Most major projects manage risk in Excel. Matt Mitchell spent a decade managing it differently - including as risk lead on a $3.9 billion offshore gas platform in the Mediterranean. In this episode, Orion sits down with Matt Mitchell - a certified risk management professional with over a decade of experience across energy and industrial megaprojects - to go deep on one of the most underinvested disciplines in capital project delivery: risk management. Drawing on his time as risk lead for the Leviathan Project, a $3.9 billion offshore gas platform off the coast of Israel, Matt explains how risk management actually works at scale - from structuring workshops to running Monte Carlo simulations to navigating the political dynamics that keep real risks hidden. Whether you're a risk professional, a project manager, or an executive who's wondered what risk management is actually supposed to deliver, this is the most practical conversation on the subject we've had on the show. Matt Mitchell is a certified risk management professional with over a decade of experience in risk and project controls across energy and industrial sectors. He served as risk lead at Noble Energy on the Leviathan Project - a $3.9 billion offshore gas platform in the Mediterranean - managing risk from FID through execution. He is currently building Electrical Grid Monitoring, a venture focused on innovative power line sensors, and is a member of Mints International. 🔗 LinkedIn What You'll Learn 1. Split risk registers aren't a workaround - they're best practice On Leviathan, Matt maintained separate registers for different project levels and stakeholder groups. A single monolithic register collapses under the weight of a megaproject. Splitting by owner, contractor, and discipline keeps risk ownership clear and review meetings productive. 2. Risk workshops only work if contractors feel safe to speak The most dangerous risks on a megaproject live inside your contractors' heads - and they won't share them in a room full of owners unless you create the right conditions. Matt's approach: structured workshops with pre-work, clear ground rules, and a facilitator who knows when to push and when to hold back. 3. Monte Carlo isn't just for statisticians P50 means you have a 50% chance of finishing on time or on budget. P75 means 75%. Matt explains how to have that conversation with an executive who's never seen a probability distribution - and why choosing the wrong confidence level can sink your contingency strategy before the project starts. 4. Risk culture is built one conversation at a time "One is greater than zero" - Matt's philosophy for getting risk identification started when a team is stuck. The risk champions program he describes is a practical model for distributing risk ownership across a large, multi-contractor project without creating bureaucracy. Episode Timestamps 00:00 - Introduction 03:00 - Matt's background and path to megaproject risk management 07:00 - The Leviathan Project: $3.9B offshore gas platform overview 10:00 - Risk fundamentals: definitions, COSO framework, and black swans 18:00 - Designing and running effective risk workshops 22:00 - The valve example: one conversation that revealed a systemic risk 27:00 - Getting contractors to surface the risks they're hiding 30:00 - Monte Carlo simulation explained in plain language 34:00 - P50 vs. P75: choosing your confidence level and defending it 39:00 - Ancient artifacts on the seafloor: when risk becomes archaeology 40:00 - Risk champions program and building a risk culture across contractors Resources Mentioned: ISO 31000 - International risk management framework COSO ERM - Enterprise Risk Management framework PMI (Project Management Institute) - project risk guidance PERT - Program Evaluation Review Technique (for smaller projects) Monte Carlo simulation - quantitative risk analysis methodology Noble Energy / Leviathan Project Electrical Grid Monitoring - Matt's current venture Mints International If this episode gave you new frameworks for managing risk on complex projects, subscribe on Apple Podcasts or Spotify. And if you're building a risk culture in your organization, we'd love to hear what's working - drop a comment below or connect with Matt directly.
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Welcome to Major Project Podcast.
We're here to talk about some of the biggest projects in the world, how they get done, talking with leaders that have been on the ground understanding this amazing space.
So today with me is Matt Mitchell.
He works, in capital projects.
He is a certified risk management professional with over a decade of experience in risk, project controls across energy and industrial sectors.
So, his prior job, he was at Noble Energy leading ri- risk management initiatives, and now he is working at Electrical Grid Monitoring, which is a new venture focused on innovative power line sensors.
Matt is also a member of Mints International.
He's got real great analytical rigor.
We've had some great conversations around solving challenging problems in capital projects and risk assessments.
I'm excited to bring them to you today.
Matt, welcome to the podcast.
Thank you, Orion.
Thanks, Matt.
And before we get started, maybe you can just give us a little bit of your history and how you got into working in major projects.
I actually started off more on the technical side IT and software development, and I, got into risk management with a couple of different things that I did.
First, I worked at Enron, and we had some formal training around risk management.
But then I worked for a software company that had a really strong risk management platform.
And so we were rolling that out to various customers and doing a lot of, prospecting, of what risk management would look like and what the global risk management system would do, and ended up going to work for one of our customers.
And as we rolled out this global risk management system, they realized they didn't have anybody to manage it, and so that became my role, and th- eventually started working on a variety of their con- construction type projects and, you know, oil and gas type stuff, and, took on the role of risk lead and ended up with some of the very large projects that they had It's interesting to go from the software side because when I look at the project control space and the software space, I feel like risk is probably the one area that I've seen more often than not managed from small to really large enterprises in Excel.
So you're really in a interesting niche to come from s- a software solution that focuses on risk, and then rolling it out broadly.
Did you, do you find that's true as well in your experience? But what is interesting about it is that for risk management, you know, you think of just any kind of software at large, the software has to do whatever the company's business process is.
But with risk management, we have some pretty good guidance out there, ISO 31000, we've got Project Management Institute, that all kind of lay out this framework of what you should be doing for risk management.
And so the software was built to, to do those things.
As I understand it, we also are gonna get to talk a little bit about the Leviathan Project.
You know, public information only, of course, but this was a large gas field project in Israel.
And so maybe you can tell us a little bit about that and your role on the Leviathan Project.
It's a very large project that takes many years to develop.
