speaker-0: Welcome back to Development Diaries, the show where we dive into the careers of leaders and change makers in real estate. Here we share their career journeys, sliding doors moments, and their golden advice to the next generation, as well as some future predictions, career highlights, and what excites the most about the sector right now. A very warm welcome to this Rebels Radio special episode of Development Diaries. I'm thrilled to be joined by Al Bins Gamble of Jetpack to discuss the BSR state of play. As well as some tactical advice around Gateway 3, safety cases, and the consequences of getting this stuff wrong. I hope you take plenty of value away from this episode. If you didn't catch our previous episode, which focused on gateway two, you can find that on the Henry James Search website under the insights section. Owl was also kindly agreed to share our next Rebels round table later this week, where a group of leaders from the sector come together and share their learnings to drive the sector forwards. But more on that later. So Without further ado, Al, welcome to the podcast.
speaker-1: Thank you.
speaker-0: Could you give the listeners a quick overview of your background and your authority on this topic in particular?
speaker-1: Yeah, sure. So for the last decade, I've been leading safety consultancies, whether that be from within an architectural practice or standalone consultancies. My background in CDM, I was a part of embracing the 2015 legislation very early on. And when the Building Safety Act came along, I did the same as well. I made a real point of being one of the, I guess, the early adopters, one of the first people to put in a Gateway 2 application and to get on the ride. you know, from there I've done over 50 applications now, seen a host of approvals. That's followed through, not just in supporting clients with design, construction, but also occupation as well. So I've been a part of authoring safety cases. From that consultancy work that I've done, made a very conscious decision to step away from day-to-day delivery and running teams and actually going into different businesses and supporting them. And that's what Jetpack is about. It's about helping others get on the ride and adopt the Building Safety Act.
speaker-0: So you mentioned there that you've had over fifty approvals. so looking at the latest BSR transparency data, the approval rates and determination times, it seems like things are shifting and in a positive way, but do they reflect genuine efficiency gains? Or do you think applicants have certain simply learned how to survive the tighter bottleneck?
speaker-1: I don't know if I misspoke there, but I've not had 50 approvals, I've had over 20. I've worked on over 50 applications. no, mean, you know, I was one of the early, one of the first people to put out this, know, freedom of information request before the transparency data existed. That was being done because, you know, there was just the radio silence with that early version of the regulator. So people didn't know what was happening. All we really had to go off was hearsay across the industry. So since the Lord Rose taken over the regulator, they have started to put out their own data now. it's starting to, I guess, be met with a level of a... reassurance, there's a couple of signs of relief going on, think as well. But I think there's that Simpsonism, you know, that says you can prove anything with data. And I think that's certainly true. You know, when we look at what came out in the last three or four days, and they're saying that 87 % approvals now or something like that, you know, I think we need to greet that with a bit of an asterisk because What people don't necessarily understand is the nuance of that. So if someone puts in a gateway to application and it gets rejected after 22 weeks and then they put in and then they resubmit and it gets approval after eight, the aggregate of that that gets put on the sheets is 15 weeks. It doesn't show that 30 week live journey of the client there and the resubmission. I think we need to take it with a pinch of salt. I think, equally there's something, I guess, a little bit troubling about, you know, reporting. I think we're on something like, I think they've done 97 % approvals on new applications that have been determined in the last 12 weeks. Now that's a fantastic number for the industry. in terms of an industry that wants to get building again, having the slowdown of the last couple of years. But that's, I wouldn't necessarily, that's inherently a good thing. know, do, I'd question whether 97 % of applications are actually deserve an approval, you know. And I think what the regulator has done, I think it's mended a lot of fences. You know, since Lord Rose came in, I think there's There's been a more collaborative approach. But with that as well, we are seeing these, you know, the average approval time now for a new gateway application is 23 weeks. And I think what the regulator is doing, it's very artfully balancing, you know, mending those fences, trying to work with the industry to get approvals, to get people building. And what is, feels like a reasonable approval time now. Now with that, what I would say is if we are putting pressure on to get it down from 23 weeks to the 12 weeks, which the legislation says it should be, then I think what we will see is quite a steep drop off of that overall approval rating as well. So I think there's just a bit of a balance act going on at the moment. So I think, yeah, there's definitely a story behind every statistic.
