This is a public episode. If you'd like to discuss this with other subscribers or get access to bonus episodes, visit www.volts.wtf/subscribe Typically, AI data centers are large, inflexible loads that the grid has to build around, which is one reason utilities take so long to connect them. Emerald AI has designed a “digital brain” that can ramp down, move, or delay computing jobs in a data center on demand, making a data center a flexible asset to the grid. I talk with CEO Varun Sivaram about how the software works, what flexibility costs the compute, why it beats just installing batteries, whether utilities can enforce it, and what it would mean for clean energy. Chapters: 00:00 - Introduction 03:05 - Temporal, spatial, and resource flexibility 06:26 - What Emerald Conductor touches on site 08:35 - Who decides which workloads can flex 10:55 - Who is liable when a job slows down 13:45 - Who actually signs the contract 14:49 - Larger and faster grid connections 18:02 - Enforcing the flexibility promise 19:05 - What broke in the demos, from bad nodes to slow telemetry 26:41 - What flexing costs the compute jobs 29:21 - Why not just use batteries, and the demand merit order 35:44 - Training, inference, and substation-scale data centers 40:23 - PJM, ERCOT, and legal enforceability 44:50 - Renewables, gas, and consumer bills
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
[music]
SPEAKER_01Okay, all right. Hello, hello, everyone. This is Volts for August 26, 2026. Making data centers flexible so they can serve the grid rather than stress it out. I'm your host, David Roberts. As attentive Volts listeners know, the U.S. grid is built for its peak loads, which only materialize for a handful of hours a year.
SPEAKER_01The rest of the time, an enormous amount of grid capacity just sits there. When a large load, like a data center, asks to hook up to the grid, conventionally what it's asking for is continuous high power, including during those peak hours, meaning it raises the peak. And if you raise the peak, you have to build new grid capacity to serve it. That's a big part of why it's taking so long to get data centers connected these days.
SPEAKER_01Utilities study them, discover that they require a bunch of grid upgrades, and then everyone starts arguing about who pays. But what if data centers could ramp down their demand during those hours so they didn't raise the peak at all? A 2025 study out of Duke's Nicholas Institute, which has since become somewhat famous in the industry, found that if new loads could curtail demand for just half a percent
SPEAKER_01of their uptime, something like 100 gigawatts of new load could be added to the existing grid without the need for new generating capacity. So how do you actually make a data center flexible like that? That is the problem Varun Sivaram set out to solve when he founded Emerald AI in late 2024. The company sells software that orchestrates computing loads, throttling, deferring, and shifting them as the grid demands.
SPEAKER_01Emerald has raised a lot of money really fast, partly on the back of Sivaram's credibility. He has an almost comically packed resume, a PhD in physics, CTO of India's largest clean energy company, chief strategy and innovation officer at Orsted, managing director for clean energy at the State Department, author of a book, Taming the Sun. I could go on, but we need to get on with the podcast. We are going to get into what data center load flexibility actually means,
SPEAKER_01whether it's reliable or just a pinky promise, and how the grid benefits if it works. So, all right then, with no further ado, Varun Sivaram, welcome to Volts. Thank you so much for coming. Dave, thanks so much for having me. Been a long-time fan. Yeah, this is long overdue. This is a long time coming. I'm excited to talk. I think the place to start is just the literal mechanics here. So you sell software called Conductor.
SPEAKER_01It sits in between the grid and the data center. When the grid comes to Conductor and says, hey, I need you to drop 20 megawatts for two hours in some sort of peak or emergency event, What does Conductor, what is it touching, what is it doing?
SPEAKER_00Yeah, great question. And to answer this, let's just back up a moment and say, in order for a data center to be flexible, responsive to the grid, there are kind of three ways that you could do that, right? I call them temporal flexibility, spatial flexibility, and resource flexibility. The first way temporal flexibility is you might have some things that are running in the data center that don't need to run that fast at that very moment. And so you might be able to slow down some of your AI computations or pause some
SPEAKER_00of your jobs, reschedule jobs. And you can do this in many ways, by the way. You can downclock some of the individual GPUs or nodes. You can reallocate the number of GPUs working on a particular task. You can force a checkpoint and pause a run. There are many different ways to do this. But temporal flexibility is, in time, can you flexibly change when work happens or the rate at which it happens? The second is called spatial flexibility. And that's in space.
SPEAKER_00Can you change where the work happens? The amazing thing about data centers is that they're connected at the speed of light with one another. And so if you're able to move an AI job from one location to another, it could be separated by 100 or 500 or thousands of miles and remain within the latency constraints of your customers. The customers might not even notice the difference while you have provided real grid relief in one location by moving work to another one. And then finally, there's what I call resource flexibility. And this is where you step outside of the data center and you say,
SPEAKER_00can we put some other stuff like batteries and generators near the data center that help that data center to reduce its net grid withdrawal or net impact on the grid for some temporary period of time? The correct way to solve this problem is to orchestrate all three of these alternatives together. They're not alternatives, they're complements. And I used to orchestrate intentionally. Emerald Conductor is literally conducting an orchestra of available interventions, temporal, spatial, and resource flexibility. And so you asked, Dave, you know, what does Emerald Conductor do?
SPEAKER_00It kind of does all this stuff. It is ensuring that the GPS And the scheduler and the AI jobs are temporarily and spatially flexible in time and space. And it's also making sure to coordinate with a local resource, let's say a battery that is on site, so that we can use what's available in the battery without running into its constraints on state of charge or discharge rate or durability. All of this is a very complex problem to solve, and we have developed an AI technology ourselves,
SPEAKER_00which is underlying the Emerald Conductor platform. We are an AI that runs AI, and we have AI agents that are inside the data centers that are orchestrating all of these autonomous decisions.