It's interesting with the backdrop of what's going on in world, geopolitical things today that, these projects are decades in the making in some cases.
You have people on and off, and a lot of, knowledge gaps here and there.
So risk management is crucial because as projects get mothballed or delayed or scope changes or even the entire concept changes, the capturing of that information and the risks that we considered and the reasons why we made certain decisions that we made, those should be documented and documented well.
And risk management is one of the best ways to do that.
We consider doing this, we said the cost was too much for that, we chose a different concept, but those things change over time.
So, you know, these huge projects, risk management is a key part of the entire life cycle of the project, even up until the point where the project might get canceled.
You know, somebody might pick it up again five years down the road, and it's gonna be important to understand what took place.
Well, so tell us about Leviathan.
What was the project and when did you intersect it? And then your role was risk, so just give us a little background there.
So, it started off, you know, it was pretty far offshore, and it started off as a floating, production, FPSO, float- floating production basically a ship.
And so that concept was kind of battered around for, I think, a couple of years.
And then it ultimately based on some of the s- the, successes of the other two platforms that had been put in it became a very large platform a little closer in.
And, and so that was the, that was the final investment decision.
But, you're talking about years of research that led into that, and so I became- this? That was around 2000- 14, 15- Was that FID? So it was not long after Tamar went in, which was, I believe, 2013.
So the concept, kind of shifted to using Tamar as part of the whole system of production, versus just having the ship do everything.
I got into that project around the 2015 timeframe, '15 or '16, I believe.
And that was, right around the time that they made final investment decision and sanctioned that project as that large, platform.
So massive platform, in fact.
So quite fascinating.
So how big was the project when it FID'd? I believe at FID, it was about 3.8
or 3.9,
something like that.
Okay.
Great.
And then your role, so you intersected right around FID, right after.
So what did you...
And you came in as a, as a risk lead.
Is that right? Risk, yeah.
So did you, when you started that job did you inherit- The risk register and like how did you approach risk right at that FID point? 'Cause that's a very interesting point when a project goes from, you know, are we doing this to like, we are doing this.
But you really wanna honor all the risk work that's gone on in the past, but you're also new to this job, Walk me through how you navigated that, 'cause that's kind of a complicated little s- point to intersect a project.
It's interesting because, obviously every company's different, every project is different.
But the better developed and the more mature that risk management process is, the easier it is to do something like that.
So in my role at that time we were working from only kind of what we had seen with the previous platform, and let's take that risk register and we'll repurpose it, and it'll kinda...
Some of these apply, some of these don't, and go forward with that.
But we eventually, this was such a large project, it had so many, aspects of it.
We eventually ended up running two different risk registers because we had so much that was on the commercial side of things, and then there was the project execution.
And, and when you, when you, kinda...
the overlap of those kind of muddies the water a little too much for the project team, so we just really wanted to focus on project execution.
What's gonna, what's gonna impact the project, and don't worry about the commercial aspects of it.
We'll manage that separately.
So you were able to kind of like bifurcate the risk register that you received, and then focus, target more in on execution risk rather than get involved in maybe the more complex commercial risks, which might have been the bigger focus pre-FID anyhow.
Right.
That's smart.
Yeah.
You know, like it's public information that, you know, they're selling gas to Egypt, right? And it's almost like maybe some of that risk involving maybe geopolitical things is a different discipline in some respects than- Yes engineering risk, which maybe is a little bit more quantitative, like, and can be defined a bit differently.
So that seems...
yeah.
I should probably back up.
So maybe we can just define when we talk about project risk on a major project, can you kind of take us through a little bit of a 101 on that and just kind of get...
give us a refresher even for the advanced project people? Because it's such a niche space, I think it's always good to go back and, and just learn.
So tell, tell me about risk.
What is risk? The ISO definition of risk risk is the effect of uncertainty on our objectives where that uncertainty is a deviation from what we expected.
That's the textbook definition from a project perspective.
So what that means is we have to consider all of the objectives of the project.
What are we trying to do? You know, of course, CD cost schedule, and, and time.
But it's most effective to boil those things down into what's the effect on the schedule, what's the effect on the cost.
Yes, you'll find things that are, are effects on health and safety and environmental and all, but those, those are, are sometimes hard to kind of quantify, hard to mitigate and, sometimes again muddy the water around what are the objectives of the project.
So focus on those objectives, identify what things could happen to prevent us from achieving those objectives.
Or if something bad were to happen, what would we do to get it back on track to make that objective? So that, that is what risk management is just trying to make sure that we prevent the things that might not allow us to achieve the project objectives.
And then does that also...
so does risk also include the upside, managing that deviation from an expected outcome? And so that's, it's an interesting perspective because the COSO ERM framework says that your objective is your objective.
If you come over or under that's, either of those is a risk and should be considered.
W- whereas PMI and, and others, in essence, they say, you know, if you come over the, you know, like if your production target is 100 barrels and you come in at 150, that's an opportunity.
But e- the, I, I kind of prefer the COSO perspective because it makes you think, "If I come over, you know, 150, can my production handle it?" So the COSO ERM is a good perspective.
This is what we wanna get.
If we go over, we have to consider what risks might occur there.
If we come under, we have to also consider, what risks could occur and what the commercial aspects of it are What I'm hearing is risk management is always has a time component in a way, 'cause it's like if we're at time T zero and you pick a point out here at T 10 or whatever and you, you also have this observer, a frame, where you're like, "By these mechanisms, this should be here."
And then risk is saying what is the actual deviation from expected, like- So there's always an element of there's a time horizon that you have to be considering, and then you also have to be considering whose perspective are you looking at for that risk.
Is there always one? We talk about risk registers, it's like that's your list of risks.
You kind of have to have alignment, right? If, if people don't understand what the goal is, you can't really tell them the deviation from that goal.
