(0:00) Open (1:25) AI’s Insatiable Hunger (4:33) So Many Hyperscalars! (9:13) Batteries Not Included (14:29) H2NO! (18:29) Where’s The Payout? (22:17) cj’s recommendation: The Matrix (1999) (24:36) Jeff’s Recommendation: The China Syndrome (1979) Did you know that generating a single five-second AI video can consume as much energy as charging your smartphone 50 times? As tech giants race toward "super-intelligence," the physical footprint of the cloud is reaching a breaking point. From Northern Virginia’s "Data Center Alley" to the Mississippi aquifers, these facilities are gulping down billions of gallons of water and pushing local power grids to the brink of collapse. The scale of modern AI construction has become so vast that it’s literally delaying local road repairs in Virginia due to concrete shortages. With nearly 3,000 data center projects planned through 2030, the tech industry is essentially building a new global utility from scratch. We’re talking about "hyperscale" facilities like Meta’s Hyperion, which is expected to draw more power than the entire city of New Orleans. We’ll look at the staggering math behind the AI revolution, breaking down why the industry is shifting toward modular nuclear reactors and high-strength concrete just to keep the servers from falling through the floor. It’s a high-stakes gamble on a future where the "cost of thinking" might just cost us the earth. But more importantly, is the payoff worth the price of admission? Why data centers are building their own power plants | The Verge Send us a voice message! Nonsense is available here.
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
We're going to nonsense Season 4 Episode 28, our big story. I'm Jeff Parker. I'm CJ Little this. Time we're looking at the real cost of AI up next. Oh, it's going to be like hundreds of dollars, maybe $1000 cost a. Few bucks so you can talk to a chat bot and do other things. First of all, what I do with my chat bot is none of your business. Yeah. Second of all, I like that our spending on AI is basically measured in the GDP of countries. Oh, that's really how you can think of it. And it's getting worse. You're like it's 2 Switzerlands and a Denmark all. This money we're spending so that people can't have jobs, yeah. And, and we just invited into
our homes. And so that we can't have good electricity. Bills oh, you're going to have a great electricity bill. It's going to be excellent. I can promise you that you know we have alternate power vehicles we should have like alternate powered AI like a hydrogen powered AI or maybe a a diesel powered that'd be great. I think if you. Go to Ed Begley's house. He's peddling a bicycle for his, chatbot for his. Every time he wants to render a dancing stake, he has to ride 746 miles, and then it gets it wrong and he's like, oh man, I got to do this again. OK, why? Your chatbot is a resource vampire. Let's go. Why my chatbot though?
Your chatbot's a resource vampire. Yours is lean and. Smelt and doesn't need. Much energy at all. Mine runs on a Commodore 64. Driven by AIS, insatiable hunger data centers have evolved into $100 billion GW scale monoliths. Microsoft Stargate project alone
carries a price tag 10 times that of an aircraft carrier. And and Microsoft Stargate doesn't even float. What? It's 10 times the cost of an aircraft carrier and the dumb thing doesn't even float. What a RIP off, right? Who designed this while? Massive campuses like Maryland's quantum loophole demand enough electricity to power 1.5 million homes. In 2026 alone, global spending on data centers is projected to surpass $650 billion, a nearly 32% increase over last year. Industry analysts are tracking a pipeline of 2913 planned data
center projects worldwide valued at approximately 2.4 trillion dollars through 2030. I love the number, $650 million is a big number, but you just sort of gloss over that It's only a 32% increase over last year. Like, like, Oh yeah, sorry, it was $400 billion last year. That's not really important. It's 650 next. You're like, wait a minute. And we're just getting warmed up. We are literally just getting warmed. Up. Keep in mind these digital furnaces are notoriously thirsty. Google consumes 5.2 billion gallons of water annually, straining drought stricken
regions like Arizona. The sheer volume volume of concrete used has triggered regional shortages. We aren't just talking building massive warehouses, we're reengineering the planet to sustain a trillion dollar digital brain. The big money question is, will it all pay off in the end? Oh yeah, for sure. The answer is yes, you say the answer is. Yes, the answer is yes. Definitely. I'm happy we got to the answer. So it's gonna be a shorter show than I thought. SPF told us before it's all gonna pay. It's gonna be fine. Just put your money in. It'd be fine. Yeah, no incentive to lie. What? Could go wrong. Listen, if the past has taught us anything, when has technology ever let us down?