SPEAKER_01Yeah, that was actually my second question. So you're not just conductors, not just controlling... The GPU, the computing, you also are in touch with onsite batteries or onsite backup generation or like the cooling system. How far do the tendrils go? I mean, is everything onsite in one way or another? Are you touching it like you can control all of it basically?
SPEAKER_00That's exactly right. And we do a lot of this with our partners and our investors that are large Fortune 500 companies that are real experts in this. We've announced our partnership with Siemens, for example, where Siemens has software that controls a lot of this technology on site. The battery, the microgrid. We have other partnerships with folks like Eaton. They have these UPS systems, GE Vernova. We have a range of partners. And what we make sure to do is the Emerald Conductor serves as this brain that says, hey, what's all the stuff on site that can provide me some flexibility
SPEAKER_00within its constraints? And how do I fuse that or orchestrate it alongside all of the So yes, you can think of Emerald as the brain or what we like to call AI factories following NVIDIA's lead. It turns the AI factory into a controllable power user. And I think this is a very profound point. Traditionally, you look at a data center or any other load, a car factory, as an unpredictable user of power that the grid has to provision for.
SPEAKER_00Like you said, David, in the intro, you said, hey, we build these massive energy systems and keep building our peak capacity, but most of the time, Transmission and distribution capacity is underutilized. Generation is underutilized. And so we're really using the grid at 50% of what it could be doing. Well, if the data center itself or these AI factories become precise, controllable energy users, I believe that makes them energy technologies. That's counterintuitive. Like you think of nuclear power plants or batteries as energy technologies.
SPEAKER_00But what if data centers were energy technologies?
SPEAKER_01Here at Volts, we're very familiar with controllable load and all its many glorious benefits. So we're going to get into some of that. But on the computing front, I have some questions about just the computing front. So one of the things your framework has is these tiers of computing workloads. There are jobs that can't be touched, that have to run all the time. There are jobs that can tolerate 10%. Throughput loss, 25%, 50%, there's these tiers.
SPEAKER_01So one of my questions is, who decides what's in what tier? Is that something that the owners of the compute tell you, or is that something that conductor... That's a great question, Dave. It's the heart of what we're doing, which is serving both sides at the same time, the energy grid's needs and the
SPEAKER_00AI customer's needs. Look, at the end of the day, AI customers are doing the most economically important work in America, right? Generating valuable tokens of artificial intelligence. And you don't want to mess with that in a way that's going to degrade their expected quality of service. And so, yes, today for our commercial scale deployments, we receive tags from the customers,
SPEAKER_00the users of AI compute, tagging which of their jobs has which flexibility parameter. And it's more than just, you know, this can be flexed and this cannot be. Some jobs, a benchmarking run, for example, you really can't downclock the clock frequency of the GPU because it'll mess with the benchmarking run. Some jobs, a fine tuning run, they can be deferred. They could also be downclocked, but some particular workloads like a serving inference job really can't be downclocked or paused because the user expects an answer within a latency bound and perhaps that needs
SPEAKER_00to be geo shifted. Within different priority tiers, you know, low, medium, high, or on a scale of zero to 100, as well as across different characteristics, preemptibility, throttle ability, the ability to be paused and checkpointed, or the ability to be moved within residency requirements. It's a complicated set of constraints, and we feed this in through what we call the normalizer to turn it into actions that we can take, and then our AI agents take the actions.
SPEAKER_01Well, I'm sort of, I mean, one of the things I wonder is if... Somebody gets that wrong. Who's responsible? Like who's holding the bag at the end of the day? Like if you could downclock the power, a job slows down and for some reason that someone didn't anticipate that breaks the job or doesn't get the result it wants or there's an unanticipated result. Is that just on the compute load for mislabeling its job or who's responsible if something goes wrong with the jobs?
SPEAKER_00Yeah, great question, Dave. And I'll use this to mention, you know, this is high stakes, high reward in kind of three different dimensions. Number one, it's massively high reward because if we make this all work, we can fit 100 gigawatts, as you mentioned from the Tyler Norris paper, we can fit 100 gigawatts of AI data centers onto the grid that we didn't think we could fit. And we'll walk through the benefits of that. So massive reward. High stakes, though, is on both sides. If you don't do this right, the grid could face reliability issues.
SPEAKER_00On the other side, if you don't do this right, the AI customers might face failed expectations, again, for the most economically valuable work in America. And the third dimension, of course, is a security dimension. AI data centers becoming energy technologies and this fusion of AI and the energy system, where we said at the Interface, Is a potential security threat, right? These are two massive multi trillion dollar networks that are critical infrastructure for America's economy. It's the backbone of our future economy. And so we've got to make sure that we're doing all of this in a very safe way
SPEAKER_00that protects the reliability of the grid, is resilient to intruders or threats from abroad and domestically, and protects the integrity of the AI workloads. Your specific question, Dave, is... Who pays if there's a screw up? And the answer to that specific question lies in the contracting, right? There will be, depending on the context, the grid, if they're offering you a faster connection, they may say, you know what? If you don't curtail your power when we ask you to, there may be a financial penalty or there may even be a technical penalty.