Right how do you...
Is that the risk manager's job, or is that...
you have to get beyond the bias.
You talk through what the risks are, things that might occur and you often get the, "Oh, yeah, that'll never happen.
I, we've never seen that."
Or, or the opposite is, "Oh, we have to...
You know, we need to order 12 extra valves because we're gonna have so many fail."
So you, you kind of talk them through.
The, the valve one is a good example where we had an engineer that said, you know, we're ordering eight or 10 or 12 valves.
I don't know how many it was, but you know, we're talking about risk.
He said, "Oh, yeah, the...
It's an ex- extremely high likelihood that, that we're gonna, they're gonna fail.
Very high."
And so I said, "Well, okay, you know, we're putting this in the risk register.
And it's gonna be at the top of the list if it's a very high likelihood."
I said, "Okay, well, if you ordered 100 valves, how many of them would you expect to fail?" probably three."
"Okay, that's a very low probability of, of that failure occurring, so, you know, we put it in at, at very low in the risk register."
So it's about having that conversation and talking them through and, and making them think about is this really a risk or, you know, have I considered all the things that, that could occur.
Well, maybe that gets into that term I think we've heard, a, a black swan.
Like, how do you...
so maybe t- talk about black swan.
Is that actually in a defined ISO term, or is it just sort of something we've come up with? That it's so, outrageous that we can't...
we shouldn't even consider it because there's nothing we could do about it if it occurred, and there's nothing we could do about to, to prevent it from occurring.
But yeah, there...
You have to focus on what you can control and what reasonably will impact the project, and that's the word that I use cannot reasonably occur.
Otherwise we're, you know, we're gonna waste a lot of money and waste a lot of time thinking about things like, planes crashing and things that, are very unlikely to occur.
So you did risk management for broad portfolio I believe for a large company, and you were managing small project risk and then really large project risk, and sort of how do you make risk economical? 'Cause I think sometimes as, like, an executive, you're gonna be looking at this saying, risk management...
Like, the risks are probably gonna occur anyhow.
I could spend millions of dollars trying to prevent that one in 1 million thing.
You know, how do you properly...
what's the right economic model to look at risk so that you're spending the right amount and being, you know, a, a good sort of steward of the funds of a project? What...
How do you balance that? Every project is different, and one of the things that, I feel like some project teams get, twisted up on is that the company might have a global risk matrix or a corporate risk matrix, but the project has to have its own.
And, generally, that's going to be in terms of the cost and schedule impacts to that project.
You know, is it, is...
Do you do the matrix at, you know, 10%, 25%, 50%, 75%, 100%, budget impact? That, that lets you frame that project in terms of its biggest risks and, you know, compare it to other projects of similar sizes or, you know, that a big risk on a million-dollar project might be $100,000, but a big...
But $100,000 risk on a billion-dollar project is really, you know, has a different frame of reference.
So, the risk matrix is the important way to differentiate big risks on different projects.
And then you rolled out, I believe as well, as part of managing a global portfolio you rolled out a training program, is that right? So when you...
but what would you say when you gave those...
'Cause w- who was your audience with that? It was like project, project control managers, the engineers, you know, folks involved in the, the project.
Like what- What do you think were some of the aha moments or things that you gave these people when you were doing risk training, in 2000? Yeah.
We used the term risk champions.
A- and what that meant was people who kind of understood and had an interest in knowing more about what project risk management looked like, that we could go out and teach them and then let them go do.
So that worked really well.
It's hard to do it all as a single individual, and risk management is all about everybody understanding how the whole process works.
So we just tried to teach everyone that we could and find interested people.
But, yeah, it was a variety of folks.
Project controls, engineers, a lot of coordinators.
So if somebody was listening to this and they were like, "I wanna set up something like that for my company," what would you advise them in terms of, like, leveling up risk? 'Cause it sounds like it's not just hire the perfect risk manager, it's actually something that has to be baked within the organization.
It, sort of it organically, kind of like safety.
You know, you don't get safe- you have to have a safety culture.
It sounds like you worked on creating a risk culture.
Yes how do you create that? It's just about getting in there and doing it.
Like, get in and start a risk register and, you know, begin working through what that whole process looks like who should be involved.
And the first risk workshop is the hardest, and after that it starts to become a little bit more mechanical and people know what they're expected to do, and you can do a lot of, prep work up front before you get into the workshop.
So it's just a matter of getting in and starting to do it, and then making it better every chance you get.
Okay, so risk workshops.
Maybe we can go back to Leviathan real quick.
I'm assuming day one you had a risk workshop to kind of, start that process.
Maybe talk to, tell us the story of the first risk workshop on Leviathan or, like, how did, how did you create that process and So it was the first workshop, yes, it was a little awkward because it was kind of the first time that team had come together to talk about risk registers.
And, the risk workshop, the whole idea is that everybody understands what those risks are and what they mean, even if they don't have anything to do with it and it's not their discipline.
And so, you know, you have a lot of vocal voices and, y- that- that's half the role, is being able to kind of manage those personalities and, "Yeah, we'll ta- Yes, let's put that in the parking lot.
We'll, we'll take that offline.
We'll talk about it later.
Yeah, yes, that's a valid risk.
Let's, we considered it and, here are the mitigations and here's why we don't think it's gonna happen."
But then, you know, once the team is, is used to doing the workshop together, it goes pretty smoothly.
So tell me about the personality management.
Like, what...
That's, that gets out of the comfort zone of the numbers and into something a little more- you know, probably a little more real about how real work gets done.
Yeah.
You know, It's, it's- Yeah it's back to the comment about the psychologist, right? Not only do you have to, manage the loud personalities, but you have to coach the quiet ones as well and, what the term they use is elicit risk.