speaker-0: So you think that as they bring the sp up the speed, the approval rate will go down. What what what do you think would be behind that?
speaker-1: Well, I think the regulators, they're just being very collaborative. They're allowing people time. You know, what's actually happening is a gateway to applications going in and the regulator off the bat isn't being able to necessarily find all the information it needs. They're being quite generous with the time to allow a design team to respond to a number of RFIs when really they could be being a bit more bit more clinical about this and actually saying, look, the information's not here. We need to just reject this. So I think there's just that balancing act at the moment, which, you know, it's for the good of the industry. But I do think, you know, unfortunately, the regulator might be making a rod for their own back further down the line if they do want to push towards, you know, 12 week approval times.
speaker-0: It sounds really important for people then to capture all these lessons now so that when they have to do it once and once only, they can get it right with without as much leeway, as you say.
speaker-1: Yeah, I think, you know, these kinds of statistics can breed a bit of complacency within the industry. Collectively, we've still got a way to go on this. You know, I can hand and heart say, you know, I've had approval on applications that, if I'm being honest, I don't think they should have received an approval. But what good looked like two years ago. is a far cry from what good looks now. that's a positive thing. We can say that that's just part of the evolution of things. That's not necessarily to say that the design wasn't compliant or anything else like that. But it's the quality of the application. It's the access to information as well. And just the amount of time that we were given to work through some issues when the regulator could have been a bit more robust in cutting us off.
speaker-0: So in summary then, there's some good news sprinkled in there, but the worst thing people can do is take their eye off the ball and sleep on this stuff and think that it's all good.
speaker-1: Yeah, definitely. the regulator is not in its final form at the moment. You know, conversations with John Palmer and stuff like that, are, they want to continually improve and, you know, they've got very much a plan of how they do that. So as with we've seen in the last year, things have got better. We need to see that continuing on both sides of the fence.
speaker-0: So gateway two approvals we've touched on there. as we all know, and those listening will hopefully be living this day to day and be be nodding along. it's not the only part of taking a scheme through construction and into operation. So we now have the added complexity and cost of the building safety levy, which is now fully active alongside the pre construction squeeze, inflation, costs, construction costs. All well reported things that don't make doing any of this easier. so are you seeing when you go out and talk to people, owl, the mid tier developers change their financial models to adapt, or do you think they're looking at alternative product altogether?
speaker-1: Yeah, think there's definitely a cooling off in the mid-market. We saw this early on with the Building Safety Act in general, to be honest. There was a lot of developers who were either diversifying and going into offices and other commercial avenues. We also saw it with the split where it was, you a developer would either do six stories or they would do 30 stories. They weren't necessarily entertaining in the middle either. So I think, there's a lot of number crunching that goes on with all the feasibility of this now.
speaker-0: Makes sense, yeah. So we were seeing people look at sub eighteen meters, single family, rental, suburban type products. If they were going to do a HRB looking at yeah, real density, which I guess is required to make viability stack in a number of cases anyway. but it'll be interesting to see how that plays out. Gareth Bacon's calls for reform have often targeted the friction between that regulatory rigour and getting houses delivered. If I gave you the power Al to rewrite one part of the BSR's mandate tomorrow, what would you choose and what would it be?
speaker-1: I'm not sure I share Mr. Bacon's kind of call for reform. To be honest, I think it's probably the first thing I say. I saw this article on Building Magazine's website in the last week. And to be honest, it troubled me quite a lot, you know, because it just seems to be at odds with what we're seeing. across the board. Yes, there is definitely a caveat to put against the statistics, but they are going in the right way. And there are good news stories out there. So calling for a reform of the building safety regulations, I the quote is absolutely not fit for purpose. As I said, think maturity of a new kind of organization and institution is going to take time at the end of the day. I think we are seeing those improvements. continuously. The main area to target is probably the remediation side. So any of the kind of category A of existing HRBs, that is an area that is being prioritized. But thinking about what I'm getting involved with day to day right now, I've said this before. I think the biggest threat to Gateway 2 applications is information management. And that's on both sides of the fence. We've got poor information management, which is causing issues with version control and everything in our submissions, not necessarily having great coordination across disciplines as well. That tends to be the areas where we're slipping up. And we are requiring these longer determination periods. Equally and by the regulators own admission their IT systems have just not been great. We're seeing applications go in they are submitted and then the information that we've submitted disappears off their system the Links that they're sharing to upload information They don't work or whatever it is. You know, there's there's a lot to be done around digital and IT. So Certainly that's an area I think that there needs to be a decent amount of investment there.