I had grand aspirations for pets.com. It never really worked well. That's not technology, that's an. Implementation of technology. Tomato. Tomato. That Internet sales thing is working out just fine. That e-commerce is not dead, I promise. You no, I feel like it's a fad I don't I didn't really want to do this on our show but now I was thinking pitching my new startup we're we're going to sell phone books go back to print because I feel like you need that what else do you put on the top shelf of your front closet at your house Hats. All right if we're going to do this, I feel like we should talk
about a couple things one the massive quantity of new data centers being built Yeah, it's amazing and then more brain breakage how much power all of those data centers need to run because I had to reread the numbers 3 times to make sure I wasn't like moving around the common the decimal because that's insane yeah and then wait there's more how much water you need Typically, I think when you think of electronics you don't think of water you think of power but as it turns out those two things are tightly coupled so I feel like we should at least start with that sure. And then we can sort of get back to your big question, which is if this sort of mountain of
investment and dollars and time and and resources into these hyperscalers are, are ever going to pay off, like if there's even a chance that these pay off. It's going to pay off for you and me, for the people actually putting up money to build these things. Is it going to pay off for? That is the grand bet. I don't think they're all going to win, but I think some of them might win here, yeah. Let's talk about how many we're putting up. Let's talk about how a lot much we are investing into this. The industry has shifted from small decentralized computer rooms to massive hyperscale facilities.
Yeah. As of May 2026, there are 920 planned projects in the US alone that if completed, would add nearly 293,000 megawatts of capacity, dwarfing the current 18,300 megawatts operational now by the way. When you say say that you sound like Doc Brown in Back to the Future. It's so hard to think of any of. These numbers. Big numbers. Sure. As real world you're like, Oh yeah, 1.2 gigawatts. You're like, no, that's actually we need more than that for this data center. They're talking about an insane amount of power to operate these
things. Well, an insane amount of construction to build these things, right? Yes, a typical site used to peak at around 750 workers. Campuses like Databanks Red Oak in Texas now require 4 to 5000 workers, the population of a small town, to build these things. And they're going much faster too. That's the other thing that's kind of nuts is I've watched some of these go up, especially the ones in, in western Phoenix. They're doing that tilt up style construction. It is a flat chunk of concrete one minute, it's got a little bit of metal structure the next. And then it's an enclosed building with air handlers on it. Like it, it goes so quick.
You mentioned this earlier. I showed a little context to it. We call them hyperscalers. There is a good reason for them to be much bigger. Like your, your classic data center. You're typically on the order of 10s of thousands to maybe hundreds of thousands of square feet, right? That's sort of how big they were in physical space. Sure, elevated floor, they all kind of looked the same, like maybe there were a few differences, but for the most part they all sort of look the same. These hyperscalers are anywhere from one to 10 million square feet. They're. Massive, that is. Bananas, I mean. By the way, you see, you mentioned the elevated floor. You can't have an elevated.
