Green Bonds, Gray Areas: How Do AI Data Centers Fit in a Sustainable & Responsible Portfolio? | Megatrends | Romina Reversi, Crédit Agricole & Steve Liberatore, Nuveen (#149)
“Just because something is labeled a green bond doesn't mean it is.” Steve Liberatore helped write the Green Bond Principles. Most new US labeled bond issuance now finances data centers. So what is a sustainable portfolio buying? This is the first SRI360° Megatrends episode: one subject, two guests, both sides of the same trade. Romina Reversi of Crédit Agricole CIB structures this paper and brings it to market. Steve Liberatore of Nuveen decides whether to own it. I expected them to fight about the label. What I got was more useful. They disagree about what a green label is for - and agree on nearly everything that decides whether a deal is worth owning. In this episode: • The industry’s go-to efficiency number is a PUE of 1.5. Steve says he still doesn’t know what it really means - and explains what he underwrites instead. • Big Tech came to market with labeled sustainable bonds in 2020 and 2021, then stopped. Labeled debt has fallen from around 5% of US issuance to under 1%, and most of what’s left is data centers. • Hyperscalers issued $160 billion of bonds in the first five months of this year. Why that much paper in one sector makes a bond buyer nervous. • Romina’s team structured the first US corporate nuclear green bond. Steve wouldn’t buy one - and owns up to a D-plus in physics. • Who is actually on the hook when the capital arrives years before the power does. “I don't think people are fundamentally opposed to data centers, it's that they don't want to be the ones who are bearing the burden of rising energy costs and decreased water availability.” - Romina Reversi, Crédit Agricole CIB What success looks like, in their words. For Steve, tracking the impacts in a use-of-proceeds deal is “the roadmap” for checking whether an issuer’s free cash flow improvement is actually on track. For Romina, it comes down to “the criteria, the transparency, and the expected impact metric reporting.” Chapters 00:00 Labeled green doesn't mean it is 00:48 $700-800 billion of capex, and 71% who don't want a data center near them 04:49 One structures the paper, one decides whether to own it 06:44 Argue the other side: what keeps a banker up at night 10:03 If the whole market goes down a sinkhole, is it still green? 12:32 PUE 1.5: “I still don't know what it really means” 16:44 98% refinancing: what does a green label actually add? 18:25 What gets a no, and the one red flag that makes Nuveen walk away 20:29 Sustainability-linked bonds: “a very easy no” 22:50 Capital, power or permission: which one stops a project? 28:34 Who's on the hook when the power is five to seven years away? 31:34 $160 billion in five months: when issuance floods one sector 33:39 Why Big Tech stopped labeling its bonds 35:55 GPU-backed private credit and NVIDIA's $105 billion backstop 38:46 A ninefold jump in grid capacity prices 41:33 Three Mile Island, nuclear green bonds, and a flat no 44:57 Are data centers cannibalizing clean power? 49:00 On-site gas: a 40-year asset for an 18-month problem 52:31 Permission: who pays for the grid? 58:39 AI's politics: when cost savings means job elimination 01:02:39 Data centers in orbit: Skynet, or “why not?” 01:08:14 Rapid fire: transition catalyst or relabeling? 01:10:32 One principle for your investment committee Guests Romina Reversi on LinkedIn: https://www.linkedin.com/in/romina-reversi-b0b00137/ Crédit Agricole CIB - sustainable finance: https://www.ca-cib.com/en/social-responsibility-sustainable-finance/our-sustainable-financing-solutions Steve Liberatore on LinkedIn: https://www.linkedin.com/in/stephen-m-liberatore-cfa-837b45233/ Steve Liberatore at Nuveen: https://www.nuveen.com/en-us/institutional/about-us/profiles/stephen-liberatore Related episodes Episode 84 - Romina Reversi on why green bonds still struggle with investor trust - Romina’s first appearance, and the 98% refinancing debate this episode picks up. Episode 61 - Steve Liberatore on why public fixed income does more impact work per dollar - The case behind Steve’s line that the instrument matters as much as the intention. Discover more from SRI360° Explore all episodes of the SRI360° Podcast · Sign up for the free weekly email update
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
SPEAKER_01I was on the original executive committee of the Green Bond Principle, so I did help to write them. Just because something is labeled a green bond doesn't mean it is. And just because it isn't labeled a green bond doesn't mean it is not. We are globally transitioning to renewables not because they're better for the environment.
SPEAKER_01We're transitioning because at the utility scale, they're cheaper on the marginal level as a power source. So we're talking about Skynet, in other words.
SPEAKER_02From a sustainable finance perspective, my answer is sure. Why not? Why can't we figure it out?
SPEAKER_03Unlock the potential of your investments to improve the world and make high performance returns. Welcome to Sustainable and Responsible Investing 360. My name is Scott Arnell, and each week I sit down with a world-class investor to uncover their secrets of profitable ESP, impact, and socially responsible investing. Find out more at SRI360.com. The top five hyperscalers are expected to spend roughly$800 billion this year on the AI buildout, and 71% of Americans say they don't want a data center built near them.
SPEAKER_03Meanwhile, a majority of the new US bonds issued that are carrying a sustainable label are specifically financing data centers. So what does green actually mean here? If you run a sustainable portfolio, these fixed income issuances are coming at you in size, and the green label alone won't tell you what you own. Romina Ravesti of Credit Agricole structures these bond issuances, and she was a founding member of JP Morgan's ESG debt capital markets team back when most CFOs hadn't even heard the term green bond.
SPEAKER_03Steve Liberator of New Vene is a portfolio manager who decides whether to own them. And he helped write the green bond principles back in the day. We get into who's really holding the credit risk when the money arrives years before the power does, and how a sustainable investor navigates the gray areas between a bond's label and reality. And now, please meet my guests, Romina Reversi and Steve Liberator. Welcome back, guys, to SRI 360. Today we're gonna do something different.
SPEAKER_03Normally, this show has been a conversation that I have with one guest, and I talk about where they came from, how they got here, what they've built. There are moments when a topic is big enough in the zeitgeist that I think it's appropriate to get more than one perspective in the room at the same time. And today, I think it's one of those moments, and we're going to focus on just one subject, the AI build-out, which is rapidly developing into the biggest capital deployment most of us will see in our careers.
SPEAKER_03And it's running into something that most financial coverage treats as background noise, maybe a wall built by ordinary people who don't want a data center next door, or some politicians from both parties who've decided this is a winning issue, while other politicians from both parties and some people from the AI industry are saying that this is something very dangerous and we got to put a pause on. And then there's a whole set of sustainability questions that aren't often as much talked about and that nobody's really quite figured out how to answer.
SPEAKER_03Let me lay out what I see as the three constraints, and then you guys can tell me where I might be wrong on this. On capital, the top five hyperscalers are now expected to spend in the high 700s to low 800s of billions of US dollars this year. And Morgan Stanley and others have repeatedly revised higher than that. And on physics, you can get a shell up in 18 to 24 months, but the queue to connect the grid in PJM, and that's the grid operator for 13 states in the District of Columbia, it runs five to seven years.
SPEAKER_03And the lead time on large transformers you need has gone from 18 months to three or four years now. And then the last one is on permission, you know, and there's been at least several dozen projects blocked or delayed in the first quarter of this year alone. And some trackers put the figure closer to 75 projects, worth something like$130 billion. New York enacted a statewide moratorium on new hyperscale facilities in July and a Gallup survey in March, found that 71% of Americans don't want a data center built near them.
