This week Steve returns to share some additional insights about healthcare construction. What are some materials in healthcare construction that require special logistical consideration? How can being a specialist superintendent help you to be more effective in identifying potential problems? How do you balance the wants and needs of an owner with your contractual obligations? Find out the answers on this episode of Joe on the Jobsite!
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Welcome back, Steve. We had a great time. I seen walking the project with you. We had our stretch and flex, which is every day for our project sites and then our morning team huddles with the superintendents and foreman's to help map out anything we need to address for the day. We do a lot of long range planning in our weekly subcontractor meeting, but the daily ones help shake out the small details that sometimes need to be addressed. whenever you're progressing
through the site yeah what do you think of our walk oh it's great man that's that's i enjoy being out there with the guys um and participating in stretching flags and and one of the things i've always strived on is to try to know know people by name and that that is very important yeah call them by name and and pat them on the back you know give them a fist bump shake their hands just random people you know, it gives them a sense that you care about them. And that just
carries on all the way through the job. We had a guest yesterday that was very attuned to that because he was taught by his father to do it, who was in the banking industry, to build that relationship with whether it's the laborer or the owner. Yeah, yeah, it's very key. You know, in our project, we've started having a 615, a little daily huddle with... some of our superintendents and PMs. I got it set up on a Teams call so people can call in if they're driving in or if they
just want to participate. And it's kind of my meeting. It's high level. Talk about what happened the day before, what's coming today, if there's any high -risk work that we got to talk about, if there's any scheduling issues that anybody sees. But it just gives us an opportunity to talk with a smaller group. And then we break up from there and then we go out to the field to do what we just did this morning with the stretch and flex and then participate in the daily huddles with the farm. Those to me are
important, not only for the team, but for sharing information, communicating the flows and the challenges. Yeah. Well, the other thing that I have noticed and feel like it's important is when you're out there talking to those. those men and women that are going to be doing the work or even managing the work. If you see somebody sitting off out of the corner or really not paying attention, you may have an opportunity to go talk to that person because they may be dealing
with something in their life, whether it's an argument with their wife or kids or a family member is sick, and it gives you an opportunity to go talk to them if they're willing to talk about it. And maybe have an opportunity not to put them in risk that day for whatever task they're doing. Because this business, as we mentioned earlier, it's all about relationships, not only with our architects and our owners and program managers, but it's the folks in the field that
do the work. And seeing that brings the point that what's really the important part. I was on a project and someone asked. uh, the owner of the company, what is the most important thing you have in your company? And he said, my people. Yeah. And from there, he said in their families and talking to that guy with this wondering and helping him people and families. Those are the
real key because they're the ones that's building the project. And if they weren't out there, we wouldn't be either. Absolutely. So go ahead. And I just think sometimes we get caught up with. Schedule, schedule, schedule, delivery, delivery, deliveries, and meeting deadlines that sometimes we forget about those people that are making it happen. Yeah. And the discussion we had yesterday was the people in making up the logistics, or earlier was the people in the logistics. In hospitals,
there are some very unique logistics systems that we have. Yep. What are some of the ones you see that you've got to plan long before they get there on how you're going to get them in the building? Yeah, it's a good point, Joe, because everything revolves around logistics. When you start that whole process, it's that. And all the way down to the nurses and people coming in and stocking the building. But some of the
key things is a lot of your imaging equipment. is that the technology is changing every single day and so one of the things that we do is is getting the owner to make decisions on equipment that helps them to finish the design and then we utilize that information to plan all of our infrastructure around around that work putting it in right and so while you're doing that then you got to figure out you know when all the doors are in your ceilings are in your floors and how
you're going to get a cat scan in how you're going to get an mri in How are you going to get your floral rooms in and get them in and get them safe and protected and kept them clean through going through an active construction site? So you would actually, like some of the imaging equipment, you would actually fly in during construction and then build a box over them? Yeah, I mean, you would want to have the box, like a typical NMRI, you'd have the room finished and have an opening left out. left out ready to put it in
or you just maybe had to set three or four panels or something on the skin then you slide that piece in uh some of the stuff will come in you know through an elevator or through the exterior door and roll down the hallway but some of those larger pieces have to be flown in and and that goes back to making sure you got you know whatever your skin is if it's pre -catch if it's metal panel is it a stucco if it's ephus creating that leave out And what does that mean throughout the course of the job and having weather barriers
in place? So you have the building in the dry, all that logistics goes back to the budget and making sure you have money in there for those things. Because I can't tell you how many times you get into a job and you realize, oh, I forgot to put dollars in there for weather barriers or any kind of special floor protection. And so, you know. a seasoned person that's been there done that with all this image equipment helps our project management team capture dollars for those items yeah so like an x -ray room that's
pretty detailed with uh the way it's put together too and has to be calculated in the time and the schedule and the coordination oh yeah absolutely because you take a typical uh you know whether it's an mri or or an x -ray room especially the ones that have lead in them You know, you're lead lining the rooms and all your boxes have to be covered and wrapped. And even the door frames have lead in them. And some architects show structural steel support to hold those frames.
