What to Do When a Client Changes Their Mind After Pre-Construction

Nov 2, 202637 minAudio
ShareXLinkedInFacebookWhatsAppEmail

You spent ten hours on pre-con. Selections are done, the Gantt chart is built, your plumber has quoted everything. Then on day one the client says, “Actually, can we do a tub instead of a shower?” - and expects it to cost nothing because nothing’s been installed yet. In this episode of Contractor Cuts, Clark and James break down why clients change the plan after pre-construction, what it really costs you, and how to set up the relationship so it happens less - and costs you less when it does. They cover: Why “not a problem” is the most expensive thing you can say on day one How an unclear final picture during pre-con sets up every late change The ripple effect of “small” changes: re-quoting trades, returns, lost time, and opportunity cost Shifting from selling a product to being the client’s representative Using the client engagement agreement to explain when changes start costing money Why benchmark walks catch regrets while they’re still cheap to fix Offering design services so you and the client are picturing the same thing A real siding dispute where everything was done right - and why they still chose reputation over $600 If your clients keep treating pre-con as a free draft, this is the episode that changes the conversation. 🚧 2027 Growth Conference - Austin, TX | Jan 10-12. Two days diving deep into your company - what's working, what's broken - ending with your 2027 blueprint. Day 3: hands-on electives like financial management and estimate writing to make it real. Early Bird (very limited): 30% off + 3 hotel nights covered. Sign up at contractorcuts.com Contractor Cuts is a weekly podcast for contractors who want to build a better business - covering sales, operations, hiring, finances, and everything in between. 🔗 Book a free call: contractorcuts.com 🔗 ProStruct360 software + coaching: prostruct360.com

Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.

Transcript

From the show. Tap a time to play from there.

SPEAKER_02Welcome to Contractor Cuts, where we cover the good, the bad, and the ugly of growing a successful contracting company.

SPEAKER_00Welcome to Contractor Cuts. My name is Clark Turner. And I'm James McConnell. Thank you for listening today. And James, thanks for joining us today. Thanks for having me. See correcting it. Resident Guest. All right. So today we are diving into you know, when I'm in coaching sessions, when James is in coaching sessions, we try to take notes of when we get asked the same thing multiple times. This is a topic that more than one person is struggling with. So we kind of make note and build the podcast from that. Um and we're taking requests. We got it, we just got an email we need to uh I want to show you, but someone requested some stuff that we talk about.

SPEAKER_00So I got a couple ideas for the future podcast. But this one That's so exciting. Yes. It's about uh it's not about construction though. Oh, great. Even better.

SPEAKER_02Yeah, it's it's about Legos. I am so excited because I have a lot to say about Legos.

SPEAKER_00So join us on Lego Cuts only on Apple Podcasts. No. Um so that this one is again, this is an issue that is live that's happening all the time. And this is something that I think is well worth covering on the on the podcast. Uh the title of of this podcast talking about asking me to do pre-construction twice. It's I I the question that I get asked is, or the the scenario that I get put out there is I did all of this work, I got all of their stuff planned, we got everything quoted.

SPEAKER_00I spent hours and hours and hours. I even have, like you said, Clark, I have my pre-construction line item and we went through and did all the pre-construction. I have my selections workbook and my gant charts and everything else that I was supposed to do. We get out, we show up for day one, and the client's like, uh, I want to change this, I want to do this, and that needs to be happened differently. I don't like this. Actually, I told you I wanted that bathtub, but I think we're just gonna do a shower. And so it's what some big changes, baby. Well, I mean, but it happens. Like you get into it, and the client is standing there um doing that, uh, really kind of changing their mind.

SPEAKER_00Yeah.

SPEAKER_01Um, we just got a vet bill. We're gonna go down from the shower stall to the tub. Yeah. Acrylic tub.

SPEAKER_00Yep, yep. And it's like I I I just spent 10 hours lining everything up during pre-construction, and now you're asking me to do pre-construction twice. I need to go back and do all of that stuff again. But my guys are here, so I'm just gonna get it started. And now Oh, it's not that much different. Yeah. Wait, you're charging me? And so uh the usually what happens when I hear of that from guys is they get mad at the client for changing their mind. Like, this person, she's crazy, it's a care and blah, blah, blah. And it's like, well, they're just doing the what you've led them to do.