Get them to tell you what is it that they're thinking and then kind of understand that and present it back to them as the, "Are you saying that this could occur?" Or, "Are you saying that we need to do this?" So it's a lot of, working with people and people management tell me more about that.
'Cause so you brought in people in the field.
Right.
So it wasn't just the corporate office, 'cause they're the ones that really are getting the project done.
Me what...
How was that? Yeah, and that's another big challenge you face is you've got these experts from the field which are necessarily there, but they don't wanna be there.
You have to be considerate of their time, do as much, upfront work as you can to make that meeting valuable the whole time they're there and meaningful the whole time they're there.
And again, that also goes back to the, the people management.
Don't let just the one person rule the whole meeting.
We need to get all the opinions and have all the conversations.
One example, we went into a risk workshop and the leader of the entire group said, "You guys are here today to tell me why X is our biggest risk."
conducted the workshop.
Everybody had their input, and X came out as the third-biggest risk from that group.
So it's about having those conversations and everybody else understanding, w- what's his risk or her risk versus mine and my scope.
So if you're facilitating a risk workshop, is there like, Is there some sort of like 80 people in a room talking about risk doesn't work? Is there...
Like how do you prep the conversation? What's a good...
Is it like an hour, hour and a half? Like how do you do those? Yeah.
Sometimes dependent on the, the size of the project and the experience of the people.
What I find m-most useful, of course, what you always want to be able to do is to start from a lessons learned review, whether that's doing it yourself and going through and saying maybe these things apply to this project, and putting them into the risk register, and going and looking at similar projects and seeing what risks they identify or, or experienced, and-- but putting all those into the risk register.
And then do as much as you can, upfront interviews with people.
You know, give them a call and just say, "Hey, we're doing a risk workshop.
Was wanting to get your perspective."
And, you know, try to get those individual perspectives ahead of the group meeting, and come with something to show them.
You know, if you start off the meeting with all those personalities in the room and you got a blank screen and you say, "Okay, what are the risks?" You're, you're destined to fail.
So w-we wanna have as much, work done upfront as you can.
But so instead of starting with a blank, like everybody list your risks, one, two, three, four, you set up a lessons learned.
Is that usually around a risk that has triggered or, you know, something like that, so it's gets everyone disarmed to actually talk about risk? Or h-how-- what's the lesson that you share? The, the PMI guidance is that a lesson learned is a future project risk.
Part of your project, you should be capturing lessons learned on a regular basis and, writing them in a way that it's useful for a future project.
And then to start a risk register to kick off a project, you would wanna go and look through the lessons learned from previous projects, especially those that are similar to the one that you're working on.
That's always the best starting point if you can do that.
Also, previous risk registers.
One of the reasons I say don't delete a risk just because it's mitigated or it's no longer applicable, leave it in there and just say that it's closed out because somebody's gonna need to review that sometime in the future.
You know, that technically would be a lessons learned review.
So that's a lot of what the homework is to lead up to the workshops And so you said the, the, on Leviathan, the workshop- the first workshop was, was obviously rocky 'cause you're just getting everything started.
And I imagine myself, let's say I'm a risk manager listening to this podcast, and I just got on a billion-dollar job, and I'm thinking about, what, what do I need to do here? One question I would have is I think everything usually has, like, a rhythm.
You know, when you look at, like, risk, safety, you know, any function within an organization, there's sort of like a sine wave of activity.
And it seems like those meetings and that sort of regular risk management process is kind of that, that flywheel.
What's the frequency that you might wanna do it, like monthly, quarterly? What are those activities that help anchor good risk discipline? I'll say, the, the easiest way to dovetail a risk review in is to kind of piggyback on a cost or schedule review, or a cost and schedule review if you can do that.
They're all related.
And it's easiest since you already have that team assembled to do that review to say, "Hey, let's, let's do risk review after that."
Okay.
And then how do you deal as the project psychiatrist during that? You know, 'cause cost review, schedule review, oftentimes I find people don't want to identify r- I, I...
risk is one of those things that, like you said, there's the quiet folks in the room, but like people oftentimes don't wanna surface risk 'cause there might be political problems with surfacing a risk, and it's actually easier in their world to like let that risk ride, and if it triggers then it's just like, "Hey, this happened."
How do you break through that and sort out the political consequences of like raising a risk for someone? 'Cause I think that sometimes keeps the risks unsurfaced.
Like do you address that specifically or is that an organic thing? Like, how do you surface risk given that it can create political problems for other people? Maybe it's like, "Why did we ever even order these types of fasteners? Like, who would order something that could rust in, in a storm?" You know, it feels like sometimes risk turns into a witch hunt, and people don't wanna be the one to kick off the hunt, so to speak.
What I will say at Noble, w- one thing that their drilling group did an excellent job of was a lesson learned review is not a finger-pointing session, and so everything is on the table.
And they're, they were really good at that.
And so we, we kind of piggybacked off of that in projects to say, "Look let's implement this really good lessons learned program, and just put everything out there."
Once people understood it they knew, yes we c- we're finding faults and things, but w- this is good because we're gonna prevent it from occurring again.
Yeah, it's, it's again back to the people management aspect of, of getting people to, to talk.
And it also, you know, the, the prep t- that you do ahead of time, if you can have a one-on-one with somebody you're more likely to get something like that and say, "Well, here's how we're gonna address it in the big group session."
Is there, on a large project, is it that anything that deviates from the expected is either a risk that was documented or a risk that you never knew about, but it all kind of fits into risk in a way? Is that...
Because I, I guess m- my question is, what do you do about those risks where something happened in the field and it caused, you know, 1,000,005- deviation on the project, you find out about it.
It's, it has nothing to do with the risk register.
It was, but it's not a black swan.
Like, is there some cleanup activity you have to do to kind of be like, "Okay, this actually was a risk we never caught"? How do you surface those? Like, how does that play in? It's the known unknowns versus the unknown unknowns.