SPEAKER_00I'll flip your breaker. And so there's a contract related to that between the data center and the grid. But the data center will say, look, you're offering me power I otherwise wouldn't get for 12 years. I'd love to get this power and let's find a way to mitigate this risk. And Emerald Conductor exists in order to make sure that with 100% reliability, we are doing the thing the grid needs in order to fulfill your terms of getting that earlier power connection. And then, of course, there's a question of, well, what if the customer said they didn't want this job to be slowed down and it got slowed down? That's also something that the reason you bring Emerald Conductor on is because it's
SPEAKER_00a production-hardened, production-grade software platform that ensures that you protect the workloads that you wanted to protect. So I hope that the risks are clear. The liabilities lie in contracting, but these are solvable problems because the reward is so massive. On the contracting, like who
SPEAKER_01cuts you a check? I guess it's a basic question. Like who are you working for? Is it the utility? Is it the data center operator itself? Is it the operator of the compute, which is sometimes different than who owns the data center? Like literally, who are you working for?
SPEAKER_00Great question. We are lucky, Dave, that we work for basically everybody in this ecosystem. And our objective is to make everybody else so much value. That we're sort of barely noticed. You know, utilities get a ton of value. And we should talk about this, Dave.
SPEAKER_01This gets to my next question. But first, I just want to know, like literally, who comes to you and says, let's sign a contract? Who is that entity? Who is the counterparty?
SPEAKER_00Yeah, to answer it bluntly, it is electric utilities, data center operators, leading AI companies that are using compute, cloud companies. It is everybody in the value chain is our counterparty because we provide services and software across the value chain.
SPEAKER_01Okay. And so then the next question is then like, what's actually being sold here? What's the value? So the obvious source of value here is that an inflexible data center is going to have to wait a long time to connect to the grid. Whereas a flexible data center might be able to I'm assuming that from the data center's point of view, that's the golden ticket there. Like that's the main source of value.
SPEAKER_00Is that accurate? Yeah, roughly right. For data centers, you want larger and faster power connections than you would otherwise get. So you might be an existing data center and suddenly instead of 50 megawatts, you get 75 megawatts from the grid. That additional 25 was you were going to wait 10 years for and now you get it immediately. And the reason is because you're willing to be flexible with that new allocation of power. And the utility said, wow, I can just grant it to you because I don't have to build out any grid infrastructure to provide it to you. So that's larger connections, faster connections as you're building a new data center.
SPEAKER_00Like you said, Dave, you're waiting in a queue for 12 years and instead you now get connected much faster because, again, the utility wants to connect you. You provide a valuable service and you're not requiring them to build out the grid and get permitting, etc.
SPEAKER_01Can I ask a couple of questions about that? One is if I'm a built data center, I'm already up and running and I have no immediate expansion plans, do I get any value from you? Or do you know what I mean? Is there a reason to do this other than Wanting more power from the grid?
SPEAKER_00Yeah, absolutely. Great question, Dave. So if I walk through what's the value that we give to data centers, the number one value is larger and faster power connections. So if you are an existing data center and you want to upgrade to the latest liquid cooling and latest Nvidia GPU, You probably need more power. And so we provide that for you. But your question, Dave, is what if you're a happy data center that has no desire to do any upgrades and you just want to hang out? Would you ever work with Emerald? The answer is you could. Because the second value stream is by making you a flexible,
SPEAKER_00grid-friendly, grid-responsive participant, you can be paid. You can be paid by flexibility markets, by utility demand response programs. Now, to be clear, these are far less lucrative than the value of getting access to power than you otherwise wouldn't have.
SPEAKER_01Yeah, that's what I sort of wonder, like that is a revenue stream. I mean, compared to the value of the compute, you know what I mean? Compared to like the value of the data center itself, it's pretty small beans. I'm just wondering if any data center is going to take risks with its compute for that prize, because that prize is relatively small.
SPEAKER_00You know, going forward, as we continue to, as the American economy increasingly uses AI inference, I expect that cost pressures on inference will grow and power is the variable cost of inference. And as a result, optimizing the power cost is probably not top of mind right now.
SPEAKER_01And the grid says, okay, then you can have the power. And then I get hooked up to the power. What's to stop me from just saying, you know, upon review, it turns out all my computing is incredibly important and can't be interrupted. And what's to enforce you actually being flexible once you're hooked up?
SPEAKER_00The contract upon which you connect. And so, again, that can be a contractual thing. Hey, you have the power so long as you're complying and you fail to comply. You know, you get a maybe it's a three strikes policy or two strikes and you fail to comply. You lose that connection. Or there's actual physical breaker control. We flip your breaker and you don't have access to the grid. Again, I want to be clear. You said pinky promise early on, Dave. You said, hey, will demand response in the form of flexible data centers actually show up? And my answer is, yes, it will actually show up. And we need to make sure that it is enforceable and reliable for utilities.
SPEAKER_01Right.
SPEAKER_00I want to get into that a little bit later, that specific question a little bit later,
SPEAKER_01but a couple more questions just about the mechanics of this working. So I read this, you know, you have this Hillsborough test case that you've written up. It's, I think, 250 kilowatts. So it's relatively tiny compared to what an actual data center is going to be. And there's a bit in there about what went wrong, where the errors were. And there's a couple of cases where some of the computing nodes were either unreachable or unmeasurable or uncontrollable for some reason.