SPEAKER_00And so let's have a conversation about how to change that. So that's what this podcast is about is how do we avoid that? And when it does have to happen and it does come up because that will happen, what do we do differently? Um, excuse me. Sorry, I'm blessed. That's something in my throat. You've a climate time of year. Um I think it's uh James, what do you think in those moments? We've all had those clients. What do you think you've done wrong in those moments?

SPEAKER_00Like, what's the wrong way to deal with that? When some when when you feel like you've spent all the time and now the client wants to change the whole thing, rewind back to less formed James as a project manager in this scenario. What is kind of the the standard thing that guys do wrong when that comes up?

SPEAKER_02Um the I think the standard thing is not a problem. Not a problem. Yeah. We'll get it, yeah, we'll take care of it. Yeah. And I I don't all of the venom and the vitriol is in the background. But in front of the client, it's yeah, absolutely. And then you begrudgingly go through all of the steps and do all the things and call all the guys, and then the client two days later is like, hey, I thought we were supposed to be at this point, and you said that and the timeline, and you never sent them a new timeline because this all happened two days ago.

SPEAKER_02You've been spending all of your time trying to fix the issues that the client just created. Yeah. And now you're pissed, and they think that they're in the right, and they don't realize that you're bending over backwards to make the project happen on the same timeline, but you just keep losing.

SPEAKER_00Yeah.

SPEAKER_02You lose on every front.

SPEAKER_00And there's this like built-in animosity that you have behind your smile towards them at this point. Yeah. And it's starting the project hasn't started, and we've got four months of dealing with each other, and I've already shoeboxed you into the problem client. Um I think that's that's that's right on. I I feel like it's always like this client's insane, this client's crazy. There's two things of why this happens usually. Number one, the final picture was never clear during pre-con.

SPEAKER_00I was not detailed enough. We did not walk through what the actual final should look like. We like obviously I got a vet bill, I got to reduce my expense on this, is not not on me. Yeah. But there's majority of the time I had a picture in my head as to how this project was gonna run, and that wasn't translated into the the scope of work and estimate, as well as sat down and walked them through, okay, so we're gonna do this and it's gonna look like this, and we're gonna have this happen. Now, what do you think about that?

SPEAKER_02And sometimes it's the fact that we don't have, sorry, I forgot to put this on airplane. Um, we didn't, there's not like an actual picture, yeah, which is not necessary for every project, it's not necessary for every person, but like not having an image, not having an actual design of this is what it's going to look like. It costs money. So we don't typically like push that towards the client, especially if they're already getting a little finicky on budget. Yeah. And then we end up in the middle of the project with all these conversations about what things should be and what it was, and it's not matching their picture.

SPEAKER_02It's like, well, we don't have a picture. You didn't pay for drawings. Like, well, I didn't know that was an option. Yep. So it like brings up all of these things of like, how do we actually convey the idea? Because you it's different in your head, it's different in my head, but the words that we're saying are like, yeah, that fits. Yeah, yeah, yeah. But there's no, there's no image that we're sharing.

SPEAKER_00Yeah. Uh you want a new shower, you're the shower that's there, you just want to pull out and replace. I'm thinking fiberglass, and in your head, it's a tile shower. And so my estimate said replace shower with new, not changing locations, just replace. And so what does that mean? And what's our expectation? Uh yeah. So the the picture's different for sure. I think the hard, the hard part too, at this point is nothing's been installed yet. And so in the client's mind, we haven't started. And so this is all part of the free work.

SPEAKER_00Yeah, we're good. No money's lost. Yeah. Nobody's on the back end. Yep. And so that's that's one of the costs that that they don't see or understand. Secondly, once during my pre-construction is happening, let's say we're doing an addition. I've met with my concrete guys about the footers and the foundation, what we're pouring for the addition that we're adding onto this house. Um, I now have a new footprint that we're changing. Or like if we're going with the with the bathroom change of we got to change what we're doing. I've already walked the job side or gone through the plans with my plumber for that bathroom.

SPEAKER_00And so now he's quoted everything that we need. Now we're switching from a shower to a tub or uh a little bit different location. Like, do we need more valves? We got to pick out a different fixture because it used to be just a single shower. And do then the style and color and what you picked out, they don't have a bathroom faucet one that also has a shower. Like, there's all sorts of things that has to happen of changing that. So I spent my time meeting with my plumber, laying it all out, getting my materials together, getting ready to put the order in. You say, Hey, I want to change this one thing.