Some of them show heavy gauge metal studs. Yeah, some of those doors are pretty big to get the gurneys in. Yep. And the doors themselves are heavy when they come in. Yeah. So, you know, being involved early on in the project, planning all that stuff. how you get that stuff in the building and how it gets roughed in. And it's just key. And you obviously don't want to go back and do any changes to those rooms because it affects, you know, cost and time and money. Yeah. So you're doing a hospital. What do you
think the value is of a mock -up in the areas? Oh, it's absolutely huge. Got an opportunity to work on a... a greenfield hospital in tampa several years ago and the owner said we're going to do mock -ups and in my mind i was thinking you know a room here a room here a specialized room and he says no we're going to mock up essentially the whole smoking part and we said how we're going to do that he said what we're going to do we're going to frame all the walls and we're
going to rough in the boxes we're going to come and look and see where they are and then when we sign off on then you can pipe it And I thought that was a unique way to do that. We had a group of people. We had some end users, architect, engineers. I mean, literally, the person would stand in the shower area and wear the emergency pull cord for somebody who falls to call a nurse. We actually moved a box from one side of the stud to the other to make sure it was in the
right place. Just to help in the location. Yep. And that's just one little item in all of the mock -ups. Exactly. And so we were able to do that pretty rapidly, and so it really didn't cost us any more time. But what it saved us on the back end is somebody coming in and saying, hey, that thermostat's not in the right place, or that light switch needs to be moved. Yeah, and you've got wall tile up or wall finishes of some sort. So mock -ups are critical. We're doing one now in a current project, doing an operating room. where we got the elapsed time
clock roughed in, we got the isolation panel roughed in, all the outlets roughed in, and then we'll get that signed off, and then we'll do the sealing system. We'll bring them in and let them do the sealing system. Yeah, because that's a lot of surgical lights, and they're not light. They usually require steel supports. Yep, and with all these specialized surgeons you have nowadays and specialized procedures, These physicians want these lights in particular locations, the big monitors where they can see what they're
doing has to be in exact locations. So there's a lot goes into it, and you only have one time to get it right. Yeah, one time. That makes the mock -up worth every dollar you put into it. Absolutely. I've done them over the years where you hang cardboard and mock -up TVs. Booms. Wall backing. Wall backing. Med gas rough ends. All that stuff. And if it's done right and people
buy into it, it definitely helps you to have a successful project on the back end. I remember seeing on the drawings, med gas walls or the head walls have very detailed layouts and what goes where. Heights, distances from the edge, even where the head of the bed hits is even laid out and outlined. So you have to get it right the first time. yeah because a lot of people that are not are not healthcare people they go into a patient room when it's all finished and they just see a few things on the wall you have
no idea what's behind those walls yeah and and getting it and getting it in its in its right location um for the end users is is really key on on taking care of patients you know we talked earlier about patients and and and If not all healthcare providers or healthcare systems wants the best care for their patients and they want to have what they need in those rooms to give that best care. Right. And one day, like you
mentioned earlier, we might be there. Exactly. Right. Yeah. So along your career, you've done quite a few hospitals, which is for reference part. Could really say you're a specialty superintendent. Yeah, I don't call myself a specialty superintendent, but there are. You know, you have superintendents. I work with a guy that actually lives in Orlando.
