Send us your thoughts! Europe's data centre boom is facing growing resistance from local communities who have raised concerns over soaring electricity demand, while others worry about the pressure on power grids and the environmental costs of powering the AI revolution. This week on Plugged In, we explore whether Europe's rush to build data centres risks pushing up energy costs and crowding out other industries - or whether these facilities could actually become part of the energy transition. We examine who should pay for new grid infrastructure, whether data centres should face stricter connection requirements, and how renewable energy, flexibility and smarter planning could help ease pressure on Europe's power systems. We also ask whether Europe's drive for digital sovereignty is accelerating development at the expense of local communities - and what needs to change to ensure the benefits of AI are shared more widely. Host: Snjólfur Richard Sverrisson - Editor-in-Chief, Montel News Guests: Liam Newcombe - GreenScale Marion Dumas - Associate Professor of Climate Policy, London School of Economics (LSE) Elias Huuhtanen - Finland Correspondent, Montel News Editor: Alexandra Carlon Producer: Alexandra Carlon #PluggedIn #MontelNews #DataCentres #EnergyTransition #ArtificialIntelligence #EuropeanEnergy #PowerGrids #EnergyMarkets #GridCongestion #DigitalInfrastructure #RenewableEnergy #EnergyPolicy
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsI think a lot of people are very skeptical that AI is going to bring benefits to society, is going to bring benefits to their economy.
Liam Newcombe – GreenScaleIf we don't build them in Europe, we will simply end up buying the services from other states.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsEurope wants to be at the forefront of the AI revolution, but the data centers needed to power it are facing growing resistance. There are concerns over power prices, pressure on grids, and the role of local communities. Will data centres become part of the energy transition, or will they put increasing strain on an already stretched power system? Well, I'm delighted to be joined by Elias Huuhtanen, who's our Finland correspondent based in Helsinki.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsA warm welcome back on the pod, Elias.
Elias Huuhtanen – Finland Correspondent, Montel NewsThank you. I'm happy to be here.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsI'd like to first of all ask you, Elias, you know, about data centers in Finland. They're quite controversial suddenly, or been a lot in the news anyway.
Elias Huuhtanen – Finland Correspondent, Montel NewsIt's a good case to kind of to exemplify the whole the wider trend that is going on in the data center industry at the moment. You had Google announce one of its biggest investments into Europe this autumn. And initially it was very very it was received very well. Like you had when when they had the press conference, they had the prime minister there, they had heads of municipalities there, kind of kind of like proudly presenting that yeah, this is this and this many billions of euros are coming into Finland, and we're happy to be able to attract these kinds of data center investments.
Elias Huuhtanen – Finland Correspondent, Montel NewsIt was seen as this kind of a you know, Finnish economy has been struggling for years now, high unemployment, low growth, and then data centers were almost seen as this like light at the end of the tunnel. Like finally, we get some investments coming in and some jobs and stimulus for the economy. And then investments are coming with a tremendous pace at the moment. And Google, they got a bit ahead of themselves, and they like they they want to have these data centers up and running as fast as possible, so they clear-cut massive forest areas ahead of getting the necessary environmental permits.
Elias Huuhtanen – Finland Correspondent, Montel NewsAnd that's really it became a huge scandal. You had the energy minister last week say that it was a huge disappointment, you know, it really put a dent into the reputation of the industry. It said that there's clear law that has been violated, and disregard for this legislation, this clear disregard cannot be tolerated. So it's a real kind of a shift. You know, it used it was this positive thing, and now it's a very you have the ministers even taking a harsh stance on this topic.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsSo Elias, we've seen a wave of protests against data centers across Europe, certainly in recent weeks and months. Where has the opposition been strongest and what do the protesters want?
Elias Huuhtanen – Finland Correspondent, Montel NewsWell, I think an obvious obvious answer is power prices. You know, that's something that really catches the attention of the wider public as well. You have massive amounts of data center investments coming in. We're talking about gigawatts and gigawatts. In Finland, 40% hike in power demand by the end of the decade. And yeah, that's definitely is of course gonna have an impact on power prices and most likely gonna hike them upwards. And another challenge, a big challenge, is the fact that any production that can match the pace of the data center investments is gonna be most likely wind and solar.
