Why is NERC so worried about data centers?

Jun 10, 20261 hr 14 minAudio
ShareXLinkedInFacebookWhatsAppEmail

This is a public episode. If you'd like to discuss this with other subscribers or get access to bonus episodes, visit www.volts.wtf/subscribe The North American Electric Reliability Corporation has issued a historic warning about AI data centers. I chat with energy experts Colin McCormick and Doug Bryan about the unique electrical engineering challenges of giant computational loads that can abruptly drop hundreds of megawatts of power in the blink of an eye. We dive into the upcoming regulatory battle between hyperscalers and operators, the sudden rush for firm gas generation, and how software updates and battery storage could eventually make data centers a tool for grid stability instead of a liability.

Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.

Transcript

From the show. Tap a time to play from there.

hello everyone greetings this is Volts for June 10th 2026 why is NERC so worried

SPEAKER_01about data centers I am your host David Roberts Traditionally, the grid planners and regulators charged with maintaining the reliability of the wholesale power grid concerned themselves with the behavior of generators, ensuring that power plants do not ramp up too quickly, trip off too suddenly or create unmanageable frequency or voltage disturbances.

SPEAKER_01loads, even large industrial loads, were presumed to be relatively safe, as they tended to behave quite predictably. That has changed with the introduction of gargantuan data centers which can ramp extremely quickly, trip offline very suddenly, or induce oscillations that mess with grid voltage. They are big enough and unpredictable enough to cause problems

that can cascade and

SPEAKER_01cause widespread blackouts. Grid regulators are taking notice. Last month, the North American Electric Reliability Corporation, or NERC, the non-profit regulatory authority assigned with maintaining the reliability of the U.S. wholesale electricity grid, issued a Level 3 warning about data centers, which, in the typically boring regulatory world, amounted to a flashing,

SPEAKER_01blaring siren. It called out the increasing threats that data centers pose to the grid and issued, alongside the warning, a set of recommendations for grid planners, transmission organizations, and hyperscalers to address those dangers. This amounts to a historic structural shift in how grid reliability is conceived. For the first time, there are loads, big and powerful and weird enough that they simply must be

drawn into the world of

SPEAKER_01grid planning and reliability. It's going to require updating all kinds of regulations and assumptions. And hyperscalers aren't necessarily going to be happy about it. To discuss the warning, the recommendations and the many associated implications, I have with me today Colin McCormick and Doug Bryan, respectively the Chief Science Innovation Officer and the Senior Energy Modeling Expert at Carbon Direct,

SPEAKER_01a firm that provides advice and counsel to utilities, tech giants and investors pursuing clean energy. We are going to talk about what triggered NERC's fears, what they want the industry to do, and how this might change the pace of data center build out.

SPEAKER_01With no further ado, Colin McCormick and Doug Bryan, welcome to Volts. Thank you so much for coming.

SPEAKER_02Thank you, David. Pleasure to be here. Great to be here, David. Thanks.

SPEAKER_01There is so much to chew on here, guys. So maybe, Colin, I'll start with you. There have been big loads on the grid before. There are lots of big industrial loads out there. Think of steel plants, things like that, that draw a lot of power. But there's something new and different about what NERC calls computational loads, which is, I think, mostly data centers, but it's also the crypto guys. big computational load so let's just start with like what is it

that these big computational loads are doing that is different and that has NERC worried well you are right that we have had big loads on the grid before industrial loads although it it is worth noting that even the largest industrial facilities historically have not drawn power at the scale that some of the frontier data centers are doing so there is a there is a scale issue but the more important

issue is the nature of that load and you referred to it as I think big and weird and it's that weird piece that is important to get your head around so the way a data center looks to the

SPEAKER_00grid is a lot different than the way an industrial load that has a lot of rotating machinery, motors, et cetera, looks to the grid. The data center interfaces with the grid using power electronics, using active electronic equipment, uninterruptible power supplies, essentially, that are doing a couple things. So they're active, they are sensing in real time the voltage and the frequency of the power that's

coming from the grid and their job is to protect the expensive sensitive computing equipment that they are passing that power through to and they are designed to be

SPEAKER_00very proactive in protecting that expensive equipment they're designed to react to very minor fluctuations, what a lot of grid planners would think of as very minor fluctuations to voltage and frequency. And if they detect those, they follow a particular standard. We can get into the nerdy exact standards later if you'd like, but they follow a particular standard that essentially has them trip offline, disconnect from the grid, and serve their computational load using backup power or storage.

SPEAKER_00And that tripping offline happens in an incredibly fast, incredibly brief period of time, 20 milliseconds or something like that. That's extremely different from the way a conventional industrial load would respond to any fluctuations.

SPEAKER_01Right. And as you were saying, some of these loads are gigantic. It's like 100 megawatts or whatever. So that's 100 megawatts of load just vanishing, basically, in the blink of an eye. That's right.

SPEAKER_00And that is... That's a big number. Now, Doug can get into this in a minute, but the grid is designed to handle a certain amount of load tripping off, and 100 megawatts, big as it sounds, is actually not outside the realm of what many grids can respond to. But we're talking not only about single data centers tripping off, we're also talking about the possibility of multiple data centers tripping offline to the same

SPEAKER_01Right, because if they're all on the same grid, they're all sensing the same fluctuations and they're all responding the same way. Exactly. And maybe,

SPEAKER_00Doug, you can get in a bit to how the grid is sort of supposed to handle this, but then we can think about how the scale is really very different.

SPEAKER_03Yeah, so the grid operators, they have tools at their disposal to handle these sorts of fluctuations. We don't have a static load profile throughout the day, let alone over the course of a year. these sorts of fluctuations are it's something that the grid operators are designed to handle so right and generators have been known to fail and trip offline which is

SPEAKER_01sort of like the inverse problem but similar And there's what we call ancillary service markets that are essentially designed to

SPEAKER_03respond to those large events. Why this is different is, A, the scale of the drop. So you mentioned 100 megawatts, David.

SPEAKER_01That was way too low. That was a way too low number. It did not sufficiently impress the audience, I think. Let's call it a gigawatt, at least.

SPEAKER_03And that's what NERC are responding to with the Level 3 alert is... gigawatt-plus scale drops off the grid. And it is that scale that is a challenge. And you're also right that because it's a load drop rather than a generator drop, there's some nuance to how these ancillary service markets are designed to respond. And they aren't as well set up to deal with the load dropping as much as the generators, as you mentioned.

SPEAKER_01So that's the sudden disconnect of one or even multiple... data centers I think is the main thing here but there's some other things too some of which I don't fully understand talk about some of these terms this is the one you're referring to as correlated simultaneous disconnection which is a bunch of data centers going offline all at once but there's also concerns about ride through and clustering training bursts low inertia maybe we could just

mention some of

SPEAKER_01these some of these other weird features yeah I mean I would categorize them like if we were to use an umbrella term it is

SPEAKER_03still related to the ramp up and down of load on the grid system.