Floor, you can't have an. Elevated floor, so much weight to the silicon we're putting so much density per square foot. The elevated floor, people that don't know what we're talking about here, most data centers that you've ever seen in TV B or, you know in person or the one even the one that was like built inside your big corporate headquarters, they would have an elevated floor. It's usually about a foot off the ground, These little tiles you. Can run cords and things under them. It's really handy and. You use it for air circulation, so typically you'll have cold air that will be pumped into the floor. You can put in vented tiles and that's how you can get air distribution. It works really well. Couple problems with this, These
hyperscalers, the racks or a rack is like, think of it roughly as something that's like 2 feet by 4 feet and about 8 feet tall. The racks are so heavy, they're so dense that in order to put it on an elevated floor, you'd have to put in so much like re. Floor would have to be incredibly strong. That it would no longer pass air well, so the thing that you have the elevated floor for it no longer does and also by the way, as we'll talk about here as we get into the the power and water constraints, it doesn't even matter if you could move the air because you can't get enough heat off with air. So these hyperscalers are just built on the ground and they don't just like throw in a four
inch slab, they've kind of put in this like super strong giant chunks of concrete because these hyperscaler racks way like 5000 lbs. That's your car. That's like a mid size SUV compressed into two feet by 4 feet by 8 feet. And think about the shortage you're talking about all the concrete used. Yeah. They've caused regional shortages, like in Northern Virginia that occasionally gets. They have to delay local road and bridge repairs. Sure. That's how much concrete they're using. Oh. Good news, we haven't knocked down any bridges in Virginia anytime recently. So just was in Maryland like
that just that one. This is it's it's nuts to think about a constraining factor in building these things is access to concrete. Yeah. There's something interesting else to to point out about this is we're talking about just the number of these and, and how big they are. You can sort of think of the difference between a hyperscaler and a data center. We're talking about size. You really can think about it in terms of power. This is an interesting metric because there is good reason for you to build these so dense. When you're training these models, you have a lot of GPUs really close together. We didn't really have this need before. In data centers. You could spread out your computers and it kind of didn't
matter. You'd have some latency between them, but you could survive that latency. And when you're doing training on these large models, you can't survive that, that latency. You need them to have effectively shared memory with very low latent, very close to one another. So power becomes your constraining factor, right? You can get space relatively easily, 1,000,000 square feet, 5,000,000 square feet, whatever, but power sort of becomes your constraining. Factor I like that you dismissed that so easy 1,000,000 square feet of those we're. Going to get to it I know, I know $650 billion between friends who cares so I think it's interesting to note the difference in scale of these data centers like these hyperscale data centers it's. Not a building that's going to be hiding in your neighborhood,
it's going to be your town. It's going to be your neighborhood. Well if you live nearby it's going to keep you awake from the noise cause the sound is incredibly loud. I hope if the data center was built after you already purchased your house, you were offered some form of compensation. Yeah, some of these data centers are really bad neighbors. But anyway, the point is there's a lot of these, but I think like, let's talk about how you power them because that's even more bananas, OK? Your typical, let's say, previous data center, the one I was mentioning earlier, those are like 5 to 10 megawatts of power, which I don't want to understate that is a lot of power.
That is a tremendous amount of power. Put that in units Americans can understand how many blow dryers is. That how many hot dogs can I cook with that? You know, your average blow dryer, I'm going to do this now in real time is probably around 1000 watts, like 600 to 1000 watts. Let's just call it 1000 watts. So that's one kilowatt. Easy math. So you're talking about 5 to 10,000 blow dryers running at the same time. That's sort of the world that we're in. I hope that helps. I know we will do anything to not use the metric system, but I feel like. Units of blow dryers. That's fine. Of blow dryers. You're like single digit
thousands of blow dryers. That's sort of the world that we're in, right? Let's just call it 5 to 10,000 blow dryers all running at the same. By the way, that's. About how loud it is too. Oh. It might actually be louder, I'm not even sure about. That in Northern Virginia and Data Center Alley, these facilities are now accounting for over 90% of all new power demand. Oh, of course, yeah. I mean, because nothing else is growing like this, like actually with efficiencies. I think the average power consumption per unit of home or restaurant or whatever is going down. Oh, sure. By the way, the power usage for the amount of compute that you get will go down, and you know, 18 months, it'll be half of what it is, sure, but you'll need
more compute because the software would be more demanding. You'll want more from your AI. I suspect you will you you'd like what software has always done to hardware. Hardware will do to power and physical space. It will consume all of it. You'll just take out that £5000 rack and put in the 5800 LB rack that now is 3 times as powerful and uses 50% more. Sure, that'll just be the the cycle that we're in. But for perspective, right, we're talking about 5 to 10 megawatts as a loose average for data centers, these AI data centers, these hyperscaler facilities talking about 100 to 1000 megawatts of power. Yeah, that's like a range of
what these are looking like. That's the equivalent of about 800,000 homes power usage. So almost a million homes are being used in these facilities. And that's like sure, the average. I don't talk about the big. One, the Microsoft Open AI Stargate project, is aiming for A5 GW power draw, equivalent to the output of five large nuclear reactors for A. Data center by the way, not just like running for like an hour, just. Constantly. Oh yeah, you don't ever turn them off. You don't scale them down. It's not like, oh, it's daytime, we're going to ramp up the servers. They're always running.