SPEAKER_00I know we haven't started yet, so that's great. Go ahead and change all this. Well, I've got to now go back to my plumber, meet with him, waste his time, wait, go cancel what I had uh sent over to get bid from Home Depot or Lowe's, wherever I'm getting my materials from. Hey, I'm gonna change this out. We're not doing that shower false. It's all of a sudden still in that order, and three weeks later, the old one, the wrong one gets delivered. I got to deal with like there's all this ripple effect at this time.

SPEAKER_02And it's all small stuff. Like I can see the comments already of like this, this would never cause this big of an issue. But it's not about the actual thing. It is the it is the ripple effect. And it's the fact that you're saying yes to something and you're signing a bunch of checks that you don't, you haven't even walked through yet. Yeah. All of the returns, all of the communication, all of the emails, all of going back into the software and adjusting things or going back into the selections workbook and editing things. And like, and like in the example earlier, all of this stuff is happening and you're doing and you're trying to do it fast, and the client it still has you on the timer of when you guys started initially before the first fumble.

SPEAKER_02Yeah. And like that starts kind of eroding the relationship as well.

SPEAKER_00Yeah. I and it's not the fact that I've got to make one return back to Home Depot. It's it's usually A, it arrives and gets damaged or missing, or I never get it back into my truck to return. So I just lost$450 on that valve and faucet. Um, and B, um even I'm I still, even though it got lost, I drove out to the job site hunting it down. I called my guys and I spent two hours looking for it. So I lost$450 on the materials that got ordered accidentally.

SPEAKER_00And I lost two to three hours of time that I should have been finishing another estimate on another job. And now that opportunity cost is could be six figures because I lost that job because I never got to that estimate and it was three days later. Like, and then gas in this economy. But I I think the the opportunity cost is something you can't price the clients, but it's like I only have so many hours in my week, and every three, five, seven hours I spend extra this week on your job is jobs I'm not dealing with starting, completing.

SPEAKER_00I'm lowering my quality to other clients because they're not getting my attention for what I promised them. And I'm not like it's just slowing down my company. Um, and so that's unmeasurable. You can't really that that's what we're talking about, like the ripple effect. How I can't price that out to a client, like, well, you owe me$15,000 because that one person said no. And I think if I would have gotten a mess in a couple days earlier, they would have said yes. Obviously, that's you can't draw that line or put past that on, but that's what I feel in my head. I'm like, oh, I I've I you ruined my schedule.

SPEAKER_00I'm gonna miss my kids' dance tonight now.

SPEAKER_02Because I'll tell you what, though, I'd watch that show. I'd like to see someone try. I'd like to see someone try and slide that one.

SPEAKER_00So here's your$15,000 change or you know, opportunity costs. You understand that. You understand business, right? It's business. It's it's homeownership 101. It's 101. Um, so let's let's kind of unwind this a little bit and how do we avoid this? Let's solve this problem real quick and easy, and it will be a shorter podcast because this is an easy problem to fix. It's very difficult to do, but uh, but the the solution is not hard. Um number one, all of this starts well, there's number two 1A and 1B.

SPEAKER_001A part seven of C. All right. So number one is your mindset and mentality of how you approach the relationship with the client. And number two is the client engagement agreement. Really? So the the relationship that we have with the client, um most guys set it up as transactional. You want a new kitchen. I am selling you a kitchen. Here's our quote. Do you want the kitchen? Yes or no? Okay, you're buying a kitchen from me.

SPEAKER_00That's that's the feeling that people have with contractors and how contractors pigeonhole themselves into the relationship. That at that point, any changes is like my waiter coming over and I'm saying, actually, I don't want the fish, I want the steak. That's part of their job because I'm buying that from them. Instead, I want the relationship to be set up where I am your representative. I am, I am your uh your partner in getting this renovation done for your kitchen. I always say when I'm coaching guys, I'm like, imagine your wife wanting to do a kitchen renovation.

