An introduction to MSL's ISAMS, explaining core building blocks, tracking drawings across nineteen stages, managing stock reservations, and key rules for new users navigating the system.
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Hello, and welcome to ISAMS Explained. This is the Level 1 episode: the big picture. If you're new to ISAMS, this is the place to start. In about fifteen minutes we'll cover what ISAMS is, how a drawing moves through it from the day it arrives to the day it's handed over, and where your part of the business fits in. As with all our episodes, this is a scripted walkthrough of how the system is actually built, and the voices are computer-generated. I'm joined by our Systems Director. Welcome. Thanks. And a quick word on how the series works.
The hope is that this episode will provide the listener with an overall understanding of the ISAMS system. Don't worry if there are any particular details that you do not follow fully on first pass. There will also be a Level 2 overall podcast to follow on from this one that will delve a little deeper into the overall ISAMS picture. the systems department will also be producing narrated videos with supporting screen shots. These will be more detailed 6 to 10 minute videos and each will be focussed on a
specific topic or function. Personnel can pick which of these videos are pertinent to their tasks and ensure that they are getting full systems support to complete these Let's tasks. start with the name. What does ISAMS stand for? Isometric Administration and Management System. An isometric, or iso for short, is the drawing a piping engineer produces for a run of pipe. It shows every pipe length, elbow, flange, valve, gasket and bolt set on that run.
In piping work the iso is the go to fundamental point of reference for all. Everything we buy, store, fabricate, weld, install and get paid for traces back to an iso. ISAMS is built around that idea. And it's our own system? It is. It was conceived, designed and developed in-house at MSL. It is a totally bespoke system customised to MSL's own needs. It is made using a relational database platform owned by Apple computers called
Filemaker Pro. it is a cloud based system running on our own cloud server. You open ISAMS via the FileMaker Pro app installed on your PC or Mac. Everyone is working on the same live data as everyone else in the company. Drawings, product alignment, procurement, goods received, material used, intelligent stock control, smart tools for production and client reporting and invoicing. All in one place, shaped around how we actually work.
How big is it, roughly? Big enough that it pays to understand the structure. There are over forty thousand isometric drawings in it, over half a million component lines on those isometrics, around 50 thousand products in the catalogue, and several thousand purchase orders. That's why the structure matters. You don't scroll through ISAMS. You find what you need. And does everyone see everything? No. Access is by role.
When you log in, your account has a privilege set: engineering, engineering super user, commercials, goods in, read-only, and so on. That decides which screens you can open, which fields you can change, and whether you see prices. So if a button you've heard about isn't on your screen, it's usually because your role doesn't need it, not because something's broken. What are the main things I need to know about? Five building blocks. Projects, isometrics, isometric components, the product catalogue,
and purchase orders. Get those five and the rest makes sense. Projects first. Every piece of work belongs to a project, and each project has a short job code. You'll hear codes like IN06, NN01, ES01 or SG01. The project holds the client, the site, the format the client's files come in, and the project's own product catalogue. When you see a list of isometrics or products, it's almost always filtered to one
project. Then the iso itself. The isometric record is the heart of ISAMS. One record per drawing, per revision. It holds the isometric number, which is the client's drawing number, the MSL reference, the revision, the pipe spec, the service, the location and module, the workpack, the attached PDF drawings, and its stage. The isometric form has tabs along the top for summary details, components, engineering, welds, flange boxes, the spool log,
attachments and more. Most people spend most of their day on that one form. You said per revision. What happens when a drawing is revised? A new revision comes in as its own record, and the old one becomes superseded. Every isometric has a status: live, superseded, cancelled, or on hold. And this is one of the most important ideas in the whole system. Only live isometrics count. The live drawings are the ones issued to the shop floor.
Material demand, reports and readiness all work off live isometrics. A superseded drawing stays in ISAMS for history, but other than recording this history and potentially some commercial implications, it doesn't drive anything. Next, the components. Each isometric has a list of components, the lines on the drawing. The MTO, the BOM, we have different acronyms for it. These MTOs are extracted from the drawing using our bespoke AI technology and
converted to a certain format of an excel file for uploading. Each line has to be aligned to a product code and has a quantity, a size, a spec and a category, like pipe, fittings, flanges, valves, gaskets or bolts. Pipe is measured in metres. Everything else is a count. Those lines come in from the client's drawings through an automated process. This allows us to process large numbers of drawings very quickly, nobody types anything in by hand.
And the product code links to the catalogue. Exactly. The product catalogue is the list of everything we buy for a project. Each product has its description, size, spec, supplier, price and a product class. The class matters. Fabrication products go to the spool shop. Assembly products go out for site assembly. SPS products are secondary pipe supports, which have their own simpler route. And Other covers anything that's none of those.
