The latest On the Move episode provides an update on the temporary closure of two lanes on SR 369 across the SR 400 (Exit 18) overpass, including the results of a monitoring period and next steps toward opening additional lanes of traffic on the bridge. #foco #forsythcounty #onthemove
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Chapters
Intro
Project Update
Traffic Impact
Traffic Flow
Layout Issue
SR 369
Baldwin Paving
Cost
Transcript
From the show. Tap a time to play from there.
[Music] hi and welcome back to on the Move where we go behind the scenes of some of fry County's larger construction projects today we're back in North fory just over my shoulder is the exit 18 overpass at Sr 369 and sr400 we got a lot of details to talk about here today and a uh plan for moving forward with this bridge before we get going let's introduce everybody to my right is John Jefferson director of capital projects with fory County Elliot bat is from Vertical Earth
and another partner on the project is Matt wlaw from the Baldwin Paving Company gentlemen thank you so much for coming up this morning thank you well let's dive right into it a lot to unpack here today let's start with where we are with this project today John I know you and I have talked about this bridge several different times including earlier this year we knew there was some monitoring going on with this bridge so what's the latest right so the monitoring period has come to an end um we've had our third party experts um Analyze That data any settlement that was occurring in the uh West approach
ramp embankment has ceased the primary settlement has ceased we also part of the reason we initiated the monitoring phase was we were looking at some cracks that were appearing in the bent one stage one cap which is the um West in bent on the north um side of the bridge so what we're looking at with that is in case you missed up one from earlier this year it's just off to to my left shoulder here underneath the signage that you'll see here if you're heading Southbound on 400 it's that side
of the bridge heading west on the Walmart side of uh of the exit there the the biggest question of all that I think everybody wants to know with this and with the work that's been going on with this bridge and and just to go ahead and clear the air right now is this bridge safe and has it been safe sure I have I have done these with you um Russell and I've stood on the bridge and said the bridge is safe the bridge is safe it's not going to fall down it never was going to fall down we're dealing with issues that um if they're not corrected
they're going to they're going to shorten the use useful lifespan of the bridge okay so now that the monitoring period is over we've seen that that settlement has ceased there on that side of the bridge so what is the action plan what is needed to to occur now and uh and what's the partnership with everybody going to look like in that plan sure so um we issued a notice to proceed we we've been working with ji in in the background behind the scenes to come up with a solution that that they're acceptable with uh and that we can get the contractor to execute so
last Friday the county issued a notice to proceed to the contractor to begin the the repair process it looks like that's going to involve taking down span one stage one of the bridge so that's the the seven beams over 400 Southbound on the north side of the bridge in order to get to the cap that that supports the West End of those beams to repair a what what appears to be a layout issue when the bridge was originally constructed and
when we start talking about taking a part a piece of the bridge what we're talking about correct me if from wrong uh is going to be the the the portion that we're looking at here just off to my left shoulder the the the west side there the portion that's already closed anyway is that is that a fair statement that's correct yes okay uh Elliot maybe a question for you with with Vertical Earth and the contractor of uh of this work what are we looking at as far as a timeline for this kind of work we're uh we're looking at about 9 months for the the bridge work uh uh to be completed um
and then probably another 3 months to finish all the uh other work to tie the road back in and and and finish the the median on the bridge and and get this project completed and closed out okay so we're looking at sometime later next year this being done now that doesn't mean that we're going to have insane closures here on 4369 right what's that what's that going to look like for that work when it comes to traffic impact with those that are commuting right here traffic is going to continue to flow the way that it is today there will be some
traffic pacing as they disassemble uh that that span one of the bridge of course as they installed the new beams as we know traffic today it's going to continue to flow in the same patterns the rants are going to continue to remain open um and and the traffic pacing and in eruptions will be done primarily uh during the nighttime hours which is a great thing because if you've driven in this area since this new interchange open you've probably noticed a big difference when it comes to your commute time because the the traffic I
mean look behind us right now if you look at the bridge traffic is Flowing behind us here in 400 traffic is Flowing it's been a tremendous Improvement and that's going to continue throughout this construction period which is a a great sign of uh of the work that's been done here alleviating some of the traffic and North fory so one of the questions that we we've received as well with this project is what exactly went wrong what was the issue to begin with uh Matt is that something you can answer yeah uh basically all we had was a layout issue which is basically our survey Department
