What does a client have to put in writing before the information about its buildings can be managed at all? I am Dr Sepehr Abrishami. I research building information modelling, and on Reimagining AEC, in a season on the ISO standards, that question comes before every other. This episode is about information management as ISO 19650 Part 1 sets out its concepts and principles.
Start with a council. Merriden District Council is hypothetical, and it owns an estate of forty-two buildings. It is about to refurbish one of them, the Merriden Civic Campus, which holds a library, a registrar's office and a public hall. Suppose the council tells its design consultant, in a single sentence, that it wants a BIM project, BIM being building information modelling. That sentence sounds like a requirement. It specifies nothing. It does not say which decisions the information has to support, who needs it, when they need it, or how much detail is enough. So the delivery team does the reasonable thing. It delivers everything it has, in the formats it happens to use. Two years later the estates team is rebuilding the asset record by hand from drawings, because nothing that arrived was structured for the questions they ask. Nobody was negligent. The requirement was never stated. The UK guidance on the concepts of the series makes the same point, that a client who asks only for a BIM project has not met the requirements of the series and will not see its benefits.
So the question for this episode is what Merriden should have written instead. Part 1 of the series answers it, although it never puts the answer in one place. By the end you will be able to rewrite that sentence the way the standard expects. You will name the decision the information serves, place each requirement at its proper level, route it to the party accountable for it, and check that every document you cite is still in force. Those four skills are what Part 1 is for.
We will build them in six steps. First the vocabulary and the principles. Then where the series came from, and what it withdrew on the way. Then the hierarchy of requirements and how a requirement travels. Then the models, containers and states that the requirements produce. Then the parties and the function that answer for all of it. And last, the series as a whole, with the UK layer that sits on top of it. Merriden stays with us throughout.
The first step is vocabulary, because most arguments about information on a project are arguments about words that nobody stopped to settle. Part 1 begins by separating two jobs that the industry runs together. Information management is specifying what information is needed and why, planning when it arrives and from whom, checking it against the requirement, and controlling how it moves. Information production is the making itself, the modelling, drawing and specifying. Management runs outward from the client, and it is a function assigned to people who already have jobs. Production sits with the appointed parties inside the delivery teams, and it is carried out to a plan. Merriden's sentence asked for production. It did nothing about management.
Five terms carry most of the weight. The first is the information container, which Part 1 defines as a named, persistent set of information that can be retrieved from a file, a system or a storage hierarchy. Each word in that definition earns its place. Named, because a container you cannot find is a container you do not have. Persistent, because a search result is not a container. And a set of information, because the container is a wrapper, not a file type. It can be structured, such as a model, a schedule or a database that a machine can read, or unstructured, such as a document, filmed footage or an audio file, which a person has to interpret. Both kinds are managed the same way.
Containers assemble into information models, which is the second term. In this series a model is not a file, and it is not whatever happens to be open in your software. It is a structured store of the information needed for decisions, and it is made of containers. Part 1 names two, the asset information model and the project information model, and we come back to both in the fourth step.
The third term is status, which Part 1 defines as metadata describing the suitability of a container's content. Status answers one question, which is what you may rely on the container for. It is not a revision. A revision tells you how current the container is. A container carries both at once, in separate fields. Confuse them, and somebody builds from a drawing that was only ever shared for coordination.
The fourth term is level of information need, the framework that sets how far and how finely information is to be specified. The note beneath that definition is the part people skip. One stated reason for defining it at all is to stop too much information arriving. Not too little. Too much. That is the problem Merriden's delivery team created when it sent everything it had.
The fifth is a pair, capability and capacity. Capability is the ability to perform, meaning skill, knowledge and expertise. Capacity is the resource to perform, meaning people, time and procedures. A team can be entirely capable and have no capacity, and that is one of the commonest failures on any project.