speaker-0: So their golden thread.
speaker-1: Yeah, I think there's... I don't know why it ever was thought like this, but the golden thread seems to only apply to just us on the design and construction side of things. And really that makes us think about what we're doing and what they're doing as two separate systems. It's not, you know, it's one system at the end of the day. And, you know, I passionately believe that... the multidisciplinary teams that are, looking at our applications, they should be accessing our common data environment, which is the single source of truth for a project. They shouldn't, we shouldn't be downloading everything and sending it to And then for them to die, it just, just doesn't make sense. We're caught, there's too much, too much risk in all of that double handling of information.
speaker-0: Yeah, I d I don't know many companies that have a moved beyond that in terms of how they store data in the cloud and using various different tools. So it's not doesn't sound like it's a technology or a platform that doesn't necessarily exist or is used in practice. so how do you feel about it as it stands today? Do you feel like it's just creating a universe of admin overhead for businesses or is it driving real behavioral change and Is there any other areas in which you see companies get getting it wrong that you wish they wouldn't?
speaker-1: I think, you know, it's uneven across the industry is one thing to say, you know, the people I see who are winning at this most are the contracted developers, because you're finding that they are engaging with the golden thread from start to finish. They have got skinning the game from design through construction and into occupation and because of that they're looking at things a bit more holistically. So I see them as the kind of the companies that are tending to get this right the most. I think there has been a lot of short-sightedness for people just focusing on Gateway 2 and then almost thinking I will figure out construction as we go and then worry about gateway three. I think that's probably the biggest message is, know, it's we need to take a step back, not just worry about gateway two and see the bigger picture in all of this and think about, you know, what are the information requirements for handover and operation as well.
speaker-0: So what would your advice for to a business that isn't also a contractor, that is a medium sized, privately owned developer, trying to make best in class buildings, trying to make the b best of the market right now, trying to make things stack, but they don't have that advantage of having, all of the risk in house and the colleagues across the desk. They have to go out and find that supply chain. What what would be the key things that you tell them like would help them get this right?
speaker-1: And I think the CLC have done a fantastic job with putting guidance out there over the last year and a half. think that, certainly their stuff last December was a bit of a game changer in, you know, telling the industry what good might look like, particularly around, you know, the deliverables for a gateway to. I think there is an important point in, you know, there still needs to be a bit more meat on the bone for what a good Gateway 3 submission looks like as well. A lot of that really depends on just collaboration and engagement. Contractors aren't going to go through this alone and succeed. They do need to be working with the client. The client does need to engage about what information they want out of the other side of all of this as well. So I think it is just Probably a criticism of kind of the way BIM has worked in general, know, historically where it's really been about exchanging information between designers and contractors. It's been relatively self-serving. It's about bookending that process, getting the client involved early doors and saying, you know, what information do you want at the end of the project so we can plan and make sure we can deliver that. So it's kind of looking through and beyond all of those gate points.
speaker-0: You may have heard me mention the Rebels earlier in the podcast, but who are they? The Rebels are a group of real estate leaders who come together to challenge the status quo, share knowledge and drive the industry forwards. We meet for roundtables and networking events and have a number of active WhatsApp communities. Our next event is coming up this Wednesday. Our has kindly offered to chair the session on all things Gateway 3, safety cases, and the BSR state of play. Do get in touch with me if you're interested in being considered for future sessions. Let's get back to the show. Sure. So Phil's in the market right now, and and you know, I'd be interested to get your view on this too, Al, but a lot of companies have been working their schemes through, planning gateways, clearing the path, you know, try to mean that their schemes become fundable, getting to that point. You know, that is quite a big project in itself. It's a lot of learning, it's some expense without necessarily guarantee of getting it. But what do you do? Do you Yeah, you're damned if you do and damned if you don't a little bit in some cases. You need to get to that point. So do you think that's what's been driving we'll deal with gateway three and construction later? Is there just been so much to manage, or has it just been a genuine lack of understanding? And what would you say to those people that have now cleared the path and are kind of heading towards the cliff edge of gateway three and occupied building assessments? What have you sat down with them for coffee tomorrow? What would your key bits of advice be to them?