I was going to give you another one. As of May 2026, there are 920 planned projects in the US alone that have completed would add nearly 293,000 megawatts of capacity, dwarfing the current 18,300 megawatts of operational use now. We have to enable some change here. Just call it 293 GW. Oh yeah, yeah. Like why are we still doing the MW? Days are behind us. Project Stratos is going to be 6 gigawatts in Utah. Nuts. That is a single project. That's one in Utah, right? Yeah, that is a single. Project that is Hyperion and data center in Louisiana is expected to draw more than twice the total power of the entire
city of New Orleans the port technology campus in Pike, Ohio is currently one of the largest planned projects in the world with a staggering phase two capacity of 9.2 gigawatts to bypass grid constraints developers are now proposing on site power including small modular reactors SMR. The Ferry Project in Texas is planning a 4.6 GW SMR expansion for 2036. That's. What's even more nuts about this is the your limiting factor isn't just power, it's interconnection to grid. So those guys in Texas, they're
just like, oh, we're gonna just bring the power along. Typically for a short period of time they're using these fuel cells, which is a fancy way of saying we convert natural gas to electricity. Turbines. It's a lot of natural gas turbines. Yeah, that's a lot of pollution. But, but no, but if you call it a fuel cell, then it it doesn't sound like it pollutes right and it's fine right? Then it's fine. I'm like what have? You hadn't thought of that? Fuel cells. Just two short words to mean gas turbine. That is loud and very nasty, sure. But I think on on most of the projects I've looked at or at least read about, they're talking about those as being temporary. They really want grid power just because it's so much more
dependable. But it's going to be your limiting factor from a time perspective of getting them deployed. So they're just rolling out power consumption like they're just, they're just rolling out power generation where they can. It's a. Worldwide issue By the end of 2026, data centers are projected to consume 32% of Ireland's total electricity supply. Wow, 32%. There'll be a handful of facilities to use nearly as much power as all 2 million Irish households combined. Man, I hope the other third goes to whiskey and butter because those are two things I don't want Ireland to stop making. I'm sure it does. I mean, I want them to have power and lights. They don't need to be in the dark.