With the words in place, Part 1 sets out four principles at clause six point one, and every later clause develops one of them. The first principle is that information exists to support decisions, across the whole life of the asset, from building something new, to altering it, to finally taking it out of service. The test that follows is simple. If no decision depends on a piece of information, ask why it is being requested. The second principle is about sequence. The client states what it needs through successive sets of requirements, and the delivery teams plan against them and hand information over in steps rather than all at once. Both sides sharpen as the work develops. The third principle is routing. A requirement goes to whichever party is best placed to answer it, or to wherever the information can be produced most easily, rather than to every organisation on the job. The fourth puts exchange through a common data environment, prefers open formats where they will do the job, and asks for written operating procedures, so that every organisation handles information the same way. The clause then adds that all four are applied in proportion to the context. Proportionate is a requirement, not an excuse.
Two more ideas complete the frame. The first is maturity. Part 1 describes stages of maturity for analogue and digital information management, with a layer for business that the earlier UK maturity model never included. Its stages are stages of practice rather than products, and the standard presents it as a perspective, not a scoreboard. The series applies mainly at Stage 2, where manual and automated working sit side by side to build a federated information model, with parts of it reaching back into Stage 1 and forward into Stage 3. Part 1 gives Stage 2 a name, BIM according to the ISO 19650 series. That is the phrase to use in an appointment, because it names a scope of practice rather than a tool, and a claim built on a tool goes out of date when the tool does.
The second idea is perspective. Clause four point three asks the information management process to recognise the different views that people hold of the same asset, and it recommends four. The asset owner asks whether the asset should exist at all and what it has to return. The asset user asks what the people who occupy or operate it need from it. Project delivery or asset management plans, resources and controls the work. And society's perspective carries planning, building control and regulatory duties. Four is a floor, not a ceiling, and a hospital trust might well add a clinical perspective.
Merriden shows why this matters. The council has to decide whether to replace or refurbish the air handling plant in the civic building. One decision. As owner, it needs whole life cost for each option and the effect on its carbon position. As user, it needs to know the disruption to the registrar's office and whether the public hall keeps its thermal performance. From the delivery seat, it needs the plant access routes, the maintenance history and the existing survey. From society's seat, it needs the planning constraint on the roof enclosure and the noise limit at the residential boundary. Ask only the first, and the decision fails in operation. Clause four point three names three points where perspectives have to be built in, which are when requirements are written, when the delivery team plans what it will produce, and when information is handed over. The first of those is where the damage is done, because a delivery team cannot supply information that nobody asked for.
So the first step resolves like this. Merriden's sentence named no decision, no perspective and no maturity position. Working harder downstream cannot fix that. Only a written requirement, from the party that needs the information, can.
The second step is history, and it matters because many of the documents still cited on live projects have gone. Before ISO 19650, UK practice ran on what is called the 1192 suite, British Standard 1192 and the parts of Publicly Available Specification 1192, known as PAS 1192. The suite was not replaced on one day. It went part by part over six years, and each withdrawal is recorded in the National Foreword of the standard that took its place.
Hold it in mind as a timeline. In January 2019, ISO 19650 Parts 1 and 2 took over from BS 1192 of 2007 and PAS 1192-2 of 2013, the pair that had carried container naming, the common data environment and the suitability codes. In the summer of 2020, Part 5 replaced PAS 1192-5 on security, and Part 3 replaced PAS 1192-3 on asset operation. So for about eighteen months, a project working to the new delivery standard still needed two old documents for security and for operation. In 2024, ISO 7817-1 superseded BS EN 17412-1 of 2020, the earlier standard on level of information need. And in January 2025, Part 6 superseded PAS 1192-6 on health and safety information. Six years, from first withdrawal to last.
Two details are worth keeping. The forewords use two formulas. Some say the new document supersedes the old one. Others say its technical content is intended as a replacement, and state the withdrawal separately. Both end in withdrawal, but if you are ever asked to evidence one in an audit, quote the foreword in front of you rather than the one you assume. The other detail is BS 1192-4, the standard for COBie, short for construction operations building information exchange. It ran on its own clock. It was withdrawn in September 2022, the same month the British edition of Part 4 was published, and the published sources disagree about what replaced it. The BSI catalogue, BSI being the British Standards Institution, names no successor. The NBS index and the foreword printed inside Part 4 name Part 4. And Part 4 sets criteria for any exchange, not for COBie in particular.
