the Hazur Projects is Radhesh Shyam Mupalwar. And Radhesh Shyam Mupalwar used to be a vice chairman and MD of Maharashtra State Road Development Corporation and who was a key person behind the completion of Samruddin Mahamag Expressway Project.
Speaker 1And so, Dheeraj, after nearly two decades of construction, And of course, several missed deadlines. The government now says that the highway will be completed by April 2027. So to what extent can this deadline be trusted?
Speaker 3So for this investigation, I mean, I spoke to a number of government officials, contractors, people working on the ground, you know, even workers and, you know, all kind of people. And an official said to me a very interesting thing. I mean, he said that, you know, this project is a showpiece example of what can go wrong in a major highway project. So I think it kind of sums up everything that there was a series of problem and it was also a learning for the ministry. But then ultimately to the, you know, a lot of public inconvenience
Speaker 3and cost overrun and had this highway could have been completed earlier. There had been more traffic, more people moving, more benefit to the government. So deadline is now by April 27. And I think after a lot of pressure from public as well as from the ministry here at the center as well, because the project has been implemented in collaboration with the state PWD, Maharashtra PWD. So there is now pressure and the entire project and everything is
Speaker 3now in the very much limelight. And government is also on pressure. So they have to complete it on time. I think now and there is this sign that, you know, in the last one or two years, the stalled section of the project was being expedited and it is now nearing towards the completion.
Speaker 1And also, are there any new safeguards in place so that these discrepancies aren't repeated?
Speaker 3Like I said that, you know, the project was a learning for the ministry as well because the officials.
Speaker 4Now said that, you know, they have made changes.
Speaker 3Number one changes is that all the pre-construction activities has to be completed before a project is awarded to a contractor. so pre-construction activities means environment clearances forest clearances or any other clearances that is required in the project and utility setting this has to be done before the contract is awarded not the other way around number one number two is a 90 percent work on the land acquisition has to be completed so it should not work like that you know let's say a section is awarded to a
Speaker 3contractor and now official is starting the land acquisition so this kind of put things backward so number two is 90 of the land acquisition has to be completed number three is that now the ministry has become strict very strict on the contractors that if there is a problem if they create an intentional problem government will take action they will blacklist them they will you know terminate the contract and yeah i mean the contractors will have to face consequences for the delay so these are key things that government has changed in their working now.
Speaker 1And next, we turn our attention once again to the country's air pollution crisis. With air quality in the capital deteriorating by the day, a group of concerned citizens including cancer patients and student activists led by the All India Students Association President Neha Bora organized a demonstration near the Ministry of Environment, Forest and Climate Change office. in Jorbaug on Monday afternoon. Neha had earlier written to the environment
Speaker 1minister asking for a meeting to discuss the worsening air quality and its impact on public health. And Monday's demonstration was an attempt to get that meeting. However, before the protesters could reach the ministry, they were stopped by Delhi police personnel and paramilitary forces. So to understand what happened during the demonstration, why were the protesters stopped and how did the ministry respond? My colleague Niharika Nanda speaks to the Indian Express's Nikhil Ghanekar, who reported on the issue for the paper.
Speaker 5Nikhil, we understand that ISA President Neha Bora had written to the Environment Ministry about the rising pollution levels. How did the Ministry respond to that?
Speaker 6So the email that she had written, as we understand, was to Union Environment Minister Bupender Yadav on the 12th of November, talking about how air pollution is affecting the health of people at large in this region, not just Delhi, but also the larger North Indian region and also other parts of the country.
Speaker 2Rather.
Speaker 6She had essentially sought an appointment with the Union Environment Minister to discuss this issue. And she had said that she wants to bring a delegation with herself, which would include environmental activist or environmentalist Bahurin Kandhari, former captain of the Navy, Mr. Ashish Jacob and Urvashi Prasad, someone who's herself suffering from lung cancer because of the high pollution levels. She has talked about it during the demonstration and we will also touch upon that later. But essentially, the ask was to sit down and seek time from the minister
Speaker 6to discuss this very serious issue. So, the ministry did not respond for the first three days after she emailed them and late on Sunday night, as we had reported in our newspaper and also on our website that the They responded to the ISA president and told her that the minister is in fact in Antalya, Turkey for the annual climate conference. And he was leading the delegation of our country. And because of his visit, he will not be able to give time. They did not essentially say that,
Speaker 6but that's what they implied. Along with that, they also mentioned that the ministry and minister is reviewing the situation constantly and they accord highest priority to this issue. It was a very brief kind of response, almost like a bureaucratic response, not really touching upon the issues of public health per se, but more so to do with, you know, the demand to meet the minister.
Speaker 4Right.
Speaker 5And Nikhil, this was not a very large group of people. And from what we understand, this gathering was quite different from the protests we've been seeing over the last couple of months, right?