It's just that you, you do as much work upfront as you can to try to identify what types of those things might occur.
You know, we talked about in the, in the Mediterranean, we had a, a survey go through where the, you know, where the, one of the pipelines was supposed to be laid, and they found some ancient jugs on the, on the sea floor, right? Yeah.
But you do the survey for a reason, and so you, you might carry some of those risks just in case.
So, it's about thinking through, you know, what, what might go wrong with each of the activities that we have planned.
And again, will it truly impact our objectives? We could have a delay and, piece of equipment arriving, but it doesn't impact the schedule.
It doesn't change our start-up date.
So okay, it was delayed a week, that's okay.
We might have some cost impact of that, carrying cost or time delay or whatnot, but it doesn't impact the objectives of the project, so it might not be as big of a risk as it sounds.
Okay, so maybe this gets into Monte Carlo and things like that.
But maybe you can talk about that, 'cause how do you actually, when you get down to brass tacks and you say, "Okay, what's the impact?" How do you quantify that? How does Monte Carlo fit in? What is Monte Carlo, Monte Carlo is a very interesting approach.
If you think of it just at its at the core, if you have an activity and you have a 50% chance of finishing up on a day, and there's a dependent activity that you have a 50% chance of finishing it on, on, on time, you only have a, a 25% chance of meeting that, that schedule, right? So that's kind of what Monte Carlo is, is it says all these activities that you have in here, you've said that you've got a 10% chance of a risk occurring here, a 5% chance here, 25% chance here.
It goes through and- Does a thousand iterations of that schedule or that budget and says, "Okay, 10 of 10 of these or, you know, 100 of these, we're gonna apply this risk, and 200 of these we're gonna apply this risk."
And then it cycles through the thousand iterations and says, "Okay, you have a 50% chance of meeting this number or this date."
And so, The company has to make a determination whether they go with, that 50% chance number, the P50 as we call it,, or something more conservative like a P75.
We have a 75% chance of coming in with this result, and therefore we're very confident we'll be within that.
So the Monte Carlo just takes your cost estimate or your schedule estimate, runs through 1,000,, or, a count of your choosing iterations of that and applies the risks that you've identified where you've said they might impact that budget or schedule Do you do the Monte Carlo monthly or is that really pre-FID before you're making your final decision, you get that P50 and you're like, "That's good enough"? Like, how often- Yeah.
Y- yeah, let me, let me back up a little bit and say Monte Carlo is most effective on large to very large projects.
A very small project, Monte Carlo is not nearly as effective, and you're not gonna get you know, the accuracy of the results that you would want to have.
For smaller projects, we have the PERT method, the Pro- Program Evaluation Review Technique.
That's what I recommend for smaller projects.
Oh how do you present it? Yeah.
So the inputs to a good Monte Carlo are an accurate up- updated budget or forecast, an accurate and updated schedule, and an accurate and updated risk register.
So, you know, if you're doing those things monthly, you can run your Monte Carlo monthly.
But Monte Carlo is, you know, you're typically talking about a very long timeline of the project, so you might not necessarily need it every month.
So we, what we did on Leviathan was we did it approximately every quarter.
We would update the Monte Carlo every month, but we would only present it every quarter.
Okay.
And then when you say present, so risks are interesting, right? Because they I think oftentimes they can go all the way up to the board level.
So you're surfacing a risk- down at this tiny little spot, and then it sort of bubbles up the organization.
How does that work for, like, Leviathan, you, as the risk manager, do you present to, like, the project director, and the project director then presents up the chain? Is that typically how risks are surfaced, the project manager, project director, you know, they ultimately own all the risks.
You know, the risks should be individually owned by the people who are working to, to mitigate or close them out.
But the project manager has final say on that.
And so, yeah, we prepare the documentation for the project manager to present those items and those risks.
And then separately the risks that are assigned to people you know, as the risk lead, you're responsible for getting those updates from those people and making sure that, that the project manager is in alignment You're working, let's say Leviathan, right? So you've got your team.
There's above you the risks are percolating kind of up through the org, right? Right there's also this sort of corporate b- barrier on big projects where a lot of times you have contractors that are doing major scopes of work, and so they have, how do you surface them from that part? 'Cause then you get this sort of like corporate boundary line, and those risks, like, how do you manage contractor risk, basically? Do you enforce it in the contract, or how does that work? What we tried to do is we would go directly to them, meet them at their office and tell them what we were doing, that we wanted to do a risk workshop with them.
Could they bring what- whatever they were working from, whatever their risk registers were.
And, you know, if, if we found deficiencies, we would just coach them and work with them to get them to do things the way that we preferred.
But we found that most of our big contractors like that did have a risk management function and they were willing to meet with us to do that.
So the risk manager is kind of a social animal, would you say, Lots of meetings.
Yeah, and what's the right way, to approach those things? Because I feel like you can kind of be the almost like the tax man as a risk per- Feels like there's a few buckets.
Either it's like, "Is this person helping me? Is this person draining my time?" Or, "Is this person going to get me?" And I feel like risk managers or risk conversations could fall into any of those buckets.
So how do you disarm folks to have, to see you as like a helpful, good guy versus other- You know, my favorite, icebreaker is, you show up for a first meeting and say, "I'm from corporate.
I'm here to help."
And, you always get a bunch of laughter.
Everybody finds that one funny.
It's like I acknowledge that it, you guys don't wanna be here and you don't wanna hear from me, but, let's get through this and, and hopefully we'll see that we're adding some value to this activity So 'cause you're a personable guy, what can people do to work on those soft skills, do you have advice for someone that...
'Cause it almost sounds like, a sort of math and science discipline of risk, and then there's this sort of social soft skill of risk.
Like, how do people...