The catalogue form also shows, for each product, how much is on live isometrics, how much is ordered, delivered, in stock, reserved and available. And the fifth block, purchase orders. A purchase order in ISAMS is the order to a supplier, with a line for each product and quantity. Each row of the purchase order contains the full technical details of item including its spec and size. It also cites the SAP purchase order number once the order has gone through SAP,
because SAP is our finance system and the only route for payment. ISAMS also uses the engine of the purchase orders to generate and issue requests for quotations to suppliers. The complete technical descriptions of all items ensure that the quotations received are accurate snd valid. So how does a drawing actually travel through ISAMS? Through stages. Every isometric sits at a stage, and there are nineteen of them. You see them as a coloured strip across the top of the isometric form,
and the current stage is highlighted. You don't need to memorise them today, but it helps to hear the shape of the journey. Go on, then. The first three are about getting the drawing in and bought. Stage one, Issued to Systems: the drawing has arrived and been loaded. Stage two, Issued to Procurement. Stage three, Processed by Procurement: procurement have checked it and the material is ordered or in hand. Then fabrication.
Stages four to nine are the fabrication track. Four and five are about stock: partially reserved, waiting on fabrication items, and then fully reserved, ready for IFF. IFF means Issued for Fabrication, and that's stage six. Seven is Issued for Fabrication Picking, when stores are picking the material. Eight is Fabrication Picking Complete. Nine is Fabrication Complete: the spools are made.
And assembly runs alongside? Alongside, yes, on its own track. Stages ten to fifteen mirror fabrication for the assembly material. Partially reserved, fully reserved and ready for IFA, which is Issued for Assembly, then assembly picking, picking complete, and Assembly Complete at fifteen. An isometric has two pointers, one for the main track and one for the assembly track, and the assembly track can start as soon as procurement have processed the
drawing. And the end of the road? The two tracks meet when an isometric reaches stage 16. From this point and onwards, ISAMS is just a basic reflection of the status that the isometric achieves on EIDA. Stage 16 is when Testing is Complete. This requires that both fabrication and assembly are finished. Then seventeen, Reinstated Fully. Eighteen is Painting or Insulation Complete And finally nineteen,
Handover Complete. That's the drawing's whole life, from the paper of the isometric to handed-over pipe, tested and installed on site. Who moves an isometric from one stage to the next? It depends on the stage. Some moves are made by people, on the stage drop-down or by clicking the strip, and ISAMS checks the move is allowed first. If it isn't, it tells you what's missing. Other moves are made by the system as a result of real work: reserving stock moves
an isometric to four or five, issuing a pick list moves it to seven, completing the pick list moves it to eight. That's deliberate. The stage should always tell the truth about the drawing. You mentioned secondary pipe supports earlier. Do they follow the same journey? No, they have a shorter one. Secondary pipe support drawings, SPS drawings for short, are loaded into the isometric section so their material can be ordered and tracked, but they have their own short stream: issued for fabrication,
picking, picking complete, fabrication complete. On the isometric form they get their own, shorter stage strip, so you can tell them apart from isometrics at a glance. Let's follow the material. Where does buying start? With the import. The client sends drawings, a transmittal of PDF documents to our doc control. As mentioned earlier, we run these drawings through our bespoke AI system and generate a specific Excel file for each one.
This contains the material list per drawing, it detects opes on the drawings and can read the valve or instrument tags on the drawings. Systems load those into ISAMS, and the import reads each material list into component lines and matches each one to a product code in that project's catalogue. Some products automatically bring companion items with them. A pipe shoe, for example, can add its pad, U-bolt, nuts and washers, because the client's list doesn't include them but we still have to buy them.
So once the lines are in, how does procurement know what to buy? The main tool is the Summary of isometric Components. You find the isometrics you're interested in, open Smart Tools on the isometric form, and run that report. It gives one row per product: how much is needed on live isometrics, how much is on order, how much has been delivered, and the shortfall still to order. That shortfall is what turns into purchase orders. And what counts as ordered?
A purchase order counts as ordered once it has been issued with a SAP number or is a free issue PO from a client. Some purchase orders can be flagged as RFQ only - requests for quotation. This is where we take advantage of our automated system that has populated up the purchase orders with all the necessary details and we pass these on to suppliers to get our quotes. Then chasing the supplier. That's expediting. Each purchase order has expected delivery dates, either for the whole order or line
by line, and an expediting log of every contact with the supplier. The Expediting Centre pulls together everything that needs chasing and everything that's late. There's a short episode just on that. And when the delivery arrives? Goods in books it against the purchase order as a GRN, a goods received note, line by line, with the delivery docket number. The docket PDF and the material certificates are saved against the order, so anyone can open them later.
