Episode 16 -In this episode of Trust the Process, Michael and Krista pull back the curtain on how builders set pricing and choose product types - sometimes years before a home ever hits the market. From raw land to market-ready, they discuss the layered decision-making process that involves zoning, lot sizes, neighborhood context, material lead times, and market forecasting. Michael shares real-world examples of two active projects - one with tentative map approval and one still in the zoning stage - and how everything from speed limits to surrounding home values can influence whether a lot holds a $1M home or a $2.5M custom build. If you’ve ever wondered how pricing is determined before there’s even a road in place, this one’s for you.
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Ever wonder what really happens behind the scenes in construction, real estate, and development? We pull back the curtain on the new home construction industry, the real estate market, and the trends shaping it all. Discover the stories, insights, and expertise behind the process of building a new home. Join us for Trust the Process podcast, and let's build something great together. Welcome back. to Trust the Process podcast where we talk about new homes, the real estate industry, construction,
and everything in between. So today we're going to talk about product and pricing. So how does a builder come up with pricing? How do we decide what's going to go on any specific lot? It's kind of a catch -22 because you're building out to a product that you're going to market. Months from now, so it's anticipating what's going to what there might be an appetite in that area for and how you put that pricing together. So an interesting topic and one that seems really
relevant for every area. These questions. It does, right? This is something you guys into play. So what I liked and I wanted to circle back to is that you're putting something out there that you're not marketing or you're trying to create manifest something that you're not going to even market. First seven to twelve months if it's a subdivision. I have two pieces of raw land right now. We're working through entitlements on I I even have I have tentative map approval on one and I won't even have The civils and all the off -site improvement permitted until October, which is in seven months from now We won't even
be able to move any dirt over there for seven months Let alone building the homes and marketing the homes and selling the homes These are residences that will be moving. You know, these residents will be moving into their homes and probably Christmas of 26, potentially. I don't know. It could easily be Christmas of 2026. So to try to imagine what the market's going to want. It's just dirt and you have to conceptualize what you're going to put there, how much you're going to price it at, how much you want to put into it to know what you might get out of it. So it is. And that is that those have attended the
map approved, which means the lot lines are there, the law sizes, everything's there. I can walk on. I know this is going to be a lot one. Once we build the street. And then we'll call this act. This is going to be a lot one. This is going to be a lot two. This is kind of views a lot two is going to have. So I am at least hemmed in a little bit by that, but they are pretty, they're like 6 ,800 square foot home sites. They're very regular. Do I build more custom semi -custom that will maximize the lots? Do I do a unique home for each lot? Do I hit the upper echelon
of the price point in the median sales price? And that area is around 650 ,000, but there's some new construction. that are in the twos. There's some luxury homes. I'm talking within, you know, quarter mile, by the way, the crow flies that are up to 15 million. Some, some celebrities live within this same zip code within the same area. Well, they'll pass this neighborhood. So how high can I push it? Right. Right. But then there's other objections to this particular parcel there. It's pretty close to a major thoroughfare and it has a drainage, uh, wash on the other
side of the road that I have to build. It's not touching my community, but it's It's an objection that might not matter for a $900 ,000 buyer, but will matter for a $1 ,900 ,000 buyer, and certainly up and above and beyond that. So I can put whatever I want there, but there are going to be objections that I'm going to hear. Two of those homes will back that street. All the homes will be able to see that street because the way it's kind of off at an L. So every single one of those, you'll stand in the garage and look down that thoroughfare. It's not an ugly thoroughfare. It's actually well managed and
manicured thoroughfare, but people go around 50 miles an hour on that thoroughfare. And another objection to that on the topic of the speed is that you can only make a right -hand turn and then do a U -turn to go out if you're going west. And beyond that, it's a bit of a view. There's something to be... I mean, it's a beautiful line. It has so many pluses. So, geographic's amazing. If you just looked at a map, you'd say, push it to 2 million because you can get it. If you walk the site, let's say 700 ,000, somewhere