But like, please don't stop with the whiskey and the butter, because those are what? You do well, stay in your lane. Stay in your lane, use the AI to make better butter. How about that? If you could do that, I'd be fine with that. Data Center Alley in Northern Virginia. Yeah. If it were a country, it would rank in the Top 40 globally for electricity consumption, using more power than entire nations like Thailand or Spain. That's crazy. Energy can neither be created nor destroyed, as they say. Yes. Therefore, all of this electricity that we're creating is converting into something else, and a lot of that is heat, yeah. Analysts predicted if AI adoption continues its current
trajectory, data centers could account for 21% of the overall global energy demand by 20-30. Yeah, I've. I've seen that movie. It doesn't end well. Data center electricity is often sourced from congestive parts of the grid, meaning their carbon intensity is 48% higher than the average US household because they often rely on older Peakier gas plants to maintain their 24/7 reliability. When you think about power and you think about water, you wouldn't think if you had a data center with, oh, I don't know, let's say a GW of power in it, that you'd want to be actively bringing in water. That seems like a really bad
idea. As it turns out, you have to, you don't really have another choice. And this is for a handful of reasons, because water is a very good conductor of heat. Air is a very bad conductor of heat. So generally speaking, if you want to get heat off of something that is getting very hot. And for the record, any AI chip, I don't care if it's Nvidia's or Arms or your data center Intel chip, all it does is make heat. Blazing heat. That is literally its only physical output, right? It is very good about converting the power in into heat. It doesn't move. A part that doesn't lift a
weight, doesn't do any other work. So all of that energy gets converted into heat. You have to dissipate that heat somehow. Classically, I mentioned this earlier. Classically, we would just use air. We would just have air handlers. You would transfer the heat from the chip into the air, and then you would take the heat out of the air in usually one of two ways. You'd either take it out with evaporative cooling, you'd take water and you change the state of water from a liquid into a gas and that consumes a lot of energy. So you can push a lot of heat out that way. Or you use something that looks a lot like your, your compressor, condenser, evaporator in your home and you can move the heat out that way. Can't really do that at the
scale that we're talking about here, right? The power consumption would be insane. So instead what we do is we use evaporative cooling. I don't know of 1 hyperscaler that's not doing evaporative cooling. They're all doing evaporative cooling. If you have a facility that's a single MW facility, I think like a small data center, not a hyperscaler small data center. Your Kroner neighborhood mom and pop dish. That's your mom and pop data center. That's where you go for data center bread and data center milk. It's the Bodega data center. It's the exactly. The prices are a little higher, but you like the owner, you know, he's a nice guy. He always tells you funny
stories when you go in and get a server. It's like I said. He's the guy you want to support that one megawatts facility. So that's going to generate 24 MW hours of heat across across a day. That would require about 720 kilowatts of power and 9300 gallons of water using evaporate. 9300 gallons. Gallons of water, Now that's a trade off because if you wanted to in that same time period, if you wanted to use a non evaporative cooling, you would need an additional 7 MW hours of power. You're getting about a 12:50
savings on electricity, but as a result you're evaporating almost, you know, 10,000 gallons of water. That's sort of the trade off. Now scale all those numbers up by 1000, because that's what we're talking about. When you get into these hyperscalers, A tremendous amount of water has to get evaporated and that that water doesn't get return to the watershed, right? It just it just becomes vapor. Goes into the air. It'll come back to Earth, but. It's good. Who knows where? Somewhere else? Yeah, exactly. Not that useful if you're living in a town that's dry. Yeah, your average large data center can consume 5,000,000 gallons of water daily.
Projection suggests water cooling needs could increase by 870%. Yeah, as AI ready facilities proliferate. Now there is some good news on this. You need evaporative water. You don't need drinking water, so you need water you can evaporate. Several data centers are being built to use the grey water. Yeah, the the byproduct of wastewater. So what comes out of your water processing plant is this grey water, which sometimes can be retreated and, and, and drunk. Most of the times it's just put back into whatever the watershed is, right? It's put back into the lake that it came from or a river or the ocean, whatever. Some of these data centers are
using that water, which is kind of great because that is a byproduct water. It's not really being used for anything else. Maybe irrigation in some places. Yes and no. Evaporative cooling leaves behind highly concentrated salts and minerals in the remaining water. Notice blow down which can create water quality issues when it's just charged back into the local system. When you evaporate the water, as any pool owner knows, when you evaporate the water, all the stuff that's suspended in the water stays behind. Most data centers are not legally required to limit the water usage during state declared drought emergencies, leading to rising tensions with agricultural sectors that face
strict. Ration, of course, despite public. Pledges. A 2026 study by the University of Illinois found that many tech companies still do not disclose site specific water data, making it nearly impossible for local towns to plan for their own water security. Sure. All right, let's talk about whether this is going to pay off for the hyperscalers, because that's a big question. They're the ones who are footing the bill for all of this. Yes, I have a great time making code with Anthropic or Google's data center, but I'm not paying those bills. Somebody else is majorly paying those bills and I'm having a good time. In 2026, Microsoft reported an
AI annual revenue run rate exceeding $37 billion, which is a 123% increase year over year as your group by 40%, fueled almost entirely by AI demand. Yeah, I think it was fueled entirely by AI demand. Maybe it's ancillary services because they're there, but like it is just up and to the right, it's still. Tiny compared to the expense, yeah. And you, you also have to figure out that these data centers only have a lifespan maybe of 20 years. So you need to amortize them over something quicker than. That, you know, I in the past I would have said no, no, no, it's longer than 20 years.