The math and science, it's like ISO 3100, right? 30- Yeah, 31,000.
And then, but how do you develop the soft skills? Or are those in the ISO docs or, like, what do you recommend there? They're not in the ISO docs and, there's not a lot of very specific guidance in those frameworks, right? So, honestly I think it's, just a matter of getting your feet wet.
Get in there and do it.
And yes, the first meeting and the first run-through is gonna be a little bit awkward people are kinda figuring out what you're doing, but after a couple of iterations it'll be a lot more natural and, everybody'll know what each personality is and it just gets easier.
So just get started, get going.
It gets easier as you go.
What's the one personality that's the most difficult, you would say, that you have to, like, manage right off the bat for risk? It's one end of the spectrum or the other.
It's the everything is bad and is going to happen and you need to put 15 risks in your risk register for me, or none of that'll never happen so don't even put it in there, right? And you have to kinda talk them off the ledge and try to explain to them is why we're doing this.
This is what we need to capture.
It's not just about you, it's about future projects the project manager wants this, and report to the board."
And so it's a, coaching and influencing activity for the ones that just kinda don't get it or, have an extreme view.
So it sounds like there's sort of two ends of the spectrum.
There's sort of the Pollyanna people, and then there's sort of this dooms- doomsayers, and Exactly sort of the center to moderate.
Yeah.
And th- those two are the ones that it's sometimes better to go meet with them in person out of the workshop and try to, you know, head off any of those types of outcomes.
We've talked a ton about the soft skill, the, process of risk, things like that, kind of approaches.
One piece that I would love to get your perspective on is technology.
I always say it's process before tool.
We have discussed the process.
But what's the role that good technology plays in risk management? And I guess I mean that from the, you were in the software side.
You said you had a really great risk platform.
Like, how do you implement good technology solutions that actually help with this situation? Yeah.
You know, it, it's, a- again, to go back to one is greater than zero.
Having a risk register is i- infinitely better than not having one at all.
And so, the s- somewhere far down the list is the what tool do you use? But the, the top of the list is create a risk register.
That's it.
You know, obviously Excel lends itself really well to doing that because you can, you specify what columns you want in the, in the spreadsheet.
The main thing is to keep it simple for the, for especially for risk reviews and especially for the project teams and te- the leads.
Keep it simple because, a fancy, complex tool sitting around a workshop is a, a big waste of their time, keep their time reviewing risks to focusing on exactly what they're supposed to be looking at and not, these, these big fancy, what's the risk velocity and what's the, we got a variety of other things that a lot of risk tools do that aren't necessary for a project.
These very involved scientific risk studies, and risk reviews like failure mode effects analysis security vulnerability analysis pick one, HAZOPs, HAZIDs.
Those are very specific and very detailed and very engineering-oriented, and they are not suited for project risk registers.
The project risk register is the simplest form of risk review that exists.
It's very basic, focused on project objectives.
So you wanna use the simplest tool you can, especially when it comes to doing the reviews and workshops But you had a tool that you said was one of the best in the industry.
Like, what was that doing that was so cool? That one was, was pretty cool because it did all of those methodologies in one single platform.
So, we actually ended up using it and kind of customizing it a little bit to make it super simple for project risk registers.
But we would in many cases export that from that tool for a review because we only wanted a few fields from that risk register, while we were doing the review.
So yeah, that's where the technology is important because you...
if you choose too complex of a tool and it's too difficult to do that export and review or, you know, put it in a PowerPoint even then it just won't get done and it won't get updated and, and, you know, you'll have bad data in there So that was really like a point solution for people that were specialists.
But when it actually came to communicating risk or trying to, like, assign s- like workflow related stuff was better managed in Excel rather than- Right having 20 people have a login to a risk tool that they have to, like, organize their risks in and all of that.
Exactly, yeah.
Okay.
And did you find that was also the case when you were doing sort of a, a enterprise-wide multi-project portfolio as well, that you kind of allowed people to...
Did you roll a tool out for that, or did you also just kind of allow people to, to work one at a time? Y- we did roll a tool out, and by keeping it simple and training those risk champions in the various areas, we were able to drive usage of it, yes.
But having those, those point contacts, risk champions, people who understood the process out in the field, that was very valuable.
And was it like for that particular case, did you start with the training and then get the tool in place afterwards? Or was it like, "Here's a new tool," and you trained as you introduced the tool? There's always this kind of question of does it help to have a system kick off? We had the tool had it rolled out ahead of time but realized that we weren't getting the adoption that we wanted, which is when we developed the training to teach them the process.
"And by the way, here's a tool you can use."
Okay.
And then you and I have talked a little bit just to like zoom out, 'cause I feel like we're sort of, we're starting to go further out.
I think you had, talked about how risk has been around for tens of thousands of years, that there's a,, a book that you recommended which maybe you could talk a little bit about.
But when you actually get down to it, like risk is a very...
is something that humans have been dealing with for many of years, and now it's kind of sitting in ISO for projects.
Where do you see risk? What do you see as the, like, history of risk? Maybe you can teach us a little bit about that, and then where do you think risk as a discipline is going in the future? Once you have that risk management mindset, it kind of gives you a different perspective of things.
It said something about how the lifecycle of a jet, it's, like 25 years for passenger service, after which it's only for cargo.
It's like, that's a risk mitigation.
We're not gonna kill 300 people, we're only gonna kill two, you know? So you have a different perspective on life when you think of it from a risk management, aspect.
But the book was the title is Against the Gods: The Remarkable Story of Risk.
And it's very interesting because it talks about some of the early philosophers and how they loved to gamble because they understood what the odds were, and they were all about taking these low probability, high impact risks, gambling, trying to win something.
And, that's not all the book is about.
It's a fascinating book.
One of the things that I say is that the AI that we're using in 5 years or 10 years is going to be reading the data from today.