Speaker 4That's right.
Speaker 6From the get-go, it was clear that even through the video messages that the ISA president had put, it was not going to be like a protest call that we had seen against, let's say, the election commission that happened in the previous month or something that happened at Jantar Mantar either during the NEET protests. This was essentially a delegation that were trying to raise questions on an issue which is largely seen as non-partisan and non-political, however, which usually does not get a lot of traction politically, either in, let's say, during the debates in parliament. So I think
Speaker 6the effort was to draw political attention to it by seeking accountability with the people who are governing on this matter.
Speaker 4Right.
Speaker 5And the protesters were restricted from going to the ministry by the police. So what happened after that?
Speaker 4That's right.
Speaker 6So, the call that was given for the demonstration and a small march of sorts was around 2 p.m. and we were there at the spot around the ministry. Usually, the Indira Pariyar and Bhavan which is housed in Jor Bagh, it is usually a very calm and leafy environment and Not many institutional buildings are around this ministry building. It's in fact housed in a residential area. We could see that right from around 1.30, 1.45 pm onwards, there was a huge security deployment of companies of Delhi Police, the BSF,
Speaker 6the SSB, etc., Rapid Action Force. And around, I would say, 3 o'clock, there was this group of people which we had talked about earlier. A lot of them were essentially ISA activists along with certain citizens and they were stopped at the intersection of 2nd Avenue and Jorbaug. There were barricades already put up there. So, it was very easy to block them off. It was not a very large group. And for almost the next one, one and a half hour, there were discussions between an assistant commissioner of police, an SHO of the Delhi police and Ms. Neha and some
Speaker 6other citizens who were leading this demonstration on who would meet them from the Ministry of Environment and Forests. Finally, what happened is that they were asked to go to the Commission for Air Quality Management, whose office is at Janpath in the Jawahar Bhavan and That's what happened. They were rerouted there. They went there and a joint secretary from the Ministry of Environment and Forest along with the member secretary of the commission met them. That meeting went on for almost an hour from what we know. And this group once again made a request to seek an
Speaker 6appointment with the environment minister to raise this issue of how this problem persists year after year despite the claims of the government to have been implementing a lot of anti-pollution measures.
Speaker 5And can you tell us how bad is the air pollution in the capital right now?
Speaker 6So essentially, as we know, pollution is something which flares up. It is not something that is not a problem in other times of the year, especially in the northern region. But it flares up the level spike during the winter times because of a variety of reasons. One of them is obviously the inversion of air where pollutants are concentrated closer to the ground. Secondly, the meteorological factors because the winds really drop to a slow pace and speed, the dispersal of pollutants that are concentrated in our atmosphere right
Speaker 6from closer to the surface till higher up, they are not dispersed quickly enough for the air to become cleaner. The local sources of pollution obviously are the same as they are throughout the year, which includes vehicular pollution, which is the primary source of pollution in Delhi. One of the leading causes, which is vehicular pollution, a large number of two wheelers and four wheelers, along with commercial vehicles that ply on Delhi and Siyas roads. Secondly, there is natural dust.
Speaker 4There is dust from construction, etc.
Speaker 6there is biomass burning which includes solid waste burning also there is contribution from the farm fires during the winter time when paddy is harvested that contributes anywhere between as small as 3% on some days to sometimes about 20% on very bad days during the winter season then there is industrial emissions obviously because there are several industrial clusters in and around Delhi and other causes such as thermal power plants in and around Delhi NCR. If we talk in terms of what has happened so far, we have
Speaker 6seen that because of the good meteorological conditions, there were rains in the month of October. So the situation was not as bad. But after November, it has started worsening. And after November, the month began. In fact, air quality index touched the severe category a few days back.
Speaker 4Right.
Speaker 5And Nikhil, keeping that in mind, what kind of efforts have been made by the government to tackle the pollution levels? We know that Grab Stage 3 has been notified in the capital, but what else has been done?
Speaker 6So for the sake of reducing vehicular pollution, the government has a few schemes which enable transition to the electric vehicles to reduce vehicular emissions. As far as landfills are concerned, the effort is to reduce the open burning. But that is one issue where we all see that open burning is really rampant in some places. So the effort is to ensure that this reduces, there is awareness on how it affects people's health, etc., Third, as far as the issue of stubble management is concerned, now for the past
Speaker 6several years, the central government, you know, primarily through the Ministry of Agriculture, they have provided machinery along with some incentives for the farmers in Punjab and Haryana and also parts of UP, Rajasthan, etc. But primarily Punjab and Haryana to wean them away from the practice of burning of the paddy straw. One of the other solutions that is tried on the ground is to, after the straw is taken out, it is sent as a raw material for fuel to be burnt in industries, in thermal power plants,
Speaker 6in biogas plants, etc. So, essentially, it is baled and this baled straw is then taken to boilers in different industries. Then, obviously, there is the issue of industrial emissions and how they were used. asked to install air pollution control devices so that whatever emissions are released into the environment are as per the permissible norms that are laid down by the Central Pollution Control Board. Those industries that are not compliant with these rules are shut down. A few days back,
Speaker 6the Enrollment Minister asked CPCB to immediately shut down almost 191 industries who are not complied with directions pertaining to these air pollution control devices. So there are a bouquet of solutions that are in place. Some of them obviously are also from the Delhi government. We all know that they have imposed restriction on the non BS6 vehicles. There is a construction ban also in place right now across NCR for 15 days which started on November 5th. This is to basically reduce the pollutant which is the particulate
Speaker 6matter 10 pollution. Now PM10 is essentially what is dust. These are coarse materials which can affect our respiratory organs. So these are some of the solutions or let's say curbs that are in place to control the pollution.