SPEAKER_01And if that happens, I think just to have a buffer, you have to assume that That that node is running at full power just to make sure you're coming in under the load you need. And then there was some issues with sort of control network getting congested when there's a big event that requires a big power drawdown. Sending messages out to all those nodes at once. You get congestion on the power network. All of this is one thing at 250 kilowatts, but then you scale up to whatever,
SPEAKER_0196 megawatts, which I think is the Manassas test you're doing. I wonder how those errors scale. I guess I'm just wondering, what are you worried about? What are the sort of failure modes that you're worried about? How many nodes turn out to be unreachable? What are you doing about this congestion issue? What are the sort of failure modes that are keeping you awake at night when you get up to scale?
SPEAKER_00Yeah, such a great question, Dave. Let me back up and just give some background about what you read and then where we are. So you read the results of our fifth demonstration on GB300s, Grace Blackwell 300s, the latest NVIDIA chip generation in Hillsborough, Oregon with Portland General Electric. And you're right. That was a demo that was less than a megawatt. Now, we've done five demos all over the world, including in London with NVIDIA and with other partners like EPRI and their DC Flex program. And I'm excited that we've just exited the demonstration phase and we've entered
SPEAKER_00the commercial deployment phase. We're now actually deployed at multi-megawatt scale at a whole data center, flexing it. In fact, two nights ago, it was my personal dream to be able to do this. And I've thought about this for the last decade. We flexed at the peak of the duck curve. Dave, you and I have followed this duck curve forever. You may know me as the guy who first put a picture of a duck on the duck curve.
SPEAKER_01Are you the one who drew that crude duck? I must have used that in like a hundred posts.
SPEAKER_00Well, no, no. Somebody else drew the crude duck. But in my book, Taming the Sun, I put a very sophisticated duck picture, rubber ducky. But in any event, so we're a level of order of magnitude or two orders of magnitude above that. You're right. Later this year, the 96 megawatt Vera Rubin Test Center with NVIDIA and Digital Realty comes online where Emerald will make it the world's first, you know, 100 megawatt scale power flexible facility. So your question is such a good one, which is what do you get scared is going to break as you scale from kilowatts to megawatts to hundreds of megawatts, right?
SPEAKER_00And the answer is you don't know what you don't know. There's a lot of unknown unknowns that you discover at each level. That's why we did the demos. Our company believes deeply in open sourcing our research and our results, which is why we publicly published a report that said, here are the things that went wrong. We've published peer-reviewed research in a nature journal, scientific journal, saying, here is the code we use to make this all work. We deeply believe in an ecosystem where all data centers can do this
SPEAKER_00and regulators can say, I know how this thing works and I trust it. And they've done the hard work to go through demos, prove what doesn't work, improve upon it, and actually make it work. And so I think about when we first deployed in this multi-megawatt facility, a whole data center, we're flexing it, and we're all sitting in that conference room around a bunch of laptops doing the first ever event where the utility says, hey, we need you to curtail. The atmosphere, one engineer told me, felt like a SpaceX launch. I think that was our head of product, Monty Shah.
SPEAKER_00She said, hey, it feels like a launch. You know, we all cheered, the curtailment happened. At some point midway through, the data center power briefly breached or went right back above the limit of the curtailment that the utility had asked. And it was kind of like thinking, you know, the SpaceX rocket, it went all the way up, it came all the way down, and then it nicely landed, but then it kind of tipped over at the end. And we're like, oh, what went wrong? What can we fix here? And so we fixed it and we continue to be deployed. And it's been a fascinating deployment where we've learned a lot.
SPEAKER_00So that's how I think about this.
SPEAKER_01Well, like the nodes that you couldn't reach or couldn't measure. I mean, one of the things that I wonder about, is that an error in... Was it the construction or the design or the manufacturing of the node that is out of your control? You're not making those. Or was it something about your measuring system that you can improve and then measure and test it better the next time? Like you're going to get some bum nodes. I feel like just the law of large numbers,
SPEAKER_00you know. Great question. And I didn't actually answer your question about like what keeps me up at night. So the way the conductor platform is architected uses a principle called virtualization from the IT world or abstraction. The goal is no matter what the underlying hardware is and what the underlying telemetry or the sensors that are reading to us the power data, no matter what it is, we should be able to make this thing work, right? And we are creating an abstraction or virtualization layer above it so that if anybody looks at a data center, if you're a grid operator, that data center presents itself to you as if it were a battery or
SPEAKER_00a controllable generator. It looks to you like the same kind of thing. And you don't have to worry about whether they're using this measuring equipment or that GPU. That's crazy, right? But suddenly we're getting it every 15 minutes. And so our AI technology needs to account for this and then make decisions,
SPEAKER_00understanding that it's like you're talking to somebody on Mars and the communication is delayed 15 minutes. That's one example of a thing we have to engineer around. Ultimately, all of these are engineering challenges. You know, the one you mentioned, Dave, was what if nodes go down? GPU nodes go down all the time. GPU nodes sometimes don't report correctly. Yeah. This, by the way, this is not an NVIDIA issue. This is often, it can be an installation issue. It can be problems with other parts of the power equipment in the facility. And you have to be able to be fault tolerant or error correcting.
SPEAKER_00And so a lot of what we do is build in the buffers and the intelligence to take care of these faults. So there's a lot of engineering, but fundamentally, my vision is, AI factory should be the most exquisitely controllable energy asset on the grid we've ever seen. They do things that nobody else can do, right? You can't move your load from one location to another at the speed of light. Like you can't move an electric vehicle from Indiana. So that's why I'm so excited. That's why Emerald does only one thing, AI factory flexibility. Whereas a bunch of other companies do a bunch of other things, which is great.