SPEAKER_00Are you gonna treat them like you treat your clients currently? Where it's like, all right, here's the quote, yes or no. Do you want to do this? I can upsell you on this and you can pay extra for this. Okay, like you don't treat your wife that way. If I was doing a renovation on our kitchen with my wife, I'd said, I'd sit down and be like, okay, here's everything you said you wanted. Here's our kind of buckets of cost. The cabinets, I got in here for about 25 grand. We really wanted those nice ones. If we want better ones, we can do the handbuilt ones, but those are like 60. I priced them out. I don't think that's a waste of money. Let's talk about it. Lighting. I think we do this.

SPEAKER_00And so with my wife, I'm I'm like trying to help figure out the budget. I'm the CEO of this project and the CFO of the project and the COO of the project. And my wife is you just took the C-suite, baby. Uh, but that's how I'm viewing the pro, right? Like, so let me help figure this out for you because I've done this before. I'm the professional. Let's talk through this quote. Now, she's not mad at me because the cabinets are 25,000 and she didn't want to spend that much because I'm not selling her cabinets. She, you know, if you go to a restaurant and the steak's$180, you're like, what the this place is insane, right?

SPEAKER_00But if I'm like, James, we got a couple different options. I know you said you want steak. Well, there is this really rare wagyu that we import from Japan same day, never frozen. It's$180 for it. I don't know if you really care that much. We've got a really good steak at$60, but if you really want to have like the once in a lifetime operator, so I'm walking you through it as opposed to trying to say, hey, here's a$180 steak. I need you to buy it. This is it. Why not, James? Why don't you want it? Right. Well, I'll get the 180 steak, but if I don't like it, I'm gonna send it back.

unknownYeah.

SPEAKER_00So I'm starting number one, the relationship is like your like your wife or like your work, you know, you're working with your spouse. This is what I see. This is kind of what I've put together. This is kind of the the budget that we're putting around this, and we need to stay within that budget. Thank you. Um, and so that that is the number one, the approach with it. Because then at that point, we go to number two, which is a CEA. And so the client engagement agreement, if you're in coaching, we give it to you, we go through it. If you're not in coaching and you want it, hit us up at contractacuts.com.

SPEAKER_00I'd love to talk with you about what you need. That being said, when I get to the CEA, I am making it extremely uh kind of lined in the sand of the conversation of what we're talking about. And I say, okay, listen, and there's a paragraph in there. I'm actually making it a little more robust for 2027, which we released new paperwork on the retreat. Um, but on the CEA, we talk through. So let me talk to you about what pre-con looks like and what entering into once you start swinging hammers.

SPEAKER_00Let me tell you the difference of chain of when we change and why I need you to really, we need to finish planning before we start and not plan after we start. And so I start explaining to the client the cost differences. And I say, listen, if we say, hey, I don't like the toilet there, I want to move it over six inches, that costs you zero during pre-construction. Once we start and my plumbers run line, and you want to move it over six inches, that could be a$5,000 change order because we've already got all the plumbing in place. The flooring is clear, like there's a lot of stuff that changes.

SPEAKER_00And I use very easy to understand examples like that. Then the client's like, yeah, absolutely. That makes sense. And I say, that goes even for this pre-construction line on my estimate. So let me tell you what you're getting and why you're paying for that. And I explain pre-con. I do this, I do this, I get pull all the materials together, I get all your selections ready for us to go through and pick out and finalize, like build your Gantt chart. I sit and talk with every single crew that you don't know that it's happening behind the scenes. I'm sitting with the plumber laying out everything once we have our decisions made. So after we get out of pre-construction, if you say, Hey, I know you haven't started, but I want to move that toilet, it's not a$6,000 change because we haven't run the pipe yet.

SPEAKER_00But I now need to go redo my materials because we have uh maybe a different elbow needed. And it's not a lot, but it's work. I need to go meet with my plumber and talk through the new plan. Get them, I might need to go to my architect and get drawings redone. So uh if we're moving locations of plumbing, depending on where we're going, the city might require us to have the right drawing. Like there's all sorts of those things. And I start kind of building the worst case scenario for my client to see what that ripple effect is. I say, listen, I want to do this for as inexpensive as possible.

SPEAKER_00And so I'm just letting you know when we get out of pre-construction, those types of changes start costing you money and I don't want to charge you money, right? It's the relationship side that we set up. It's not, well, that's gonna cost you more. It's I don't want to spend your money on that. So let's figure this out before we start. Right. And so that's it's this I'm saying the same thing in both those statements. It's the rate relationship change that we're doing. It's oh, I want to protect your money. And as soon as we get out of pre-con, don't make me uh like spend any extra.