SPEAKER_01They all are basically about that.

SPEAKER_03For example, the training burst, that's a function of AI training loads and the various stages that they hit through the training process. Sometimes they ramp up the GPU use as a function of the part of the problem that they're looking to solve. Sometimes they ramp down at a similar extent. that's part of it is like the scale of the or the ramp rate as we call it so the scale of the load change and then what we were talking about the beginning is these tripping off the grid altogether so the load is maintained but

it's actually moved behind the meter it's moved to these uninterruptible power supplies shift that load in order to protect the very expensive GPUs and other IT equipment and the argument

SPEAKER_03there is that they're tripping off too easily and that NERC is saying there needs to be a standard for or there needs to be presses in place that allow for that ride through as you mentioned so maintaining connection to the grid even during these sorts of events up into a point there will be a point at which they allow for it but they think it's happening too easily at the moment Right and I think we've already said this but I'll just emphasize it one more time which is that you can have multiple data centers they're all

sort of being coordinated by the cloud kind of so they're all like it's like one's ramping up they could all be ramping up really quickly and they could all be disconnecting really suddenly so it's not even just like one big data center is the threat it's these clusters of data centers I mean you get a cluster of gigawatt data centers then you're like two gigawatts three gigawatts all of a sudden you're just like

SPEAKER_01exactly beyond anything ever contemplated with similar sensitivities to dropping off and located in a similar part of the grid that spells trouble David it's worth noting that this isn't even necessarily data centers being coordinated in the cloud they're sensing the same electrical

SPEAKER_00grid conditions so they don't need to be coordinated in the cloud they're responding to the physics of electricity flow on the same physical grid And the synchronization has to do with the fact that they're all programmed to respond the same way to those grid conditions. and so this is not we should say theoretical this is not a theoretical concern about things that might happen so just talk a little bit about

what has happened that has caused NERC to sort of slightly panic like this like these dangers have come to pass various places tell us like what are some of the you know examples that NERC is responding to yeah you don't get a level three alert from NERC from a

SPEAKER_03theoretical problem I think is the way to put it yeah so the direct response is so the incident that's often referenced is in Virginia of course you know data center alley ground zero really so in the summer of 2024 a kind of minor equipment failure on a transmission line led to a very brief series of voltage dips on the transmission grid these are so minor that it wasn't particularly noticeable like the lights didn't flicker or anything you know you or I wouldn't have noticed it

but the data center UPS the uninterruptible power supply systems noticed and took that automated action that we've been talking about and they did it at a gigawatt scale so we're talking

SPEAKER_0360 data centers I think it was around one and a half gigawatts effectively simultaneously dropped off the grid in response to that single transmission fault and switched to on-site generators. So that mass reaction was kind of triggered by these mechanisms that we've referred to, and it forced PJM, the grid operator, as well as Dominion, to scale back the output from power plants in order to protect the grid infrastructure, which was essentially to avoid

a worst case scenario of what could have been cascading power outages in the region.

SPEAKER_01Yeah. And we've talked before on the pod about inertia, about these large spinning masses that are sort of there to absorb, you know, these brief fluctuations, but you are just not going to have enough spinning masses to absorb a gigawatt and a half. You know, like, I mean, even trying to ramp back power plants like how quickly can PJM ramp back a gig and a

half of power plant output like like literally how long does that take well that is definitely not

SPEAKER_01happening on a seconds time scale right here and you know it's worth noting that the generators for a long time as you mentioned earlier the generators had to develop the ability to ride through some of these disturbances and continue to generate power and they're subject to a very specific

SPEAKER_00different standard that requires them to be robust against some voltage and frequency fluctuations. So part of the way to think about this is the kind of the mismatch in tolerances right now between the generator side and these large data centers. The large data centers basically trip off at the first sign of trouble, the generators ride through, and I've got a pretty severe instantaneous imbalance between generation and load. So I really need to align those ride-through conditions better

between the

SPEAKER_00generation side and the large load side.

SPEAKER_01Right, which means regulators, the people in charge of reliability, have to start dealing with these large loads, which they've more or less not really had to pull into this whole world before that's the kind of the ship we're talking about yeah and I do want to clarify one thing like would you characterize this as the people in charge of computational load like doing something wrong behaving irresponsibly or is this just sort of like something that's happened sort of like

inherent to the technology

SPEAKER_01like is in other words is there blame to be apportioned here

SPEAKER_03I mean, I think, you know, the deployment of the data centers and how they're responding is going to be a function of the processes and procedures that they are exposed to as regulated entities. What was interesting in the, like basically what triggered the level three alert on the regulation side, so obviously we've got the challenge on the grid, on the regulation side, NERC, as part of like the previous alert, there's a level two industry recommendation. They did a survey to basically look at of the grid operators,

SPEAKER_03transmission owners, distribution providers, do they have sufficient processes, procedures, or methods to address the risks associated with computational loads? And the results were fairly robust that, on the whole, the answer is no. I think it was 87% of transmission owners and distribution providers don't have clear facility design modeling and performance criteria for large loads in their interconnection requirements so it's largely you know the change in the grid is so rapid and at such a scale that the regulation is trying to meet

the moment I think is how I would phrase it a familiar story here on Volts which is these really

SPEAKER_01massive huge rapid changes in an industry and a sort of regulatory world that was accustomed to moving at a rather sleepy pace. And like that's yet another mismatch. Like everybody in this world is having to just move a lot faster than they are accustomed to moving. And listen, I don't want to say that the regulators are sleeping at the wheel.

SPEAKER_03What is done in the grid operator room is, frankly, it's wizardry to ensure that the grids continue to be reliable. But it's a real step change in what they're being asked to deal with.

SPEAKER_01Well, this is a little bit of a side question, but you kind of teed me up a little bit there, which is I've been wondering, so like the whole problem here is that these things are happening faster than operators can respond to. And I sort of have been wondering, like, is there any prospect that if operation of the grid becomes more software-based and digital and sort of faster than if there's any prospect of them catching up and being able to

move faster,

SPEAKER_01or is this all going to, you know, for the foreseeable future, is it all going to be about trying to slow down the changes on the load side? Do you know what I mean? Like, is there a prospect on the horizon of sort of like faster, more digitized operator responses? I think there are groups looking to answer that exact question with this exact

SPEAKER_03problem with technology solutions and it's largely through what we would probably traditionally call load flexibility or demand side response and is about ensuring that there is greater communication between the data center operator or whatever the computational load is with the grid operator and the utilities I mean that was one of the direct recommendations of the essential actions from NERC was having basically I think they even said it could be done via phone if you want.

Like having a direct line of communication between the grid operator and the data

SPEAKER_03center operator.