Merriden may still hold contracts that name withdrawn documents, and the transition guidance, PD 19650-0 of 2019, which BSI has since withdrawn and which I cite here as history, was clear about them. A project that contractually references BS 1192 or PAS 1192-2 continues on that basis until completion. Withdrawal removes a document from the catalogue. It does not reach into a signed contract. Where there is no such obligation, the UK guidance advises moving across at the start of a stage rather than in the middle of one, and the earlier in the life cycle the better.
The words changed too, and some of the changes carry more than a new label. Employer and supplier became appointing party, lead appointed party and appointed party, so that the same terms can describe a refurbishment, a facilities management call-off and an in-house team. The client's plain language questions split into two levels, project information requirements and exchange information requirements, which is what lets requirements pass down a supply chain without everyone receiving all of them. Volumes became a federation strategy and an information container breakdown structure, which moved the emphasis from the shape of a division to the reason for it. Level of model definition became level of information need. One responsibility matrix became two. Suitability became status, and the areas of the common data environment became states, and those last two are close to straight renamings. So of seven changes, five changed the idea underneath. That is why a find and replace on old templates does not make anyone conformant. Two documents were new altogether, the delivery team mobilisation plan and the information delivery risk assessment, each answering a failure the earlier suite never caught.
Then the question everyone is asked in public. Are we Level 2? The documents that defined Level 2 are withdrawn, and PD 19650-0 said the ISO standards do not define it either. The old UK maturity wedge and the stages in Part 1 agree on the direction of travel, with information and collaboration both maturing together. And the scope of BIM according to the ISO 19650 series takes in everything the UK labelled Level 2, with parts of Levels 1 and 3. They are still not the same claim. Much of the practice survived, because the principles behind Level 2 were rehoused in clause nine of Part 1, on container-based collaborative working. So the honest answer takes thirty seconds. The two overlap substantially. The Level 2 documents are withdrawn. The claim available now is conformity with named parts of the series.
Merriden holds a register from a library extension delivered in 2016 to Level 2, with an employer's information requirements document, a BIM execution plan and a volume strategy. That record stays true, because withdrawal does not rewrite what was done. What cannot be carried into the new appointment is the Level 2 claim, the suitability code schedule, the volume strategy and the level of model definition schedule. And the question the council asks has changed. Not whether the old project was Level 2, but which parts of the series the new appointment will name. That resolves the second step. A level cannot be audited, because no current document defines what to audit against. Conformity with named parts of the series can.
The third step is the centre of Part 1, the hierarchy of information requirements. Almost every information failure traces back to a requirement sitting at the wrong level. Clause five point one sets the starting point. The appointing party works out what information it needs about its assets or its projects to support its objectives, and those needs can come from inside the organisation or from interested parties outside it. During delivery, requirements are pinned to project stages. During operation, they are pinned to trigger events the organisation can foresee, such as planned maintenance, an equipment inspection or a change of asset management provider.
There are four levels, and each answers one question. Organisational information requirements, at clause five point two, ask what the organisation needs to know to run itself well. They arise wherever the organisation sets its direction or answers to someone else, in strategy, in portfolio planning and in regulation, and some of them, such as producing annual accounts, have nothing to do with assets at all. Asset information requirements, at clause five point three, ask what the organisation needs to know about an asset in order to operate it, maintain it and make decisions about it. They cover what information is needed and how it is to be produced and controlled. They are prepared for each trigger event during operation, and they are written so they can go into appointments. Project information requirements, at clause five point four, ask what the organisation needs to know about this particular project, and Part 1 says they come from both the project management process and the asset management process. Both. A project requirement written only from the project side delivers a building the operator cannot use. Exchange information requirements, at clause five point five, ask what one party requires from another under a particular appointment, to what level of information need, and by when. This is the only level that reaches a contract, and so it is the only level a delivery team can be held to. Everything above it is the client's own reasoning.
Notice that the questions narrow as you go down. Follow one Merriden thread through all four. At the top, the council has a board objective to cut operational carbon across the estate by forty per cent against a 2024 baseline. For the Civic Campus, it becomes a need for energy consumption by system, plant efficiency ratings and replacement dates. For the refurbishment project, it becomes the predicted energy performance of each design option and the as-installed data at handover. In the design consultant's appointment, it becomes an energy performance schedule for each option at Stage 3, to a stated level of information need, in an agreed format, by a stated date. And a building services task team produces it. The objective at the top mentions no asset and no project. The deliverable at the bottom mentions no carbon target. Neither end can see the other, which is exactly why the two middle levels exist.