SPEAKER_03So today I'm happy to have two guests joining me who've been here before: Romina Reversi from Credit Agricole and Steve Libertor from Nuveen. Welcome back to both of you, and thank you both for being gluttons for punishment. Now, since both of you have been on before, I'm not going to go into your backstories, and I suggest that listeners go back and listen to each of your episodes to get the full story. But I do want to say just a little about why I chose each of you for this particular conversation.
SPEAKER_03Romina, you were on the episode 84 talking about why green bonds still struggle with investor trust. Well, you weren't just a commentator on the early green bond market. You were actually inside of it as one of the founding members of JP Morgan's ESG debt capital markets team. And this was back around 2015 when a lot of CFOs hadn't heard the term green bond, and the entire business was being built from scratch. And then before that, credit agricole, your current firm, was a co-founder of the Green Bond Principles and the Equator Principles.
SPEAKER_03And then, Steve, you were here in episode 61, where you made the case that public fixed income does more impact work per dollar than private markets. You run just over$20 billion of fixed income assets for Nuving, and that's inside a firm that manages over a trillion dollars overall. And you made the argument in that episode that I've been thinking about ever since that the instrument matters just as much as the intention. And I think data centers are about to test that argument pretty hard, and I wanted you here for that.
SPEAKER_03Romina structures this paper and brings it to the market. Steve decides whether to own it, and that's the tension I want to work with for our talk today. I want to ask each of you to argue the other's position. And I don't want a caricature of it. I want the strongest version that you can build from the opposite chair. So I'll start with you, Romina. You originate and structure this paper. Make the strongest case you can that this financing cycle is overextended and ends badly.
SPEAKER_02This market has been in existence in the data center space in Green Label actually for some time. This growth is not new. These green frameworks are not new. In fact, the sustainable green label from a data center perspective only has more than doubled since 2023. And we've seen a number of issuers, Vantage, Switch, QTS, they're coming back to the market. QTS has done over 24 billion of green financing, and that includes a 4 billion green bond.
SPEAKER_02So then that leads to your question, Scott, of what is the biggest reason, the best argument as to why these green issuers should come to market with a green label as opposed to a non-green label. What I think is the primary compelling case is the fact that it is a communication tool for these issuers. There are obviously a number of binding constraints against data centers that they should be communicating on, whether that's energy consumption, rising electricity prices, transmission infrastructure, water consumption, land use, the noise, the community.
SPEAKER_02And in my opinion, adding that green label is an opportunity to showcase how they are mitigating some of those risks.
SPEAKER_03But what about the big picture? It's not only green label. I mean, there's a lot of data centers that aren't being finance that way. But if you're sitting in Steve's chair, what would be the thing that would keep you up at night?
SPEAKER_02So that's a hard question because I've only sat on the bank side. I've never been on your side, Steve. So it's good to keep to look at it from the other point of view. But do I believe the way these data centers are mitigating the key sustainability-related financial risks are sufficient? And from an energy or pushback perspective, are they implementing sufficient mitigation tools that I can reasonably say this can fit within an impact fund, within a green fund that I am managing as opposed to simply a traditional fund that does not have a green or an impact lens.
SPEAKER_03And Steve, now the reverse for you, make the strongest case that this is completely rational, credit worthy, and backed by balance sheets that can absorb all this.
SPEAKER_01Clearly, in our lifetime, this appears to be the largest scaling of investment and infrastructure investment that we've ever seen. You simply can't ignore it. And you have to do as good of a job as possible as understanding what is really being done within these structures and these transactions. And what we have seen is whether they come with sustainability labels or not labeled, or they have sustainability features or not, these are being built. And you need to understand, you know, the opportunity set that you're faced with as the investor.
SPEAKER_03Romina, now tell me where you actually disagree because the green does sit within the bigger market. Obviously, you might think it's super green, but if the whole market goes down a sinkhole, that's not a very sustainable investment.
SPEAKER_02I'm going to answer the question from a sustainability lens and a framework perspective. And in the data center space, sustainability is increasingly becoming tied to both completion and permitting risks. So I mentioned before this laundry list of scrutiny that we are seeing. And there are a couple really great examples of that scrutiny. For example, we've seen Virginia, it's one of the largest data center markets, but local opposition is increasing quite a bit.
SPEAKER_02So what does that mean? I mean, projects are being delayed, they're being canceled, there's permitting challenges, community challenges. We saw something with QTS that planned a development. And then after that, it was actually litigation prior to the project securing a local approval. We've seen the same in Texas, where you have a governor that is saying Texas is the epicenter of AI development, but then there are actually moratoriums that have later been implemented.
SPEAKER_02So that's the landscape. But since I am simply coming at it from a green and climate perspective, I think it's important to realize that this is all happening in the context of increasing climate hazards, the frequency, the intensity of what we're seeing, whether that be hurricanes, flooding, drought, et cetera. And to bring it all home to why a green framework in this environment that we are sitting in, it really does, in my opinion, provide a structural way for these data center issuers to show that they are thinking about the challenges that the community faces, the regulators, you know, showing how the underlying physical assets are being designed, operated with more efficiency.
SPEAKER_02And so I'd say there's an argument there for why to have a green label versus not have a green label, showing that the business in a way is more sustainable and better able to weather these risks that are in the market.
SPEAKER_03Steve, from your perspective, what's your argument, why you're cautious or what keeps you up on the buy side?
SPEAKER_01You really have to understand the use of proceeds. You have to understand what reporting is available to kind of verify how that capital is being deployed. And what we've seen with the data center space is kind of varying issuance quality, whether it's labeled as a green bond or isn't labeled as a green bond. When you dig in, you know, a lot of the securities that are tied to data centers within fixed have labeled themselves green, primarily based on a metric called power usage effectiveness or PUE.
SPEAKER_01And that is a number that I still don't know what it really means, right? It's not a relative number. It doesn't state, you know, on a comparable basis what it really means. It's just a PUE of 1.5 is considered efficient. And if you're below 1.5, that means you're really efficient. Well, I don't know what any of that means because, like I said, there's no relative assessment of that. So when we look at a transaction, what we're going to look for are metrics that we understand and can give some relative assessment of.
SPEAKER_01Or are there characteristics that we can dig into that will allow us to feel comfortable that the particular project is meeting our definition of being green and sustainable? So that's going to be looking at how are you sourcing your power? You know, are you using renewables in some way? Where in the country are you building? Right. That's another factor. You also have water efficiency and usage. Even though most centers have what would be considered closed loop water use systems, you know, it's still a question, you know, do you really want a data center built in a water-stressed region?
SPEAKER_01Then you kind of, you know, dig further into kind of the social and community aspects. What work has gone into the community engagement to get support? You know, like we've seen a lot of pushback. All of these data centers have been talked about being built are not going to be built. What work has gone into working with the community? Are you taking over a fouled industrial site and remediating it and simultaneously setting up programs at the local community college, for example, to train people to eventually go to work at the data center?
SPEAKER_01Are you talking about the taxes that you're paying that are going into the local school system? A lot of that has to go into kind of the evaluation of whether or not something is sustainable. And for us, you know, again, as a total return investor, we're digging into this not just because we want to make sure that it fits our definition of being green or being an impact investment, but it's all about the financial thesis of the investment. We know that the biggest cost associated with the data center is cooling.