SPEAKER_01Don't make me do this to you. I can't believe what this guy's making me do to his wife.

SPEAKER_00I can't believe it. Uh does that make sense? Am I making sense on this, James? Yes. Um yes, you are. Well, uh, talk to me more. Uh, expound on the pre-construction side of what I'm talking about because because you're really good at this part of it. Um what's the pushback when you're having that conversation? What else did I miss from the CEA that you kind of bring into that conversation as to preemptively letting them know where it costs them more, and then you get to be the good guy, okay?

SPEAKER_00I'm not gonna charge you for this. Uh, but if we keep changing them, I'm gonna have to pay my plum or something because I've wasted a bunch of his time.

SPEAKER_02I think it I think it's we get hung up on examples because the thing is it's not it's not necessarily about the actual thing because in all actuality, if we're moving a toilet six inches, we probably don't even need to get drawings redone. We probably don't even need to get different materials. We could probably just get an offset flange and that could save us. But it's the concept of there are 12 variables, client, that you're not thinking of that it's my job to know.

SPEAKER_02And so you have to you either have to trust me, as I'm telling you right now, that changes when we make changes after this point, it's going to cost money. And giving an example like you gave for a client is great, they'll understand that. Um but like it's once it actually starts, it's not just right after the CEA and right after pre-construction that people make changes.

SPEAKER_02It's all the way down the project, and that's why the benchmark walks are so important. Yeah. At any point where there is a we we're not going, the everything becomes exorbitantly more expensive beyond this point to make changes, that's where a benchmark walk needs to sit. And that conversation happens with clients before any benchmark walks are even done. It happens during the CEA. It can happen well before the CEA as we talk through them about what the working with us on a project is gonna look like.

SPEAKER_02Once we get the framing done, yeah, the city is gonna come in and tell us if the framing is done correctly, but that doesn't mean that it's fitting what you need necessarily. Once you walk into that closet and you're like, you know what, this is smaller than I thought. We made the bathroom bigger, we mean we made the toilet room bigger than we needed to make it. Can we expand this closet? Yeah, we haven't run any electrical, we haven't run any plumbing, we haven't put any flooring down, we haven't put any sheetrock up. It's gonna cost 20 bucks in material.

SPEAKER_02I gotta the framer come back out, it's gonna be half a day's worth of work. 600 bucks. Yeah. Great. Once anything else happens, multiply that by three, four, five, because of all the trades that need to come back in and and execute on the change. Yeah. So let giving them an understanding of just a really small concept like that can help them understand why the changes that they're making are may affect the project way more than they're thinking.

SPEAKER_02Yeah. Just walking them through all the steps. And it's frustrating, I think, for us because I agreed to do this project for you. I agree to basically educate you on as much as I need to educate you on. But there's a certain amount of this that's like I don't I don't know what you do for a career, but I'm sure that you would be bothered if every time that something happened, somebody was asking you to explain to them exactly how you got to that place.

SPEAKER_02Like this is my job. This is this is my job to fix these issues as they come. And if I have to explain my knowledge to you every single time and walk you through all this, it's like there's no trust there, we've not built any rapport. But it it's a hard it's a really hard line to walk. Like some clients get really hung up in those spots, and you can make or break the project by not. Laying this out very well.

SPEAKER_00Yeah. And I think the there's so many scenarios we can't cover them all, but I think the the big thing that we're aiming for with this is I want to notify the client ahead of time as to what can cost them money and how I'm trying to avoid that. So when it does happen, that makes sense. So again, the the steak at a restaurant example. There's been I I've seen on a restaurant like, hey, we can do this certain type of meal. It takes 24-hour heads-up notice because they do, you know, that it's a 24-hour cook and they do it sometimes.

SPEAKER_00Yeah. And so that also says they say to you, hey, this is if you order it 24 hours in advance, this is you're going to be paying for it. Yeah. Because we're going to have to start cooking it and we, this is a special order thing that no one else is getting. To me, as a as a customer, that makes sense. If the next experience at a different restaurant is the waiter comes over and say, Hey, I want, uh, I want the hamburger. And they say, Great. And then 10 minutes later, I say, Hey, Ashley, can I have the steak? They're like, Yeah, but we're going to charge you a$10 cancellation fee on that hamburger.