Two misfilings cause most of the damage. The first is an organisational question dropped into an exchange requirement without being translated. Reduce our estate carbon by forty per cent is not something a design consultant can deliver. The energy performance schedule that informs that decision is. The second misfiling is asset requirements that arrive only at handover, when the design is fixed and they can no longer shape it. Part 1 places asset requirements above the project for exactly that reason. On a live project you usually discover a misfiling from the bottom, at handover, and the work is to trace it upward until you find the level where nobody asked the question.
Now the mechanism, and it sits in Part 2, at clause five point two point one. It is the most usable clause in the delivery standard, because it tells the appointing party what to establish in an exchange information requirement, in five parts. The first part is the requirements themselves, derived from the organisational, asset and project requirements above them. If the client cannot say which higher requirement an item serves, the item is not ready to issue. The second is the level of information need for each requirement, not a single setting for the whole appointment. The third is the acceptance criteria for each requirement, tied to the project's information standard and its information production methods and procedures. This is the part most often missing, and without it acceptance becomes a matter of opinion, formed at the worst moment, when somebody is waiting to be paid. The fourth is the supporting information a tenderer needs to understand each requirement, such as asset information the client already holds and, most useful of all, a worked example of a deliverable of the same kind. The fifth is the dates, set against the information delivery milestones and the client's key decision points, after the client has allowed for its own review and assurance. So the deadline for information is the decision date, minus the client's review time, minus its internal assurance. Skip that arithmetic and you set deadlines that guarantee late decisions.
Then the requirement travels, and two things happen at once. It is sub-divided and routed, so that only the relevant part reaches each party, which means a task team never receives exactly what the client issued. And a lead appointed party may add requirements of its own as it passes them on. What it may not do is quietly drop one it was given. What keeps this safe is clause five point three of Part 1. Across all the appointments under an asset management strategy, the requirements have to form one coherent set that covers every asset-related question the client has. No single appointment has to be complete. The set does, and only the appointing party can see the whole of it.
At Merriden there are four lead appointed parties, and four different exchange requirements. The project manager's asks for programme and decision point dates and confirmation that information delivery risks are being managed, with very little geometry in it. The cost consultant's asks for quantities and cost data at each decision point, at a level suited to estimating. The design consultant's asks for predicted energy performance by option, spatial coordination information and the room data the registrar needs. The principal contractor's asks for as-installed plant data, commissioning records and the maintenance access information the estates team will need. None of them is complete on its own. Together they cover the ground.
One term from those five parts needs a closer look, level of information need. The current standard is ISO 7817-1 of 2024, and BS EN 17412-1 is withdrawn. Any material that still cites the withdrawn number has not been maintained since 2024, and you should ask what else in it has not. The framework describes information in three kinds, geometrical information, alphanumerical information and documentation. Three, not one. When someone uses the term to mean how detailed the model is, that is the commonest error in the subject. The method rests on four prerequisites, which are purpose, information delivery milestone, actor and object, and they answer why, when, who and what. The specification is informed by those prerequisites but does not contain them, so that the same specification can be reused at another milestone. Take Merriden's air handling unit at a single milestone. For a whole life cost purpose, alphanumerical information carries the weight, meaning capital cost, expected life, service intervals and energy use, and the geometry can be minimal. For spatial coordination, the geometry carries it, meaning the overall envelope, the connection points and the space needed for maintenance access. For handover, documentation carries it, meaning the commissioning records, the operation and maintenance manual and the warranty terms. One object, one milestone, three purposes and three different specifications. The older single numbers for level of detail could not express that difference, which is why an inherited legacy schedule has to be mapped rather than translated. The episode on level of information need takes the method much further.
So the third step resolves. A good requirement is placed at its level, written in five parts and routed to the party best placed to answer it. And it is the set of requirements, not any single appointment, that has to be complete.
