Joe Westgate steps into the trailer to discuss his background as a scheduler and gives Joe Smith some suggestions for his project. How can a well made schedule help with staying in budget and on pace? What are the key points of the critical path? How can being too far ahead of schedule impact a project?
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Good morning. Welcome to another edition of Joe on the Job Site. I am Joe. I am here today with my guest, Joe Westgate. He is a longtime tradesman, been in the business for 30 plus years, and he's worked his way up from working in the field to a scheduler using the Primavera P6 program. He's one of the key instruments in teaching me how to use the program. how to schedule the building, how to make it work, the things to look for.
One of the things I've always enjoyed with him is when he walks the job, he knows what it's supposed to look like by looking at the schedule. So, Joe, welcome this morning. I'm glad to have you, and thank you for taking your time out to come and join us. I would like today for us to, we're going to do a short session here, and then... uh if you would i'd like to walk the job with you and see your thoughts on how the project is when you uh the window behind you when it
starts to get daylight we're gonna take a walk on the job very good so i mentioned your years in the industry how many years have you been in this industry uh 38 years before i retired and and retired now and enjoying it enjoying it immensely Great. Made a good living. Made a good income. Oh, very good. Made a nice retirement. Destruction is a great industry to be in. So for the folks here, how did you get your start? What brought you into the industry? Who was your
mentor? And what kind of key components helped lead you to where you're at? Because I've been around you for 25 years plus, for sure. And you taught me many things. vision of making a schedule was extraordinary how did you get started well started back in the 80s um i was driving truck for a living and i was a teamster in the union and i woke up one day and said i really want to keep doing this when i'm 50 years old so i
uh my wife would work for a construction company got to know the people there she worked with i just went in and asked them for a job one day And they hired me shortly thereafter to be an assistant field engineer and taught me on -the -job training for laying out buildings. My first job was a 10 -building prison in Massachusetts, a brand -new three -year job. And we had over a mile and a half of footings and foundation
walls to lay out. And once they were done, we laid out all the walls and stuff inside the building. I met a guy there. He was my mentor. He was going to move on to another job, and he requested I go with him and be his lead engineer on his job. So it was continuing the layout. Yeah. Right. And he made me an assistant super when I went over with him. And I worked there. And I got
asked to be a scheduler one day because... One of the guys that was asked to do it never replied back to the company and said he was interested. So I got a call to the office one day and said, hey, we'd like you to be our scheduler for our company. And I said, well, I've never touched a computer in my life. And he said, well, you weren't an engineer before you came here either, were you? You learned. I said, good point. Yeah. And so, yeah, I went. Two and a half more years,
I worked for that company. We had a downturn in the early 90s. Things started to get slow there. And one of the superintendents I used to work with, he ended up going to another company looking at a casino. This was in the Rhode Island area. Rhode Island, Connecticut area. Yeah. And so I ended up going to work at a casino up there and stayed there five years working on that. So you were assistant superintendent, mostly laying out? In the beginning, in the first job. I went on to be the scheduler on the casino.
On the casino. Yeah. Okay. I did two and a half years of scheduling on the first job, but I did the five years of scheduling on the casino. On the casino. And that's where I've been ever since. So I've been in the scheduling since early 90s. So. Your education was you graduated high school. Graduated high school. Went truck driving. Worked in a warehouse, started working in a warehouse. You know, we're in the teams to union and decided to get out of that and try something better.