in between. The conservative side of me will say, oh, don't push it. You don't want to hear these objections. But then the other part of me thinks, gosh, there's two guard gated country clubs around the corner from here. There are $25 million homes that are visible from the parcel. All the new construction in that area. So if you want to be in that area, and it's a very desirable area, all the new construction is luxury. And the few production builders that are in that neighborhood are 1 .2 is the lowest So I know that is that my floor So I think my floor is
probably 1 million and I think my ceiling is probably 1 .5. So now it comes to all right Let's find that price Let's find that product that will that will carry that sales price because we think the neighborhood and the lots can carry that sales price What kind of designs finishes and square footage and amenities are people going to expect for that sales price and that those are knowables I can get an idea of where the market is. Those can change a little bit. The finishes, the, you know, and we're going to use this quality of the product. Yeah, we can do Whirlpool versus Jenn Air if we find that. We've
kind of maxed it or if, heaven forbid, anything should happen or something opens up and then you realize you want to build a little bit higher. Which I'm doing on my Serene project. You know, it was kind of slated to be in this 1 .5 and then I've based off of the preliminary interest we're getting. I'm realizing, no, these are probably $2 million homes and they will become $2 million homes if we do them right. Let's do black aluminum windows. Let's do glass garage doors. Let's do really nice finishes. We're working with plans that I have already finalized and designed. So that part now I can't change. So as you kind
of use, you start making those decisions and then you have to try to right. So this parcel I bought with the tentative map approved. So that part was decided for me. Okay. I know they're going to be 6 ,500 square foot home sites. They're going to be irregular. It's going to be hard to get like two different models on these these lots. So I think that that made it a little bit easier for me. And then I said, okay, well, what can go here? And then once I designed those homes and finalized and pay for architects and engineers and get that process started, now I'm locked
into the structures. And then there's only so much I can do from there to either save money or maximize returns. So you just kind of go as far as you can to the brink. And then as you make decisions, when I build in country clubs, I roughly know the lot. So I'm only doing usually one off. I mean, we have a batch running through for in that in South Shore. So those I had the lots and I was able to put the same plan on two of them and then a similar plan on the third and then a single story another just to mix up my product offering. But once I had all the architectural design now we're pouring those foundations this
week. So I have to order windows. I ordered windows on one or windows, you know, this week I have to have all the windows order because they're six weeks out. So as the lead time item starts to come to where I need to have them order it so that they're here on time. That's when I start making decisions. Aluminum thermally broken bronze aluminum windows, bronze color aluminum windows are roughly twice as much as the same product in vinyl and then fiberglass somewhere in between. Energy efficiency. Yeah, there's some. Do I buy a name brand? And with that one, when you're building in South Shore, you're limited by the
HOA too. They have criteria that you have to meet for the exterior. Oh, for sure. Yeah. Yeah. I just can't, I can't change anything on the outside. Once I submitted it to the HOA, submitted my design and my elevations. That's it. I can change windows, but I have to reapply. So this one, I'm deciding to do a bronze window. I just have to send it in. That's an approved window, but FYI on this one, I'm going to do that. So there's certain lots that I can, after I kind of walk them in and simmer on it, I think, okay, can I push this one? to 2 .5. Okay, this one has some objections and I've seen the flier where the foundation is and just kind of locked it in 3d space. This one might be a one eight fiver.
Let's dial down the spec a little bit to vinyl windows. And then maybe I'll do a lower cabinet line that's not as custom that's still appropriate for 1 .9. But not something that would carry me up to 2 .5. But those are, you know, making those decisions on the fly, as we get hit certain cutoffs. So you got to go all the way back now to when it's a parcel. Thankfully, this one as an example is something that I had the lot sizes, but now is time now that the engineers are working on the civil improvement plans and the trains left the station, so to speak. I have to start
conceptualizing the homes that are going to go there because that's another three to four months worth of architectural and engineering that I want to overlap with the engineering of the actual parcel and the site work so that I can have my homes in for permitting when I'm doing all the road, the curb, the gutter, the walls, the grading. So that when all that's done, I have a permit for the house. So it's actually sooner than you might think in the process. It's more upstream than you would think. Many people might think, oh, the developer just graded all these lots and the roads been built and the curb and gutters.