And so I feel like where risk management is going is leaning on AI to help us figure out what we need to be doing to avoid risks, not only in the project world, but, you know, broadly.
And I think that AI, but just like everything else is going to help with that focus on risk management and history and what has happened and good outcomes and bad outcomes, and how do we prevent that? How do you see...
Is risk, like you run your Monte Carlo and then you also run your LLM,, is it sort of a new category of risk identification and forecasting? Like, how do you see this AI tools intersecting risk, like in a practical way? I think Monte Carlo was maybe sort of a rudimentary early, application of AI, right? Where it's saying we have the compute power to go through these cycles of, of trying to forecast what, what you think might happen.
Whereas AI, I think would be a little...
will be, better at saying over the course of the life cycle of the project, you know, these things did or didn't occur, and therefore your Monte Carlo is changing in this way, or your potential outcomes are changing.
And I think AI will outpace Monte Carlo as an approach to, you know, the, the potential outcomes of a project AI is like a super Monte Carlo.
Right markov chains are kind of like, chained together tokens where you're like, "This is probabilistically connected to this, that's connected to this," and then you zoom that up into trillions of connections.
And so that's kind of like if you took your risk register and then you broke it into tokens, which would be like words, and then had probabilities that...
You know, instead of Monte Carlo having a schedule that has like 10 dependencies that it's running it on, an LLM is looking at those tokenized values and running it against trillions of connected points to like suss out probabilistic outcomes.
So it really does seem like, yeah, maybe it is like a super Monte Carlo in a way.
Yeah, and the Monte Carlo is very dependent on the quality of the inputs, whereas with AI I feel like, you can be a little softer on that quality and still have a good outcome.
And also I think it's easier to look across other projects with an LLM than it is to, today's software.
Do you see as the downside of this AI in risk? Obviously hallucinations, things like that.
Is there some dangers that the future holds? I still think for a lot of project scope y- you have to have the expert opinions.
AI can do a lot but, you need people who have the experience and, and have been through it.
I don't think for some project disciplines that there is a, you know, near to midterm risk of anything going away for, for them.
I believe those skills and experiences are, are important to have, and the- it'll be a, a long time before those are impacted by AI in my opinion.
So what's your...
Are you thinking we're probably 50 to 100 years away from just robots building everything and doing their own risk registers and- Once we're fully globalized, right? I say that because who knows what the future holds.
I mean, just the last couple of years of technology, you know, seems like w- we've made some pretty big leaps.
Let's say that I'm a project director and I just hired a risk manager for a mega project.
What advice would you give that project director to enable that risk manager and get their risk going? Like, what am I doing to help the risk situation? If that person is starting from scratch obviously we need to know wh- who to talk to make those connections, establish those relationships, get to know the leads of the various disciplines that'll be working on the project, if those are known at the time.
But yeah, certainly develop those relationships as early as possible.
Okay.
I'm vice president of this company.
We're gonna take on this mega project.
We just FID'd or we're a little bit into it.
How do I know if risk is actually being managed well? What are the signals that I could see where I'm like, "We probably have a risk problem we need to, like, figure it out," or, "This is excellent.
Risk is running really well in my organization"? What would you advise someone like that to look for? As long as they are very well aware of the risks of their various projects, I would say it's running well.
One of the main things that I encourage people to do is to describe Risk in a way that it can be understood by someone who has nothing to do with the project.
Okay.
So, they need to understand exactly what that risk is, not just $10 million.
We have to say what that risk is and it has to be described in a way that is meaningful for outside parties.
Okay.
So if I'm an executive and I'm, I'm s- looking at this project and I get the risk register out, and it's highly technical stuff where I'm like, "I could not hand this to an investor or somebody else, and they would have no idea what's going on here," that's probably- Correct a flag that you wanna you wanna take a harder look at risk and, and maybe level up a little bit for the organization.
Absolutely what if I'm on a project and I wanna be I'm like a scheduler or an engineer or someone in the field, and I wanna be good for the risk manager.
Like, what advice would you give them to support this new risk manager that started, Always analyze inputs into your, your cost or your schedule with a little bit of skepticism, and ask questions to try to make sure that you as a, as the scheduler or, or as the, cost control person, also buy into that result and, and you know what the risks are, and you know that they have been identified and/or mitigated.
Okay.
And then I guess one last thing if I'm starting a new project, should I insource or outsource risk? What's the, what's the cost benefit on that? Because a lot of big orgs, they just sort of have a outsourced risk function, and some people bring risk in-house.
Do you have a strong preference or opinion on that? I found it to be pretty effective to be insourced.
Obviously, not everybody can or, or wants to do that.
And certainly with risk management, if it's not very well understood in the organization, it might be more effective to outsource it.
Certainly I, I have a little bit of a bias that I can recognize there that, it worked really well by insourcing it.
But I, I would just say, you know, again, a- a- all of those key things, making sure that, that whoever the person is that's doing it, especially if it's outsourced, that you know that they're meeting with those key, individuals, key contractors, discipline leads, having regular meetings, having regular updates, and describing risk in a way that your organization can understand it, not just the risk manager.
Y- you can have success either way.
Okay.
Is there a single takeaway that you would love for someone to get from our conversation? What do you think is the most important thing or one of the most important things that you'd like them to remember or that we could highlight? I would say there are a couple of key concepts in risk management that have always stuck with me.
One of them I, I said a little bit ago a lesson learned is a risk on a future project.
I feel like lessons learned are extremely important.
Whether you call them that or not, you know, even an old risk register is a lessons learned register, right? You've captured a number of lessons learned there.
So, risk, lesson learned is risk on a future project.
And then another one that I found in an old Navy training slide deck was change is the mother of all risk.
Okay.