The fourth step follows the requirements into what they produce, which is the information models, their containers and the states those containers pass through. Start with the two models. Both are structured stores made of containers, both hold structured and unstructured information, and both grow as delivery and asset management proceed. The asset information model, at clause five point seven, serves decisions about operating, maintaining and managing the asset, and the appointing party holds it between projects. Part 1's examples show how little of it is geometry. An equipment register, the running cost of maintenance, installation and service dates, and who owns the property. The project information model, at clause five point six, supports delivery. It carries the design and construction information, from geometry to programme and cost, and it is kept afterwards as an archive of the project and for audit.
The common misconception is that the asset model is simply the project model after handover. It is not. Merriden's asset information model covers forty-two buildings whether or not any project is running, and most of it has nothing to do with the Civic Campus. The asset model is also an input. At the start of delivery, relevant information moves from it into the project model, and at the end, relevant information moves back. If the council supplies nothing at the start, a task team surveys the building again, at the council's expense, to rediscover what the council already knew. A neglected asset model costs money on every project, usually without ever appearing as a line item.
The word relevant matters in both directions, and the test for it changes. At the start, the test is whether the information would change what the delivery team does. At the end, it is whether it would change what the operator does. Apply the first test at the end and you hand over a complete design record and no operating record. Clause twelve point one sets out what happens when a project ends. Containers needed for asset management transfer into the asset model. The rest, including the archive, are kept read-only, for any dispute and for lessons learned. And how long they are kept is itself a requirement, set in the exchange information requirements at the start of the job. At Merriden, what the estates team needs to run the building and plan its next change moves across, from the as-installed plant data and commissioning records to an updated spatial record of the refurbished areas. The superseded design options and the coordination comments stay behind, read-only. Almost everything that moves comes from the principal contractor, because only the party that installed and commissioned the plant can supply it. A client whose asset requirements reach only its design consultant will not get its operating record, however good that consultant is. That is routing failing.
Now the containers. Part 1 says that one model does not have to sit in one place, and that container-based working lets the common data environment workflow run across several systems or platforms. A distributed arrangement is anticipated by the standard. Anyone who says the series requires a single platform has read something into it. Clause ten point four pairs two connected ideas. The information container breakdown structure sets out how information is divided into containers. The federation strategy sets out how the parts recombine into one federated model. The reason you divide determines how you recombine. Annex A of Part 1 gives three reasons for dividing. Concurrency, so that separate task teams can work at the same time without clashing. Security, so that sensitive content can be restricted without restricting everything. And transmission, so that containers stay small enough to send over a poor connection on site. Where security and concurrency pull apart, let security set the boundary, because a concurrency problem can be scheduled around and a security requirement usually cannot.
At Merriden, the registrar's office stays open throughout construction. So the sensible division follows that constraint, with separate containers for the live registrar area, the refurbished civic areas and the new extension, each divided again by discipline. Federation then has a clear job, which is bringing the three together at each stage so that clashes at the junction between the extension and the existing building surface early, rather than on site.
Every container also needs a name and three pieces of metadata. The UK National Annex to Part 2 sets the structure of the unique identifier, and the UK guidance works an example, a structural specification identified as N E W P, A B C, X X, Z Z, S P, S, zero zero zero one. Read it back to front, and it is the first specification from the structural discipline, for all levels, not tied to any one system, from the originator A B C, on project N E W P. You know what is in it without opening it. But the codes mean nothing without a register that records what each one stands for, and that register is the document most often missing from an otherwise well-run environment. The three pieces of metadata each do one job. Status says what the container may be relied on for, and clause twelve point one puts the risk on anyone who relies on a container for a use its status does not permit. Revision says how current it is. Classification says what it is about, and in the UK the annex requires Uniclass 2015, using its project management table where possible. Metadata is set first by the author and then amended through approval and authorisation, which makes it evidence in any later dispute about what somebody was entitled to rely on.