And now they're probably starting to think about it. And now they're probably starting to think about homes they put there. By the time they're at that point, they better have their homes and permitting if not permitted because you want to get going. The cost of money is just astronomical. It's around 1 % a month. So if you're borrowing $2 million on that project, It's costing you $20 ,000 a month to sit on it. So you want to overlap as much of your time as possible. So you minimize that downtime. You have to go through engineering. You have to go through the civil improvement process. You have to go through public works and you have to go through actually developing it. You might as well. You have to go through
that anyway. So you're paying carrying costs on that as it is, you might as well get all your engineering and architectural work done at the same time so that you can be ready to go. So that being said, you're doing this pretty upstream, right? You're, you're, you're year before you're breaking ground even on the site development on the site work your year and you're trying to conceptualize the plans so that's where i'm at on this particular project and then i have another project that's even farther upstream because that one is kind of in the same area has a lot of the same objections is hemmed in
by two existing neighborhoods one more high -end and then one You know, I don't see lowering because it's still really desirable area, but it's below its production It's below the median sales price that right neighborhood So we've got those two things kind of working either fit with us or against us And then I also have to figure out how I want to lay that out because I have to go to the city either way for a zoning change So do I maximize it? It'll only hold about 11 to 12. I could probably hold 19 total It'd be a lot of site work, but practically it can hold probably up to 12 And if I did a custom, it could
be down to three or four, just luxury infill homes. So where do I go? So I'm going to shoot for the highest density possible, see if the city will let me do it, which would be, I don't want to say highest density possible because that'd be like around 19 or 20. So I'm going to shoot for 11, where it's like the most practical, highest density, that balancing act. And if they'll give me that kind of density, then we'll have 11 homes approved with that 10 of the map. Then when I have that kind of clarity, then I can decide what kind of product is going to go there. So to get 11 homes are going to be like 35 by
140 foot lots. So it's going to be a narrow home, about as wide as a garage and a front door. So you got to get real creative architecturally on the second floor to make it stand out. And then you have to pick your spec level to say, well, that's, I mean, there's some views there because you're getting farther up the mountain. When you're at that point, uh, the road is not as busy. It's about a quarter mile up. So, um, but it is also a right turn only U -turn. There's some objections there and you gate it. Do you not? So the reason I don't mean to dodge your question, but if you're going to do those things,
if you're going to gate it, if you're going to make it an 11 home HOA, it's going to have high HOA fees because it's divided over only 11 homes. Then you better have a home that's going to carry that kind of HOA and then you better make it worth it to have it gated. So you probably need to maximize your building pads to get 29, 3 ,200 square foot homes, maybe even do a third floor. Rec room observation deck because there are some views up there said pump up the square footage. So those are the decisions that I can't really get my head around it right now, but I want to
go into that into that price point. You know what? I want to be at that one, one, two, one, three. So I'll just have to see if the city says you can only do seven in the lot while it's become a lot wider. And they're larger, lower density. Maybe I can push it to one vibe, but there is a number where I just, no matter how Even if I just did one home there, it's still going to hit some resistance. So there's just kind of that balancing act and that one is as far upstream as you can get. It's raw land and I'm working with the zoning changes as we speak. The engineers, we're going to have our tentative map by Monday.