SPEAKER_00We do one thing because we think AI is going to account for most of the American economy this century, most of the electrical load. And we are going to make it a very community-friendly, grid-friendly asset.
SPEAKER_01In terms of what it costs the compute jobs to be capped or slowed down like this, you know, you have in your test, NVIDIA attested that the performance was acceptable, that the performance of the jobs was accessible. But you also acknowledge in this one white paper, and I don't know if this has changed since then, that no one has actually done the actual Hey there, everybody. Don't worry, I'm not going to tell you about a new mattress or push a credit card on you.
SPEAKER_01This isn't an ad. There are no ads on Volts. It is supported entirely by listeners like you. If you'll indulge me for a second, I'd like to ask for your support. I started Volts because we're all surrounded by depressing news about climate change
SPEAKER_01and misinformation about clean energy and it's never been more important to share the stories of the real people on the ground doing the real work of transition and all the ingenuity and courage and public spirit they are bringing to it. People are hungry to hear these stories, to learn from and find inspiration in them. I've heard from people who change majors or careers after hearing episodes of Volts. People using it in classrooms, community groups, even state legislators who have passed bills inspired by specific episodes.
SPEAKER_01Sharing these stories matters. It makes a difference. If you have found value in it and want to help me continue doing it, I hope you will join the community of paid subscribers at Volts.WTF. It's about the cost of a cup of coffee a month. If you don't like subscriptions, you can make a one-time contribution, leave a review on Apple or Spotify, or just tell a friend about Volts. I am grateful for any and all support. If you're already a paid subscriber, thank you. And now back to the show.
SPEAKER_00And how tightly measured has that been? I'm so glad you brought this up, Dave. The central question is, can we make sure it's not costless, but as, call it, inexpensive or as hassle-free for customers, for us to every so often gracefully reduce their power?
SPEAKER_01Because again, like these jobs are worth way more to these companies than power is, right? Like the cost... And again,
SPEAKER_00to the American economy. I mean, this is the lifeblood of the American future economy. We cannot screw this up. And so... Yes, Dave, to your question, we have in very great and meticulous detail measured this. Our chief scientist, Professor Aisha Joshkun, has done academic peer-reviewed work on ensuring the service level of critical jobs. We ourselves have published papers, for example, with Nebius, NVIDIA, and National Grid in London and EPRI, where we showcased not only that you could precisely meet over 200 grid events,
SPEAKER_00but you could do so while protecting the throughput of the token throughput, the other performance metrics of critical AI workloads. There's no such thing as a free launch, Dave. And so therefore, there will be some jobs for which there is a reduction in performance or a delay, but we ensure that That we are meeting the customer constraints so that if they designate a job that's non-interruptible or non-preemptible or super high priority, that job culminates in the time that the customer expects it to culminate in.
SPEAKER_00So we have very detailed metrics tracking. We've published it. We've also done metrics tracking with Oracle where we moved AI inference, serving inference workloads. Like Dave, you're talking to ChatGPT. We've moved queries from Virginia to Chicago at the speed of light and kept it within the latency bounds that you would expect when you're having that conversation with a chat bot. So Dave, you ask, you know, hey, is Varun actually informed about what he's talking about? And you want that answer to come to you before I give my next answer, right? And it's going to come to you on time, no matter if it, Got processed here or there within certain bounds.
SPEAKER_00So yes, we have deeply studied it.
SPEAKER_01Got it. Okay. And here's the question. This is actually the very first question that occurred to me when I heard about what you're doing last year. And I've been wanting to ask it to you for ages, which is like, As you mentioned, a lot of these facilities have batteries on site. And one way to get flexibility is just to draw from the battery instead of from the grid, right? I mean, this is a time-tested way of operating grid flexibility. And I'm just sort of wondering, like, isn't that...
SPEAKER_01And doesn't it require much less engineering and all this sort of like very complicated real-time orchestration? You know, a battery and it's meterable. You can just flop over to the battery and flop back to the grid when you need to. Why not just do that? What is the incremental value add of this detailed load orchestration versus just a battery?
SPEAKER_00Yes, yes, and yes, Dave, is the answer to your question intuitively, right? And then I'm going to tell you why counterintuitively I have a different answer. But the intuitive answer is yes, yes, and yes. Of course, you should just treat this data center as a black box. Who the heck knows how much power it needs? But we'll just stack a ton of batteries and generators right next to that data center. And so whatever the grid needs that facility to do, we'll just take care of it with the batteries and the generators. And that should work, right? And there are a few reasons to understand why that's probably not the right solution.
SPEAKER_00The first is that it's expensive. If the grid tells you, look, in order to connect you, I may need to curtail you. Now, it's once in a blue moon, but I may need to curtail you for two hours. We actually just did a 24 hour event to prove that if the local substation went down and they had to repair for 24 hours, could you curtail? Good luck trying to size the super expensive battery to provide all of this flexibility.
SPEAKER_01Enough batteries to run your facility for 24 hours would be cost prohibitive, I think.
SPEAKER_00And even less than that is pretty cost prohibitive. But, you know, wouldn't it be nice if you only had to put a two hour battery on your facility for part of your consumption and the rest of it was done through this nuanced, sophisticated computational orchestration? Well, then you're saving on CapEx and it's a better together approach where the battery does some of the work and the computational flexibilities does more of the work. So, yes, it's a lot of complexity that goes into our Emerald Conductor platform. But it makes for an ultimately cheaper, better functioning system.