SPEAKER_01But nobody's going to make a phone call in seconds. Do you know what I mean? You're not going to have a human being who's ever going to be able to react within milliseconds. Only software could possibly do that. David, I think this points a little bit to the push for more ride-through capabilities. Trying to say, hey, data center loads, maybe you do need to be more tolerant. Maybe you need to slow down that sort of instantaneous trip off to be a little bit

SPEAKER_00more compatible with response time that's feasible on the grid. So that's the spirit of that sort of direction of solutions. and I want to talk a little bit later about how the data center people feel about that but one other question which I was not you know reading through all these PDFs was not totally able to wrap my head around is how do inverter based generators play into all this so last year NERC issued another issue three alert poor NERC is

SPEAKER_01like has become quite neurotic. Last year, NERC issued a Level 3 alert about inverter-based generators, which for listeners' benefit is just basically like solar and batteries and some wind, I think, effectively renewable energy. I know they issued a warning about them, and I know somehow all this stuff about computational load interacts with concerns about inverter-based generators somehow, but what is the relationship there?

SPEAKER_03Yeah, I mean, the relationship is that in a similar fashion to how the computational loads don't provide this kind of synchronous and inertia-based interaction with the grid, the inverter-based resources, they aren't the same as your traditional synchronous generators, your gas, your coal, your nuclear, that have physical inertia, which is the rotating mass of the turbine resisting frequency changes. And so if a large load suddenly disconnects or generator trips,

SPEAKER_03inertia buys the system a few seconds to respond. In the same way that computational loads don't have that, these inverter-based resources, your solar, wind, and batteries, they don't have that by default. And so it is actually somewhat analogous in some ways to the challenge here. And I think there are threads that you can pull on that make it relevant to the Level 3 Alert for the inverter-based resources that NERC put out. But there are, I mean, we've flagged some of them already, the A, the scale and the speed at which these things can drop off.

SPEAKER_01So this gets to, we did a pod, jeez, I don't remember, last year at some point, about grid-forming inverters, about the ways that inverters can be programmed to provide inertia. We call it synthetic inertia. And it seems to me like the scale of this is like you're either going to have to build a lot more spinning masses. It seems like a more practical and viable solution to me, especially given there are more and more and more inverter

based generators coming online to just like make sure all those inverters are programmed to respond to this

SPEAKER_01with I do think that's basically true, and there's some interesting lessons maybe from history here.

SPEAKER_00About a decade ago in Germany, there was an interesting problem called the 50.2 hertz problem, 50 hertz being the European grid.

SPEAKER_01Right, ours is 60, theirs is 50.

SPEAKER_00Yeah, exactly. And on the German grid, a lot of rooftop residential solar power systems were being installed, and they had inverters to convert that DC power to AC. And those inverters had initially been programmed with a very hard cutoff when they detected the And nobody cared about this in the first couple of years

because there weren't very

SPEAKER_00many of them and it didn't really matter. But the problem began to snowball and grid managers realized that since every single one of them was programmed exactly the same way to trip off at exactly the same, you unintentionally created the synchronized trip off effect, which really could have cascaded. and the point for our conversation here is there was a solution and that was to reprogram those inverters to sort of have essentially a scramble a little bit of randomization on the exact number so they weren't all perfectly synchronized but that was a software push more or less and when you're looking

at trying to deploy big changes to the grid yeah I think I would probably take a software update over

SPEAKER_00some sort of hardware install any day of the week

SPEAKER_01Yeah, yeah, that's, it is sort of like a mirror image problem. Yes. And it's kind of has been, is being solved on the inverter side, is being solved on the supply side, and basically just, you know, we need to have a similar solution on the load side, more or less. It's worth mentioning that there are some grid regions that have implemented these

SPEAKER_00voltage ride-through requirements for large loads. Not very many of them, but there are some sort of early adopters here. Southwest Power Pool, you're seeing German FinGrid. The problem is that those are scattered. There are not very many of them, and they're not the same. So they've set up different ride-through and different reconnect requirements. They're not following a consolidated standard across the industry.

SPEAKER_01This brings us quite smoothly into what NERC wants people to do. There are seven core recommendations. Maybe we could just walk through. I mean, and they're really like everybody involved gets some of these recommendations. Like nobody escapes NERC's eye. These are transmission planners and utilities, regulators.

SPEAKER_03Yeah, there's about a dozen acronyms at the top. yes this was a real acronym soup everybody involved in this world is being asked basically to do something so maybe just walk through some of those recommendations like who's being asked to do what here yeah so as you said the seven essential actions they're kind of bucketed into I'd say like communication and modeling and then actual operational implementation on the communication

piece you know there's stuff up front that you know the first essential action is essentially that they need to planners need to collect the right data from data centers so they need

SPEAKER_03to be able to define exactly what technical information they need from computational loads and require transmission owners to collect it as a condition of interconnection so that's right out of the gate something that you know in some jurisdictions this is being done but it is a prerequisite to all the rest of them I would say and presumably you're going to want to sort of standardize what that information is. You're going to want for computational load to have a sort of standardized set of

SPEAKER_01data that they provide ISOs and the like.

SPEAKER_03Yeah, so this is an interesting one and I want to get Colin's take on this because we were just kind of discussing it a bit earlier. There's a kind of baseline here. For example, the types of grid stability studies that they expect to be done and they provide a recommendation of the type of modeling. But the language, it isn't fully prescriptive. It's not saying like, here is exactly the process that needs to be done. And some of the language leaves it up to interpretation to the

extent that we may

SPEAKER_03end up with more data points to what Colin was talking about around the ride-through process. And so that's one that's one of them better information from computational loads

SPEAKER_03Yeah, the second one is running grid stability studies. So basically simulating these exact instances and being like, how do we have the mechanisms in place to deal with it? And helping identify where the grid is vulnerable. So planners have to model what happens to the grid if a large amount of computational load suddenly disconnects. So a trial run for what we are actively seeing it, but you know trial run so that they can hopefully mitigate it and

that's also the ISOs and TSOs being asked to do that yeah that would be right yeah another one is commissioning what it's what's that all about no I think this is a very interesting one so commissioning is a concept you get it with a lot of construction projects

SPEAKER_00when you're finished with a commercial building you need to run through a commissioning process before you actually deliver it and that's not necessarily in place or standardized for data centers connecting to the grid This commissioning recommendation is saying that essentially you need to be evaluating the as-built data center, the electrical characteristics, and how it will actually respond to grid disturbances in a not purely a modeled sense, but also actually as-built. And you need to iterate or refine your model based on what's

actually in the facility. I will say one fascinating thing I find in this is there's a push to do this,

SPEAKER_00you know, where possible, full facility load and no loan test should be done with all the compute equipment in place. Interestingly, we often see data centers built in phases.