speaker-1: I think the main thing that's not really been understood around your Gateway 2s is the role of the accompanying documents, in particular the construction control plan. That is where the client sets out their policies and strategies for managing competency, managing building regulation compliance, managing the golden thread. That is the key document. Whatever we say we're going to do in that document, we need to live and breathe all the way through construction and all the way through to your gateway three. And if we do that, then, you know, it should be, should be a fair, well, as pain free as a process as possible. But what we should be committing to is documenting the build as we go. There is extra expense in that. There is probably a slowing down of the program to achieve that as well. The regulator isn't necessarily going to be looking for every bit of evidence that you've got. But you do need to be able to have it there at end of the day. So that if they want to do a sample or anything else like that. then you've got a robust argument. ultimately, what this is about at Gateway 3 is having sufficient evidence to demonstrate that the building has been built in accordance with building regulations. I think one of the biggest challenges in all of that is around change management. Even the best Gateway 2s, have been subject, after approval, been subject to a number of design changes. And it can be for a multitude of reasons. It could be a supply chain issue. It could be a funder, a new funder has came on board and wants to change things, which we do typically see. With that change management, it's just making sure that that's fully documented and robust. Because ultimately, If we get to gateway three, we do need to have an auditable trail about all those decisions that they've gone to the regulator at the right time, et cetera, as well. So I think that that can be a bit difficult to manage because I think construction is very much, being around probably having a problem solving mindset on site, you know, where we can come across an issue and then we just want to respond to it and keep the program moving. The mandate around design changes now is that we stop, we take a breath, we change the design. It might have to go for an application or whatever it is as well. it is changing that culture on site a little bit as well.
speaker-0: Are there any other areas that you that worry you in terms of where people might be sleepwalking in to create a problem for themselves?
speaker-1: Yeah, well, it's on design changes again. If you do a major design change, you have to put in a change control application. That can take six weeks for determination. There is very much a defined list in the higher risk building procedures regulations that defines what a major is. Equally, we have notifiable. Now, notifiable is the one I'm bit concerned about because Okay, you don't have to put in an application to the regulator and wait six weeks. You just have to notify them about the change. But there isn't a timeframe for the regulator to come back and respond to you on that change. And working on one project, we've submitted a notifiable change and the regulator has came back with some concerns and comments 11 weeks later. Now the horse has already bolted at that point, you know. decisions have been made and things have moved on. Now, we're early in the program on that and we can work with that. But if we are putting the notifiable changes towards the end of the project, and I suspect it's a resource issue that has made it so we've not had the comments back for nearly three months, we could end up with a bit of a car park at the end of at the end of the project with loads of, or certainly a decent number of design changes that have not been looked at yet, which could cause a threat to the Gateway 3 as well. So those notifiable changes definitely put pressure on those who are involved in mediating them. So the principal contractor, the principal designer, the clients as well, and any of the designers who are going to be involved. When we do a notifiable change, we have to be very, very certain that it's going to be a compliant solution. And if we do have any kind of concerns about that, we need to be engaging with the RBI on the job as well. And hopefully getting, I can't say a bit of a steer because they're not allowed to do that now, but some kind of conversation about our thoughts.
speaker-0: Yeah, and I guess what it also puts pressure on is the financial viability of the business plan. If you're IRR driven or time driven or if you're working in purpose built student accommodation, you try to open that building for a a a year, academic year, then it's it sounds like a game of spinning lots of plates and then making sure the first one doesn't drop but by the time you've got the last one spinning.
speaker-1: Yeah, I've worked across a range of clients. The ones who are involved in students accommodations seem to be, you know, the far most concerned ones out there. Obviously, they're looking for deadlines of September ready for occupation on every single year. Any slippages in program can really affect things equally. NHS. There's a lot of development going on on hospital campus. The way that the buildings are configured by and large. It could be an element that's over 18 meters, but a couple of corridors away down in some basement or whatever they're looking to do some other works, it still qualifies as a HRB. So that can be very, very time sensitive as well. those are the two kinds of categories of work. I think historically as well, they're live in, well, certainly hospitals being live environments, it makes it a bit more difficult. University campuses, hospital campuses as well, record keeping can be a bit more challenging just because of the volume of things going on as well. If they haven't got great, you know, existing data or drawings or... they're making a lot of assumptions in their design work, which can be a lot more challenging as well to get decisions on as you go through Gateway 2.