I think he's retired now. And he was a structure skin guy. He didn't care about... drywall or the doors inside the building he was all about getting the structure built and the skin roof zone windows in and and all the components that go with that and then once that's done he moved on i've worked with superintendents that were special to specialize in imaging uh imaging departments you know you take a you take a hospital most of your imaging equipment is on the first floor
and some of those compartments depending on the facility are 20 25 000 square feet It's just absolutely packed full of imaging equipment. And that's really all they want to do. They don't care about a kitchen. They don't care about a, you know, a patient room or ORs. They want to do imaging. And so you get, you definitely have some specialized people in the field. You know, I think I told you earlier, I worked on a project here in Orlando. It was a parts distribution
center. Really one of my first experiences with floor levelness and floor flatness the ff yes sir and so uh and this this project had what they call super flat slabs yes and so there's a whole process of how you put those in and how the concrete is cured and how it's sealed and and i was amazed that there was that side of the business that i had never been exposed to years ago when they were building the vab vehicle
assembly building out at our favorite uh place on the coast right or the company i worked for was hard to do the super flat you don't think much about the undulations and how they can affect a forklift and these were robots that were pulling parts and doing the stuff and you don't really think about it but when your rack is 40 feet tall with the parts And that thing is just a little out of level, and it telescopes up to
get that part rack and pull it down. That's a lot when you put 40 feet on it in either direction on the top. It can make a difference of the load. Oh, yeah. And I built a track for an Indy racetrack, and it had walls around the perimeter. And they were leaned, and as they traveled around, the lean increased and decreased. So the Indy guy came down and we punched the walls and he said, you're going along this wall at 160 mile an hour
and you have something sticking out an eighth of an inch. He said, if it sticks out a quarter, you could total the car. We went around over a mile of track checking for that. And I walked it with him for three days, marking and checking so that we could have it right for that racetrack. Yeah. And those are the kinds of things that. that we as senior level superintendents need to share with our young people. Just plant the seed. Sometimes it's just a matter of planting
a seed. And so they remember that. And it's amazing the things that you remember and the things you don't remember. But it seems like things like that you just described sticks to people and they remember that. And how that correlates with healthcare facilities. you know you have an operating room and and most everything in an operating room now has wheels on it right so it's easy to move in and out for cleaning and that kind of stuff and so you want to make sure that if
you set something up you don't want to have to lock the wheel you want to set it there and it not roll uh so having having not necessarily super flat slabs but having level and flat slabs in operating suites And wherever we have, you have gurneys where patients are being traveled around, you know, so many times nurses get distracted, you know, as they're moving a patient around and they'll stop and talk to somebody or handle something else. You don't want a patient rolling down the hallway if the floor's not level. That
would be an unfortunate sight. Now, but you've, you know, I use the reference specialty contractor and, but. You've done a lot of health care in your career. And in that, in mentoring other people, as you spoke about your mentors as you were coming up, there's a lot of things that you realize quickly right off the shoot by looking at the drawings that might take someone else a while to think of. You know, I've done a variety
of projects, maybe five health cares in my entire career. I've done nuclear power plants. Tunnels, directional boards under buildings, movie sets, hospitals, hotels, theme parks, and all other kinds of systems. And the one thing that I remember from doing each one, especially their one -offs, but they're not all the same, is you got to look at it. And I had to work at finding the details and digging through the drawings to put the vision
in my head of 3D to build it. But you would walk in in a hospital job. with your experience and go we need you've got it already clicking and picked up yeah and and a lot of that just there's years of experience and that's what i try to communicate with with our young people uh had a had a little situation the other day um related to louvers so on the exterior of the building so the the mason was out there hey steve i need
the louvers laid out I said, well, you should have the submittal already. And he goes, well, I think our office has it, but I don't have it. So I called the project manager. Project manager says, I'll send it over to you. He sends it over to me. I start looking at it. And the submittal was perfect. You know, the size of it, the width and the length and all that stuff, the specs, the NOA information was in there. But what it didn't have, it didn't have the dimension off the center line of a column. or the elevation
