S7 E6: A Lineman's Perspective–Restoring Power with Eric Brown

Sep 17, 202612 minAudio
ShareXLinkedInFacebookWhatsAppEmail

Send us Fan Mail This episode gives listeners a behind-the-scenes look at how JOEMC linemen respond when an outage is caused by a vehicle accident. It focuses on the August 21 broken pole on Gum Branch, the challenges of working in rain and traffic, the safety steps involved with downed or energized lines, and the coordination needed to replace the pole and restore power. Through Eric Smith’s firsthand account, the episode highlights the skill, teamwork, long hours, and member-focused commitment behind getting the lights back on safely.

Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.

Transcript

From the show. Tap a time to play from there.

SPEAKER_00This is Flippin' the Switch, a podcast from Jones Onslow EMC, where we're getting to know the people and stories that make our co-op and community so special. We'll share energy tips, co-op news, and conversations that give you a closer look at the people, places, and stories that make our community a great place to live. So let's get started.

SPEAKER_01Hello, listeners. Today we're taking you behind the scenes of a recent power restoration and talking with one of the linemen who was there. On the night of August 21st, an accident caused a vehicle to strike and break an electric pole at one of Jacksonville's busiest intersections. It was raining, the situation was challenging, and restoring power took a lot of coordination and hard work. Today, we're talking with Eric Brown to hear what happened that night and get a first hand look at what goes into restoring power after an outage.

SPEAKER_01Thanks for joining us, Eric.

SPEAKER_02Yes, ma'am.

SPEAKER_01So first just tell us your title. Tell us what you do.

SPEAKER_02I am the crew foreman for the conversion at Johns Onslow EMC.

SPEAKER_01Where were you when you got the call?

SPEAKER_02So when I got the call, I was laying in my boat working on it under my shoulder, and I was a little bit surprised at the thunderstorms that were rolling in.

SPEAKER_01Okay, so you were off that day.

SPEAKER_02Absolutely.

SPEAKER_01Oh wow. So how did you end up coming in?

SPEAKER_02So even though you're off as a lineman, you're pretty much on call 24-7. So when that when the storm started rolling in, it was getting bigger and bigger, outages started popping in. We've got an outage map. I had just recently checked that. They were scattered about, so it wasn't real alarming. So until Shane gave me a call and said that we had a broke pole up country. So and up country is toward Trenton, the other side of 70 on Highway 41, is where it ended up being at.

SPEAKER_01When you arrived, what did you see?

SPEAKER_02So that pole, it was caused by down trees, and we had a small break in the storm, so we were able to get to work pretty quick, but then it filled in pretty quickly with another pretty heavily rain and lightning storm.

SPEAKER_01Okay, so was this the same day as the the pole break on Gum Branch?

SPEAKER_02Yes, ma'am. This was earlier in the day, so this was at three o'clock during the day. You know, still some linemen were at work, but we were we worked 410, so I was off on Friday. So I came in at 3 o'clock and started that pole.

SPEAKER_01Well, how did you end up at Gum Branch?

SPEAKER_02Once we finished that pole, we were leaving, everybody's heading home, all the houses were pretty much cleared up, and dispatcher came on the radio and said that it had a broke pole at the corner of Western Boulevard Extension and Gum Branch that we needed to head that way. So I I said 104 and told her that we had already separated that you know she needed to get with everybody individually. But I did ask, could you come back with that intersection one more time? Because I knew what that was gonna entail.

SPEAKER_01So when you got to that intersection, what did you see? What did it look like had happened?

SPEAKER_02It it was it was a mess. Knowing that Duke also served off of that pole, the joint use pole, and it was gonna take more linemen, more personnel from two different companies to work together to get the lights back on, a busy intersection. Also, we had to call in emergency locates because there's gas, fiber, water, you name it in that intersection.

SPEAKER_01Okay. So you mentioned all of those factors. Another thing to remember about that night is it was raining. Yes. So when it's raining and you're in a busy intersection, how does that affect the work that needs to be done?

SPEAKER_02It takes a lot of time. Not only what we had to do was gonna take a lot of time, but they was ten, fifteen JPD directing traffic, keeping them off of us. Once they've got that kind of under control, I think PSG came in, they actually shut the road down and detoured them around like Lowe's food and things like that. So the whole intersection looked like a ghost town by the time they got everything detoured around us.