SPEAKER_01So if we know that you're building in a more moderate climate, you're using a lower cost renewable source of power, you have a closed-loop water system, you've built in a windier part of the country which just naturally is cooler, then what you're pointing to in the future is data centers going to be more cost effective to run. Obviously, a lot of the work that goes into this analysis is who's the ultimate guarantor or who is the credit that's going to eventually be on the hook or responsible for paying it.
SPEAKER_01And that goes back to the first question, Scott, around why you would want to look at this, is these are very credit-worthy entities. These are the largest tech companies in the world who don't issue a lot of debt to begin with. So if you're trying to get exposure to them, this is a way to do it. But if you know you're investing in a data center that's using low-cost renewable in a non-water stress region that's worked with the community and is supported by the community. And if for some reason company A doesn't take over at the end of the period of time when they are supposed to, for whatever reason it might be, that's going to be a much more attractive data center for every other company looking for a data center because of that efficiency.
SPEAKER_01And that's where the sustainability aspect ties into the financial rationale of why you're making that investment.
SPEAKER_03I want to talk about labels. And Romina, I want to pick up where we left off in episode 84. That one study I found roughly 98% of the U.S. green bond proceeds over a decade went to refinancing rather than new green projects. And you told me that that misunderstands what a green bond is for, that additionality for a green bond means capital direction and disclosure, not project level additionality. I'm not going to relitigate that, but I want to test on the case that exists right now.
SPEAKER_03A data center bond finances a building whose entire purpose is to consume enormous amounts of electricity off in front of a grid that's still largely fossil fuel. The PUE power usage effectiveness is the standard efficiency metric. A 1.2 PUE on a coal-heavy grid still puts a lot of carbon in the air. Does your argument survive that case, or is this where the label finally breaks down?
SPEAKER_02It's challenging to get a green bond that's 100% forward looking, and it doesn't diminish the additionality, in my opinion, of a green bond if it is refinancing projects versus forward looking. So we're not going to advise a client not to issue a green bond because it's 100% refinance. We advise them well, you will get this question. This is make sure you're prepared to answer it and explain your pipeline. And ultimately the most important, which I think you alluded to in the prior episode, and I completely stand by is the criteria, the transparency, and the expected impact metric reporting.
SPEAKER_02Green bond principles, they're still not prescriptive.
SPEAKER_03Tell me what gets a no. You told me in the same conversation that we had that you sometimes do tell an issuer that this isn't in their interest. What would make you tell a data center client no?
SPEAKER_02Entirely no to a green bond. The bar for saying entirely no here's a very small case. I think even if you have some of these older frameworks and they're simply looking at PUE and they're not touching on some of these others, you still could come to market. You could consider that it's a lighter green versus darker green that has other considerations within it.
SPEAKER_02But for it to be an entire no, do not come to market at all. I think that is more reserved for some of these more challenging cases that we've seen within the FLB space or targets that are not relevant core and material to the business, more secondary KPIs. That's a bit easier to say, no, it shouldn't be included, or in some of the carbon-intensive issuers where they simply don't have the right use of proceeds or even in completely different sectors from what we're talking about today, beef production, right?
SPEAKER_02There are some where it's really, really challenging to get on board with a green label.
SPEAKER_03And Steve, what do you actually require operationally before Nuvene buys a data center green bond?
SPEAKER_01Yeah, for us, you know, we we don't really pay too much attention to the label itself. We don't look at PUE, whether it's labeled green or not. We're gonna look to see what are the direct and measurable economic, environmental, and societal benefits of that particular project.
SPEAKER_03Is there a single red flag right now that makes Nuveen walk away from a data center, credit, or green bond?
SPEAKER_01There's varying levels of disclosure. If we don't receive a lot of disclosure about a transaction, then we don't participate.
SPEAKER_03Romina in episode 84, you said it's actually a good thing when a sustainability link bond misses its target, because that's evidence that the target was real and that the target was ambitious. So is use of proceeds even the right instrument for this sector? Should a data center be financed with a sustainability link structure where the coupon steps up if they don't actually procure clean power, putting real money on the line?
SPEAKER_02In my opinion, the best structure is use of proceeds because I think that that encompasses a variety of different green elements and the community side. It's not to say that an SLB could not be possible for a data center, but I think it would be a missed opportunity not for some formals to go with green use of proceeds. Then there's also the question of investor demand. What narrative are you trying to communicate from adding a green label? And when you use an SLB, many times it's for issuers who say are CapEx light and they don't have enough CapEx fend, or where there is a very clear KPI of emissions reduction that can be used as the primary KPI with some secondary KPI.
SPEAKER_02So I would advise a data center client to start the green label. If they kind of think it makes more sense, but curious to hear Steve's view as well.
SPEAKER_03Yeah. Steve, would that change your answer at all?
SPEAKER_01That's an easy one for us. We have been a long time skeptic and critic of the SLB market. And so for us. It's a very easy no on anything that's an SLB. To us, use of proceeds is the best structure and one that allows for us to really understand where the capital is being deployed and track the underlying impacts, not just because we want to produce an award-winning impact report, but because a big component of our financial thesis and investing in a sustainable manner is the belief that if you're doing this correctly, you're deploying capital to issuers who are going to use it in a way that's going to help them generate more sustainable free cash flow in the future.
SPEAKER_01So by being able to track the impacts inherent in a transaction, it gives us the roadmap and the ability to assess whether or not that improvement in free cash flow generation is actually on track based on the transaction we invested in.
SPEAKER_03Three constraints capital, power, and permission over the next three years. Which one of these is binding and which one stops a project? Romina, why don't you go first?
SPEAKER_02I'm going to double-click on power since I'm coming at it from the sustainability lens. And the reality is the power system wasn't built for this type of demand growth, right? The power system is not anticipating the AI demand growing as quickly. And we're seeing these tensions emerge between all the stakeholders. That's the utilities, the regulators, operators, generators, the communities, as many different parties here with different constraints and pressures.
SPEAKER_02You mentioned PG, PJM, right? So we do have those regional grid operators that are dealing with a record number of interconnection cues as these large load customers are all seeking increasing access. So we have a couple of examples that we've seen there. AEP recently discussed potentially exiting PJM and SPP because of the difficulty and the delays that are tied to bringing on this generation that's needed to meet the large load demand over the next few years.
SPEAKER_02Then there's also the implication of power prices on the largest electricity grid in the country, PJM, which operates not, as you said, across 13 states in the Eastern and Central US. Power prices has actually jumped 76% in the first quarter of this year due to demand from data centers. The stat on that is from a report from Morningstar Analytics. And electricity costs have increased as much as 267% in the areas near the data centers where there's significant usage.
SPEAKER_02That's over a five-year span. That stat is from Bloomberg News. So to answer your question across the three, I would say yes, there's absolutely real constraints on the power side. And I think the more interesting question becomes: are data centers part of that solution? Are they large enough to support the new investment in the new generation, the transmission upgrades, and this grid modernization that really may not have occurred otherwise? I do think that power is going to be a constraint.
SPEAKER_02This is a timely episode that we're recording with all of the AI news that has come out over the last week or so. And is there going to be a slowdown or not? And what that means for the US versus other world powers, I still think that your point two is a real constraint that we'll have to work through in the coming years.