Elias Huuhtanen – Finland Correspondent, Montel NewsLike you're not gonna build a new nuclear reactor in in a couple of years, it's gonna be decades. So we're gonna get more renewables. And then all the problems that we had with renewables so far, you know, the intermittency and volatility, they're most likely gonna get or it's gonna be a big challenge in the coming years.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsPeople feel also that the social benefits aren't the same as maybe in some traditional industry. Would that be correct as well?
Elias Huuhtanen – Finland Correspondent, Montel NewsYeah, definitely. You know, we only have so many grid connection points, so a finite amount of grid, that means a finite amount of investments that can come and use that grid. So when you have these data centers that are just like coming, like a tsunami coming in, it might mean that there will be some kind of other investments that maybe bring more jobs or more obvious benefits for the side than are now put at the back of the queue because of the backlog. For example, green steel meals or green hydrogen projects, that kind of stuff.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsElias, thank you very much indeed for setting the scene for us this week.
Elias Huuhtanen – Finland Correspondent, Montel NewsThank you.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsWell, I'm very pleased to be joined by Liam Newcombe of Greenscale. great to have you back on the pod, Liam.
Liam Newcombe – GreenScaleAnd thank you. Great to be back.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsAnd Marion Dumas of London School of Economics. Welcome to the pod, Marion.
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsThank you so much for the invitation.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsI'd like to start with you, Marion, and talk a little bit about the benefits of data centers. They they bring significant investment, but they require enormous amounts of electricity and grid infrastructure. So, how do we determine whether benefits outweigh the costs and who ultimately captures those benefits, Marion?
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsThat's a that's the important question, right? We can think of costs and benefits, you know, in a very sort of narrow localized way, or at the scale of the whole economy. So let's take it in by piece. At the scale of the community, I think the big these are where the biggest issues are. It's not completely clear where the data center is located, whether the community benefits, because the computing is going to be used by people possibly far away.
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsAnd so really a big issue around the backlash with around data centers is whether these agreements are being rushed through without much community consultation to assure that there are benefits that make sense to local communities, or whether they're just being rushed through so that we can reap the benefits at the scale of the economy as fast as we can, but sometimes without having thought through very carefully what those society level benefits we aim to obtain.
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsSo from an energy point of view, it's very early days. People are very concerned about the consumption of energy. But the computing can be used to also save energy. And so there's a delicate trade-off here. There's a really interesting new study that came out regarding Veolia plants, you know, wastewater treatment plants, where they use advanced AI models to optimize in real time, like make a digital twin and optimize the plants. And they save 10% of energy and use only 1% of that is the energy from the compute.
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsSo the cost benefit there in that sort of very localized sense of the plant, the wastewater plants, we pass the cost benefit. Whether we pass it at the level of the whole society and the whole economy really depends on so many things. And I'm happy to dive into how we can think about that more broadly in terms of both the resources and the value added to human flourishing.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsYeah. We'll come back to that, Marion, I think. But Liam, what's your view here? How important is it to involve local communities in the construction of and the operation of data centers?
Liam Newcombe – GreenScaleIt was important to start with, it's becoming unavoidable now. So our our head of sustainability, Anna, would tell me sustainability is local. And it's absolutely the case. Each location has different constraints, issues that could be addressed, and opportunities. So you really can't turn up to, for example, West London or Stockholm with the same, we're going to build a really great sustainable data centre story, because the opportunities are different, and the things that the local people are likely to value from you are very different.
Liam Newcombe – GreenScaleSo I think there's a real risk at the moment, and this is being borne out with some of the sites in the United States, that simply putting money into a community benefit fund and saying, hey, we're going to pay this much per person per year actually comes off as bribery rather than any actual well-intentioned and honest attempt to answer the question for the local residents of why would I want a data centre in my town? So we need a very clear answer to that.
