Meta "paying their own way" on $1 billion data center in east Tulsa
TULSA, Okla. - In a room five stories above Black Wall Street, Oklahoma political leaders, Partner Tulsa and representatives from Meta announced the official groundbreaking of a new data center that will bring over $1 billion in investments to east Tulsa, despite environmental concerns from some residents who protested outside the event.
The AI-optimized Tulsa Data Center will mark Meta’s 28th in the country, 32nd across the globe and its first in Oklahoma, the company announced. At more than 2 million square feet, the data center is located at the Fair Oaks 2,000-acre industrial innovation park in east Tulsa.
Meta says the project will support roughly 1,000 construction jobs and 100 operational jobs after completion. The company also said it will invest $25 million in infrastructure costs, partner with Tulsa Tech and Tulsa Community College on local workforce development, and assist low-income residents with water and utility bills. It promises to replenish the water it uses and eliminate added energy costs for rate payers.
“It’s one of the largest private investments in our state’s history and direct investment, really in Oklahoma’s future,” Gov. Stitt said during a press announcement closed to the public. “Meta could’ve built anywhere in the world, but they decided to build in Oklahoma.”
Five stories below, a group of protesters formed outside the entrance with signs and chants expressing concern over the impacts to water, energy and land. In a response to questioning from In Depth With Deon Podcast, Gov. Stitt described those concerns as “legitimate.”
“I think what people are concerned about is, is my electricity bill going to go up? Are they sucking all the energy out of the grid? That’s a legitimate question,” Gov. Stitt told IDWD. “Or what about water? Is my water bill going to go up? But I think if you answer those two questions, like, these guys are paying for their own water, their electricity, the infrastructure, none of that is on the rate payers. And that’s really all we’re concerned about.”
Not all residents see it that way. Cheyenna Morgan is Coalition Coordinator for Stop Data Colonialism.
“Energy isn’t our only concern. Obviously, we’ve got concerns about the water. What we do today affects how our future generations will be impacted,” Morgan told IDWD. “They’re requesting massive amounts of water.”
For “Regular Tulsans”
The project’s groundbreaking comes as Tulsa seeks to become a national leader in the accelerating tech economy. The investment from Meta opens up a part of the city that has lacked development, amenities and jobs, says City of Tulsa Economic Development Director Erran Persley.
“So, for regular Tulsans, this really opens up east Tulsa,” Persley told In Depth With Deon Podcast at Tuesday’s groundbreaking. “That’s going to be thousands of new homes. It’s going to be retail outlets out in East Tulsa. They’re not there now. It’s going to be park space, open land, and it’s going to be jobs.”
Partner Tulsa, the city’s economic development authority, praised the project after years of planning. Meta’s plan includes supporting community organizations like Eastside Rise to expand community gardens and public art. Formerly referred to as Project Anthem, the details of Tulsa’s first data center had remained private until Tuesday’s groundbreaking.
“Projects like this remind us that economic development is indeed a team sport, and it takes all of us working together to bring these projects on board and to get them moving forward,” said Michelle Barnett, Senior Vice President for Economic and Workforce Development at Partner Tulsa.
Community Input and Water Output
The celebrations and cheers from state leaders and company officials at the Vista at 21 stood in stark contrast to the chants of opposition from protesters on the ground level shut out from the private event.
Communities around the nation have expressed strong opposition to data centers in recent months, and Oklahoma’s two largest cities - OKC and Tulsa - have passed moratoriums on the construction of new projects. Tulsa City Councilors carved out an exception to the moratorium for Meta’s Tulsa Data Center.
Cheyenna Morgan of Stop Data Colonialism questioned the process.
“There’s actually also been no community engagement on this project. They’ve been seeking out this project for four years, and this project has been approved for two, and there’s been no meaningful community relationship building,” Morgan said.
The Environmental and Energy Study Institute (EESI) is a science-based educational resources for policymakers created in 1984 by a bipartisan group of Congress-members. It estimates a large data center can consume over 5 million gallons of water per day, or enough to supply a town of 10,000 to 50,000 residents.
Meta announced plans to make the Tulsa Data Center “water positive” by 2030, claiming the company will restore more water to local watersheds than it consumes.
“We’re partnering with Phytech on a water restoration project that will provide irrigation technology to Tulsa area farmers to help them minimize water withdrawal while optimizing yields, saving energy and reducing costs,” Meta stated in a press release.
The 10-year goal is to use Phytech’s plant-sensor technology to save over 50 million gallons of water per year.
“They’re creating these narratives like water neutrality, when, in fact, the water neutrality is manufactured by them to make it sound like they’re putting more water into the communities that they’re taking water from,” Morgan said. “You can’t un-pollute water. You can’t remove the chemicals that will be put into these facilities to cool these facilities. You can’t restore watersheds.”
Subscribe to In Depth With Deon. An independent media platform that amplifies the voices and stories that too often go unheard.
This is a public episode. If you'd like to discuss this with other subscribers or get access to bonus episodes, visit indepthwithdeon.substack.com/subscribe
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.