Last in this step come the states of the common data environment. Clause twelve point one places the current revision of every container in one of three states, which are work in progress, shared and published. Alongside them sits the archive, a journal of every container transaction and an audit trail of how each container developed. The archive records what happened, and it is written as things happen, not swept up at the end like a folder. In work in progress, a task team develops its own material, and no other task team can see it. In shared, containers are visible to the appropriate parties, including other delivery teams, subject to security, but they cannot be edited. In published, the information may be relied on for the next stage. Two transitions carry different owners. The check, review and approve transition into shared is made by the originating task team, against the information delivery plan and the agreed standards and methods. The review and authorise transition into published compares all the containers at an exchange against the information requirements, for coordination, completeness and accuracy. A container that fails goes back to work in progress, to its author, and not back to shared. If you find an error in a colleague's shared container, send it back rather than fixing it, because editing it moves responsibility for its content to you without anyone having agreed to that.
The UK status codes come from the National Annex to Part 2, as revised in 2021. S zero is work in progress. S one and S two sit in the shared state and are non-contractual, the first meaning suitable for coordination within a delivery team and the second suitable for information to other task teams. S three is for review and comment within a delivery team. S four sends a container to the lead appointed party to review and authorise, and S five sends it to the appointing party to review and accept, which matches the two steps of authorisation and acceptance. The A codes are published and contractual, and the B codes are marked deprecated. There is no code for suitable for construction, and none for as-built, so those come from the published state and the project's own information standard. Shared containers carry preliminary revisions starting with P, and published ones carry contractual revisions starting with C. Templates still in circulation carry codes such as S six and S seven, which predate the revised annex and are not defined in it. The episode on the common data environment takes these states and codes much further.
The fourth step resolves on one idea. The requirements produce models made of named containers, and the states, codes and metadata are how anyone knows what a container may be trusted for.
The fifth step is about who answers for all of this. Part 1 uses three party terms. The appointing party receives information, works or services, and in practice it is the client, the asset owner or the operator. A lead appointed party is any organisation holding a direct appointment from the appointing party. An appointed party provides information inside a delivery team, and may hold appointments of its own below it. Which term applies depends on position in the appointment hierarchy, not on the kind of work. A specialist consultant appointed directly by the client is a lead appointed party, however small its scope. The terms are neutral on purpose, so that they imply nothing about liability or seniority.
Three team terms group those organisations for the purpose of managing information. The project team is the appointing party together with all its delivery teams. A delivery team is a lead appointed party together with its appointed parties, and to the client each delivery team is self-contained, reached only through its lead. A task team does one particular task inside a delivery team. Part 2 maps the interfaces between them, with requirements and exchanges running up and down, and coordination running sideways between task teams. And it states plainly that its map does not show who holds a contract with whom. Information flow and contract structure usually look alike. They are not the same, and treating one as evidence of the other is how people assert duties that do not exist.
Two cases trip people up. A project usually has several lead appointed parties, not the two tier one suppliers the earlier suite suggested, because every organisation appointed directly by the client qualifies. And one organisation can hold two positions at once. A principal contractor leads its delivery team and authorises what that team submits. It also produces information through its own people, as an appointed party. So the firm authorises its own work. That is normal, and it needs separating deliberately, by different people, rather than happening by accident. Drawn out, Merriden has one appointing party and four lead appointed parties, which are the project manager, the cost consultant, the design consultant and the principal contractor. That makes four delivery teams, one of which holds only the cost consultant, and it is still a delivery team. There are seven task teams, architecture, structure and building services under the design consultant, and groundworks, envelope, mechanical and electrical under the contractor. Twelve organisations make up the project team, and their size makes no difference to their position.
Then the question asked on every project. Who is the information manager? The current series has no such role. PAS 1192-2 pinned the work to named posts, such as a project information manager and a task information manager. The current series replaces them with a function, described in the UK guidance as the collective responsibility and authority for the information management process, assigned to people already in post. It is assigned at two levels. The appointing party assigns it across the project, and each lead appointed party assigns it within its delivery team. The guidance is firm about timing. The function has to be assigned before any lead appointed party is engaged, and that includes the project manager. Wait for the project manager to sort it out, and you are already late.