speaker-0: So we and and hopefully some really good tangible actions slash reminders there that you've shared already. We know real estate is a game of risk and we know everyone that's involved in the sector is working with a degree of uncertainty around occupation, around demand, around funding, all the things that we've mentioned. Why is this something that people need to sit up and take s take seriously? And what are the consequences for getting this stuff wrong?
speaker-1: I think ultimately the consequences are going to hit the wallet at the end of the day. know, 23 weeks for a determination on the Gateway 2 is having put millions up front into design is not where you want to be. You know, we want to get that down to as lean as possible. there has been success stories. I've seen Gateway 2s go through in 13 weeks, which is great. equally, clients are still struggling with funders to try and pique their interests. I've seen funders walk away after Gateway 2 has got rejection, even though there was a high amount of confidence that upon resubmission, that the approval would be given with a couple of tweaks. yeah, it's certainly, it can be a bit of a turn off financially. As you say, that's the game, isn't it? There's risk involved here. What it's about is about de-risking it as much as possible. So as I said, I think information management has a real big role to play in that, having good systems in place. good naming conventions, creating sufficient time for coordination as well. You know, I'm sure contracted developers, everyone out there wants to squeeze the design program as much as possible to get that gateway to submission in. But, you know, we can be any smart pound foolish with that. And actually if we just take a breath and take another couple of weeks, dot the I's cross the T's, we can actually self-serve. save themselves a bit of pain down the line.
speaker-0: To measure twice, cut once. What about gateway three and safety cases? What can you share around that area? What are the consequences of getting that wrong? What have you seen so far? I appreciate not everyone has got this far yet. So maybe you've seen a bit more than others. But might have been much data around this topic.
speaker-1: it's still relatively new for a lot of people, as you say. Gateway threes are the biggest risk in as much as that the project is going to be at peak debt at that point in time. And there is a statutory eight week wait period. Now, we're not seeing that being hit by and large at the end of the day. So what we are doing by not... hitting that is we're delaying occupation when we're at peak debt, which is hurting return on investments at the end of the day. So getting that right is absolutely crucial because until we've got our completion certificate, we can't register the building and we can't occupy it legally. So that's absolutely crucial. I think the way of de-risking that as much as possible is just about ongoing dialogue with your your multidisciplinary team, your regulatory leads, your RBI, and just trying to take them on that journey. I've heard some positive things from regulatory leads that they're going to be engaging with you on different packages of work throughout, not just coming to site, but having a look at the documentation of what's been built throughout the process. So sign-off almost becomes fairly iterative throughout the build. So it's not a to-da moment, Gateway 3. I've yet to really see that come into play though. But there are some conversations out there that suggest that that might be coming in a more fuller form soon. But I think equally the sleeper one with that is safety cases down the line. We can register a building. we can provide the key building information off the bat at the end of the project. I think the best decision there is to build your safety case immediately, not to wait down the line because you might not be left with all the information that you need to do it. So as soon as the project is finished or even just a little bit before start engaging with a consultant to build safe, to build your safety case and just make sure you get everything you need out of the, out of the contractors and designers and everything before, before they leave the project. Cause ultimately, if we get too far down the line with it, you could be looking at intrusive works to find out information about the building that you otherwise could have had.
speaker-0: And ultimately you could lose your right to occupy.
speaker-1: Well, that's the absolute worst case scenario. can't... Well, going back to last September, when I spoke at Houses of Parliament, there was the news headline that hit that morning that someone had gone through kind of a pseudo gateway three. So it was a transitional scheme, but they still needed to provide evidence. And it had taken them like six months or something. And this was around the argument that they didn't have necessarily sufficient information to demonstrate that the building had been built in accordance with building regs. So, you know, it can be very, very costly if we're not doing that. as I said before, understand what you want to do during your Gateway 2. Commit to it in your construction control plan and live it and breathe it. And hopefully it will be as pain-free as possible.
speaker-0: Thanks for sharing that. so you were saying around Gateway Three being an eight week wait or supposed eight week wait. Have you got any data around what it's actually looking like right now? And what or what would be your best guess for th those that are listening?
speaker-1: To be honest, I've turned off that data a little bit, to be honest, with all the caveats that go with it. But I've seen 16 and 24 weeks on these. yeah, I think, unfortunately, we are you are looking at probably around double at the very earliest.