Oh, okay. So we'll have that submitted to the city and then we get comments back about two weeks later where they'll say, oh, too many homes. We don't like this. We don't like that. We're worried about the traffic on Horizon Ridge and the right turn only. And we're just We have these reservations. Could you do, could you either address these things or could you do eight or could you do seven? And then it'll change. It'll change what I put there. So those are the, that's the decision making. So I already risk on your part. You're just making decisions that had, like you said, upstream so far upstream from where the boats will actually float. Right. You're
really making decisions. Right. Guessing that you've been any times and they're educated guesses. You've done it enough times. I have to know but there's still some uncertainty in it and a risk. It's a lot of uncertainty and we're talking on the one we just mentioned. Now we're talking some of those cells might the last four or five might easily be in 27 could easily be summer of 27. I'm not going to build all 11 at once. I will flood the market. So yeah, I might deliver some in 26 even that's really aggressive. Depending
depending how much infrastructure there is and how much land moving you have to do in order to make the lots accommodate what you're talking about. It's a lot. It could be. It's time consuming. If you want to know how time consuming, you can go back to our codes episode. I know everyone's chomping at the bed to go to that codes episode. We also talked a lot about the timeline. We did. Not the bill to sue primarily, but on the timelines in general. It is. And our subdivisions episode as well, we talked about how long it takes to get through a tentative map and entitlements
and zoning changes and civil improvement plans and public works and department of transportation. And thankfully these aren't affected by that. It's a city road, not a state road, but there's always something, there's always some weird thing that has a hillside overlay most likely. we'll see, which requires a lot more studies. We'll have to 3D map the slope. We'll have to say how many dead sage brushes we're removing and how many desert hairs we're removing and desert tortoises and scorpions and beetles might be displaced. Yeah. Yeah. So there's going to be, it's a developing
story. About a six month timeline for that hillside overlay. Yeah. You can do other things during that time. So yeah, it's yeah. But more or less by the time you're through it all, by the time you do the 3D mapping and send it through and do all those studies. And it's probably, I don't know, in the order of around $50 ,000 worth of additional engineering and surveys and statements and legal fees. And it's usually advised to get a lawyer through those things, not in that adversarial position, but just to have a lawyer on your side, working you through it. Those are Those are the
factors that affect the product and it's not that simple. It's not just oh, I've got this 50 by 100 lot I think I'll put a 2 ,000 square foot home here and call it a day, right? And it's interesting because again, you know, it's kind of a pullback on the curtain now we're seeing some of those decisions that are made in advance and You know drive around town and you see the outcropping of homes pop up and you're like, oh that must have just started but to think about all of the time and it you know Right hours of thought in process and policy and all of those things and then like you're saying sort of a
strategic pieces that you know if it were. pure homes. These will be the ramifications if you build a little bit larger homes these so all those pieces that go into it and all the brains and thoughts that have gone into it before it ever even starts to look like it could be a salt parcel. So it's interesting. Yeah, thanks for for the behind the scenes look. These are the kind of things that we hope to hear about and look forward to hearing more of them from you. Thanks to you guys for joining us on another episode of Trust the Process Podcast, and we
will look forward to seeing you again next time. Thanks. Bye -bye. Thanks for tuning into the Trust the Process Podcast. Make sure to follow us on Spotify to stay in the loop with the latest insights, project updates, and everything in between. See you next time.
Trust the Process Podcast | Episode 45 You see the finished homes. We show you the steps it took to get there. Today, one of the steps nobody puts on a highlight reel. The financing. Krista and Michael sit down with...
The 2026 housing market is showing more activity, but that doesn’t necessarily mean it’s getting easier. In this episode of Trust the Process, Krista and Michael take a mid-year look at the Las Vegas housing market -...
Every community has a starting point, and often, it begins with a conversation. In this episode of Trust the Process, Michael and Krista take listeners behind the scenes of Mesa Verde Enclave, a proposed four-home...
S2 Episode 42: Trust the Process Podcast Building a home involves hundreds of decisions, and not all cost-saving choices carry the same impact. In this episode of Trust the Process Podcast, we explore the concept of...
Episode 41: In this episode of Trust the Process Podcast, we pull back the curtain on how our business actually runs day to day. From the outside, it can look like a large operation with endless resources - but in...