SPEAKER_01Usually you think it's capital. And I think that with these three, it feels like capital is probably the easiest one to resolve and solve. You know, obviously you're talking about the world's largest tech companies. There are growing concerns that you've had these issuers, why they're all extremely strong credits for the most part, is they were massive free cash flow generators. They're now not. They've quickly reverted to not being free cash flow positive. So there could be growing concern over time about the how much capacity can these issuers take on from a debt perspective or ultimately a leasing perspective or some form of obligation.
SPEAKER_01But at the moment, they're generally triple and double A rated names. So they certainly have the ability to take on additional debt load. The question is more around price. What does it cost to get the transactions done? That seems to be the bigger issue, but the capital still seems to be available. Permissioning and power, I think those are the ones that are really going to be more problematic. And the permissioning, we're seeing that just because you're seeing much more pushback. And most people don't want a data center built near them. There is growing concern around both what the data center represents and not just from an environmental perspective.
SPEAKER_01Are we funding our future elimination of our jobs? And in the worst case scenario, are we trying to kill all of ourselves? I feel sometimes like I'm the only person who's watched Battlestar Galactica that showed how this already worked out. So that I think is going to be the big challenge. And then the power, I think, kind of falls into that category as well, because a big part of this is, as mentioned by Romina, is getting the power up and running for these data centers. And you can go behind the meter, which is likely to become what is going to be necessary for a lot of these, because that's going to be the quickest way to mitigate the unintended consequences of higher power prices for everyone else, but also potentially alleviate some power constraints by if they're building behind the meter power that could then be put into the grid as well.
SPEAKER_01But then we're right back to it takes a while to get connected to the grid. The grid needs to be modernized, especially to take on more renewables, especially, which are quicker and available to get onto the grid. You're not facing the G Vernova situation where right now the backlog for a gas, a natural gas turbine is six years. So if you're looking at needing to be able to get the grid updated and modernized to the point of being able to obtain and put on more renewables.
SPEAKER_01So to me, it feels like though permissioning and power are far bigger concerns at the moment than capital. Although, as I mentioned, capital could become a problem if these issuers go from being strong AA credits, free cash flow positive, to negatively impacting their credit quality and not generating free cash flow over time.
SPEAKER_03What's happening right now is that mismatch between capital and power availability, capital's being committed faster than the physical reality can deliver, who's the one holding the risk in the end?
SPEAKER_01Ultimately, depending upon which structure you're looking at, right? So if it's a corporate issuer, your corporate is ultimately responsible for the debt. And in a lot of the structures that we've looked at, usually the way that they are structured is that if the ultimate hyperscaler is not directly responsible, they become responsible once certificate of delivery or completion of delivery of the construction of the data center itself becomes completed.
SPEAKER_01So in that instance, you're then still looking at the hyperscale or ultimately being on the hook if they can't get this project up and running and being productive.
SPEAKER_03And Romino, when a client comes to you wanting capacity online in 18 months and the power to run it is really five to seven years away, what do you tell them?
SPEAKER_02I fully agree with Steve's point earlier that PUE was an early indicator that somehow got used and tagged to that 1.5 number as the industry's foundational metric, but it is not sufficient on its own. And two facilities that have a very similar PUE can have very different environmental footprints. These deals are getting gobbled up anyway. Many of the frameworks from a couple of years ago are still being used, and these deals are vastly oversubscribed.
SPEAKER_02Why? Because fundamentally there's still a lot of capital, there's a lot of demand. The perfect is the enemy of the good.
SPEAKER_03Romina, are you structuring deals right now that that timeline mismatch is obvious in there?
SPEAKER_02There still is no definition on what a green data center is. As Steve said, something can be green, labeled, but not be green, and also be green, but not be green labeled.
SPEAKER_03Steve, are you buying deals like that where you see that difference? What appears to be more capital than power available?
SPEAKER_01We have not. Most of the deals that we have seen have been basically structured with everything ready to go, or in a construction phase with committed power available within the time frame of completion. And that would be something we would be looking at in the evaluation, because at that point, a lot of these deals, you're taking some level of potentially construction risk, or you're taking the risk of a credit at the beginning of the project who's building the data center who's a lower credit quality than who ultimately takes on the obligation in the long run, which would be the hyperscaler.
SPEAKER_01So if we try to minimize any opportunity for there to be an inefficient project or an unusable project that would allow the ultimate higher credit guantor effectively to take over the obligation.
SPEAKER_03First five months this year alone was$160 billion. Tech issuance now accounts for roughly 60% of the year-on-year growth in U.S. investment great corporate credit supply. Steve, this is what you do for a living. In plain English for someone who doesn't run a bond book, when one sector is 60% of the growth in investment great supply, what does that end up doing to your portfolio?
SPEAKER_01Yeah, it gives you a concern about making sure that you're doing the best you can to evaluate which of these particular projects are the ones you really want to invest in. When you see that much of a flood of issuance, you automatically know you're going to have what we consider winners and losers in that issuance. And you want to make sure that you're evaluating the risk and return profile as accurately as you can and understanding that where the valuation is for each of those securities. And that's why I think, as I mentioned earlier, using a sustainability lens to evaluate these projects, I think puts you in a stronger position to specifically identify which issues you want to be involved with from a risk return perspective and a long-run financial viability perspective.
SPEAKER_01But it is a concern when you see that much issuance in one space because that's usually a sign of some type of bubble where what ends up happening is issuance occurs that maybe wouldn't have been able to be issued when you were in 2020 through 2024, when you only had 20 to 25 billion of issuance in the space for the year. You had a reasonable pace of issuance and you were able to spend time correctly evaluating each transaction. When you just have a flood in one particular sector, then you know something is going to get missed, right?
SPEAKER_01Or there's not as much evaluation occurring as there would have been historically, which to us means you have to take even more time to specifically identify which securities you want to participate in.
SPEAKER_03Romina, Amazon's later deals this year have seen oversubscription compress quite sharply from the levels we saw earlier in the year. So is the market telling us something with that?
SPEAKER_02From a sustainable finance perspective, I think it's interesting to keep in mind that actually none of these deals have been labeled. We saw a number of tech companies, hyperscalers come to market circa 2020 and 2021, all with sustainable finance frameworks, and those were labels, but then there was a drop-off, and the recent deals are not labeled. We've seen a rapid decline in U.S. issuance over the last five years. The percent of debt that has a sustainable label in the United States about five years ago was around 5%.
SPEAKER_02And every single year over year, it has been dropping. So we are at sub 1% of total debt issued from US issuers across currencies has a label. The concentration of what you're seeing from a green perspective, a majority of the US labeled issuance is in data centers right now. And so from an investor perspective, I think it's a similar question of your overall portfolio, forgetting about labels, has a concentration.
SPEAKER_02Then if you're running a sustainable portfolio or green bond-related fund, there's also this concentration in an environment where we continually get the feedback from investors. What would you like to see more of? Diversification of issuer types. Right now, we're not seeing very much diversification of issuer types in the US at all. But what is the alternative that we saw say to three years ago? There still was not very much issuance. So I am at least delighted to see that we are seeing green issuance, albeit in a concentrated way in the United States, as opposed to what we're seeing in Europe or the multilateral development banks, Asia.
SPEAKER_01I think that that's a very specific to U.S. corporate issuers. One of the things that the data kind of points out is that other than U.S. corporate issuers, pretty much every other sector within fixed has actually been at or above the prior year's pace of issuance.