speaker-0: So we will come to some positive news to to end the show. But before we do that, Al, if you were sat breakfast next week with someone that might be listening who works for a developer in the hate or a contractor and in the world of HRBs, what else would you be saying to them to do or not to do that you haven't already shared? What can we give the listeners as a takeaway?
speaker-1: That's a very good question. You know, as a whole, the industry is getting it wrong. You know, I think we're seeing that with the positive news around approvals and everything else. the industry has gone on quite a big journey over the last year in particular. I think CLC guidance has helped us understand what good looks like. I think the advice is, and I said before, is just to protect against that complacency. what good looks like today is not what good is going to look like in six to 12 months time. And I think it just means that we need to continue to commit to invest in this, you know, with the amount of time and money we put into growing our understanding of it all.
speaker-0: And are there any other resources that you think people should follow or make sure that they're in touch with? You mentioned the CLC. Clearly they can also get in touch with you on LinkedIn and connect and follow some of your posts. Are there any anywhere else that you point people in the direction of? Fair enough.
speaker-1: No, what I will say actually with that one is the regulators actually made quite a big effort to share a lot of information themselves on their new website as well. I say no, it's probably about six months old now, but there's a lot more information on there. Compared to when going back to the HSE iteration of the regulator, I think it was a bit more sparse. even cryptic actually, some of it, you know, there's a lot of very helpful kind of guides on there as well.
speaker-0: And before we wrap up, I think, yeah, from my perspective and the reason that we've done podcasts like this, roundtable events, you know, we are all in this as an industry together. And I have seen, you know, one of the positives for me is that collective sharing of knowledge, swapping of stories, you know, we need to learn from each other's progress, mistakes, lessons learned. what else makes you positive despite all of the above?
speaker-1: I think the general vibe of all of this is positive. I'm probably not doing the best to portray that, but I've been through the mill a few times. think it is, yeah, it is largely positive. I think, as you say, the collaboration across the industry is very good. The knowledge, I think because of that, you know, the... we've gone on this journey together. think expectations on projects are fairly well understood now across the board. Designers know what they need to do. They know what to expect from a principal designer and vice versa. And I think as well, what we have seen is more client engagements as well, which I know is something that the regulator is very keen on seeing on all of this as well.
speaker-0: And what does good client engagement look like? Just more regular communication and getting in touch with them sooner, getting on the front foot.
speaker-1: Yeah, well, at the end of the day, you you could say that there was a certain type of clients before the regulator, particularly on design and build contracts that would sign a piece of paper and it go over to the contractor and everything thereafter is the contractor's problem. That's not good enough. That's not what we're expecting to see. Clients have duties on these projects, you know. The gateway to submission is a client's duty at the end of the day. It's their responsibility. Yes, they can give the authority to someone else to do it on their behalf, but it's their duty at the end of the day. All the documents that we're submitting, those accompanying documents, the change management plan, the construction control plan, ultimately it's about the client's policies and strategies and procedures. for delivering on all of those as well. So it does require a lot of engagement from them. They are signing declarations to say they've checked the competencies of all the persons involved as well. it's, it is, I mean, the legislation pushes you that way at end of the day, but I think the industry is much better for that.
speaker-0: Yeah, it sounds like some real progress is being made. People are better understanding their role that they play, how to tackle it. right gives me faith that, you know, with more lessons learned as we navigate the next wave of gateways, the industry will only get stronger and the whole thing becomes smoother. So thank you, Al, for taking time out of your busy schedule to spend time with us today. I know it's such a big topic. We're trying to fit it into a commute sized episode. So if anyone wants to talk to you more, are you happy for them to reach out to you on what's the best way for them to get in touch? Yeah.
speaker-1: absolutely best way to get in touch with me is just on LinkedIn. Albins Gamble, can find me there.
speaker-0: Great and I hope and I hope they do. So thank you again for joining us. It's been great to catch up. And I hope you as listeners have enjoyed it. We'll catch you soon. Thanks so much for tuning in to this episode. Your support means the world. Please feel free to like, share, or pass the podcast on to a friend or colleague. Do drop me a line with any suggestive topics you'd like us to cover on future episodes and recommendations of guests that you would love to see us interview. Till next time, go well.