SPEAKER_01Real quick, just on the duration question, because you brought it up and I wanted to ask about this. So I see the logic where a battery can do two hours, but if you have an event that lasts longer than two hours, orchestrating the computing doesn't get any more expensive in hour three or hour five or hour 24, right? So like on a long duration event, I totally get the advantage here. Steve McLaughlin
SPEAKER_01Is the orchestration of the computing just for kind of
SPEAKER_00the edges of that bell curve? It's not for the edge cases. Now, I will say there is a journey that we're going to take the whole industry on, which is we'll start by working with you on the edge cases to say, look, the load orchestration of the compute, the AI flexibility, we'll do that for edge cases. But your traditional way of operating for the last two decades is never to touch the compute. We'll largely leave you alone. But where I want to bring everybody is in the long run. AI should really be flexing a lot more often.
SPEAKER_00Not just during emergency events, you mean, like on a routine. That's exactly right. In a way, of course, that's respectful of the true performance constraints and requirements that customers need. But this is the most elegant way to provide flexibility to the grid at scale. And let me just walk you through what this means. Shail Khan, who led our recent strategic expansion round from Energy Impact Partners, you know, he tells me the reason he He wanted to invest was he had this aha moment. He said, you know, in the electricity space, we have something called the supply curve or the merit order.
SPEAKER_00We say, you know, some things are really cheap to dispatch. Some things are really expensive to dispatch. And you like arrange them in order and then you do the cheap things first and the expensive things later. And he's like, I can now draw a similar curve, but for the things that you could dispatch at the data center. And In many cases, there will be some AI jobs that show up as very short vertical bars on that merit order dispatch curve. Like there will be things that are inherently flexible. The customer is really not going to mind if that batch inference job or fine tuning job got slowed down for a bit. It literally was not important to them that it happened at that moment.
SPEAKER_00And so it comes before the battery, right?
SPEAKER_01So it'll come before the battery on the merit curve of demand response, basically.
SPEAKER_00That's exactly right, Dave. So you visualize the same thing that Shale did. In the long run, Dave, again, I founded this company because I'm pretty deep AI maximalist. I think AI is going to be transformative in a good way. But if we have a ton of AI and it becomes a 50% or more user of the American power grid, I see a future, mid-century, 2040, when half the work is done by the underlying
SPEAKER_00Thank you. And that combination, that complementary physical grid and what I call the meta grid, the AI grid working together, that's the thing that makes electricity affordable and reliable for communities and gets available.
SPEAKER_00All of the AI benefits that we want for our economy.
SPEAKER_01So you're talking about moving from this is an emergency or peak shaving edge case to this demand flexibility is providing 40, 50% of the total picture.
SPEAKER_00It's the way the grid works in 25 years and hopefully much earlier than 25 years, hopefully in 10 years. That's the way the grid works.
SPEAKER_01Well, let me ask about this thing because one of the things that's happening in AI, I think listeners may be familiar with the sort of difference between training inference. Training is when you're training up these models and you're doing, it's a big burst, highly intensive, you need really sophisticated GPUs, et cetera, et cetera. And moving to inference, which is actually using them in the field, Steve McLaughlin
SPEAKER_01It seems like on a macro level, we're moving more and more toward inference. More and more of the compute is inference, which, again, is much more time sensitive. So is that shrinking the total pool of kind of controllable, movable... Compute load? Is the move into inference tightening the parameters, I guess, is the question.
SPEAKER_00Yeah, great question. And my answer to this is, it's probably an oversimplification to separate the world of AI into a bucket called training and a bucket called inference. There's There's actually a lot of small, small buckets. You have model fine-tuning. I think this will become a large user of compute as we start to enterprises fine-tune open-source models to meet their needs. There's inference that is extremely latency-sensitive, sort of latency-sensitive, batch inference that is not very latency-sensitive at all. There's a lot of different ways that we use compute.
SPEAKER_00I also, by the way, happen to think that we will continue to have large frontier training model runs And counterintuitively, those are probably the ones that are least amenable to the kind of flexibility that the Emerald conductor does. Because look, if you're training Opus 5 or GPT-6, it's a massive, highly synchronized operation across, in many cases, lots and lots of data centers. That is a complex use case that we probably want to not work on right this second. Can I just cut in and
SPEAKER_01ask a question? Because this occurred to me, actually, like if you have conductor running, say, at five different data centers and there's a compute job like, say, the training thing you're referring to that is itself spread across those five data centers. Can conductor, can it conduct all five at once? Like are the conductors communicating with one another such that they can do sort of like macro conducting of multiple data centers at once? Does that make sense?
SPEAKER_00Yeah, great question. It's a project we're doing together with EPRI and others like NVIDIA and Prologis. It's called the distributed data center, substation level distributed data center project, where at the substation level, you often have like some capacity, but not a whole lot. I don't know, five to 20 megawatts. But you could build these distributed data centers at multiple substations, each of which is flexible. So every so often the substation is going to have two megawatts of capacity or otherwise 18 megawatts. And orchestrated together, those five or 10 or 15 distribution level data centers act as
SPEAKER_00a virtual aggregated single data center.
SPEAKER_01Right. They can sort of move the compute to the substation that's got slack at the moment,
SPEAKER_00right, is the idea. Or they can slow down or downclock compute that's happening at a substation that's constrained. So temporal and geographic or spatial flexibility, you put them together. And then, you know, as you correctly said, multiple smaller data centers can be aggregated into one larger virtual data center. And look, we're going to be looking for power everywhere. And the lower levels of our network, the distribution level, the substation level, there's land, there's power. It's just, you know, not as convenient as getting a nice large one gigawatt chunk that's firm.