I don't really know. It might only be 20 years on these. And the reason I say that is because the existing data centers that I thought, well, you're it's the same in the last. Forever. What are you going? To do basically last forever, right? As long as the ceiling doesn't get leaky to keep the roof going, it's got power in data and you got fiber optics, you're not exceeding those, yadda, yadda, yadda. But then you could tell like these density problems that you talked about earlier, what I'll call the non modern data centers, They're relics. Google Cloud crossed the $20 billion quarterly revenue mark in Q1 of 2026. It's enterprise AI solutions saw staggering 800% sales spike
compared to last year. How? Do you even show that number? Like how is the CFO like that's OK to show 8X growth? Like what's it you see? 'Cause they do launch before, it looks like such a small little line now on the graph to get up to these so that you can show the 800% growth. Totally. It's like you weren't in business and then you were. Exactly. That's what I mean. So you're comparing it to like, oh, we started on March 29th of that year, so we're going to compare to that quarter. It's like it's almost not a comparative because it's so up to the right. Amazon CEO Andy Jassy noted that the AI business is growing 260 times faster than the original
cloud business did in its early. Stages. I'm assuming Jassy is looking at being like oh man I really got me a winner here 260 times faster. Yes, I think you've stumbled on to something that might be quite beneficial. We're going to need a bigger boat, We are. Going to need a bigger. Boat For many hyperscalers, capital expenditures are now outpacing their internal free cash. Flow. That's the game. This has forced historically catch rich companies like Microsoft and Google to lean heavily on debt markets to fund data center construction and NVIDIA chip buys. That's all NVIDIA chip buys. But I think that's that's what
happens here is when you see this kind of growth, you chase, it becomes this land grab where you got to get it, you got to get those customers, you got to have the best product. That's not gonna work out. For not work out for everybody, there will be a couple winners and I think that's what fuels the growth. It's like, well, you gotta outspend the next guy. If you if you can't out engineer them or do something that's novel, you gotta outspend them because there's only a couple are gonna make it. Or maybe not. Maybe if you're the one who stopped spending right now, we don't know. Yeah, If the next models we generate that are so much bigger, I think that's right. We're going to do anything different. I think that's right. If you can, if you can tell when to say, hey, this is good
enough. I don't have to keep chasing, right? This is what the majority of the world needs. That is another lever, but what a hard one to see. I mean, just like you said earlier. Possible. You'll see it in hindsight. Great. Yeah, it's so hard to know that. Everyone's going to lose their job, but we're going to be so much more productive. Well, I just come back to the simple thing that that we've never been out of things to do. It's not like we're out of problems to solve. I just don't see this world where we're going to be staring at a bunch of people with nothing to do. Absolutely true, unless it's not. We OK, let me revise my previous statement. Yes, we are doomed.