Clause seven of Part 1 names three kinds of function. Asset information management leads in validating information supplied by appointed parties and in authorising it into the asset model. It starts at the earliest stage of asset management and is involved in every stage of delivery, rather than consulted at handover. Because an asset outlives everyone working on it, the clause also asks for succession planning, which is a requirement about the next twenty years sitting in a clause most people read as being about this month. Project information management leads in establishing the project's information standard, its production methods and procedures, and its common data environment. Task information management sits with each task team, covering its own information and its coordination with other tasks. The complexity of the asset scales the first, and the extent of the project information scales the second, so a small job gets a small function. The guidance names the risk honestly, that someone holding the function alongside a day job lets it drop under pressure. At Merriden, the asset function sits with the estates team. The project function sits either with the council's own staff or with an outside party under an agreed scope of services. And a task function sits inside each of the seven task teams.
Clause eight frames capacity against the deadline, as the ability to complete an activity in the time required, and asks the appointing party to review each prospective delivery team's capability and capacity before appointment. The team may carry out that review itself, so a capability statement in a tender is often a self-assessment, which is a good reason for the client to set the scope of the review explicitly.
The record of who does what is the responsibility matrix, at clause ten point three. One axis carries information management functions. The other carries information management tasks or information deliverables. Functions, then, not job titles and not organisations. A matrix headed with somebody's job title stops being accurate the day that person moves on. Part 2 turns the clause into two documents. The high-level responsibility matrix comes with the tender and allocates responsibility for each element of the information model, with its key deliverables. The detailed responsibility matrix follows appointment and says what information each task team produces, when it is exchanged and with whom. The familiar convention of responsible, accountable, consulted and informed is useful and widely used, but the UK guidance notes that it is not a requirement of ISO 19650. It is an expansion, and you need to know which is which when you are asked to evidence conformity. The episode on roles and the responsibility matrix takes this further.
So the fifth step resolves. Accountability in this series attaches to positions and functions, assigned early and recorded on the right axes, and not to a person with a title.
The sixth step stands back to the whole series, because the last of the four skills is knowing which document answers a question and whether it is still current. Six parts are published. Parts 1 and 2 arrived together in 2018. Part 1 gives the concepts and principles. Part 2 gives the delivery phase as eight activities, from assessment and need to project close-out. Part 3, in 2020, covers the operational phase. It has the same shape of process, but trigger events drive it rather than a programme, whether planned, like a refurbishment, or unplanned, like a flood in the night. Part 5, also from 2020, is the security-minded approach, and it opens with a triage that decides whether the rest of it applies. Part 4, from 2022, covers information exchange in either phase. And Part 6, from January 2025, covers health and safety information, and its National Foreword states that it neither defines nor changes any statutory duty.
Once you know their jobs, routing a question takes seconds. Who compiles the master information delivery plan is Part 2. A pump failing overnight is Part 3, as an unplanned trigger event. Whether a drainage layout should be visible across the supply chain is Part 5, a triage question before it is a permissions question. Capturing a residual construction risk so that the operator sees it is Part 6. And how much geometry is needed at the next milestone is not in the series at all. Several things people look for inside ISO 19650 sit in standards of their own. Level of information need is ISO 7817-1. The classification framework is ISO 12006-2, and Uniclass is the UK system built on it. The information delivery manual is ISO 29481-1. And the schema most people mean when they say open format, Industry Foundation Classes, is ISO 16739-1. The series is bounded, not incomplete.
Part 4 earns a few sentences here, because it settles what has to be true before a receiver can rely on an exchange. It names two decisions. Decision A approves a container for sharing, inside the originating task team, by someone other than its author. Decision B authorises and accepts it for publication, with the lead appointed party authorising and the appointing party accepting. Part 4 then sets six mandatory criteria for reviewing an exchange, which are the use of the common data environment, conformance, continuity, communication, consistency and completeness, and it adds a seventh that is informative only. The familiar label, the Five Cs, keeps the five that begin with C and drops the first. An exchange emailed straight between two task teams can pass all five and still fail, because it bypassed the environment and left no status, no revision history and no audit trail. The episode on information exchange covers Part 4 in depth.
Then the UK layer, which exists only in the British editions. A National Foreword sits at the front. It states what the document supersedes and what is withdrawn, and it changes no requirement. A National Annex sits at the back and clarifies how the standard is used in the UK. In this series the annexes are informative, but they hold all the UK operational detail, so a project that does not reference them simply does not have it. Part 1 carries a foreword and no annex. Part 2 carries both, and its annex, revised by corrigendum in February 2021, supplies the status codes, the revision codes, the container naming and the requirement for Uniclass. Part 4's annex clarifies its review criteria for UK use and is largely about COBie. If your copy has no National Annex, you are reading the international text, and you do not have the UK codes.