Speaker 5And Nikhil, you also had the opportunity of speaking to Urvashi Prasad who was one of the demonstrators and also someone who is battling lung cancer. Can you tell us what did she say regarding this?
Speaker 6So we spoke to Ms. Urvashi Prasad who is a public prosecutor Health professional, she has also worked in the government sector in the Neeti Ayog, which is the government think tank. And she spoke about how she was diagnosed with lung cancer, which is particularly, you know, characterized as a non-smokers lung cancer to be specific. And that is the worrying part that she tried to raise awareness about. That it does not matter anymore if in Delhi NCR region you are a smoker or not. The kind of exposure that people have year on year, week in week
Speaker 6out can expose you to these kind of harmful gases and pollution that will lead to something as serious as and potentially fatal as cancer. So she was, I mean, extremely well aware of the issue we found and she wanted to essentially highlight this point to the ministry that it is not only about whether in terms of the administrative and governance actions, whether the pollution... is being curbed, it's also important to raise awareness about how serious the public health impacts can be. Because more often than not,
Speaker 6pollution gets often boxed into an environmental issue, but does not get enough talked about as the kind of health suffering that people have. It may not Always be as serious as cancer. Cancer is obviously one of the worst outcomes.
Speaker 4That can happen.
Speaker 6But there are also respiratory ailments that people face on a daily basis. There is COPD, one of the more other serious ailments that people face, which is a pulmonary disorder. So this is the kind of points that Ms. Prasad wanted to raise with the ministry. That's what we found after speaking to her yesterday.
Speaker 1And in the end, we talk about Uttar Pradesh's voter rolls, where Chief Minister Yogi Adityanath's claim that 1.27 crore Hindu voters were missing after the special intensive revision has hit a wall, as the Election Commission says it does not record voters by religion at all. UP Chief Electoral Officer Navdeep Rinwa said, The commission's database contains details such as a voter's name, age, gender, address, and date of birth,
Speaker 1but not religion or caste. He also said no names were deleted on the basis of religion, caste, community or locality. Now, that makes the Chief Minister's figure difficult to verify using official Election Commission data. As reported by the Indian Express's Lal Mani Verma, Rinva suggested that those making religion-based estimates may have analysed the electoral rolls using privately available software. But the commission itself cannot confirm how many Hindu or
Speaker 1Muslim voters were removed because it simply does not maintain that information. The clarification came as Uttar Pradesh published its draft electoral rolls following a special summary revision. And the numbers show something important. The state now has around 13.58 crore registered voters and an increase of 18.84 lakh from the 13.38 crore voters recorded after the SIR in April. Of those added back, around 10.96 lakh are women and 7.87
Speaker 1lakh are men. But there is still a much larger numerical gap. Government population projections estimate that Uttar Pradesh has around 16.16 crore people aged 18 and above. Compared with the 13.58 crore names on the draft electoral roll, that leaves a difference of roughly 2.58 crore people. And notably, around 1.64 crore of that gap is among women, compared with about 94 lakh men. The revision process is not finished.
Speaker 1Voters can file claims and objections until 16 December. These will be disposed of by 28 December and the final electoral rolls are scheduled to be published on 4 January. You were listening to Three Things by The Indian Express. Today's show was edited and mixed by Suresh Pawar and produced by Niharika Nanda and me, Ichha Sharma. If you like the show, do subscribe to us wherever you get your podcast. You can also recommend it to someone you
Speaker 1think may like it, with a friend or in your family. This is the best way for people to get to know about us. You can also tweet us at Express Podcast or write to us at podcast at indianexpress.com.
First, we speak to The Indian Express’ Diplomatic Affairs Editor Shubhajit Roy about the 2026 Quad Summit in Manila, India’s role within the grouping and what its expanding cooperation means for relations with China and...
First, we speak with The Indian Express' Sukrita Baruah about women who provide household services via applications like Pronto and Snabbit. She talks about their experience, their earnings, and how their lives have...