Liam Newcombe – GreenScaleAnd I think the first part of that answer is that we need to be, and this is supported by a lot of people with more skill in social things than I, we need to engage very early with the local people. So turning up and hiding aspects of your planning application under NDAs and things like that simply sets a scene where the local people are going to probably quite rightly not believe what they're being told because they believe the the people planning to do it are hiding from them. So I think starting off with the engagement with the community, openly asking what issues do you care about?
Liam Newcombe – GreenScaleWhich things could we impact and deliver? Do you want some heating for school sports halls or do you want a community benefit fund for your council to spend? What might actually move the needle for you? And importantly, what might allow those people to develop some trust that the developer is isn't simply there to extract from their area and profit from it?
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsAbsolutely. I mean, maybe we'll come back to some of these areas, but if I could just have a have a question for you, Liam, before we go back to Marion. And this is about the topic of additionalities. So could data centers help finance new renewable generation and grid infrastructure? And how do we ensure they're generally adding capacity to the system rather than simply competing for what's already there?
Liam Newcombe – GreenScaleAbsolutely, and it's a really important question because people are becoming more aware of, for example, annually matched guarantee of origin certificates and other mechanisms that are used to say our power's 100% green, when in fact it isn't. You you might have bought the same number of megawatt hours of green power over the year as you've consumed, but for example, if you're in the UK for 20 to 30% of the year, you'll have consumed a reasonable amount of gas power due to the mix on the grid.
Liam Newcombe – GreenScaleAnd there's a growing awareness that as we increase the total demand on the grid, and there's a lot of legislative instruments, particularly in the Iberian Peninsula, looking at this at the moment, what we shouldn't do is drive up the amount of fossil generation on the grid. So additionality is two things. It's funding or causing to be developed new renewable energy sources, but also importantly, there's a locality element there as well. If you're not going to stress the grid, and also if you're going to support local employment, the more of those assets that you can bring into visibly in the economic locality, but also the grid locality.
Liam Newcombe – GreenScaleAnd realistically, I think we see quite a few countries moving towards hourly matching rather than annual matching to test whether you're over what proportion of the year your additionality is actually having effect.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsWe had a very interesting podcast episode on precisely this issue a couple of weeks ago, Liam. So but Marion, what's your view here? Because there's often, you know, there's talk of a lot of these data centers being fired by fossil fuels. And that in and there's a perception. Is that a wrong perception?
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsNo, I don't think it's wrong. I think we've seen a lot of data centers being rushed through, overstepping consultation processes that are normal for other types of infrastructure build-out. It takes years to build a new transmission line. If we think of the local impacts of data centers compared to a transmission line, they're at least as important, as large. And yet communities wake up and these things have already been approved in some cases, and not in all jurisdictions.
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsIn the US, we know that a lot of data centers are coming with, you know, gas turbines. So it's not at all a misperception. This is a really big problem. We're building up fossil fuel assets that will create lock-in into more fossil fuels in the medium term. So it's very urgent that communities rise to this situation and make their voices heard. But I think there's also an opportunity for international cooperation or coordination on this, you know, maybe now with the change a bit in the political landscape of the US, because it's one thing for European countries to ask for this, but of course it creates an uneven playing field.
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsSo even within Europe, to agree on some minimum requirements for how these contracts are being agreed upon would be very helpful. Rather than one community at a time having to fight for their rights. So I think it's both a bottom-up and a top-down process here that is rather urgent.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsAbsolutely. And and Marion, just before I could see Liam nodding there, I'm sure he's got some some comments on that issue. But do you think talking about the costs here to consumers, do you think they should operate in a different kind of tariff structure or a connection regime, given the scale and the characteristics of their demand?
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsYes, absolutely. There are several risks to in terms of how these pricing structures and contracts are developed. One is stranded asset. Like in a sense, there is speculative demand. We don't yet know if all the compute power that's being built up will be used. So people are concerned that you build this up, use your rights on the transmission queue, and in the end, not all of it will be used, and we're left with this infrastructure. So it's there are clauses like having exit fees and collateral and minimum billing.