So you've made your way up the craft by learning. Yeah. Taking someone offered an opportunity, working at it and moving yourself forward. What kind of, how did you learn? The schedule, what programs were you using? How did you learn the programs? Well, the first class I had to take up was DOS. That's how far back I go. Yeah, that's called old. You know that, don't you? And so it was P3 at the time, not P6. Right. And so
I learned it on DOS. I went to premium rare classes. I went to computer classes and learned it. And then just walking the job with the superintendents. I've known how to put buildings up, so that just came easy to me. And just getting the right flow and sequence of work down and the right amount of duration on activities, putting it all together, working with good teams. That's what we did. So you went for... Primavera P3 at the time. You went to class, attended classes. Now, is
this something you did at night or did you do it like they send you to the training? They would send you to the training, you know, plus you're working with the software. I would just basically throw into it. Said, hey, we're going to give you a computer. You're going to learn it. We'll give you six months. If you don't do it, then you're going to come back to be in a system suit. Then you've done it and well that's a story that answers the story where you're at now. Well, yeah So I just learned I was always a pretty
good sponge. I could Exhaust a lot of information from different things and and Computers took to me pretty good And that that was it. Well until I got to my second job that I Still didn't want to be a schedule I mean, to me, it was, yeah, it hadn't settled on it yet. It was still a ways of means to get through the downturn of the economy. And so I remember my first review
with the company that I went to at the casino. They asked me whether I see myself in five years. And I said, well, I see myself as a superintendent. The project vice president looked at me and said There's something wrong with you Because you've already passed that Think of what you've got you don't work Saturdays. You don't have to move every five years You're home with your family every night. Yeah, you're not working the weekends
concrete pours late night So I said moment took me a while to get it. That's right. And then I seen a lot more opportunities for me in scheduling than I did because there was a lot more superintendents out there in the industry, all project managers. So at the time, there was very few schedulers. And so that's where I found my niche and hooked up with some good companies, got to travel the
world, work all kinds of different projects, airports, prisons, colleges, hospitals. Sewer treatment plants, freshwater treatment plants, casinos, run a gamut. So you've got to see and experience the time on each schedule, different types of jobs. Oh, yeah. High rises to Miami to, you know, work at theme parks here in Orlando. Right. I remember that some of the stuff we've done together where I learned from you some of the schedule techniques and the do's and the
don'ts. Yeah. And through your career. You mentioned a minute ago that you felt like you weren't in the right place there for a while doing scheduling. What clicked in your mind besides the conversation you had that said, inside, I think I'm staying where I'm at. I can do it. Because you have a natural ability with the program. I do. And so you just don't want to get tossing them off.
You just. Say, well, maybe this is where I'm supposed to be. And as time progressed and working with P3, I was actually one of their beta testers when they went on to go into the Windows version of P3. And then once we got into Florida, I was one of the beta testers again for the new P6 program they had come out with. Updated version
of the schedule. Yeah, in the early 2000s. So I've been, you know, using Primavera products, which is now Oracle's product, but it was... Back then it was Primavera. And I, you know, know it forwards, backwards, and so... So you started out in the field, you worked your way up, you took the training, you took the time to learn on your own, and... You had a little time where you questioned about, do I or do I
not want to be? Now that you've done that, what did you find rewarding about staying in the scheduling? You know, everybody has the enjoyment that they like in their field. I like building buildings, and you've come through scheduling, and it's one of the things you've always seemed to enjoy around me. I like the people. To seeing other projects, because I get to see it every other week. Where the field team only sees it day to
day, they don't see the changes. Yes, it's such a slow progress day to day, you don't notice it much. Right. But I can go back to them and say, wow, look at it, what you guys could accomplish this week. But sometimes I can say, wow, we didn't get much accomplished this week. But most of the time you... it goes well and it goes good. And you have the camaraderie of the team. And on certain teams, you get along with better than other teams. But I'm lucky I can, like a chameleon,
just kind of get inside the heads of the superintendents, try to extract what they're trying to do on the job and put it into that computer. Right. So if I can do that, then I can tell their story. And their story is how they're building that job day in and day out. And communicating it to the team. And communicating it to the team, communicating it to the owner, communicating it to upper management, who sometimes don't realize what the team is doing. And they need to get