SPEAKER_01Yeah, right. Yeah. That's what I was going to ask. Like, do they have all that together in one place before they connect? no I think this opens a really interesting set of questions so does that create

SPEAKER_00this issue where grid operators are going to have to kind of continuously commission or revisit commission as new computational load is installed and you could argue that's a very good thing to do from a grid stability point of view but it's a complete pain in the you know what from the data center operator point of view and that's a distinction that I would make between what the NERC alert

SPEAKER_03recommends and what so in ERCOT there's a proposal in place for grid ride through and it's only for new interconnections. Whereas this is saying at the very top there's a line that identifies it that says this is for both existing or new and existing computational loads. And I think one of the essential tasks is actually redefining what counts as a change. And it's basically broadening that definition so that more things count as a change

SPEAKER_03and so it would be required to be reviewed through this process.

SPEAKER_01Yeah, it seems like you're going to get into fuzzy territory here. Like if you're just sort of adding, you know, you can sort of imagine a data center sort of adding just kind of one rack at a time. You can imagine these incremental changes, like how big of an incremental change triggers a new commissioning requirement. That just seems tricky. Very tricky to me. So those are the informational, the communication, the modeling ones. The next one on my list is protection.

SPEAKER_01I'll just throw that out. What does that mean?

SPEAKER_03So I think that's evaluating and addressing the ride through gaps.

SPEAKER_01So,

SPEAKER_03you know, planners have to identify where data centers would trip off during a routine fault and work on fixes to prevent unnecessary disconnection. So more kind of operationalizing the grid stability studies that is done in one of the previous stages. And then fault recording. What's that?

SPEAKER_00This gets to the point of how complex some of these UPS, these uninterruptible power supplies, potentially can be. They're highly active devices. They can not only, as I mentioned, sense frequency and voltage, but they'll include sort of smarts like incident counters. So they may actually not trip off the first time they see a voltage fluctuation, but they may count up, oops, I saw three, I saw four within two seconds. Now I'm out. And that kind of behavior is very complex to model if you

aren't aware of the very

SPEAKER_00specific logic in the UPS. And to really sort of trace the root cause of events, you would really like to have very high time resolution data on what was actually happening during that dynamic fault event. You'd really like to have granular time-based information on that. And that's what the spirit of this recommendation is, is install equipment that can really record that data to be used in root cause analysis after the fact.

SPEAKER_01All of these so far sound basically like informational, like better modeling, better communication. What are they recommending physically for computational loads to do?

SPEAKER_00This is a bit of what Doug and I were talking about earlier. If you look at the language here, you might think, coming to this, you might think, geez, NERC should have said voltage drive-through sounds really important for large loads. We're going to be a little bit more aggressive about saying that. Voltage ride through is either mandatory or strongly encouraged. Large loads shouldn't be allowed to interconnect to the grid until they demonstrate they can perform voltage ride through in certain conditions. That's not where the language has landed. It's a lot more gentle.

SPEAKER_00You know, coordination with competition load customers where possible to maximize the ability to ride through. So there's a lot of reasons for that. You know, Doug mentioned earlier the concerns from the data center industry, large load Dr. Justin Marchegiani So I think we're seeing a little bit of trying to be sensitive to that issue, push a little bit, nudge now, but not lock in a hard mandate without the remainder of that ecosystem in place.

And it's probably also a function of where in the process this alert falls, right? Grid entities of many shapes and sizes have until August to respond to this.

SPEAKER_03Following that, there will be new reliability standards drafted. And unfortunately, with these processes, it will take a couple of years for this to be enforced. You wouldn't expect it to be enforced until August. ah I put myself on the spot but 20 2027 2028 is probably like a realistic time frame these are gentle recommendations but presumably this is part of a process that is evolving in the direction eventually of requirements

real requirements so

SPEAKER_01this brings me to sort of FERC What is FERC's involvement in all this? Is it the case that once some of this gets worked out a little bit, FERC is going to be the entity to implement these requirements?

SPEAKER_03Yeah, I mean, typically that's, I guess, the NERC to FERC pipeline. Right. NERC develops reliability standards through these processes and then has to submit them to FERC for approval and then once FERC approves a NERC standard it becomes mandatory and you know there might be financial penalties for not subscribing etc etc so this current guideline right it's a voluntary guideline is a signal for what the mandatory standard will look like before it actually you

know arrives in force and I think relatedly what is the large load working group is that FERC related or is that pre-FERC in the NERC to FERC pipeline yeah it's a NERC initiative I can't remember exactly when they started but I think they were like the large loads task force and now they're large loads working group and they've effectively been publishing white papers and guidelines like they were in charge of the associated

SPEAKER_03reliability guidelines that came with this that talks not only about these super short-term events, but also how you bake in these computational loads into long-term resource planning. They had lots of things to say about load forecasting, and NERC has been generally quite... They've had a lot to say about how the approaches to load forecasting are not sufficient going forward because of the event we find ourselves in. Yeah, I want to return to that in a minute because that's a super interesting question.

SPEAKER_01But one of the questions is raised, and I guess this would be a good time to ask it, which is a lot of this sounds like the hyperscalers who have just been out basically cowboying up and throwing these giant loads on the grid and like throwing gas generators all around them and just it's a there's been a real wild west vibe to all this going on and here comes the dreaded nanny state coming to tell these cowboys uh like get

your shit in order

SPEAKER_01here so I sort of wonder what is the hyperscalers attitude toward all this because this I don't see how this is going to avoid ending up in a situation where basically you as a data center developer as a data center operator are going to have a lot more work on your plate basically you're going to have to do a lot more data gathering data reporting etc etc I wonder like are they what's their kind of disposition toward all this

SPEAKER_03Yeah, I would definitely use the case in the States that is furthest along on this file is that ERCOT proposal, that ride-through proposal. And it's in its second or third iteration now. The first proposal, the Data Center Coalition, right? So that's the kind of groups that you're referring to. They filed these formal objections to the original proposal. And it largely centered on the hardware damage argument that Yes well this is my question like like presumably there's a

reason that they trip off so easily is that they're protecting extremely expensive and valuable equipment

SPEAKER_01is Can you ride through and ensure that that equipment is not damaged? Presumably they're a little sensitive about this.

SPEAKER_03Yeah, certainly. And whether or not the equipment is expensive, but it's what the equipment is doing. That is part of the arms race we live in, which is ensuring that you're serving the AI loads that are coming through your system, be it inference or training. And so It's a similar reason why there's been challenges in getting typical demand-side response mechanisms, which are price-based.

You're dealing with entities that set a very high value on the power because it's delivering these services that are obviously the apple of the market eye at the

SPEAKER_03moment. I think it's entirely feasible to design these systems to ride through better.