SPEAKER_03Steve, let's look at where the real duration of credit risk is accumulated, which is specialized private debt. And as of June, Core, we've had$13.6 billion outstanding under GPU collateralized loans, and then just closed another$2.6 billion at SOFR plus 5.5%. That's five-year debt backed by customer contracts averaging three years, secured by chips that face hardware obsolescence every 12 to 18 months. From a fiduciary standpoint, before we even touch on ESG, how does anyone underwrite that?
SPEAKER_01In a lot of instances, a lot of these data centers and a lot of the tech companies, even the hyperscalers, will have debt in other formats that have to be considered part of your evaluation of the creditworthiness of that particular issuer. So that's probably one of the bigger factors that we've seen has just been the growth in the private debt market where there is just more opaqueness, right? You don't have marks, you don't really see terms as well. So you don't really know effectively what's occurring within those markets, but that you have issuers now that are kind of coming to all markets simultaneously and attempting to raise capital and determining effectively for themselves at any point in time where they're receiving the best effective financing.
SPEAKER_01So it's no longer just, hey, this company is a publicly traded company, all they will have is publicly traded debt. It's not the case anymore. You have to dig in to evaluate their entire balance sheet because there's a good likelihood they've tapped other markets to raise capital. And that has to be a part of your evaluation.
SPEAKER_03Nvidia's stepping into this breach with a capped$105 billion residual value guarantee for SB Energy's ports technology Ohio campus, and they're making a lot of other cloud capacity commitments. Steve, does Nvidia's guarantee change anything about your answer?
SPEAKER_01I don't think it does. I think it may actually amplify it a little bit because what we're also seeing is another somewhat unique characteristic of the way that the hyperscalers and the data centers and AI participants have kind of evolved, has been a lot of what you would consider to be kind of intercompany, you know, support for one another, where they're supporting each other's operations, similar to kind of what you saw in the 1980s in Japan, where each of the individual, you know, entities or families at that point in time were supporting the other ones.
SPEAKER_01So there was a lot of intercompany transactions that only amplify potential credit risk. So it's another unique characteristic of what we have seen that's not been something historically that you have seen in the public debt market.
SPEAKER_03Let's move into the power question, which is the physical problem. Where does electricity come from? PJM cleared its 2025-2026 capacity auction at$269.92 per megawatt day. And then subsequent auctions hit a cap of around$333. And the prior year it was$28.92. That's more than a nine-fold increase in one year. And the Independent Market Monitor for PJM reported that data center load growth was the primary reason for that.
SPEAKER_03And American Electric Power is reporting 69 gigawatts of signed new load through 2030. That's roughly double its entire existing system's peak demand. If the grid in a region is already stretched and the queue is five to seven years, how do you separate a sound infrastructure credit from a speculative overbuild? Steve, maybe you can take that one.
SPEAKER_01One of the challenges we have is we know already that the existing US power grid is strained, right? It's old, it's inefficient, and we haven't really had a lot of investment made into grid modernization, but it is something that I think our political leaders have identified as an area for focus. I think that's why you're seeing more data centers trying to come up with behind the meter solutions where they're having to bring their own power. Can that be a partial solution to grid issues where if they build enough of their own power, that's actually more than what they need, they can put more of that back into the grid.
SPEAKER_03But is that something you can actually diligence or are you taking it on faith?
SPEAKER_01Depending upon what stage of a project you're looking at, all you can do is evaluate the information that's available to you. If you're looking at a transaction and it's a data center that's bringing its own power, you can evaluate where in the process they are for their power. Are they just saying, hey, we're going to have our own power, but we don't, we haven't contracted for land, we haven't already purchased the equipment that's necessary, we haven't already started construction, even though the data center has started construction. We haven't already started the regulatory process of working with the local utility.
SPEAKER_01So there is a way in the diligence process to be able to evaluate where that issuer may be in the process. But if they're not completed, in some ways you're having to take them at their word that what they are saying they're going to do, and because they've already committed capital to some of this, that they're going to complete it in a reasonable period of time and in good faith.
SPEAKER_03So the buyers are going around the grid. Microsoft signed a 20-year contract to restart Three Mile Island. Never thought I'd read that. 835 megawatts, priced at an estimated 110 to$115 per megawatt hour, according to a Jeffries analyst. Meta's committed to as much as 6.6 gigawatts of nuclear by 2035. Romita, you told me in episode 84 that nobody in this industry really wanted to talk about nuclear. A lot more people are now.
SPEAKER_03And you actually structured the very first U.S. corporate nuclear green bond. Is nuclear PPA structuring a scalable model, or is this something only a mega cap can afford?
SPEAKER_02Nuclear, let's call it, you know, five, eight, ten years ago in the green frameworks community was historically not included in green frameworks. And then we saw it be officially integrated into the EU taxonomy that came into effect in 2023. From there, we saw a number of deals in Canada and in France. And you mentioned, Scott, the US nuclear deal that I talked about in the previous episode for Constellation, which was the first ever US corporate nuclear green bond.
SPEAKER_02And since then, we've seen mostly positive reception to adding a green label with nuclear. One other element to the narrative beyond nuclear that I think will be interesting to watch is actually how utilities are becoming more sophisticated in the way that they structure tariffs to ensure that data centers, large load customers, really cover those incremental costs that are associated with the large amount of electricity that are needed.
SPEAKER_03A lot of European mandates still say no nuclear, though, no?
SPEAKER_02They do, yeah. And when we've done nuclear green bonds, we do a survey of investors, and a majority of them cannot still put it in their dedicated green bond funds. So it's not to say that nuclear has been widely accepted as green for all green bond funds, and investors are communicating that, but there is a strong reception towards the inclusion, and that's a stark difference versus what we saw in you know pre twenty twenty two.
SPEAKER_03And Steve, would you buy a nuclear backed green bond if the power under it is priced at roughly double the market rate?
unknownNo.
SPEAKER_01No, we would not. Nuclear at the moment and the current technologies is not something that our investors have indicated an interest in supporting. Bear with me, I got a D plus in physics in college. So I may mix these two technologies up. I did do much better in my finance classes. In the current technology of fission, you still have the same ultimate problems. You still create nuclear waste that we don't have a process for storing or remediating in any way. And the plants can still blow up.
SPEAKER_01So those are issues that are still evident within the technology. The Volctel plants were the last two fission nuclear plants constructed in the US. They were more than a decade and more than$20 billion behind schedule and over budget. So you still have the financial issues of being tied to fission, maybe not presenting the clearest case from a financial perspective of why you would want to use it.
SPEAKER_03It's a bit more complicated than what meets the eye if you haven't spent a lot of time thinking about it. But Steve, when a hyperscaler signs a massive long-term PPA and they take an entire nuclear reactor or an entire regional solar farm off the market, are they actually adding new clean power to the system? Or are they just cannibalizing the existing zero carbon base load and then they force the local utility to run fossil peakers and or coal plants longer to serve the ordinary residents?
SPEAKER_01Trying to understand what it is that you're trying to do in decarbonizing and transitioning to renewables, right? We are globally transitioning to renewables not because they're better for the environment. We're transitioning because at the utility scale, they're cheaper on the marginal level as a power source. If you're a data center and you're taking an entire solar project and using that power, you're meeting the marginal demand with the cheapest form of marginal power, which is a renewable.