Even the annexes carry dates. The Part 4 annex, published in 2022, still uses the 2013 stage names from the Plan of Work of the Royal Institute of British Architects, which the 2020 edition had already renamed. And the Part 2 annex, revised in 2021, still points COBie structure to BS 1192-4, which has since been withdrawn. Drafting a standard takes years. Every document in your reference set has a currency date, including the documents about currency.
At Merriden that point becomes a short check, and the scene is my own illustration rather than part of the case. Before the four appointments go out, the council's project information function opens the front matter of every document the requirements cite. Parts 1 and 2 are named in their British editions, so the Part 2 annex is in the set. Any level of information need schedule citing BS EN 17412-1 moves to ISO 7817-1. And COBie stays only if the council wants it, because the series requires a project to agree a data exchange standard, not to choose that one.
The guidance has moved as well. The UK BIM Framework, launched in October 2019, was renamed the IMI Framework in May 2025, after the Information Management Initiative that began in November 2024. nima, formerly the UK BIM Alliance, maintains it with the support of BSI, and in June 2026 it added guidance on Part 6. Guidance written under the old name is still useful, as long as it is cited for what it is. And there is a newer map of the field, PAS 1958, which BSI published in March 2026 as a guide to how the data and information standards for the built environment relate to one another. It explains and recommends. It sets no requirements.
Finally, one look forward, and it is labelled as such. Draft revisions of Parts 1 and 2 were open for public comment from March to May 2026, and a draft revision of Part 3 followed, open for comment until July 2026. The drafts propose a single information management process across delivery and operation, a shift in terminology from building information modelling towards information management, and a narrower role for Part 3 as implementation guidance. None of them is in force, and no publication date has been announced.
So the editions to cite are the ones in force today, Parts 1 and 2 of 2018, Parts 3 and 5 of 2020, Part 4 of 2022 and Part 6 of 2025. No draft content belongs in an appointment or a tender, Merriden's included, however confident anyone sounds about the final text. What is worth planning for is a period in which both editions are cited across a portfolio at the same time, as happened when the 1192 suite was retired.
That resolves the sixth step. Knowing the series means knowing what each part does, where the UK layer adds to it, and how to check that what you cite is current.
Let me draw this together. The question was what Merriden District Council should have written instead of asking for a BIM project. The answer is a requirement, written by the party that needs the information. It names the decision the information supports and the perspectives that decision has to serve. It sits at the right level of the hierarchy and reaches each appointment as an exchange requirement in five parts, acceptance criteria and dates included. It is routed to the party best placed to answer it, inside an information management function that was assigned before anyone was appointed. And it cites current documents, Parts 1 and 2 of 2018 with the 2021 UK National Annex, ISO 7817-1 of 2024 and the later parts as they apply, with the 1192 suite treated as history.
Three things are worth taking into your own work. When you read any requirement, ask which decision it serves and which level it belongs at, and if you cannot answer, it is not ready to issue. When you set up a project, assign the information management function before you appoint anyone, and record it on a matrix that names functions, not job titles. And before you cite any standard, open its front matter and check the edition, the foreword and whether you hold the annex, because currency is a habit rather than a fact you learn once.
For reading, start with ISO 19650-1, especially clauses five, six and twelve, then clause five point two point one of ISO 19650-2 with its UK National Annex, and PD 19650-0, withdrawn guidance now read as history, for the transition from the 1192 suite. The UK guidance on concepts, Guidance Part 1, is still the most readable companion. The next episode, The Delivery Phase in ISO 19650 Part 2, is about the eight activities of the delivery phase, from assessment and need to project close-out, and who answers for each one.
Reimagining AEC is where I, Dr Sepehr Abrishami, keep testing the standards against real decisions, and this is the test I would leave with you. Find one requirement on a project you know, in practice or in research, that nobody can trace to a decision, and follow it upward until you reach the level where the question was never asked.