SPEAKER_00It's not impossible to design UPS systems to do more ride-through except a wider tolerance band. They've just always been governed with a different design principle in mind. They've been built according to something called the ITIC curve, which specifies a little bit of a conservative view about when to trip off. But from an electrical engineering point of view, it's certainly not impossible to build more protection and to allow longer ride-throughs. It's more of a question from a hyperscaler point of view about

the availability and

SPEAKER_00the validation of those devices. Thanks a lot, ERCOT or whoever you told me I have to go do this. Who can I buy them from? Have you qualified them? That's a supply chain headache I don't want. So I think you need to look more to that than any sort of fundamental electrical engineering limitations. Well this again tees up my next question really well which is what physical or

SPEAKER_01electrical engineering changes can hyperscalers make to be better grid you know here on Volts one of our slogans is it's all really just batteries in the end so I'm wondering is this is this also in the end just more batteries so like what what do we want computational loads to do in electrical engineering terms to be better grid citizens hey there everybody don't worry I'm not going to tell you about a new mattress or push a credit card on you this isn't an ad

SPEAKER_01There are no ads on Volts. It is supported entirely by listeners like you. If you'll indulge me for a second, I'd like to ask for your support. I started Volts because we're all surrounded by depressing news about climate change and misinformation about clean energy. And it's never been more important to share the stories of the real people on the ground doing the real work of transition and all the ingenuity and courage and public spirit they are bringing to it. People are hungry to hear these stories, to learn from and find inspiration in them.

I've heard from people who change majors or careers after hearing episodes of Volts.

SPEAKER_01People using it in classrooms, community groups, even state legislators who have passed bills inspired by specific episodes. Sharing these stories matters. It makes a difference. If you have found value in it and want to help me continue doing it, I hope you will join the community of paid subscribers at volts.wtf it's about the cost of a cup of coffee a month if you don't like subscriptions you can make a one-time contribution leave a review on Apple or Spotify or just tell a friend about volts I am grateful for any and all support if you're

already a paid

SPEAKER_01subscriber thank you and now back to the show you know here on Volts one of our slogans is it's all really just batteries in the end so I'm wondering is this is this also in the end just more batteries so like what what do we want computational loads to do in electrical engineering terms to be better grid citizens it is in many ways all batteries in the end although

SPEAKER_00there's we can talk rectifiers and inverters as well Yeah, I think there are, first of all, software updates. So for example, the idea of these event counters I mentioned earlier in the UPS logic, gosh, I saw three or four events within the same four seconds. I'm taking that as a sign something large is wrong. I'm tripping off. You can just change that in software. You can just not have an event counter or not include that as one of your trip off. That's a software update. And indeed, that would likely,

SPEAKER_00you know, that would be one contribution to being a better grid citizen. What you're otherwise talking about is putting more stress on the battery component of the UPS, banging on that a little bit harder, or at least accepting a little bit higher risk that that's going to have to absorb voltages, frequencies outside of a current comfort range. That can involve equipment updates that may involve somewhat modified designs in the electrical engineering. You know, those are two sides of the sort of software update and hardware

update that would

SPEAKER_00apply.

SPEAKER_01Is anyone talking about trying to make the compute itself more flexible?

SPEAKER_00Well, at a macro level, absolutely. Lots of interesting ideas about and we're seeing them implemented about scheduling big compute jobs. and there's a lot you can do on that. It's terrific to see some work on that. That involves planned flexibility, right? So not responding to unexpected events.

SPEAKER_01Well, just like you were saying, like they were asking inverters to like randomize a little bit, not do all the same thing at the same time. I mean, you could see it's kind of a similar thing on this side, right? Like randomize your compute loads a little bit so that they're all not doing the same thing at the same time.

SPEAKER_00Yeah, no, that's an interesting idea. I think that randomization would apply more in these UPS systems that are facing the grid. So, you know, some percentage of them would trip off at low, you know, minor voltage, or there would be sort of a scatter of their thresholds to trip off. I mean, another challenge that we didn't even mention this earlier, there's equipment damage, but compute loads that are in the middle of some complicated computation and have a lot of sensitive data in active memory, if power goes down, that data is all gone it wasn't written to drive so you get

data corruption even if the physical system isn't damaged you get data corruption you obviously get certain you know loss of service if these are cloud servers but there's a range of concerns that have motivated the data center designed to be very conservative about yeah it's like playing a video game and you have to go back to the previous checkpoint yeah and you realize that it's very far I lost all my progress that's right

SPEAKER_01All right, I'm not sure if this is the time to raise this or if this is even relevant here, but there's a lot of talk about the distinction between co-location and behind-the-meter power responses. What is that distinction and how does that play into all this?

SPEAKER_00So the behind the meter concept is, of course, having generation on site, but on site in such a way that it's electrically connected directly to the load. It's not going out to the grid and then back. And I think in the extreme case of that, what we might call a fully islanded system, where the data center has literally zero connection to the grid, then this problem essentially goes away because the data center but nobody's nobody's really doing that ain't nobody gonna really do that

that's exactly right so that's an extreme case that's silly to think too much about I think what we're looking at more of these hybrid arrangements where you've got on-site behind the meter generation but you also have a grid tie and there's you know there's reasons to believe this could actually make it a little bit more problematic because that's

SPEAKER_00an even more active system In cases where that behind-the-meter facility is providing part of the load and the grid tie is providing part of the load, that mitigates the problem because the data center is using less grid power than it would in other contexts, but it makes it a more complex problem because you've got more pieces of the puzzle there to balance out. Yeah, and all these regulations that apply to generators to try to make them good grid

SPEAKER_01citizens, are they applying to these generators behind the meter? I would say that's an aspect of the NERC alert that we haven't fully touched on is that it includes a they want to see the full apparatus they want to understand in your you know your little in your campus what is everything going on there including any co-located generation and so I think that has dual purpose right one is are you therefore you know if you have sufficient backup generation are you therefore more likely to trip off and have more sensitive

tolerance to that And then also to Colin's point of what is then the interaction between the generator that is behind the meter and the load that we are servicing as the grid

SPEAKER_03operator.

SPEAKER_01But as I understand it, they're insistent on the difference between behind the meter and co-located, which is one of the things I'm groping. What does co-location mean in this context? I would view it as the data center is physically sited at a power plant or vice versa. and it takes power directly without it flowing through the transmission system. Right, but not behind the meter, but not behind the data center's meter, just literally physically located next to a power plant,

SPEAKER_01which is also, but the power plant is hooked up to the larger transmission system. You're right. And so is the data center.