SPEAKER_02So that was great because there was no way we could have changed it because Duke's lines actually cut caddy corners across Western Extension.

SPEAKER_01Let's let's talk about the work itself for a minute. So when you get there, what's the first thing you have to do?

SPEAKER_02First thing we have to do is identify everything, get the lines de-energized and get them grounded to make sure that the linemen and the public are safe.

SPEAKER_01Okay. So once this the scene is safe and we have all the the live lines picked up or turned off, what goes into replacing the electric pole? So is it is it as crazy and difficult as I would imagine?

SPEAKER_02Yes, it can be. The most challenging part to this pole was so it was it was broken multiple places. It had all the wires hanging basically freestanding to get that portion of the pole, that 20, 30 foot piece of pole down without breaking anything else, any adjacent poles, so we had to rig poles down line and up line to keep them from breaking, so we could take the knives off this pole and get it down. So it took us just over two hours just to get the pole top down without breaking any other structures.

SPEAKER_01So you're talking about how the poles are connected and how you had the the possibility of breaking another while working on that one. So the pole broke near the top. Is that why?

SPEAKER_02It doesn't really matter where it breaks. If you've got to take the lines off, and like I say, Duke's was dead-ended in an angle, so they had to cut wires down, we had to cut wires down, and once you cut them wires down, there's another pole taking the strain of that wire because it was dead-ended on this pole guide back. So there's other precautions you've got to take to make sure you don't cause more damage than what you ended up started out with.

SPEAKER_01So this sounds like quite the on-taking.

SPEAKER_02Yes, ma'am.

SPEAKER_01How many how many linemen would you estimate were out there?

SPEAKER_02We had approximately 17 just with Jones Onslow and with Duke that has Maztech working on theirs, the contractor. I'm assuming just spitballing, they had around 15 to 18 as well. Wow. Plus, they had some Duke representatives on site.

SPEAKER_01So you you mentioned that it's a joint use pole with Duke Energy. What exactly does that mean and how does that affect the restoration process?

SPEAKER_02Okay, so what it means is that basically you've got poles that will have Jones Lonslow and Duke on them. So, you know, we've got certain areas that we provide power to as well as Duke. So in these intersections of where we cross each other, we share utility poles to save space on the side of the road for dwellings, businesses, and so forth. So we would be, in this case, we're on the bottom serving, and they're on the top riding.

SPEAKER_02So they're riding through our service area to get to their next service area. So that's that's how we intermingle just where we cross at, cross paths. They've we've got the share utility polls.

SPEAKER_01Okay, so when you're out there, how is the work divided up on a joint use project?

SPEAKER_02So in this case, we are responsible for the poll. It's our poll. They're just riding. So we we are responsible for the poll. So we had the poll delivered. Once we get everything secure, they're alone working as so our buckets and their buckets are intertwined. They've they've got their stuff grounded, we've got ours grounded. They're letting their wire down. We're working together to get this you know done in a reasonable time, even though it was not a race, it was more like a marathon with with this particular pole. So just just for instance, most pole change outs are two to three hours, and this one took 11 hours.

SPEAKER_02Just one pole alone. We had 14 grounds, I believe it was, just on one pole alone to make sure we had everything grounded so everybody would be safe.

SPEAKER_01Okay. So eleven hours.

SPEAKER_02Yes, ma'am.

SPEAKER_01Were you the only linemen out there that had been off on that Friday?

SPEAKER_02No, ma'am. They they was multiple that had been off. It's when you when you get called, especially on something like that, it kind of lacks a fire in you. It's what all linemen really drive to do. And you've got to have some gumption about you to be able to go work all day, like most of the guys really did have to work all day that day, and it was an extremely hot week. We were very fortunate that we're not fortunate that it got broke, but we were fortunate that it got broke at the time it did get broke because it was raining, it did turn the night, it was a little bit cooler.