off the floor so we had to start digging through drawing it took us several drawings to try to find that information and there was a couple dimensions that were missing that we ended up having to call the architect and get the information so we can get it in the right place yeah and it's that kind of stuff that that the that our project management team are reviewing submittals and i try to tell our team is is you gotta you gotta you gotta You've got to pretend that you're building it, you're installing it when you're
reviewing that submittal. And sometimes we don't have the time to do that, but I said it's okay to come and talk to us as superintendents. Hey, take a look at this. And I've got a couple of people that are really good about coming and talking to me about particular items. Yep. And that's a key issue or key point when you're with your field team and all the things that you're doing. Yep. is coordinating with PEs and the PMs on the products. A lot of times they just
get worked through the system. And it's important that superintendents are very busy. They have a lot on their mind and a lot on their plate. But taking that time sometimes to take a look at that yourself. Yeah, absolutely. And I've got to a point in my career where I'm not in the weeds as much as I used to be. I miss that. But I've got to a point to where, you know, our project, we have, you know, almost 30 people on our team working. And I've come to realize
I can't be involved in every situation. That's true. I can't be on every email. I can't be copied on every email. But that's why we mentor and train and foster good communication across the teams. Yep. And you'll agree that when you have a big job like that and so many different team members trying to get everybody to communicate is key. You know, we mentioned coordinating all
this stuff. And it's no disrespect to the architects and engineers, but they do the same thing. They work in vacuums sometimes. You know, the mechanic guy's over there. He's designing duct work. to to meet his criteria for his end results and and then come to find out that the duck is too big and the ceiling's got to be lowered with architects over here saying you can't lower the ceilings and or and electricians designing can lights that won't fit underneath the ductwork
that has to lower the ceilings down again so us as senior level people getting involved early on to talk about some of those things just planting the seed with them yeah And in being involved in the BIM and Revit process, you know, I sat in on several meetings through the course of this job with our BIM and Revit team. And I sat there and listened for 45 minutes of things that they had under control and they were doing a good job. And then there was like three minutes
of a discussion that really meant something, that I was able to offer up some. my opinions and suggestions that hopefully will save some time and some changing out down the road. Right. So kind of back to the specialty, there's nothing wrong with being a specialty superintendent. It's an advantage. There's nothing wrong with any area a superintendent covers. I didn't want to leave that kind of taste in anyone's thought.
Relationships are some key elements, and we touched on those earlier. And you mentioned where you had did five projects for one owner. And it was repeat business to one owner. That carries a lot of merit as far as the teams that were on that project and the people and their attitudes and the relationships that were built with the owners and the architects and engineers through
those five projects. That's not very often you see a company or a superintendent on five projects with one owner. No, it is. It's rare. But I just want to go back and touch on the specialty superintendent. You know, me at my level now, I would love to have a few specialty superintendents because it would give me a comfort level to know that my guy that's doing the imaging, he knows what he's doing. Very true. You know, so. It's OK.
It's OK to be that specialized guy. But understand that not every not every job has particular piece of equipment or or areas that that are your expertise. Right. So I just wanted to let that get that out. I agree with it. It's important for people to to gravitate to what they what they like and their passion. Right. And that's the key element. You've got, you don't want to wake up at 50 years old, knowing you're 20 years from retirement going, man, I really hate my job. Yeah. Having,
and you said it earlier, you fell in love with the industry. Yeah. And that's what you like to do. I went through the same thing with myself and it's key. Get your fit. You're happy. You earn a good living. And that's what life's about in the family. Yeah. And, and, you know, to go to the, go to the relationship. piece of this business I have been accused over the years of being uh of being an owner's superintendent looking
out for the owner kind of what we're supposed to do we we are but I will tell you it it is a it's it's a fine line right because we all have a contract we have to we have to build by or build under and we're all tied to that contract but we also need to listen to the owner as well on what they on what their needs are because you know as drawings get developed uh they're not builders owners are not builders doctors
are not builders right it's not built and we start building things they realize oh i didn't realize it was like that and so that's why i've always encouraged us to bring facility people out the presence of the hospitals that i've worked with out and walk the job so they can see the progress And that builds respect. That builds trust. And I've always told, if you go to these presentations and you sell, you're selling yourself.