SPEAKER_00And as we prospect for power, these cool ideas are all going to utilize this one fundamental concept, power flexibility. That's why we think of ourselves as a frontier research lab. We do frontier research on how to make AI possible. And it can be used in all these cool cases. Another cool example is you could theoretically put AI on a naval ship, for example, or in a forward deployed theater where there's an imperfect power grid and flexible AI compute enables you to handle fluctuating power envelopes.
SPEAKER_00So you can really think outside the box. This is a fundamental attribute of compute is its power flexibility.
SPEAKER_01So this is like multiple data centers aggregating acting as one. This is not... I think
SPEAKER_00it'll happen pretty soon. We have a project underway, but I do love the pun you made, Dave. It is happening on the edge. That is right.
SPEAKER_01Edge computing. Okay, let's get back to the enforceability issue. So... The market monitor and PJM recently called data center flexibility, quote unquote, a regulatory fiction, which means that PJM, it can ask for flexibility, but can't really enforce it. Can't statutorily sort of expect it. And so refuses to kind of plan around it. So I'm wondering, like, would you support that?
SPEAKER_01Making flexibility, if someone says they have flexibility, making that legally enforceable, basically such that entities like PJM, you know, because with a battery, it's measurable. There's a meter. You know what I mean? Like you can measure exactly what happened. You can enforce it. You can, in some sense, plan around it. This sort of aggregated stuff, I think PJM is not quite confident yet. So is there a way of making it mandatory and legally enforceable that you would support?
SPEAKER_01Or how do you think about that? How do you think about that issue?
SPEAKER_00Yeah, the answer is yes, absolutely. If we're going to make this work, if data centers are going to get faster and larger grid connections in return for promising flexibility, that That promise needs to be legally enforceable and technically enforceable. And so I 100% believe that we need to prove to regulators, to governors, to utilities that data centers will 100% show up when And they're asked to show up if the reward they got was larger and faster connections. And the market monitor is right to say,
SPEAKER_00hey, historically, the performance just hasn't been great of demand response. But let me tell you, Dave, this is a new category, new class of flexible power users. So the last thing I'll say is, I think ERCOT, Texas, ERCOT has done a great job of developing a framework, a legal framework for how this could work. They say, a flexible data center is welcome to connect It'll be what we call
SPEAKER_00a provisional controllable load resource. It'll actually be dispatched via the dispatch system. It can provide its willingness to curtail. And the willingness is a economic number, $2,000 a megawatt hour. You really don't want to curtail. But, you know, hey, if we reach that condition, then we will dispatch you. And it's a legally binding thing that you have to do. And a condition of being connected is that that makes the data center the same sort of entity as a generator or a battery or anything else that is dispatched.
SPEAKER_00It is legally equivalent. And I think we have the technology to make that possible. Interesting.
SPEAKER_01Well, on that note, you know, we were discussing earlier, like if you're just a fat and happy data center running along, like why would you want to do this? Once it is demonstrated that it is possible for data centers to be flexible, I wonder if you ever foresee a day where it simply becomes mandatory and For all data centers to be flexible. In other words, right now I think there's like data centers get grandfathered in if they don't have this stuff installed. But theoretically you could come along and retrofit an existing data center
SPEAKER_01with this and make an existing data center flexible. And if that becomes possible, do you think that's ever going to become simply mandatory for all data centers? Well, look, I think it's wrong to paint all data centers with the same brush.
SPEAKER_00There are So AI specifically, not just all compute, but it's AI specifically that you think is flexible. Well, that's where we've chosen to focus. We believe that there is technical room to run here, that there is an economic value driver. They really want access to larger and faster power. And we believe that the right way to do this is to provide incentives. The carrot approach, not the stick approach.
SPEAKER_00The carrot approach is if you want the power, here's how you come get it. And, you know, if you want to do the traditional route, go ahead and do the traditional route. It just might take forever. And I think that's a workable solution that, you know, the AI community can get really excited about.
SPEAKER_01Interesting. Okay. And Volts is about decarbonization ultimately. So one of the sort of conclusions they have in that study is that flexibility, all things being equal, favors renewables over gas. I think they found that 20% flexible demand avoids a fifth of new gas construction. And that sort of scales like 50% avoids half the gas construction. But I'm curious about the mechanism of that,
SPEAKER_01whether you believe in that and whether that's part of your motivation here.
SPEAKER_00Dave, it's why I started the company. I sincerely, strongly believe that by making data centers flexible, again, as AI data centers become the largest user of electricity on the grid, their flexibility, Ceteris Paribus, pulls new clean energy from intermittent renewables onto the grid.
SPEAKER_01Hmm.
SPEAKER_00You know, I've spent my career in the renewable industry. Man, would I have loved to have an offtaker that's a flexible data center. It's massive. It is responsive. It helps me use my resources, my electrons when they're produced. Like this is a massive win for making the grid more amenable to connecting clean energy resources. Dave, I'm sure you saw this report that came out in the last couple of days that said the net impact of data centers published in Nature, a peer-reviewed journal, It's going to be bad for climate because it's going to increase the efficacy of oil and gas extraction.
SPEAKER_00I think that was the primary driver of increased emissions, even as it, in a less pronounced way, advances renewable energy.