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsAnother risk is, as we talked about, is that there's an increase in load and especially in peak that's not met by new generation capacity. So here it's about building up new firm capacity. And Liam was already explaining some of the details of that. But there can also be requirements on flexibility that you can have curtailment so that you use more of the headspace in the grid system rather than peak time, locational pricing. If you're in an area of the grid where it's not very congested, maybe the pricing structure doesn't have to be as or the requirements on these contracts may not have to be as stringent.
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsAnother part with you know the uncertain demand is that you can sort of hijack the connection queue. And that then crowds out other uses on the grid. So to have a ramped up staged approach where it's only conditional on having built up the new capacity and on having on really needing the extra energy. So I think you know, contracts in Ireland have been fairly good in this respect. So this is really the there, these contracts really need to be tailored, negotiated, and legitimate.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsAbsolutely. Liam, what's your view here? I mean, the speculative demands, hijacking queues, what are the real issues here for the sector that they have to address?
Liam Newcombe – GreenScaleAbsolutely. And there would be issues just for the data center sector, even if we weren't impacting other areas of the economy. The most of the connection queues in the Western world have been a little bit broken for some time, but the massive influx of prospective developers who are trying to get a a package of land with power so that they can market it for AI data center developers really exposed that our first applied, first served queue structure may not best serve the social interests or the economic interests of the country.
Liam Newcombe – GreenScaleSo Marion's made some very good points there. So picking on a few of those, Q order is now up for debate across much of Europe. So we see a number of the Nordic states now, I believe Denmark has deprioritized data centers into the you might get connected, but there's no obligation section of their queue, and a data center has to bring something to the grid to effectively make it into the you're valuable enough to be connected. We see other Nordic states doing similar things in terms of that prioritization.
Liam Newcombe – GreenScaleOne of those things you can bring along is significant flexibility so that you're not going to cause peak transmission planning build-out or peak generation build out. In other areas such as Ireland and even in the US, we see grid operators telling data centers that they must bring their own generation capacity. Now, whether that's on-site or somewhere else but close enough on the grid to effectively be local, they're saying do not push up the costs in capacity markets for other consumers.
Liam Newcombe – GreenScaleAnd it also reduces the competition for generation assets between the very large data centres and the power grids serving them. I think the US is a different market with very cheap gas and particularly with demand for AI frontier model development scale, so the multi-gigawatt loads, and that's not really what we're seeing in Europe. At the other end of Europe, we see something quite different, which is I think most people have seen some of the news on the Spanish royal decree. Whether it survives this current election round is a different question.
Liam Newcombe – GreenScaleBut Greece and Portugal are going in a similar direction, and what they're saying is you have to match a certain proportion of renewable every hour of the year, so that you can't cause peak generation stress. So for data centers, I think to get connected, we need to bring something to the grid. So if we're going to build our own HV connection infrastructure, obviously we're going to hand that back to the TSO for adoption. But I think what we need to see is an ability for the TSOs to be more than just responsive to a connection request and to step forward and say, actually, if you're going to build that piece of transmission line, we'd really like to serve some other things off the other end of that line.
Liam Newcombe – GreenScaleCan we have a combined plan, please? Because for the data center developer, what we want is the connection. And if the connection can do some good for other people, that's just going to make things easier for us in planning. We're basically going to have to bring some form of demand flexibility in most markets now so that we don't block development of housing, other industry, other commerce, and data centers. We have a very good opportunity to provide different levels of demand flexibility. We typically have our own firming generation, but there's also infrastructure assets we can use there as well.
Liam Newcombe – GreenScaleSo it's evolving quite quickly. What's interesting to me is how different regulators in different countries with different stresses and opportunities are approaching it very differently. The Nordics want us to bring along some flexibility or grid supporting assets. The Iberian Peninsula wants us to not make their grid any dirtier and not push up their peak price when they're running on gas backup. So it's back to the sustainability argument. We have to look very much locally, and we need to work with the local infrastructure operators and government as well to understand what does a good data centre look like in Bulgaria or wherever else we're going to go and build one.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsMarion, what's your view here in terms of I mean Liam's mentioned the sort of Nordic model, the TSOs and the regulators, the policymakers, are more becoming more and more stringent or or putting more specifics specifications in place. And likewise in the southern European sphere where you have a set percentage of renewable generation that should fire up with the power of the data centers. Where, what's your view here? Which is a bit of both, or which would you think is more suitable?