it. Who is one of your more memorable mentors? One, two, or three of them that you had as you were growing, as you were coming up this way. And I don't mean the guy you broke the pencils at and threw them at him. He was one of them. Rick Bundy Sr. was definitely one of my mentors later on in my career when I got to Florida. When I was up in the Northeast, Ernie Barrett was the guy who was instrumenting. instrumental in getting me to go with him on his job and gave
me more responsibility as an assistant field engineer on his project. Right. And before that, it was a guy named Bob Condon who was the guy who taught me how to do the layout, read drawings, and be proficient in what I was doing, line and grade. Yeah, so your mentors and the stacking and learning your career developed you as you
made it up the ladder. Right. And had a great success and made a good living at it. Very good, yes. And now you've retired, and so there are areas, and what we're here today is to talk about the schedule and teaching and things. Yep. And when you're in this industry, What do you see as the most challenging part of today in this industry for a scheduler? The industry today
as a scheduler has become less about the building and more about the dollars and what they can get in shorter periods of time. How fast can you build it? Yeah. So if it really needs 12 months and the owner says, I want it nine. And most of the time, you know, we'll build a schedule. They'll ask us to build a schedule. How long is it going to take? You build that original
baseline and let's say it comes to 30 months. Well, a lot of these companies today, they will go and say, we can do it in 27 to 26 months. So. then you gotta go back and you gotta negotiate with the subs and your team to find where can we extract four months from what's it gonna require
right two flow lines oh two shifts what what are you gonna do you know uh how many cranes you're gonna have you gotta figure out on that and things like that you gotta put it in and a lot of times When you're forced to cut time, you don't make the schedule. It's hard to make a schedule when you're starting from behind the eight ball on your very first update. It's hard
to transition that shortage of time and convert it, because I've been on projects where they've done that, and you don't really think about it. When you cut three or four months off the schedule, Yes, we're saving the GCs for the owner of those months, but you need additional people and additional staff and additional subcontractor. Big additional cost. To bring them up. That GC savings sometimes isn't always a great dollar amount. I've had projects where the owner needs it open by a certain
day because of a fiscal period for dollar value that they have to do. in their business model outline, however they have the challenge and they decide they're going to do it. It's tough to do. And I've been on some that have been great. I've been on some that have just been a challenge. And the other thing, when you're shortening the schedule in today's time, you got to look at long lead items. You know, a transformer now to get on a project, especially if it's three,
four, 8 ,000. KVA, you don't get it in weeks anymore. It's close to a year. Well, I know switchgear during the COVID downturn was definitely 52 weeks plus. And most of the schools that they give you a contract is for a year. So how can, if you're not going to get your switchgear for a year, how can you open up? Well, you have to
do workarounds. You've got to go get rent, temporary transformers, temporary gear. And if you don't have that in your original contract, you're going to take a beating. And your schedule reflects it too. Yeah. So that's how we ended up getting through making it is get the school open and then take out the rented equipment, make the last tie -ins and get final CO. Yeah. So. So
when you're looking at a schedule, a lot of times you're taking the first blush. You're usually involved with the superintendent and the PM or the PX on this thing. And you've had to take the time. When we get our RFPs and RFQs, there's usually start on and must open by or a CO date or something. That's your controls for developing
a schedule. What are some of the most important things that you, items, people, or what you do when you're developing the very beginning schedule? Well, you need a team that is knowing the job, who's spent the time to research the drawings, understand their point of view, how they're going to build this job. now you can the worst thing that i find is when i sit down with a superintendent
and we build the schedule the way he's going to build it and the next thing we know that schedule is done on this job he is going on to another job and now we bring in another superintendent and he doesn't have buy -in on this he has a whole another opinion and by that time it's it's dead locked in because we've already did the The baseline submitted it to the owner, to the subs. They've all agreed to it. And now he's
got to live with it. And then he sometimes will not accept it. I never said I could build it that way. But if you get a superintendent who's willing to work, and little by little we can manipulate with him to make it his. then the thing goes a little bit smaller. Right. So that's a pretty good insight on some challenges to making the schedule. Have you got any other ones you