From that moment the material is in stock in ISAMS. How does ISAMS keep track of stock? As a ledger. Every movement is a line: received, reserved for fabrication, reserved for assembly, transferred between product codes, written off, and so on. Nothing just changes a number. So you can always see why the stock is what it is, on the Stock History tab of the product. The headline figure people care about is available: what's in stock that isn't
already promised to another isometric. Promised how? By reservation. This is a big idea, so it's worth a minute. Before an isometric is issued for fabrication, ISAMS reserves the exact material it needs, item by item, in priority order. Once it's reserved for one isometric, it's no longer available to the next. Without that, ten drawings could all look ready while sharing the same ten elbows. Where does that happen On IFF Preparation for fabrication and IFA Preparation for
assembly, both in Smart Tools. The readiness report shows each isometric with a coloured chip. Green means everything's available. Orange means something's on order but not yet here. Red means something isn't ordered at all. From there you allocate stock, and fully covered isometrics are reserved and move to the queue, ready to be issued. And if an isometric is nearly ready but one item's missing? Then it can be issued with exceptions.
The available lines are reserved, and each missing line becomes an exception: a quantity the stores still owe that isometric. Exceptions sit on the Exception Queue until stock arrives and they're filled. Nothing is quietly forgotten. So the isometrics issued. What happens on the shop floor side? Stores get a pick list. Issuing from the IFF or IFA queue creates a draft pick list that pools the reserved material by product code.
Once it's issued for picking, stores pick it, confirm each line as full or short, and complete it. That's what moves the isometric from seven to eight, or thirteen to fourteen, and books the material as used. And welding? Engineering assigns the welds on each isometric, one line per weld. This gives us a base to help populate up the weld log. It also gives us the weld count per size which allows us to calculate the weld
inches on each isometric and it allows the commercial department to know how much to charge the client for the welding on the isometric. What about spools? The spool log on the isometric records each spool made from the drawing. If a spool has a problem, it can be put in quarantine with a reason, and the Quarantine Register lists every quarantined spool by project, so nothing defective goes out to site by mistake. You mentioned the commercial department and charging the client.
Can you expand on this somewhat? Yes, of course. A very large part of ISAMS is generating what the commercial department calls the measure. This is basically where we charge the client for every isometric that we fabricate and install. To charge the client correctly not only do we have to have an entire list of every single component that was used, but we also have to charge for welds and flange boxes, insulation, cladding, etc. The commercial aspect of ISAMS is only available to people working in the commercial
department but our ability to very quickly populate the measure, and have that as a running tally throughout the lifecycle of the project is a great benefit and value to MSL. Some of the measures for projects can be 100 thousand rows of information so that scale alone can provide us with challenges. The material we are tracking so carefully, what about getting it to site? Material for site goes out on an MTR, a Material Transfer Request, which lists what's going where and for which workpack, with its own status steps.
Workpacks themselves are how the site groups isometrics into packages of work, and there are reports available on ISAMS that show the status of all isometrics within any pack and the status of all the material on these isometrics. That's a lot of screens. How do I find my way? Three things. First, the Main Dashboard. It's the home page, with buttons for isometrics, the product catalogue, purchase orders, suppliers, goods received, delivery dockets,
MTRs, workpacks, modules and projects. Second, the isometric form and its tabs, where most of the day-to-day work happens. Third, the Smart Tools button on the isometric form. It opens a menu with two halves: Production, for IFF and IFA preparation, the queues, pick lists and exceptions, and Reports. What reports are there? The Summary of isometric Components, the Full Isometric Report,
the Measure reports, the weld reports and the Quarantine Register. They're built on the server, so they're quick even over a slow connection, and most have an Excel button that exports exactly what you see on screen. You keep saying find the isometrics first. Because it's the single most important habit in ISAMS. Almost every report and tool works on your found set: the records you've currently found on screen. Find the project, or the workpack, or the isometrics you care about,
then run the tool. If a report looks wrong, the first question is always: what was my found set? Before we finish, what are the golden rules for a new user? Five Rules that I would recommend for the beginner. number. One: everything hangs off the isometric and the product code. Get those right and the rest follows. number Two: only live isometrics count, so check the status before you trust a number. number Three: use the proper route.
Move stages with the stage controls, reserve with the preparation screens, pick with pick lists. Don't try to type over a stage or a quantity to make a screen look right. number four mind your found set. and finally number five, if something looks wrong, say so. The system is developed in-house, changes are backed up and tested offline before they go live, and problems you report get fixed. And what's next? Level two which goes a step deeper: how revisions work, what each stage gate checks,
how the stock figures are worked out, how reservation and exceptions really behave, companion items, workpacks, and who's allowed to do what. Thanks very much. Thank you too. That's been ISAMS Explained, Level 1.