SPEAKER_03Yes. So that would be like the case I gave is the full behind the meter case, the co-location case, which is you know relevant for like I think the you know the FERC directive to PJM to like develop these co-location tariffs and obviously I'm sure you've done another part on this on the PJM tariff discussion but that is more about okay how do we then interact the co-locate to resource the load and the service firm or otherwise that I will receive from the grid so I see that's kind of how I

would view them slightly

SPEAKER_03separately at some point in one of these PDFs sorry to give you a big syllabus of reading there I can't keep them all distinct in my head but somewhere I saw a demand response brought up and referred to in this context as a ghost battery which I thought was fun but like what is what I think that was my term so I'll take credit for that oh good nice work I love a good new term what how does that what is the operational relevance here like how is demand response like Volts listeners

are very familiar with demand response which is just you know demand ramping up and down in response to grid conditions as opposed to just generators ramping up and down how does that interact with this with the data center mess specifically yeah it's definitely

SPEAKER_03under the umbrella like I would This whole conversation is related to data center flexibility. It's like you are either flexibly interrupting the power supply and going behind the meter or you're flexibly responding to grid constraints, prices, what have you. the distinction I would make is that most of the conversation around demand response is occurring in these planned as Colin put it right these planned responses whereas this is is flexibility of a different type

and it's arguably by dropping off the grid which is what you want in some of the planned cases you're

SPEAKER_03creating problems so They're under the same umbrella. And in fact, you know, I think there's various initiatives going on, like the EPRI DC Flex Initiative. Like they look at both. They're considering the array of this challenge and not excluding one for the other, but they are certainly different.

SPEAKER_01Is there such a thing today as demand response of any scale that is capable of responding at the level of milliseconds and seconds? Is that even a thing that computational loads could procure if they wanted to?

SPEAKER_03Without going back over this, I would argue that that is what the uninterruptible power supplies are doing. That is their demand response in a way of responding to an issue in these

SPEAKER_01sub-second or second intervals. Well, I guess what I had in mind is like, you could say as a computational load, like if we drop off, if we have this other demand response out there, you know, demand response is not just demand decreasing. You could potentially say, hey, we'll ramp up demand elsewhere to compensate for this. I just wonder if that is even like a possibility. I would frame that as the current sort of frequency stability ancillary services market where some very fast responding asset like a battery or

like a flywheel is is essentially on a very short timescale ready to ramp up or down to respond,

SPEAKER_00you know, sort of seconds to respond to small mismatches.

SPEAKER_01Yeah, I guess one way of putting this is like ancillary services are, in my understanding, are mostly out there doing relatively small scale work. It just seems like if you're putting gigs, if you're involving gigs, all of a sudden ancillary services, you need a lot more of them. Yeah. that's right I think the ancillary services market is growing right it's growing in volume and price the type of resources on the grid might be saturating that so like batteries for example yes I mean one of one of the sort of

critiques about the economics of batteries you know people are saying oh batteries are value stacking they have multiple values they can one of the things they can do is play in these

SPEAKER_01ancillary markets and then the response to that has always been well you know you put a few batteries on the grid and you basically saturate the ancillary services market and then it's not a value for any batteries beyond that but if all the sudden ancillary services markets are like booming in volume all the sudden again lots more batteries yeah you're back to lots more batteries as your answer I think maybe I'll put my more engineering than economist hat on but I think trying to build a you know gigawatt scale ancillary services market to protect against this

possible load trip issue is

SPEAKER_00probably the wrong direction unscalable I think This is what motivates the look at the ride-through requirements of the engineering solutions at the data center, rather than trying to stand up as separate.

SPEAKER_01So that was sort of my question. Realistically, you're not going to get gigawatt-scale ancillary services that can respond in seconds.

SPEAKER_00And wildly uneconomic to pay them to sit around in case they're open. so yeah right sit around for completely unpredictable exactly yeah so in sporadic events yeah so it's mostly going to be solved at the computational load yeah level I did want to touch on one sort of mirror image aspect of this which Doug mentioned earlier but we should expand on a bit the reconnection problem so here you've got a data center that's tripped offline because of a problem and and maybe it was justified maybe not it's gonna come back

well and there's a big issue so is it coming online you know as soon as the

SPEAKER_00internal logic in that UPS says I'm good just 100% back online well that boy yeah that if that happens in a synchronized way across a gigawatt that's just as big of a problem as tripping off right then you have grid operators telling a gigawatts worth of generators come online quickly and then like seconds to minutes later saying okay go back online go back offline quickly you gotta smooth that out somehow it's just crazy so the problem is there aren't broadly accepted standards of exactly what that looks like

SPEAKER_00and You do want to get them back online, but you've got to think carefully about how to do that in a smooth way that doesn't put you right back in the hole. And so that we see in this discussion as well, the ride through, but then the reconnection piece is sort of less intuitive, but just as important or else you're recreating. It's the mirror image of the trip-off problem.

SPEAKER_01Right. These are not even ramps, really. These are like cliffs.

SPEAKER_00Well, they could be ramps. I mean, that's sort of part of the thinking is that maybe there's a maximum ramp rate that the UPS is allowed to do, and then that's a potential solution.

SPEAKER_03And that's a problem that is actively in these discussions, right? I think we focus the conversation on ride-through and that full tripping, but what I mentioned earlier around the training loads and how they spike and dip and it's exactly that those ramp rates and there are guidelines for how fast load should ramp up and down and in some cases they're outside of those regulations right generators are supposed to ramp up like as we say these are our generators are already under a lot of regulations and they are not allowed

to do these giant cliffs yep so speaking of like what people are doing about this you mentioned that

SPEAKER_01ERCOT has some regs in the works presumably state legislators and regulators you know they're all everybody in the world is freaking out about freaking out about data centers freaking out about computational load like what is what are states doing about all this like there's all these bills I know about data centers like in every basically in every state legislature at this point like is this part of what's in those bills what are state legislators and regulators doing right now

SPEAKER_00Well, we've taken a look at this to some extent, and largely these reliability issues are not in the purview of state legislators. They're not necessarily front of mind. Maybe in the last week or two, given the NERC alert, that's begun to change. But the focus of the legislation has really been around environmental impacts of data centers, power price, you know, sort of raw power, consumer power price impacts. And then on the flip side of the coin, you see plenty of efforts at the state legislative level

through tax credits or

SPEAKER_00other things to attract data centers to the state. But these reliability issues are really out of sight for many policymakers. And maybe we're going to see some motion on that. At the same time, NERC is doing its job. These are highly technical issues. And they probably should be largely addressed at the existing level of NERC.

SPEAKER_01I almost wonder, from the state perspective, it seems like one of the things, if you had godlike powers over all this, one of the things you would do to increase safety is not... cluster these loads geographically it seemed so that they're all on the same grid it seemed like you might want to geographically disperse them I have no idea sort of like what regulatory lever you would pull to do that but is that even on the table well a couple thoughts on that there's an engineering

reason for that so voltage disturbances tend to be more limited as the scale of the grid whereas

SPEAKER_00frequency disturbances affect the entire balancing area so Yeah, if you can get outside of that sort of radius. On the other hand, many jurisdictions, you know, want to attract data centers. Data Center Alley, Virginia is the, you know, is the grandfather of them all. I mean, that's the exact opposite. So I think you do have a little bit of a collision of the economic arguments around wanting a tax base, wanting whatever it is to cluster, and then these great engineering arguments of, no, no, no, no, no. Please keep these a little farther apart for these stability issues.