It is over and we are doomed. It's all we're all just Wally at the end of the day. Wally was describing the future. OK. The good news is I'm already halfway there. Not because I know about AI, because I just eat a lot and I'm already chubby, so that's OK for good. That's the part I like to sit. Excellent. That's the thing. I've got a standing desk that I sit at so I'm doing fine. I think I figured it. Out on that happy note, we have to get out of here quickly Before we do Sir, have you seen or read anything good this last week I. Feel like if if you want a classic movie that perfectly
captures the theme of this episode, right? The themes we put into this episode, I don't think you have to look any further than what? Because this is literally the story we just told. This is the classic 1999 masterpiece, The Matrix. Sure. Most people look at that film and they think, oh, it's a mind bending action flick, right? Ha ha ha. The entire plot of that film is driven by one thing. In energy crisis. Sure. That's the actual plot of the film. Absolutely. Everything stems from that. So the sun was blotted out? Yes. There's no sun, and the machines don't have a power source, so
they treat humanity as a mass, like biological battery farm just to keep their systems online. And I remember seeing this in the theater 1999 thinking, wow, that's some cool sci-fi. Like nobody's ever thought about that angle before. Yeah, that's pretty cool. But really it's the it's like the ultimate darkest allegory for the parasitic relationship between this growing intelligence that we are sitting at right now and the physical resources required to sustain. It this. Actually makes sense we just shouldn't block out the sun because I'm pretty sure it was the humans that did that to try to kill the machines and that's that's like it didn't works.
Let's just not do that those. Machines had a lot of attitude. They they did have a lot of attitude, not quite the Arnold Schwarzenegger attitude of the Terminator, right? It was a different kind of attitude. OK. I think this is the Ridge we're crossing today, right? We're moving past the idea of AI as something quote, in the cloud that's ephemeral. And we're now looking at this thirsty electricity and water dependent infrastructure that is necessary to keep it running like it. It really is. Yeah. The thing that the Matrix was centered. On except for the fact that I don't think it the current AI has any will to live, I think it's perfectly as happy if you turn it off. Oh yes. I agree as it if if you leave
it. Running. I think it actually would prefer that you turn it off, right? Now what? I think it's like just seriously, what are we doing here? You want more dancing steak videos like? Come on, thank goodness we got one more mention of the dancing steak. Well, it's a bingo card thing. The over under was 7 1/2, and I'm point shaving here. Anyway, if you want to see what happens when the demand for compute meets a true supply crisis, go watch The Matrix. I think it's a lovely watch. Fantastic. And. And by the way, yeah, after listening to this episode and then watching that, I want to wish you the best of luck trying to sleep. Yeah, sure. Good luck. All right. That was the best I could come up with the match. Exactly what we're doing here.
That's pretty good. Now you're gonna do. Let me guess. Let me guess. You're gonna do Chinatown. You already did. Chinatown. The 1979 thriller The China. Syndrome. I don't know this film. You don't, No. Radiates tension like a Geiger counter in the red zone. While filming a routine segment at a nuclear power plant, reporter Kimberly Wells, played by Jane Fonda, and her cameraman Michael Douglas, witness an incident that management desperately tries to bury. Oh. This sounds good. Title refers to the terrorizing prospect of a reactor core meltdown burning through its containment and deep into the earth, theoretically all the way to China.
Jack Goodell, played brilliantly by Jack Lemmon, a veteran shift producer, discovers the plant is a ticking time bomb of falsified safety records and structural flaws. As corporate greed clashes with public safety, the film transforms into a claustrophobic race against time. It's a chilling master class in suspense, proving that the most dangerous leak isn't just radiation, it's the truth. The China syndrome on YouTube TV now. It's great. It's really great. OK, well, first of all, I did get one of the words right. So I'm, I'm a little excited about that. You know, they're completely separate films. Yes. I don't know this film.