had a hiccup whenever laying it out but at the end of the day we're going to address this we're going to fix it as John said the bridge is 100% safe we just got to fix where the bridge is positioned that's pretty much what we're doing with this correct work so we're talking about uh traffic impacts primarily on 400 and we're talking overnight closures temporary overnight closures but on 369 itself it's looking like at this time no closures right that's that's correct the 369 widening is open to traffic two lanes in each
Direction and we'll continue to stay that way all right Matt let's let's turn to you with Baldwin Paving what what's the role for baldwi going to be in in this project why are you why are you guys here today and uh and what kind of workers you going to be providing yeah so Balwin Balwin pavin was the original contractor that built this bridge the spam one as we talked about um we have exited the bridge business in 2022 so what our role is is we have subcontracted out to uh ER Snell who's
going to be performing the work and behind the scenes we're going to be coordinating with fory County Vertical Earth er Snell and Dot to make sure this project goes as smooth as possible seamless and safe as possible uh one thing I do want to add is Ballwin stands behind our work and this will be 0 to taxpayers Zar to the county Z to the dot Baldwin paven is covering 100% of this cost and that's probably a question a lot of people are asking right now it
certainly is it's a question we we've received through through our Media Partners and on social media as well is what's the ultimate cost for this additional going to be for the taxpayers and that answer is none Baldwin Paving will be picking up that tab on the repairs that are needed for this so so a quick recap here of what we've covered so far cuz again it's already a lot uh the monitoring period has come to a close again that monitoring period has been on the current closed section of the sr400 overpass here uh at 369 that monitoring period shows the settlement that was a concern early on appears to
have stopped underneath which is great news here when it comes to the work needed however cap is still needed to be replaced on that portion of the bridge just over over my left shoulder here if you're heading westbound on 369 uh over 400 and that's going to take about a 9 9 to 12 month period for that work to be completed however traffic during that time will be flowing both on 400 and on 369 okay got to catch some oxygen after all that it's a lot to unpack here with this this work but at the end of the day uh certainly a great sign with that
monitoring period and what that revealed here for this work um let's talk about the SR 369 widening project in general uh that that's a great project again we talked about traffic on 400 but on 369 as well where are we at with that full project we're in the punch list and closeout phase so there there's a few minor items that need to be repaired in in Vertical Earth and and their subcontractors are working on getting those items finished all right so we're talking about full widening of Sr 369 uh getting close to being completely
done there once the the bridge is also complete and opens up to all traffic things will really be flowing here North forite but as you can see here today it's about 10:00 in the morning on a Tuesday right now and traffic is Flowing great so great news there gentlemen anything else in this project that the folks here in fory County need to be aware of or maybe in those in Dawson County driving through or Hall County sure I I wanted to say how much I personally appreciate Baldwin stepping up and and uh repairing this I that the county appreciates that my department
certainly appreciates it Partnerships at work here g dot for Scythe County Vertical Earth Baldwin ER snell a lot of different agencies involved with this work and we're looking forward to it being complete we'll have more details online at forite co.com on our social media channels and of course at TV for Scythe AT&T channel 99 Comcast channel 23 gentlemen we really appreciate you coming out here today providing some of those details hopefully we'll be talking about another update on this project soon and getting close to being fully open thank you thanks so thanks so much
for watching as always we appreciate you being a part of on the Move we'll have more of the latest construction projects here in fory County don't miss it and more details on this project coming up soon as well thanks so much for watching [Music] [Applause]
You’ve seen a lot of work happening along McGinnis Ferry Road, but what’s next for the widening project? In this episode of On the Move, Capital Projects Director John Jefferson shares an update on the utility...
A "pause" on residential zoning applications has been in place in Forsyth County since early 2025 as the County addresses what is ahead for residential growth in our community. What's next as the moratorium comes to a...
Over the next year, Forsyth County leaders, policy makers and planning officials will be working with our community to create a shared vision for our future. “Foster Forsyth”, an update to the County’s comprehensive...
Forsyth County’s On the Move series returns with an update on improvements to the Big Creek Greenway at the Fowler Park Trailhead. Crews began replacing the existing boardwalk with a precast concrete boardwalk system...
Forsyth County Senior Services is routinely winning state, regional and national awards for their offerings ranging from active adult recreation programs to senior support services all while breaking down barriers in...