SPEAKER_02If this had had happened in the middle of the day, say that Wednesday or Thursday of that week, it would have been terrible. Yeah. Or 110 degrees index and trying to do all this work, plus the fact it's in the middle of the day with businesses, people going to and fro, at least in the middle of the night, most people are off the road per se. So that was a blessing. If if it had to be broke, it it picked the right time.

SPEAKER_01Right. All right. So you spent 11 hours at that one, but you had been to another restoration earlier in the day. So how many hours did you end up working on your day off that day?

SPEAKER_02So I had approximately 14 to 15 hours that day.

SPEAKER_01Wow. So uh what would you have been doing on your on your Friday night otherwise?

SPEAKER_02Well, once I finished repairing my boat so we could go to the beach the weekend, other than the rain, I could really see myself sitting in a recliner watching my TV show after maybe eating a lovely deer my wife had prepared with and with my daughter.

SPEAKER_01Well, we appreciate you being out there. So when you're working on a restoration like this, do you think about the members waiting for their power to come back on? And how do you balance the the urgency of getting the lights back on with making sure the work is done safely?

SPEAKER_02It definitely runs through your mind thinking about somebody at home without power, especially the elderly or somebody that needs power for oxygen or anything that they may need as far as you know, medical assistance. So it is it is urgent and it is on your mind. It weighs heavily on your mind. But most importantly is the safety of your fellow employees and the public. So that's number one no matter what circumstance it is. So once you handle that, you can just start digesting the pole, picking it apart, and you just got to start somewhere.

SPEAKER_01Well, when you look back at that night, what stands out to you the most?

SPEAKER_02How two companies come together and solve the problem for the public.

SPEAKER_01So what do you wish our members knew about what goes into this type of work and restoring power after an outage like this?

SPEAKER_02The sacrifice that uh our linemen and employees take, like I say, a simple day off, turn into a very busy afternoon, night, and early morning.

SPEAKER_01All right. Well, thank you, Eric, for taking the time to share your experience with us and for giving our listeners a behind-the-scenes look at what goes into restoring power. And thank you to our listeners for joining us. We hope this conversation gave you a better understanding of the work that happens behind the scenes and the people who are working to safely get the lights back on. Until next time.

SPEAKER_00Thanks for tuning in to another episode of Flippin' the Switch. Be sure to follow J O E M C on Facebook and Instagram to stay connected with your electric co op and learn about energy tips, updates, programs, and more. Until next time.

Open the transcript file

Hosts and Guests

Nobody is credited on this episode yet.

Credit the people on this episode

Be the first to rate this episode

More episodes

All episodes
  1. Behind the Outage: The Role of Dispatchers

    Oct 20, 20268 minAudio

    Send us Fan Mail Behind every power restoration effort are people working long hours, communicating constantly, and pulling together to serve our members. Hear the August 21, 2026, outage story from a dispatcher’s point...

    Credit the people on this episode

  2. A Lineman’s Mission Trip That Brought Electricity To Rural Guatemala

    Jun 30, 202615 minAudio

    Send us Fan Mail A light switch feels ordinary until you stand in a place that has never had one. We sit down with journeyman lineman Joe Zernhild from Jones-Onslow EMC, who volunteered for a mission trip to Guatemala...

    Credit the people on this episode

  3. S7 E4: Celebrating the Month of the Military Child with Hug A Hero

    Apr 2, 202621 minAudio

    Send us Fan Mail On this episode of Flippin' the Switch, we sit down with Trisha Dyal and Carol Jameson to trace how a single handmade “daddy doll” became a nationwide resource for military families, powered by a tiny...

    Credit the people on this episode

  4. S7 E3: Energy Through Their Eyes - A Visit to Clear View Elementary

    Mar 18, 202617 minAudio

    Send us Fan Mail Career Day gets a lot more interesting when the kids take the mic. We’re at Clearview Elementary with students who tell us what they learned about Jones Onslow EMC, what electricity powers in their...

    Credit the people on this episode

  5. S7 E2: Dreaming Big in a Small Town with Schumata Brown

    Feb 23, 202619 minAudio

    Send us Fan Mail What does it take to turn a “passage to the beach” into a small-town destination? We sit down with Maysville’s town manager, Schumata Brown, to unpack a lifetime of roots, the courage to lead at home,...

    Credit the people on this episode