SPEAKER_00I think those are, unfortunately, kind of in tension.

SPEAKER_01Interesting. And just maybe listeners have this question on their mind.

SPEAKER_03Isn't this a podcast about decarbonization? Yeah. this has been mostly just about electrical engineering and about about data centers and their effects on the grid but this is on the contrary David it's called volts and we are talking about voltage right we are very much talking about volts here but is there a decarb angle to all this like like lots of data centers seem to be

SPEAKER_01lunging for gas and like in ERCOT the number of gas entries into the interconnection queue is up 150% and like some renewables are withdrawing from the interconnection queue and it seems like at least the hyperscalers are looking at gas as a reliability solution that they need that is distressing I guess I just throw it out as a general matter like how can we respond to

these issues and regulate in such a way as to include decarbonization in the conversation as to

SPEAKER_01steer things toward renewables and batteries rather than gas plants

SPEAKER_00Totally agree that this needs some more thinking. And I'd argue the economics are a piece of this. I think we are going to see that the renewables and batteries side in the long term is winning out on costs. And hopefully that'll drive some thinking. I hope that's true because I say it like 50 times a lot.

SPEAKER_01But that doesn't seem like what they're doing right now.

SPEAKER_00You know what I mean? A lot in the queue. And of course, we'll see what's completed, what supply chains for turbine equipment enable. We've taken a look at the projections for new gas production, you know, 10, 11 BCF a day is what you're seeing from Q. That's a lot. There's a lot of upstream methane leaks to think about there. On the other hand, you know, delivering that requires gas transmission pipeline, distribution infrastructure that doesn't necessarily exist. So I think it's hard to project a real completion rate.

I do wonder how much there's a world of kind of zombie gas projects or partially

SPEAKER_00completed ones where the economics don't make sense one or two years in, three years in. But can you explain what is going through the hyperscalers' minds that they are going for gas?

SPEAKER_01What are they thinking? So, you know, you mentioned reliability from the perspective of the data center.

SPEAKER_00You know, I'm not worried about the rest of the grid. I'm worried about enough power for me. The solution of having my own on-site generation kind of seems good at first and I can see the appeal in the near term I kind of want And to some extent it seems to like free you from some of this nanny state regulation of the grid right I think that's a mirage though so you do still have to get the gas on site and that involves working with pipeline permitting and construction potentially so I think there's if you want to use the nanny state metaphor I don't I don't think you're necessarily getting away from that fully

SPEAKER_03You know, at the end of the day, firm power is hard to procure. And I think that's largely the reason for going so all in on gas. I'd say like my take on the decarbonization angle is that kind of back to what Colin said when we were talking about, and David, you preface this, you're like, is the solution batteries? It always seems to be. Well, you know, there are, we're making leaps and bounds in long duration energy storage technologies. They are really having a big moment in

SPEAKER_01Yes. Upcoming pod on that, by the way, the role of long-duration energy storage in this data center mess. Perfect.

SPEAKER_03I'm sure you'll discuss on that. They can do a job in firming up renewables and providing that firm power and potentially play a dual role. The uninterruptible power supplies, it is switching to batteries. That is often the means of switching. And so... I think there are links to decarbonization solutions that are burgeoning at the moment that could play a role here beyond what we're seeing today.

SPEAKER_01Yeah, I always wonder, like, people talk, these hyperscaler guys talk about firmness as though it's some magical quality. I just don't know, like, what firmness you're getting from gas that you don't get from storage. Like, it's the same, the electrons are the same. If you can call on it and it provides you the electrons, then it's firm. Like, it's hard not to see an element of, let's say, masculine energy involved in preferring gas or nuclear for your firmness over batteries. But, like, operationally,

I'm sure the folks at Form Energy would fully agree with you and the challenge up to now has been the duration and the cycling and we're potentially finding

SPEAKER_03solutions to that Well also I'll just add as we think about these questions of how inverter based resources can be reliable on the grid and how these similarly power electronics based loads can be reliable on the grid working through those engineering issues and showing that a inverter based renewable resource and large loads behind power

SPEAKER_00electronics can work reliably as long as standards are aligned and we solve some of those. That's an important piece of getting towards that decarbonized grid, of giving engineering confidence that, yeah, we can do this. We just got to work through the problems.

SPEAKER_03I always take the long view that this challenge is, it's acute and it's here today, but it is something that long-term decarbonization requires us to figure out because much of the solution to decarbonization is to electrify. And yes, we are So let's move into I think sort of the final cluster of questions which have to do with so

if you are requiring all this of hyperscalers a bunch of new reporting maybe some new electrical engineering requirements maybe more batteries on site there's no way around the fact that however this settles out it's going to be a bigger there's going to be more requirements and obligations put on the back of hyperscalers and

SPEAKER_01then you would think this sort of inevitable result of that is going to be that it's going to be a little bit slower. Like if the ISOs and the utilities are all have these new reporting requirements, they're all communicating more, they're all doing more modeling and better modeling, et cetera, et cetera, et cetera. It seems inevitable that that's going to slow stuff down. So then You might think, well, these projections people have of massive data center demand coming online. Well, maybe these projections need to be scaled back a little bit.

SPEAKER_01And then you get in this weird recursive thing because like modeling... future demand is part of this now but like the requirement to model it is in some sense affecting how fast it's going to happen so like is it fair to say that all of these requirements if put into place are going to slow the rush to data centers and thus that some of these wilder projections are probably not going to come to pass who would be an energy system modeler hey especially a

long-term forecaster that

SPEAKER_03That sounds like a terrible occupation.

SPEAKER_01This is your job, Doug. I want a firm and clear answer on this.

SPEAKER_03So, yeah, I think it's a very difficult thing to foresee. And what I liked about the NERC Alert is that they paired it with these reliability guidelines that really had a bit of a playbook for how they think we should be thinking about load forecasting approaches when it comes to data center load. you know we've talked about this internally that there's a few ways you can forecast this so you can look at hyperscaler CapEx announcements and SEC filings

you can look at the GPU and chip shipment data and then you can also look at the interconnection queue although typically you have to provide a pretty significant

SPEAKER_03haircut to that I'm inclined to agree with you that it creates more obligations and challenges to getting interconnection such that it makes that job even more difficult to do David I'll give it maybe a bit contrarian perspective which is I actually think the incremental effort here is pretty minuscule especially compared to the other challenges that you know rapid data setter build out already faces so getting

SPEAKER_00sufficient switchgear and transformers

SPEAKER_01Yeah, there's all these supply chain challenges that people are, and especially if you want to run your thing on gas, too. That's right.