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsAgain, as Liam said, it's really about the risks and opportunities of the energy system where the data center is going to be located. I think also some of these advantages for the grid as a whole are not necessarily what's most salient for local communities who may or may not either understand that the benefits or those benefits might be quite diffuse for the broader population. So that's just getting that is important right, is important, but it's not enough.
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsThere's both the story for the local community, and there's, I think, also the story that we're telling for the nation as a whole. Why do we feel so rushed to get these things approved and rolled out in certain countries with very little consultation? Like I'm seeing near where I come from in France, and sort of like almost it's it's all it almost feels like a panic planning. We need this as fast as possible. Or in Wales. The question is: do we have a narrative that sounds legitimate and even exciting for French people, English people, about why we want so much computing power.
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsI think a lot of people are very skeptical that AI is going to bring benefits to society, is going to bring benefits to their economy. And so I think getting that story right is really important. It's absolutely not impossible. There are lots of benefits to AI, but we need a plan for how to capture those benefits in a way that feels inclusive to people. So there are all these different layers to getting the costs and benefits right.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsI mean, I think you're absolutely right, Marion. That sense of urgency. We've got to build it because if we don't, the Americans or the Chinese will. Isn't that a bit the narrative here, Liam, that we in the in the geopolitical setting, we've got to be first. We've got to drive the industry because otherwise they will do it first before us. Is that sort of driving this sense of urgency and building new new centres?
Liam Newcombe – GreenScaleI think there's a couple of elements there, and and Marion's absolutely right. We need to answer the question in addition to the why do I want a data centre in my town, why do I want data centres at all? And the the argument because Google Maps on your phone won't work without them is wearing a little bit thin for people at the moment. So the the argument for urgency, I think, is in two parts. One is, as has been mentioned, if if we don't build them in Europe, we will simply end up buying the services from other states.
Liam Newcombe – GreenScaleAnd those could be countries that we have varying levels of diplomatic relationship with. Let's not assume that America is going to be the only exporter of AI services. But the second part is the EU and associated states such as the UK are developing quite strong sovereignty preferences here. And that's not just to support local development of our ability to deploy AI and build businesses, services, support our economy using it, and UK government is very strongly engaged in that, but also to ensure that our access to it is is controlled under our keys and not somebody else's, so that we can't, as we've seen with the US suspending access to frontier models, those things we do not know how our geopolitical relationships are going to play out over the next five, ten, twenty years.
Liam Newcombe – GreenScaleSo I think there is a very clear desire, certainly at EU level, to build out European sovereign cloud and AI capacity. There's been very little successful build-out of the cloud capacity, although we have seen a number of European governments switch from American productivity app products to open source or European. But perhaps the rollout of AI is being taken as a a strong opportunity for the European governments to say, okay, this is all being built new.
Liam Newcombe – GreenScaleThe question is where does it go, not how do we migrate off something that we're importing? So perhaps this is our good opportunity to put it in locally, develop the skills, and build those things that Europeans are very good at, which is taking tools and building services and supporting other parts of our economy and then exporting that to the rest of the world. Developing frontier models, I'm not sure that's a productive thing for Europe to try and do. I'm not sure a Stargate-sized data center really works, especially not at our power prices.
Liam Newcombe – GreenScaleBut doing things like a startup at Imperial, I'm biased I went there, Polarom, are doing using AI to very significantly accelerate material science in particular batteries. Those things have real value because we take those and we enable Europe to develop battery chemistries and manufacturing technologies so that we don't have to import the whole final value-added product from other regions. So there is an urgency.
Liam Newcombe – GreenScaleHow we should rank that against other activities in our economy, I think is beyond my pay grade and probably belongs to the politicians.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsAbsolutely. And we'll put it onto onto their desks. I think there's also a risk here of, you know, as Marion mentioned at the start, you know, potential stranded assets as well as the technology moves much, much faster than the rollout or development of the assets. But if I just have a final question, if you can, we're running out of time, fascinating discussion. I'll have to have to invite you guys back. I think this is really, really interesting. We're getting to the real core of the issues at hand. If you could change one thing about how Europe plans and regulates data center development, what would it be, Marion?