SPEAKER_01So from the perspective of overall demand, you're at least not negatively impacting the current balance and the current mix. But that is a concern that if they're the one signing for the lowest cost utility scale project, does that potentially run the risk that other ratepayers are going to be stuck paying a higher relative cost because the cheapest marginal forms of power are all being basically taken behind the meter?
SPEAKER_01You've got to bring your own power, which then theoretically there shouldn't be an impact on the existing grid framework and the existing cost structure.
SPEAKER_03Romina, how do you defend additionality when a client's corporate sustainability report claims the facility is 100% clean energy? But upon pushing down on the analysis, the physical electrons displacing that load on the local grid are coming from natural gas.
SPEAKER_02Would this have otherwise occurred if not for this financing or if not for this project? And I think in and of itself, having additionality from the perspective of a green investment is additional versus the alternative. But then there's the second layer of additionality of whether or not, say, that PPA would have occurred or would have enabled this clean energy to happen had it not been signed.
SPEAKER_02I would argue that both are additional, just in slightly different layers of additionality. It's very similar to the question that we asked in the early days of the green bond market is a green bond additional or not, which is one of the favorite questions circa 2015. Since we know had the green label not been added, well, the transaction probably still would have happened. So therefore, if you're looking at additionality from that perspective, then you could argue no, it's uh not additional.
SPEAKER_02But if you look at additionality with a different definition, then perhaps the answer is yes. Oh, very much in the eye of the beholder for both cases.
SPEAKER_01Depending upon the nature of what the data center is investing in from a power source, let's say they're bringing their own power and it's a solar project with battery or it's a wind project with battery, whatever it might be. Wind and solar are technologies. So the more that's invested in them over time, the cheaper they become further along. So if you have additional investment into solar, wind, battery, all of those are technologies that will benefit from the equivalent of Moore's law for semiconductor chips.
SPEAKER_01And so that could be considered a positive in the long run to further help bring down the cost of power in the long run. But in the long run, we're also all dead.
SPEAKER_03Thank you for that. About 64% of power sector leaders say that they plan to install gas turbines on site behind the meter, skipping the queue entirely. Paybacks of six and a half to eight and a half years. Here's the problem with that. You're installing what's effectively a 40-year asset to solve an 18-month problem, maybe? You know, is behind the meter gas a pragmatic bridge? Are we locking in carbon infrastructure and building the stranded assets of the 2040s?
SPEAKER_03Romina, do you have a view on that?
SPEAKER_02From a green framework perspective, and when we're looking at data centers and the two options, whether it be behind the meter generation or co-location with renewables, what we would like to see is renewables to be included. And so, yes, rather than relying on the public grid, you're seeing this dedicated generation on site. And that is going to have a benefit and reduce the pressure on the broader grid. I think that we will continue to see that as Steven mentioned.
SPEAKER_02And then if there's co-location with renewables built alongside these renewable energy projects, and then you have a dedicated source of clean power, that could also improve the economics of the renewable energy project. So I think that there is a lot of additionality between those two areas. And then what we didn't mention too much yet is the growing interest in battery storage integration. So batteries storing that excess renewable power, reducing the strain on the grid during these peak times, and then how that ultimately community pushback, because that's such an important part of the permissioning and the challenges that we're seeing in data centers right now.
SPEAKER_02But how do each of those elements then help from a community perspective, lower the costs is a key question that we also take a look at and help to advise on.
SPEAKER_03You wouldn't structure a behind the meter gas deal from a sustainable finance perspective.
SPEAKER_02With a pure green label, that would be a challenge.
SPEAKER_03And Steve, would you own something like that or not?
SPEAKER_01I don't think so. From the perspective, are you answering a 18-month problem with a four-year asset? I think that we're realistic in the reality that we're still going to be using fossil fuels for the foreseeable future, right? So if we're going to be using them, natural gas is the one you want to be using because it is the cleanest burning of all the natural gases. The U.S. has a an overabundance of natural gas. So you somewhat mitigate that global commodity price risk. And so if it's a choice between, you know, natural gas and coal, that's a pretty easy choice.
SPEAKER_01Same if it's, you know, oil. And when you look at the current mixture of the grid, you would want to see kind of that introduction of renewables as much as possible, again, because of the financial benefit of them in addition to the environmental benefit. But as a starting point, the natural gas would be, you know, your most prefable of the fossils. But we also have to keep in mind, you know, we hear that a lot about we're gonna, we're gonna come with our own power behind the meter and we're gonna use natural gas.
SPEAKER_01Well, do they already have the turbines on site? Had they already purchased them? Are they being delivered? Because as I mentioned earlier, the current backlog is six years.
SPEAKER_03I want to move into the permission question. And this is the part that most financial coverage treats as background noise. I don't think it is. Tech has ordered an audit in August that froze interconnection for unverified projects. Loudoun County in Virginia scrapped buyright zoning. Virginia now charges a tax on data center electricity consumption. Residential electricity prices rose 7.3% between April 25 and April 26th. His summer's cooling costs are projected up another 10.5%.
SPEAKER_03And at the same time, an E3 analysis, Virginia's own legislative commission, found no historical evidence that data centers have been subsidized by residential ratepayers. But, and this is an important one, the Independent Market Monitor for PJM reported that data center load growth increased capacity costs by$9.3 billion, or 174% for the 2025 and 2026 delivery year, compared to a world with no data center demand.
SPEAKER_03I'm not sure how you calculate that. And those costs get spread across all ratepayers by the utility. So I guess the honest answer to whether electricity prices are being impacted by this build-up seems to be not directly, not yet, but increasingly in some regions through the capacity markets. Steve, does any of that show up in your credit analysis?
SPEAKER_01It definitely feels as if this similar to kind of like the inflation question, right? You may be able to point to data that says that there is no inflation, but people feel like there is. So it's it's a question that has to be addressed. It's hard to imagine that there wouldn't be an impact, given, again, the constraints on the overall grid. We know the inefficiency, the ineffectiveness of the current grid, the delays in getting new power onto the grid, that you've gone from an industry where we saw power increase somewhere between 1 and 3% a year to jumping into the double digits and they're not being an impact on pricing.
SPEAKER_03Romina, Pennsylvania now makes anything over 25 megawatts pay 100% of the grid upgrade costs that it causes? And WC Energy requires customers below single any minus to post collateral against power commitments, Oracle sued to block that, then drop the suit, agreed to pay. How do cost, cause, or pay rules change a deal that you're structuring? And is that something your clients absorb, or is that a reason to go somewhere else?
SPEAKER_02Doesn't change anything from how we address green framework updates. So when we're taking a stale framework from a couple of years ago and updating the criteria for the use of proceeds specifically, we really are focusing on four areas. It's the energy efficiency, POE, the low carbon electricity, then the water efficiency, the water usage effectiveness, and finally the community infrastructure impacts. Those are the four main. That being said, I definitely think that the pushback is likely to continue over the next two years.
SPEAKER_02We're not going to see signs of stopping. There was a survey conducted by the University of Pennsylvania in August, found that about 61% of U.S. adults oppose the construction of new data centers in their area. That's up 12 percentage points from February. I don't think people are fundamentally opposed to data centers. It's that they don't want to be the ones who are bearing the burden of rising energy costs and decreased water availability. So wherever there are solutions that the data centers can take on those costs, or there can be structures with utilities that bear the cost of that increase, I think that that will help to mitigate the issue.