People tell me I'm good at it, but I don't think I'm good at it. But once you win that job, then... you're proving yourself that you're doing what you promised, right? And then during that course of that job, you're actually winning the next job and you don't even know it. Yeah. By being nurturing the owner, the architect, and in some
cases, program managers in that process. And you know, when you think about it, our ultimate goal on the project. is to deliver a project to the owner that meets their needs and their functions and their vision for their product. And if we don't do that as a team, we miss the goal marker. Absolutely. Because they like the on time, on budget, and fits their needs and
works with what they had envisioned. And sometimes you get into some tough conversations when an owner didn't understand what was on the drawings. to what's really in place. And our goal is to help work through that too. It's one of the relationships you have. You know, we got a few minutes left, but I'd like to hit on logistics. The project you're on has some very unique logistics. It's a hospital. It's active. You're working around active underground, active overhead, and some
of the challenges you have. If you were going to talk about logistics, some key things that you dealt with, we touched on the elevation of the building earlier and that you lowered it for work until you have to bring it up to the 13 elevation to finish and pour the slab. Yeah. What were, what's some key thought and logistics you would like to share when you're working on something of this site? Well, the current project probably from a logistics standpoint is probably the most challenging. projects and it's probably
around that 10 number uh we have we have no we have no on -site parking yes that's right everybody was bust so everybody is bust over uh over to the job in the mornings in the afternoons we have constant buses running throughout today you know that's been a big challenge now that we're now that we're we're actually working two shifts and up until about a week ago we were working pretty much around the clock other than Sundays. Right. And so we close the loop road
down at night doing precasts and underground utilities that's in the roadway. So, you know, making sure that we keep the hospital operation and trying to meet with them and letting them know where we need to be because they have, you know, an active hospital has deliveries 24 -7. And people coming in and out. Yep. I mean, medical supplies, the dumpsters, the red bag dumpster folks are always there throughout the night. Right. And so managing not only our operation,
but letting the owner know what our operation is, understanding their operation, and what do we need to do to do our work, but also keep them in operation. You know, even from a noise perspective, dealing with noise and disruption. That's right, Kent. Whether you like it or not, they're sleeping at night. They're sleeping. They're sleeping at night. And so trying to be, I mean, even the simple thing is when you're flying material, you know, everybody's got a whistle and they're
blowing the whistles. And the backup bell's on the equipment, you know, talking about what you can do to muffler those noises. And then just our office is, you know. quarter of a mile away and so having you know buggies or gators going back and forth right walking and and if it's raining and bad weather you know all those components but i and on this particular project those utilities i mean we're right up against the main oxygen bulk tank and so we've got we've got protection
there over the over the exposed piping A nail fall from the eighth floor and puncture a copper line or one of the lines on the evaporator. The system goes down. And you've got babies up there in the NICU that you can hold a little baby in your hand that's depending on that oxygen. And we're working next to that oxygen line. And trying to get that message down to all the workers.
And I'm talking about, when I say workers, not the foreman, not the superintendent, but the guys that are out there driving nails, running the screw gun, sweeping the floors, moving debris around. All it takes is one little accident, and it's a disaster for those patients. Right. And there's no way around that part. Nope. And the only way is to not let it happen. Yep. And so we know as superintendents, You know, not
having, you have to be humble, right? So when, and know that you have to utilize the people around you to support what you're doing, your thought process, you're collecting all this data and you need it from everybody. We don't want anybody on the team that don't have a voice. Right. Because. Somebody remote offsite that don't know, or even the, some of the young people coming in that, that thinks about something,
listen to them. It could be something you should need to consider. I agree with that. Yes. I've always tried to lead by example. I've always tried to want everybody to have a voice. Right. And, but I've also told people that if you have a voice and we have. have can't agree on a situation moving forward that somebody somebody along the way has to make that final decision right in
more cases than not it's it's either the superintendent or the project manager making that final decision right but at least you've let everybody else hear uh you've heard their voices yep yeah you know today we've had a lot of good information shared and I think our viewers are going to enjoy it. I appreciate you coming out today, Steve. Thank you. Especially for driving all the way up to Tampa and it was 36 degrees outside. It's cold in this little place, isn't it? Yeah, it
is cold. I thought you had the heater up a little better in this office. I don't think he's working on it while my feet are cold already. So thank you for coming today. We appreciate it greatly. And we'll look forward to. If we have some more time, we might dive a little deeper in some of the details. I'd love to do that. And thank you for having me, Joe. Appreciate it. Thank you. This is Joe. This completes another edition of Joe on the Job Site. Thank you.
Today, Tim Ferris rejoins Joe to discuss his role within the ACE Mentorship program. How did Tim get his start working with ACE? What does Tim do to help prepare students to meet the expectations and work they will be...
Today, Tim Ferris joins Joe to discuss his career and some of the projects he’s worked on. How did Tim transition from college sports to construction? What are Joe and Tim’s experiences dealing with tornados while on a...
Today, Juan rejoins Joe to discuss the ACE Mentorship program in depth. What do ACE Mentors teach to the students and how? What kind of events and activities does ACE offer for students to participate in? How does ACE,...
Today, Juan Torres Hunt joins Joe in the trailer to discuss his intro to the industry, from his experience with his father to becoming a project manager. How did having mentors help Juan when he was trying to find his...
Today, Travis rejoins Joe to talk in depth about the ACE Mentorship program. What is the goal of ACE and how do they work to achieve it? What are some examples of events and activities that ACE uses to help introduce...