want to share with us on when you're making schedules, some of the challenges that you've had? Well, besides the time frame and the superintendents? Yes. Everybody builds their schedule to the perfect world. You don't fit the time in for weather delays. Oh, you know, well, we'll say the owner is responsible for two weather days a month, and we eat the other two. Well, if you're only
working five days a week, and you get a rain on one day, you need those four Fridays to make up time. If we give them away... So the only option is to work a Saturday to make up the loss. Or Sunday. Or Sunday. Now, because we've already lost another. Yeah. Rain day. So, I mean, it's just some of the things that I see that put in some of these contracts that I just would not agree with. And, you know, and float is what
the amount of time you have the cushion between the start of the job and when you have to turn over. So it's telling you if it's a positive 18 days, if you go once you take that 18 days and it winds up being zero, you're now critical path. If it goes negative, it's telling you you're pushing the end date out. Or on the other hand of this, if we put in a contract that we own the float, that we create, that helps us, then
it's ours. Right. You caused us to lose some of that float. It's on you. So if it's 18 days and there's a force majeure that beyond control that causes the loss, then they own it. So we have the 18 days. If it kicks down to 16 days, then they own that four days. That's actually a delay of four days. Well, they shouldn't own it if the float is ours. Right. But if they own
it. They own that. Well, what do you mean own? Do you mean the... So if the owner says that the float on the schedule is theirs. Is theirs. Correct. That's what I'm saying. If we put it in our contract, the float belongs to us. So if we get ahead on the structure and we pull in the structure by a month, we should be allowed to keep the end date the same and show the positive float. Right. instead of always making the schedule
zero float on everything. Yeah, which would, if you were 30 days ahead at that time, you would then pull the end date back 30 days. Right. And that's not... My contract finish date is X date. Now, I can hold that date there, put a finish no earlier than date on that. And anything before that we finish is ours. Right. Anything finishing
that due to us is our fault. Right. If it's not our fault, then we'll build a fragment into the schedule to show what pushed out that schedule. Right. Delay. Weather, hurricane, material, not on time, something that could push it out. The components of the schedule and the timing and the people that develop it. Your time and your
experience is vital to share when developing these schedules. Yes. And your variety of structures that you've built or buildings that you've scheduled for building. And that's an experience that you've earned and grown as you've come up through your craft. And for a new person coming into it and say, I'd like to be scheduling. One of the strong parts that I remember when I first met you was you could walk the job and I could write what
I wanted on that schedule update sheet. And you could say, no, it ain't going to happen. You're showing me done. And I can tell you right here, you got two more weeks. But we would always go back and solve an approach to keep us on target and work through it. Now, how one of the times in. as your career is scheduling your moments of fun and your logics and stuff, if you were to do this over again, would you do scheduling?
Yeah. Or I said today, yes, I would. You've had a great career at it. I've sat with you many a times. I've listened to your teaching other people on it and how the time goes. When you're developing the schedule and you have a young scheduler with you, what do you try to instill into that person? Him or her, because I've been
around women and men schedulers, and there's some good ones. What would you try to instill in their mind to get them to grow and learn the craft? Rule number one, start your schedule. It's the team's schedule, the superintendent's schedule, who lives it, breathes it, eats it, smells it 24 -7. You're there every other week or once a month, depending on how many times
you schedule. You cannot possibly know every in and out of that project. You could be up to snuff more than most people, but you're not going to know yourself. was doing on that job yeah he's the superintendent's got that mind yeah sight of the job and when he looks at that schedule he sees every little part and pieces i like having the project team participate project managers
product executives project engineers but i want it all funneled through one person That would be the lead slash general superintendent running that project. Yeah. That way you don't get miscommunication and five different stories. So the best thing I do is I ask my general is to accumulate all his data from his field staff. Right. Simulate
it into the schedule for me. Then I'll do the... the data dump put it all into the schedule see oh they do this oh they got that point this week great so you get to see it feel it taste it yourself then print it out then sit down with the project team mainly the superintendent yeah and first thing we hit is the milestones see how you're tracking see if we're hitting those dates are we coming in early are we coming out late you