SPEAKER_02And then tying it back to green frameworks, that's where a green framework in and of itself can be helpful for communicating these projects in a more responsible way, framing what the long-term infrastructure benefits are. And it is more than just having a tool to defend project legitimacy, but actually to communicate how they're being proactive on these topics that are challenging across state lines.
SPEAKER_03Steve, I mentioned WEX Energy Tariff forces non-A-tech clients like Oracle to post cash collateral so residential ratepayers aren't stuck paying for stranded substations if an AI venture for some reason folds. As an ESG credit manager, do you view those protective tariffs as credit positive because they protect the S in ESG, which would be ratepayer equity, even if they increase capital friction and cash burn for the tech borrower?
SPEAKER_01Yes. I would say that that kind of falls into the category of the way that we evaluate from a credit perspective. So as a bondholder, a lot of the regulatory components of certain industries. So thinking of like banking and utilities, for example, generally we as a as a credit investor would consider those as a positive. They're supportive of credit quality, credit strength, and solid balance sheets.
SPEAKER_01So from our perspective as an asymmetric payoff asset class, that additional regulatory support, we feel though it would be a positive. I think in the instance of the example we're using here for an Oracle or any lower credit quality issuer, we would consider that another positive because what that would tell us is that the issuer under question, if they went into this deal and recognized they were going to have to post collateral to ensure completion and ensure that the local communities were not negatively impacted, then that to us would probably increase our comfort level with the evaluation that that issuer did to enter into that transaction to begin with.
SPEAKER_01That would have had to have been another component in their analysis, and that would be something we would ask them about so that they could make us comfortable that they considered those factors before agreeing to it.
SPEAKER_03I want to ask you both about something bigger because it's not just the ESG and sustainability backlash that's hitting this sector. AI itself has somehow become politically contested. And in the US, there's one side saying we have to win the race against China, and that means removing every regulatory constraint, and then we have another side saying that this is concentrating wealth and power dangerously and fast. And in both cases, the data center is the physical object in the argument.
SPEAKER_03That's genuinely a new situation for a sustainability mandated investor. You both were already navigating the ESG backlash in America. Now you're in the middle of the AI politics too, you know, where does that leave you? Romina, I'll start with you.
SPEAKER_02In structuring green frameworks, if I bring the question back to the use of proceeds perspective on data centers, in my opinion, it still boils down to those core components that I mentioned earlier, and they only become more relevant with that increase in AI usage. Is there a social question to be asked, a social use of proceeds from the AI increase that can be integrated within frameworks?
SPEAKER_02Absolutely. From a social perspective, how do you ensure that communities or target populations are upskilling and their jobs are not being replaced as a result of AI? I mean, I was in conversations with a number of multilateral development banks who are thinking about reporting not only on jobs created, but jobs saved as a result of the efforts that they're taking to make sure that there is proper training so that jobs are not lost from an AI perspective and that will be integrated within social frameworks.
SPEAKER_02So I think we can come at the AI increase from two ways. Yes, the data centers and the fundamentals there, but also from a social perspective and include it within some frameworks, the in the tech space, the MDB space. We saw this with the inclusion of 5G internet in some frameworks from a social perspective five, 10 years ago in low-income countries. What does it mean to have high-speed internet and how that increases access?
SPEAKER_02So I think it's a similar question on the social side now with AI that we can also frame it as what are the positives and what are those social impacts for target communities that can be included within frameworks for sustainable finance?
SPEAKER_01Steve, where does it leave you? The social component of the evaluation is becoming just as critical as kind of the environmental and the financial, because without that local community support and a feeling as if that data center and AI is actually an additive component to the overall economy, it's challenging to finance anything, right? One of the concerns there is about AI is that we've yet to really see anyone articulate what the revenue growth opportunity is from the deployment of AI, it's all really been about cost savings.
SPEAKER_01And we all know what cost savings means in the corporate sense, that just means job elimination. So being able to understand that this technology, similar to previous technological revolutions, you know, whether it's the PC or the internet, actually ends up being a net additive to employment and job creation. It's going to be hard to really fund a lot because otherwise you're kind of looking at funding an entire infrastructure whose purpose really is to eliminate jobs, which is a negative for society clearly, and also a negative for the economy in the long run.
SPEAKER_03I want to end somewhere where it's maybe a little bit unexpected, but I think we got to go there. SpaceX has filed at the FCC for authority to operate up to a million satellites as orbital data centers. Pilot compute nodes are going up on Starlink V3 hardware this year. Axiom put two dedicated nodes up in January. A company called StarCloud has an Nvidia H100 running an orbit right now. And both Google and Anthropic are both reportedly in discussions with SpaceX about orbital compute.
SPEAKER_03Here's the pitch. Unlimited solar, when you got this data center in the right orbit, you're in sunlight more than 99% of the time. No water needed. It's ass cold up there. No grid Q, no zoning board. The binding constraint on this build out turns out to be permission, things like community objection, political backlash, regulatory moratoria. Then isn't orbital data center the perfect sustainable and responsible investment solution?
SPEAKER_01So we're talking about Skynet, in other words.
unknownYeah.
SPEAKER_01Right. I mean, I think it's interesting because this really gets into kind of the heart of what I consider the biggest misperception or misunderstanding about sustainable investing, right? Is that there's nuance to all of this, right? That the way you framed it, that sounds exactly what you would want. That would be the most efficient use. You're not taking up any land. You don't have to worry about environmental impacts terrestrially. You're not going to have to worry about, um, like you said, water usage, all the power you need for free. It's already really cold. So the the pure amount of power you're going to need to power those are going to be substantially less.
SPEAKER_01But what is the regulatory environment around which those data centers are operating? Because it's a lot easier for people to go and your local regulators and your local politicians to go to a physical facility in their district or in their hometown to see what's going on and or at least be able to get a sense of what exactly is occurring once you leave the planet, right? You're basing a lot more of this on what is the regulatory setup and structure by which they're going to operate, and how comfortable are you as a society with believing that things that you cannot see that are completely removed from anyone physically being able to see them are doing the things that they're supposed to be doing or that you're being told that they're doing.
SPEAKER_03You don't see this as a feature, you see this as a bug.
SPEAKER_01I would say so. And again, like I said, I can't get Skynet and Battle Sargalastica out of my head. So I may be uh I may be biased in that perspective.
SPEAKER_03Romina, what's your view on this?
SPEAKER_02From a sustainable finance perspective, my answer is sure. Why not? Why can't we figure it out? I I think it's upon us as underwriting banks to understand the art of the possible, to go to the ESG investors, understand their views, see what they would like to have, go to the second party opinion providers, see what their views are. I view the structuring role and has always seen it as we are creating the link between the issuers, the investors, and those who are.
SPEAKER_02Providing opinions, weaving in our own views, and bringing a credible deal to market, are we well received and a positive communication tool and all the other hosts of benefits. So data centers in space, let's figure out a way to make it work for a green framework.
SPEAKER_03Steve, that's essentially what you were pointing out. There's a governance issue there, right? And Romina, you don't see that.
SPEAKER_02I think that there are governance challenges and there will be governance risks that would have to be mitigated through disclosure. I'm more so coming at it from the perspective of it's not a no. It's a what what is the art of the possible and how do we instill clean sheet thinking to see how it could be done?