SPEAKER_00There's a huge supply chain constriction there. So, I mean, I would argue that the headaches that these requirements create are pretty far down the list of stuff that would slow a project down. The way it could turn into a headache is if a mandate were put in place prior to a clear standard and compliant equipment being broadly available on the market. so if the regulars get it wrong and get ahead of where feasible solutions are available then yes it can turn into a headache but in and of itself I think if the if compliant voltage ride through compliant UPS's are available a

data center project developer can probably get by by specifying what they are providing a little bit more data and to the grid operator and I think that's actually a relatively minor lift compared to all the other headaches high up on the list of that project but

SPEAKER_01yeah like carbon direct your firm one of the white papers uh One of the white papers you sent me says pretty flat out that a majority of the data centers in the queue are probably not going to get built. So why is that? Oh, well, that's a whole podcast of itself.

SPEAKER_00I mean, I think there's... It's the other hassles outside of this? I think those are heavily other hassles are driving that. I mean, I... Grid reliability is an important thing to think about and we see it growing and that's why it's great that NERC's replying here but the compliance requirements I think compared to yeah compared to other headaches of securing sufficient bulk power at all sites securing like I said switchgear and transformer equipment other equipment shortages Those are slowing down projects today in ways that are far more

substantial.

SPEAKER_00So I would argue that the ask being made of the hyperscalers, while I agree there's a pain in the ass factor, is not that severe here. There's a lot of benefit to grid stability that can be done with a pretty light lift. But it is the position of Carbon Direct that the wilder projections of data center

SPEAKER_01load are overheated.

SPEAKER_00It's a position. I mean, I think our analysis shows that there's a lot of load being added. But yes, if you took the outside numbers, no, those are pretty far off base. We're going to see a lot of load. And also, if it's a 40% completion rate, that's still an enormous amount of load compared to historical. So getting too wrapped around the axle on this, I think, is not merited. There's a huge, huge, huge planning challenge to be met here. But yeah, the outside numbers, I would, our analysis says, don't take those to the bank. Okay really final question which is you know we've done pods a lot on like EV

charging and sort of the kind of TLDR on large scale EV charging is if you do it in an uncontrolled wild west manner it could screw up the grid badly but if you do it in a planned and rational manner not only could it not be a detriment to the grid

SPEAKER_01it could prove an active help to the grid like you can use it can be a tool an active tool for grid stability and for grid reliability and I just kind of am wondering is the same true of computational load is it the case that if we get this right and the right requirements are in place that computational load could be an active help for grid

SPEAKER_00stability and reliability or is that too optimistic I'll start and let Doug wrap up. I agree very strongly with that computational loads sitting behind power electronics if done right can absolutely be a positive contribution to grid stability and that involves shifting some of the design basis so that it's not purely about extremely conservative protection of sensitive computer equipment it's about also taking into account writing through faults and potentially some active

grid stability support through frequency reg or other similar kinds of things

SPEAKER_01I mean, if you could make a gigawatt scale data center into a demand response tool, that's a giant demand response tool. Absolutely.

SPEAKER_03Like the stack there, right? It's almost of a VPP. You've got on-site generator, you've got battery backup systems, you've got, in some cases, controllable, flexible load. And then you've also got fast responding power electronics. So I know you've done pods on VPPs, but that's a decent recipe for being a good asset. So I would concur with Colin on that.

SPEAKER_01Well, that seems like a good optimistic note to end on. my audience does not always respond well to optimistic takes on data centers there's a lot of I mean whatever else you can say about hyperscalers they have not done very good PR for themselves they've not told their story very well but like if you can get multiple gigawatts of new load to be responsive and responsible just

SPEAKER_01could have a happy ending

SPEAKER_00I think so. I mean, David, I'll just say, I think the details are so nerdy here and trying to even grasp why this matters. I mean, Doug and I were talking about this fun analogy, the bicycle analogy. about when you were a kid you might have ridden one of these bikes with no gears and you know pedal brakes and when you got going on those bikes blazing downhill and those pedals are whipping around there if you take your feet off the pedals the bike speeds up the frequency speeds up because it's not having

to sort of carry the load and then if you want to put your feet back on you damn well better be sure you're synchronized with those pedals or it's gonna it's gonna really slam into you

SPEAKER_00and hurt you That's what's going on here on the frequency side about connecting and disconnecting from the grid. And this is often not very sort of physically intuitive to people about why any of this matters. It's just about total megawatts. And conveying that a little bit might help open up that.

SPEAKER_01So you need gears.

SPEAKER_00Yeah, yeah, sure.

SPEAKER_01And more sensitive brakes. Something like that, yeah. We have family injuries to attest to just the problem you're talking about. That's right. All right, guys, this is so fascinating. Thank you so much for coming on and talking through all this with us.

SPEAKER_03Thanks so much, David.

SPEAKER_01Really appreciate it. Thank you for listening to Volts. It takes a village to make this podcast work. Shout out especially to my super producer, Kyle McDonald, who makes me and my guests sound smart every week. And it is all supported entirely by listeners like you. so if you value conversations like this please consider joining our community of paid subscribers at volts.wtf or leaving a nice review or

telling a friend about

SPEAKER_01Volts or all three thanks so much and I'll see you next time

Open the transcript file

Hosts and Guests

Nobody is credited on this episode yet.

Credit the people on this episode

Be the first to rate this episode

More episodes

All episodes
  1. Can a developer turn data centers’ reputation around?

    Nov 20, 20261 hr 6 minAudio

    This is a public episode. If you'd like to discuss this with other subscribers or get access to bonus episodes, visit www.volts.wtf/subscribe When people push for better data centers, they picture hyperscalers - Amazon,...

    Credit the people on this episode

  2. “Repowering” worn out solar fields could create gigawatts of new grid capacity, quickly

    Nov 18, 20261 hr 18 minAudio

    This is a public episode. If you'd like to discuss this with other subscribers or get access to bonus episodes, visit www.volts.wtf/subscribe America’s first big wave of solar power installations, built between 15 and...

    Credit the people on this episode

  3. The federal permitting bill has been updated. What changed?

    Nov 11, 20261 hr 59 minAudio

    This is a public episode. If you'd like to discuss this with other subscribers or get access to bonus episodes, visit www.volts.wtf/subscribe The Senate’s bipartisan permitting bill got a manager’s amendment last week -...

    Credit the people on this episode

  4. So, how about those midterm elections?

    Nov 9, 20261 hr 26 minAudio

    This is a public episode. If you'd like to discuss this with other subscribers or get access to bonus episodes, visit www.volts.wtf/subscribe Last week’s election was a blue wave all the way down the ballot: Democrats...

    Credit the people on this episode

  5. Best of October 2026

    Nov 6, 202614 minAudio

    This is a free preview of a paid episode. To hear more, visit www.volts.wtf Volts published eight conversations in October, which is a lot for anyone to listen to. We’ve rounded up the highlights into less than an hour....

    Credit the people on this episode