And if you think about that, as a concept, a lot of times when you have bad outcomes, it can be traced back to some kind of a change or a decision or something that we did differently than we had originally planned.
And so anytime there's any talk of change, that, that should be a risk conversation change is the mother of all risks.
It, kind of gets back into how time is always required for risks.
Right.
Yeah.
Yeah.
It's...
and the, and the whole CUSO concept, right? This is your outcome, and any deviation from that is a risk.
Yeah.
So what advice would you give if someone's listening to this and they're in college and they wanna go become a risk manager? Do you have advice for someone that might be pursuing a career? Just keep in mind that project risk management is the simplest form of risk methodologies that exists.
It's very basic, that the simpler you approach it, the more success you'll have and the easier it will be to replicate that success over time, especially over the life cycle of a project.
Keep it simple.
Don't overanalyze the, all the Google results that are out there that tell you what project risk management should be.
It's, it's very basic.
But how do you get a job in risk? So there are, there are jobs open currently for project risk managers.
That does exist as a role.
Typically, it's within, like, an EPC-type company, and they're working across multiple projects, which means that that company is trying to, have a, a discipline across every project that is risk management.
Kind of everything we described today.
Those jobs exist.
You know, you, you...
it's, sometime easier to move into that role once you're within a company and are working on a project.
That sometimes is a, a good approach to getting into that role.
It's kind of how I found myself there.
So it's sort of a lateral move.
You sort of start on these projects and then make your way into the risk space when a opportunity opens up.
Yeah.
If you're really into risk management as a discipline you, you'll know it, right? But, for an organization that recognizes the value of that, they love to have people in those types of roles.
If I'm that student, how do I sense-check that myself? Like, let's say I'm, like, an engineer, I'm thinking about risk.
Maybe that's where I wanna go.
But then I'm like, "You know what? I really don't like working with people."
You know, I think from our conversation we'd know, okay, that your profile might not actually enjoy this.
Or what's something students could think about to, like...
someone who's very curious and loves to always be learning, because every project Is different.
The scope of the project is different.
Materials are different, right? So you always have to think through what is different about this project? What risks might I have? What have I not thought of yet? So it's like if you're considering a job in patent examining, you might want, think about risk too, right? Like just being able to be on a continual learner as well.
Yeah.
It sounds like you have to kind of have that curiosity.
I've heard it said that,, you know, a project manager might work on three projects in their career but when you're talking about a risk manager, you, you are likely going to work on dozens of projects.
Well, is there any books or industry associations that you would recommend? We talked about Against the Gods: The Remarkable Story of Risk.
Any other sort of resources out there or things that...
podcasters you follow, anything that other people could go deeper with? I would say the Project Management Institute guidance on risk management is really good.
It's applicable.
There are some concepts in there that are, maybe a little more advanced for some projects, and it tries to be, all-encompassing every type of project.
But that's good guidance and it's specific to projects.
So that's kind of where I would start.
I mentioned ISO 31000.
That is a framework and it's more geared toward corporate-type risk management implementation, so I wouldn't say let that be too much of an influence other than to say that there's a process that should be followed.
Same with COSO ERM.
Another good reference is, I believe it's ISO Guide, I think it's 73, but it's all of the definitions of terms around risk management.
The one I gave about the definition of risk, that's from the ISO Guide, I think the number is 73.
That's another good one to get familiar with.
Cool.
Is there any conferences that people go to on risk that are really good to go into or surface? Is it really the PMI conference or is there like little niche risk people association? Yeah, I mean, there, there's all kinds of stuff on LinkedIn that you can find.
Risk can mean so many different things and project risk is, is a very specific discipline within that larger risk concept.
But things like IPA and project analysis, they do a lot of, of project specific focus on risks.
So any kind of IPA conference you can attend, I would encourage.
Matt, I really appreciate you joining us, sharing all of your wisdom.
Is there any other tips or tricks you want to leave us with before we wrap up? That's one thing we didn't talk about just the terminology.
Settle on a set of definitions, and just know that people will have experienced other terms that meant the same thing.
Mm-hmm.
Like severity or impact, right? Those kind of mean the same thing or in a risk management, in, in risk management terminology.
But just define what all those terms are for your project and for your program.
Going back to, like, having a singular perspective is really important- Right because if you have two different scales that you're measuring things against, doesn't work at all.
Do you send out that appendix to everybody before as, like, a prep activity? Or how do you actually get that front and center? We build it into the guideline documentation.
So anyone who's curious enough to read that would, would see it.
But yeah, at, at a workshop, we typically would have a series of handouts, your risk ra- risk, matrix so, you know, people are, are grading their risk, they know what they're working from.
And then, you know, terminology, definitions.
Well, Matt, thank you for joining us today.
I was- learned so much, about Leviathan, kind of your role in that.
We went deep on the high end of risk with Monte Carlo and down to the low, sort of just conceptual definition of it.
I, I can't thank you enough for taking us through this.
Sure appreciate your time today, and hope that we get to chat with you again about this important topic.
After two decades of failed attempts, Steve Adler did what no Austin mayor before him could - he got 58% of voters to approve a 20% property tax increase to fund a city-wide transit system. In this episode, we go deep...
In this extended conversation with AJ Waters, we go beyond the job site and into the question a lot of younger people are asking right now: is construction still a safe bet? AJ makes the case that it absolutely is and...
In this episode, Orion sits down with AJ Waters, field COO for public sector at Procore, host of The Engineerd Life podcast, and one of the most widely-traveled and well-connected people in the construction industry....
Project control teams are bigger than ever; more schedulers, more risk managers, more reporting managers. And according to Ahmed Abdelfattah, they're delivering worse results than when one planner ran everything with...
In this bonus episode, Hannah Garrett shares practical advice for students, career changers, and professionals hoping to enter the fast-growing data center industry. She explains why emerging leaders should embrace AI,...