SPEAKER_01I think that it has it flipped. Well, also, and just also, it's visibly right in front of us pulling a crap load of gas onto the grid, like whatever it might do in the future right Right now, it looks like hyperscalers are herding to gas. Like the gas pipeline is jammed now and gas companies, you know, their stock is rising and they're building on-site gas plants. So like when, if AI is going to benefit renewables, when?
SPEAKER_00As soon as we demonstrate demand flexibility and get it scaled up, which is what we're doing. I mean, I just want to be clear here, Dave. I think demand flexibility is something both parties can get behind whether or not you care about climate. If you do care about climate, you get a lot of clean energy on the grid. If you don't care about climate, you get a lot of other benefits. Consumers pay lower power bills, ceteris paribus, all else equal, a flexible data center will serve to reduce cost and affordability pressure on local bills because you don't have to build out exorbitant infrastructure
SPEAKER_00to serve higher people. It tends to democratize AI by getting more GPUs onto the grid so everybody can get access to life-saving AI innovations. It improves grid reliability because flexible AI data centers can respond to the grid, be good grid citizens. You know, responding to lightning strikes that we demonstrated in our demos in London. And all of these community-focused benefits happen if AI data centers become flexible. It's why, you know, I strongly support Republican Senator Dave McCormick's covenant
SPEAKER_00For how you get data centers to be community friendly. And plank one of that is just make sure that they have positive grid impacts and don't raise rates. And flexible AI is the only way to do that. There is no way to do it otherwise. You can't say, I'm just going to go off the grid because then you'll have an implicit cost increase by using equipment that can't then be used in the public power grid. That's also, by the way, a death spiral effect for utilities. You really don't want data centers to just entirely go off grid or even worse, go into space. So I really think that, and I'm not saying that out of jest,
SPEAKER_00I actually, I really admire what Elon Musk and StarCloud and others are doing to bring data centers. So you think that nature paper is wrong? I think that nature paper did not assume that Emerald AIs and others, like Google, by the way, Google is an absolute pioneer here. A set of actors doesn't make AI flexible and therefore a fantastic grid participant and citizen. Mm-hmm.
SPEAKER_01And so talk about the logic or the mechanics of how this lowers consumer bills because it's not intuitive.
SPEAKER_00Yeah, absolutely. And I think this is one of the most important parts of Emerald, right? Again, going back to Senator McCormick's covenant, if you're a data center, you want to be welcomed by the consumer. Don't raise their power bills, all else equal, and be a good participant on the grid. Don't cause blackouts. And this is possible today. And the reason it's possible is if a data center shows up to town, by the way, chances are if a data center shows up and it's a highly utilized data center, Just that new load, the math probably already works out for that data center to support affordability, but to guarantee it,
SPEAKER_00a flexible data center that's willing to ramp down during peak demand and when the grid needs it, a hot summer day when everyone's running their air conditioner, for example, That flexible data center can be connected utilizing the existing grid infrastructure.
SPEAKER_01Right. You don't have to build new stuff. That's the basic here. You don't have to build new stuff. You're using existing stuff.
SPEAKER_00Well, to be clear, we will have to build a lot of new stuff, right? But, Dave, what I would like is for the rise of AI demand to grow even faster. Thank you. That it's utilizing more highly. And that helps to, all else equal, reduce your bill. Now there's a bunch of other stuff that we're doing where like weatherizing grids for fire risk, et cetera.
SPEAKER_00And so your bill may end up rising nonetheless, Dave, but all else equal, the net effect of the data center coming, if it's flexible, is to control that rate pressure. All else equal, it's to reduce your rates, Dave.
SPEAKER_01And just it spreads the existing costs, the existing per unit costs of the existing infrastructure over a larger load.
SPEAKER_00And thus kind of the per customer cost reduces. This is did a whole pot on this dynamic.
SPEAKER_01All right. All right. Well, final question. How long until... It is standard for a data center to be flexible, like you say, five years, 10 years?
SPEAKER_00In the year 2030, you can't add a gigawatt of data center load to the American grid without it being flexible.
SPEAKER_01All right, then we will wrap up there. Thanks so much for coming on and talking us through this fascinating stuff you're doing.
SPEAKER_00You're the best, Dave. Thanks so much for the time. It's so great to do this with you. Thank you.
SPEAKER_01Thanks everybody. You've been listening to Volts, founded and hosted by me, David Roberts, produced by Nate Peavy, and supported entirely through the generosity of listeners like you. If you enjoyed this conversation, please consider telling a friend about Volts. That's how this show grows and survives, through word of mouth. See you next time.
This is a public episode. If you'd like to discuss this with other subscribers or get access to bonus episodes, visit www.volts.wtf/subscribe When people push for better data centers, they picture hyperscalers - Amazon,...
This is a public episode. If you'd like to discuss this with other subscribers or get access to bonus episodes, visit www.volts.wtf/subscribe America’s first big wave of solar power installations, built between 15 and...
This is a public episode. If you'd like to discuss this with other subscribers or get access to bonus episodes, visit www.volts.wtf/subscribe The Senate’s bipartisan permitting bill got a manager’s amendment last week -...
This is a public episode. If you'd like to discuss this with other subscribers or get access to bonus episodes, visit www.volts.wtf/subscribe Last week’s election was a blue wave all the way down the ballot: Democrats...
This is a free preview of a paid episode. To hear more, visit www.volts.wtf Volts published eight conversations in October, which is a lot for anyone to listen to. We’ve rounded up the highlights into less than an hour....