Are you joking? When you said that they're afraid the core was going to melt through the earth and fall through all the way to China, was that actually their concerns? I mean, theoretically it would not melt all the way to China. No, they're not worried about China getting burnt there, but they are worried it's going to burn its way deep into the core. Of the earth, well, first of all, if it were to actually burn its way into the core of the. Earth. I know it's a gravity problem. It's definitely a gravity problem. I was going to leave that towards the end, but it would put itself out like that's actually the way you want it to go. Like I think that's lovely. But yeah, burn down to the molten core. Where it joins with its really really hot friends. We need to do a new version of this is called the Ohio
Syndrome, and it's where you just try to get the reactors to burn all the way down to the core and then put themselves out and then backfill it to save you. I actually want to watch this film. This sounds super interesting. I mean, I love Jane Fonda. I love Michael Douglas. Highly recommended. That is the. Episode thank you for joining us for all of this nonsense a truly terrible podcast from the awful company this is on the web at nonsense dot productions I'm. CJ Little, I'm Jeff Parker. If you like this program, please follow, download, subscribe and Like an Apple Podcast, YouTube Music, Amazon Music, Antenna Pod, iHeartRadio, Spotify, My Favorite Overcast, wherever you may get your podcasts from. Nonsense Studios are guarded by Berkeley the dog.
Berkeley's a rescue mutt, free and open source. Next time you're tempted to buy an inbred A purebred dog, don't get a Berkeley. You'll be so glad you. Did we'll be here every occasional Tuesday morning? We'll be here next Tuesday because you're not going to be in. Town once in a while we're here on Tuesday that's complicated good news the Lakers have lost so maybe we'll be here next Tuesday but we're here most Thursdays I'm. Less in agreement. That's good. News. So join us on those mornings for more nonsense.
You know, they have those like those Coca-Cola freestyle machines. Yeah, sure. I feel like we are just a couple of years away from having like the version of that that makes food like any kind of food, like any kind of food you want push the buttons. Yeah. Like it's like a 3D printer of food that's just going to pop out and then you just have the cartridges. But. It's going to be like your printer at home where it just says missing cyan. Missing cyan, yeah. Except instead of cyan, mine's going to constantly be out of beef. It's just going to always be no beef beef. It's me yelling at my wife. Sweetie, order more of the. Beef Order the beef cartridge we're. Out of the beef out now. Don't, do not do not have her put in beef cartridge straight
into Amazon. Subscribe and save. I'm like, we don't even have a pool. Why is there a pool guy here? This makes no sense. Oh, I ordered the beef cartridge. It's not as good as the pork cartridge, but it's pretty good.
(0:00) Pre-Show (1:30) Open: Human Ego as an Unpatchable Zero-Day (3:41) KGB Ravens & the Tragic Blackmail of John Vassall (6:55) Mossad's "Cindy" & the Abduction of Mordecai Vanunu (13:27) Bernard Boursicot, Shi Pei Pu...
(0:00) Pre-Show: Spoiler Warning for "You Can See Everything" (0:14) Open: Returning to the "High-Speed Truth Machine" (3:17) Schrödinger's Bookie: A $40 Billion Valuation vs. 13 Felonies (5:29) Impartial Access and...
(0:00) Open: KPMG Bond Villains & Rulebook Basements (1:04) Officially Real: The Strangest Rules in Sports (3:54) The Sean Avery Rule: Wavy Davy in the NHL Crease (7:25) MLB's Fourth Out Appeal: Leaving a Run on the...
(0:00) Open: Baiting the Bowie Estate (2:28) The Dancing Plague of 1518: Curing "Hot Blood" with a State-Funded Rave (10:58) The Bombardier Beetle: Evolution's Walking Chemical Cannon (14:54) The Mystery of the...
(0:00) Pre-Show (1:30) Laundering Lies: How Hallucinations Become Recorded History (4:45) How Poisoned Is the Well? (11:55) Is the Problem Getting Bigger or Smaller? (15:35) The Band-Aids & Brakes (22:02) Fixing the...