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsAbout the data centers, I think we're seeing we've discussed interesting emerging great practices. So, I would say monitor the best practice and try to negotiate that these become sort of a floor rather than a ceiling. But I would say it's I'm more interested in the bigger question of why do we need these data centers? What is it going to do for society? And I think really articulating the vision, the strategic vision, and having enough policy that is about strategically deploying AI to solve public problems, engineering problems that are really pressing is what I want to see.
Marion Dumas – Associate Professor of Climate Policy, London School of EconomicsAnd, we've seen in our research that clean technologies are much better poised than dirty technologies to make good use of AI. But these spillovers and innovation, they also can be deliberately and strategically designed so that they are much larger in scale. And so I want to see plans for how are we going to deploy this in hospitals? How are we going to deploy this to make the grid work better, and so on and so forth.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsAbsolutely. So, Liam, same question to you. If you could change one thing about how your plans and regulates data center development, what would it be?
Liam Newcombe – GreenScaleOkay, well, Marion's covered the broader scope better than I would there. So I will narrow my scope down to closer to my day job and data centers and energy. So I would say, and the speed of deployment thing works at both ends of this. We can build new renewable generation much faster than we can. I think everyone knows how long it takes to buy a power turbine at the moment, and that may be a good thing in restricting our ability to create more CO2. So we have enormous cash flows coming out of AI through data centers and building associated energy infrastructure, if that's on-site temporary bridging or firming generation, etc.
Liam Newcombe – GreenScaleI think what we need to do is enable a structure where governments and regulators give us as data center developers a much clearer indication of what it would be beneficial to bring to this piece of grid. So if we want to go and develop a data center in Sunderland, for example, what does the grid already have there and what what would we need to bring to it for benefit? Do we need to build a renewable energy hub with sub-market price power and open that up to other commercial industrial consumers to assist the local economy there?
Liam Newcombe – GreenScaleOr do we need to build a piece of transmission? Or do we just start with, as a number of the Nordic states have said, a minimum floor for flexibility? Don't specify the technology, but say you lot will be able to flex. We don't care whether you turn your compute down, use some battery, or have an appropriately emissions-controlled backup generation plant, but you're going to bring flexibility to this grid. And if we do that well, data centers should actually be able to stabilize and support that grid and enable other things to get built.
Liam Newcombe – GreenScaleThe houses, businesses, all the other things stuck in the grid queue. I think we have to fix that, or the sector is going to continue to have serious trouble with planning, permitting, and social license to operate.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsThank you so much. Fascinating discussion. I wish we had more time, but maybe at another juncture. So thank you very much for being guests on the Plugged In podcast. And to you listeners, thanks for listening to this episode of Plugged In. If you enjoyed this discussion, please like, rate, and follow to make sure you get the latest podcast episodes as soon as we release them every Thursday. Finally, you can head to montelnews.com for more news and analysis from our team of journalists across Europe and beyond.
Snjólfur Richard Sverrisson – Editor-in-Chief, Montel NewsSee you next time.
Send us your thoughts! Battery storage is booming across Europe, driven by the rapid growth of renewables, volatile power prices and an urgent need for flexibility. But as more batteries come online should operators and...
Send us your thoughts! Big Tech is buying huge amounts of renewable electricity to power data centres and the push for AI, but how green is that power really? And could changes to the rules governing corporate green...
Send us your thoughts! As Donald Trump pushes for a peace deal in Ukraine and takes an increasingly conciliatory approach towards Russia, what could it mean for Europe’s energy markets? This week on Plugged In, we look...
Send us your thoughts! Grid congestion has become one of the biggest obstacles facing the Dutch energy transition, with businesses and new projects struggling to secure connections as electrification puts growing...
Send us your thoughts! Europe’s energy infrastructure is facing a growing range of threats, from physical sabotage and cyberattacks to hybrid warfare targeting the wires, the pipelines and the substations that keep...