SPEAKER_03I really don't think that this is that far away. It sounds like a skynet, but I think it's a lot closer than we think, especially now we have delivery systems and so forth to do this. But lest anyone go away thinking there's a potential sustainable, responsible investment panacea out there. Let me take you through the physics. Me, a guy who only got through high school physics class because my girlfriend did my homework in a vacuum.
SPEAKER_03The only way to shed heat is to radiate it. So to dissipate one megawatt and keep the chips at a stable temperature, you need roughly 1,200 square meters of radiator, which is about the size of four tennis courts. So I EEEE Spectrum modeled the coatings degrading over time and found you need 40% more radiator area by end of life. So BCG puts the 20-year total cost of ownership at two and a half to three times a ground-based bill. On the other hand, you know, Jensen Huane says the economics are poor today, but the category is worth pursuing.
SPEAKER_03And that kind of goes to your point, Steve, that with more investment in something, the cost is going to come down eventually, but it's not necessarily a shoe-in because the cost right now as it stands today is higher than what we can do in a land-based installation. Okay, so to wrap it up here, I just got a few rapid-fire questions. And you guys just give me whatever comes to your mind and nothing does. You can take a pass because that's okay too. I'm gonna ask each of you the same thing. In 2030, the binding constraint is capital or power?
SPEAKER_03Power. Power. Data center green bonds today, transition catalyst or mostly relabeling? Romina?
SPEAKER_02Transition catalyst.
SPEAKER_03And Steve?
SPEAKER_01I would say catalyst.
SPEAKER_03Baseload power for AI over the next five years, nuclear or on-site gas? Romina? Both. Alright. Steve?
SPEAKER_01On-site gas.
SPEAKER_03GPU back private credit keeps growing, or we see restructurings in the next two years? Romina? Okay. Steve? I think we probably see restructurings in the next couple of years. Alright. The thing that stops a project in 2028. A regulator, a community, or the bond market?
SPEAKER_02Regulator.
SPEAKER_03Steve? Community. Orbital compute by 2035 real commercial workloads or still in demo mode?
SPEAKER_02Real commercial workloads.
SPEAKER_01I would say it'd be a real possibility, yes.
SPEAKER_03We started out asking you guys to take each other's positions and then counter react. Has anybody learned anything or heard anything that you haven't heard before coming on today? Anything that changed your positions or made you think differently?
SPEAKER_01Having these discussions always, I feel like you learn something, especially when you kind of take a different perspective. When you go from buy side to sell side and have them perspective, I always feel like there's valuable understanding in kind of the approach and what's being thought about and what people are thinking about. But from a perspective of changing opinion, I would say no, for me at least.
SPEAKER_02From my perspective, the opportunity to hear the investor viewpoint, that is the core of this role, is to understand what the investors would like to see, to illuminate what is possible. And so to hear that from one of the foremost investors in this space, I would say I learned a ton and definitely am leaving this more knowledgeable than I came in. So thank you.
SPEAKER_01Oh, geez, thank you. That was very nice of you, but always remember I'm often wrong, but never in doubt.
SPEAKER_03All right. See if someone is listening to this who has a sustainability mandate and a mandate to generate returns, and their investment committee is going to ask them about data centers next quarter. One principle, what do you give them?
SPEAKER_01You have to understand the underlying project. You can't look at a label and you can't rely on PUE. You have to understand the intricacies of power generation, water use, physical location, and absolutely community involvement and community acceptance.
SPEAKER_03Okay. Romina, same question from your side of the trade. What should they insist on before they participate?
SPEAKER_02Absolutely insist on strong disclosure in the use of proceeds and in the framework. Insist on an audit on the use of proceeds, insist on the expected impact metrics that we would like to see in the disclosure. I think those are key to maintaining a credible market when it comes to labeling. And ask questions. Ask ESG-related questions. Because if not, then issuers, bankers assume that there is an interest, which really is not true.
SPEAKER_02So saying nothing is quite a challenge in the ESG space. It's assumed to mean that it doesn't matter and that's not accurate. So vocalize your opinions. That is absolutely crucial.
SPEAKER_03All right. Before I let you both go, I want to make sure people know how to follow you and learn about the great things you're doing and get in touch. So, Romina, where can people find you and find out about all the great things you got your team's doing at Credit AgriCole?
SPEAKER_02Best place is LinkedIn. I unfortunately am addicted to LinkedIn. I don't have other social media though, so I have that. But I am always posting on what we are doing on my webpage for LinkedIn related to Credit Agricole Sustainable Finance.
SPEAKER_03And does Credit Agricol have a sustainable finance part of their website?
SPEAKER_02Yeah. We have a sustainable finance part of our Credit Agricol Corporate Investment Bank website where all of our press releases on deals and our commitments can be found, as well as posting on the C A C I B LinkedIn as well.
SPEAKER_03Steve, same for you. Where can people find out about you and your newveen team and what you guys are publishing, what you guys are doing?
SPEAKER_01Yeah, for for the most part, we certainly have a page on sustainable finance on the nuveeen.com website and can drill into the work that we're doing in fixed income as well on LinkedIn. We usually try to update that with kind of new, unique, interesting things that we've seen or done, or market developments. And that's probably the easiest way to find it.
SPEAKER_03All right. And that's why for someone to reach out to you is on LinkedIn as well. Absolutely. Okay, everybody, we have all these links and details in the show notes of the episode. And as always, you can go to our website at sri360.com. Steve and Romina, thank both of you for coming back on today.
SPEAKER_02Thank you so much. It's really a pleasure. Appreciate it.
SPEAKER_03Thanks for having me, Scott. I've enjoyed it. Yeah, good to see both of you again. Thanks again. All right. Goodbye, everybody.
SPEAKER_00You've been listening to SRI 360. If you enjoyed it, please hit the like button and subscribe to get future episodes. You can find an archive of all previous podcast interviews and more articles and information on SRI ESP Impact Investing, Sustainable Investing, and Socially Responsible Investing at our website, SRI360.com. If you'd like to read more lessons learned from world-class SRI investors, get a copy of Scott Arnell's book, Sustainable and Responsible Investing 360.
SPEAKER_00It's a must-read for anyone wanting to know more about investing for positive social, environmental, and ethical impact. All with market financial returns. These are the stories and tactics of those leading the way as sustainable and responsible investing goes mainstream. Sustainable and responsible investing 360 is now available in hardcover, e-book, and audiobook format wherever books are sold.
Retreating, or getting more rigorous? Money has pulled out of sustainable funds and the White House has tried to cut the fund behind America’s community lenders. Five people close to the capital say what impact...
The alternative protein boom rested on one bet: that the move away from animal products would keep accelerating. Kim Odhner, who has backed the sector since 2016, calls that the fatal flaw. Now he's raising a new fund...
Blended finance still hasn't mobilized the private capital it was supposed to, and the person saying so runs a fund built to take the junior, higher-risk slot so bigger investors can come in. Satu Santala, Managing...
Does impact investing cost you returns? Will Richardson concedes that sometimes it does, then makes the case for "impact lock": impact built into what a company sells, so it can't be stripped out. Amber Electric went...
$27 billion left sustainable funds in a single quarter last year. Is impact investing being defeated, or purified? One of the people in the room when the field got its name says the money that left was never committed,...