know What's happened? Yeah, a lot of that. Are we maintaining? Yeah, you'll get a letter in the mail that says, oh, by the way, you're not getting your Twitch gear for eight more weeks. Well, that is when you have to build a frag net. Right. Yeah. And what we'll do is we'll talk more about it a little bit in a future reference about how we do that and where we put it in a schedule. Right. But yes. It's interesting how a young person, you know, the opportunities that you have, and they're still out there. for a
young person who wants to move up in the industry in scheduling. But a key component is understanding how the building is built so you can visualize what's being said and what's being done and how it progresses on the project. And is it accurate? And that's part of the scheduling part is you want to see that the schedule is accurate and it reflects no matter what. the true status of the project. The good, the bad, but you want,
because the good, the bad, and ugly, because if you have a challenge on a project, you can't ignore it. You need to address it and reposition, reset. talk to the subcontractors, go through the owners, drive up to the supplier who's making the windows or whatever, see that they're actually going to be made. If he says you're going to experience a two -week delay, you want to go there and see that I got the material here and I'm building them. I'll have them to you in two weeks. You got to get that comfort level. And
by driving up to those places and seeing them, whether it's millwork or windows or door frames or doors and hardware. or components of finishing that always challenge your systems gear, all of the fun stuff. Train is up in Tennessee. I like driving up there. It's a good drive. They've got a great plant, too. And when you're up there and you can look at it and see, okay, they're going to have it. So now I can go back to my schedule, and this is what we're going to do and figure a workaround with your help and how
it fits in the project. It may tell us, okay, Mr. Window Guy. Now that the delay was there, we need two crews. We need to do two flow lines. We need to do a couple of other areas. You need to find out things early, not later. Right. And the worst thing a team could do is hide the fact that they know something, but they didn't tell us about it until later. That's getting snake bit. Then it becomes, well, if you told us six
months ago. We could have did a what -if scenario. A workaround. A what -if schedule to see how that is going to impact us. Now you waited six months. We know how it's impacted you. Yeah. We could have maybe done something better six months earlier with a workaround schedule. Right. To correct it, submit it as a no -cost change order to the owner, and move on. And get it through it. And get through it. Yeah. As you can see
out the window there, Joe, it's getting daylight. And if you have some time today, I'd like to have you – I love peer reviews. I'd like to have you walk because, as you can see, we're working on our schedule here. We've got it going in our – this is our procurement phase in our contract. On the back wall, we have the actual work. I like using the string and hanging it on the wall so I can move it day to day. Making this large enough that you can actually see your progress just by looking at it. If I can make a suggestion
to you, I like what you're doing there, but I would like to see more of those schedules stacked on top of one another. So in your meetings, you can go back and say, hey, look, this update was saying we're starting here, but last update was this subcontract that you said you were going to start here. Yeah. Things like that would help you out. And you can look at it. Because you have the history. Just keep pinning them on top of one another. Yeah. Six -week look -aheads. Just keep pinning them on top of one another. Yeah. And everybody can see it. Splash, splash
like that. So if you've got time, I'd like to walk the job with you and talk to you about the project. And maybe you'll see some questions and insights for me on the schedule that I haven't considered. And then we can meet back here again and do another session and talk about scheduling and parts and pieces and some of the intricacies of the schedule. That would be great if you can find the time. Okay. Great. We'll do that here. So this is another edition. We're going to continue
shortly with Joe Westgate, our retired scheduler. Thank you. This is Joe on the job site, and we'll have another edition here shortly.
Today, Tim Ferris rejoins Joe to discuss his role within the ACE Mentorship program. How did Tim get his start working with ACE? What does Tim do to help prepare students to meet the expectations and work they will be...
Today, Tim Ferris joins Joe to discuss his career and some of the projects he’s worked on. How did Tim transition from college sports to construction? What are Joe and Tim’s experiences dealing with tornados while on a...
Today, Juan rejoins Joe to discuss the ACE Mentorship program in depth. What do ACE Mentors teach to the students and how? What kind of events and activities does ACE offer for students to participate in? How does ACE,...
Today, Juan Torres Hunt joins Joe in the trailer to discuss his intro to the industry, from his experience with his father to becoming a project manager. How did having mentors help Juan when he was trying to find his...
Today, Travis rejoins Joe to talk in depth about the ACE Mentorship program. What is the goal of ACE and how do they work to achieve it? What are some examples of events and activities that ACE uses to help introduce...