SPEAKER_00I didn't know, I didn't know that. You know, we never talked about that. Right. And so the the difference of understanding ahead of time and hearing about it and making the decision, knowing that that could happen is okay by me. Not knowing and changing my mind, and all of a sudden you Ding me for stuff that I didn't realize the change of like I would have thought more about this ahead of time if you would have told me that, James. Yeah. Like that sort of that is on you as the project manager.

SPEAKER_02I think that's the rub though, is it's like what is explaining it? Yeah. It's like you could go through the CEA and do a fine job of explaining this, and then something happens that is an example that you didn't cover. Yeah. And it's like, I just you guys should have prepared me better for that. And I know we are solving the issue, but the frustration on the back end is what all do I need to prepare you for? Yeah. I I don't know.

SPEAKER_02I'm lost now too as to what you need to be prepared for because we went through the CEA and it's like you can re the client will receive these things as examples and extrapolate them until it doesn't suit them. That's how it feels.

SPEAKER_00Yes. I think two things. One number one, I always offer design services. Yes. So hey, I've got someone that can build this and sketch up or even like AI these days. Did you hear how quickly I said yes? I was like so in agreement with that. That was so good. Thank you. Felt good. Felt good for you to agree with me finally. Yeah. Um, but I have a design line item on there, and I want them to say no, I don't want to pay that$500. Uh, I'm I'm good without it. Cool. You're a funeral. I just want to let you know. And I leave it on there, I put it at zero, uh, requested a remove.

SPEAKER_00And I always tell them this is so you can see, and we can both have the same visual as to what this is gonna look like at the end and make sure that that we're on the same page on it. This ensures that you're gonna save money if you don't like the way something looks once once we start put installing it. I want to make, I'm trying to minimize your spend. And that 500 bucks for where we send the plans and what we're doing to so and so is gonna build it for us, right? And so that's that's number one to avoid it. Number two, this is not a end all be all cut and dry.

SPEAKER_00If you do this, you won't have this issue anymore. This is we're taking 28 fires down to seven fires on a job. So a great example literally happened. I got a final email this morning where I'm CC'd on it with our with our uh general manager on uh a company I'm an owner in um uh in a different state. The we had a project. You don't know her. She goes to a different school. She goes to a different school. I'm not gonna even name the state or company because we're active with this client.

SPEAKER_00Um we have a project on it. She said, Hey, my project manager said that the conversation was, I'm replacing all the siding on that garage in the future, but I don't have the money right now. So just match the siding as close as possible on that patch that you're doing because I'm gonna replace it all. That's what my PM captured. Um the client now says, that's not at all. Why would I pay for something twice? I want I want it to be the right way the first time, and blah, blah, blah. That was her response.

SPEAKER_00But that's what my PM captured from her. And on the quote, he wrote, we're gonna replace it very detailed uh siding line item. And again, this is a patch. This is a small, I mean, it's like a 10 by 10 area on on the side of the garage, but it said, um uh color match uh as close as possible, standard uh siding white or linen, I think was the was the standard that we had that's off the shelf, kind of we can get uh quickly budget uh allowance,$700 for this many square feet, whatever it was.

SPEAKER_00Um we went, we had the guys ready. She signed the quote, she agreed color match as close as possible. It's an off-white color siding. We got the closest one that's in stock because she wanted to keep the price down. She didn't have, you know, she was the whole job was about budget. Lining up to be a great project. Yeah. And so we get out there with the siding. The guys show up to install it and they put the first piece up. And she's like, that's not even close to a match. It's like, well, it's off-white and linen. Um, this is what we quoted.

SPEAKER_00It's$700 for this siding because it's the cheapest that we can do that matches. And she was like, that's not it. I need it, I need it to match. And we're like, well, okay. So we hunted it down. There's a special order from Canada that we found that they're shipping. It's a six-week wait on it. That when we brought it to our siding guy or our supplier, they matched the color and found the closest, like really, really good service on it. And we're like, hey, the special order is$1,300 for that siding. I'm not gonna charge you for the guys coming out for the day. I'm not gonna charge you. But if I would have known you needed steak from the beginning, I would you would have had to pay$1,300 for the steak.

SPEAKER_00I would have quoted you that. But you thought the hamburger at$700 was fine. And how'd it go? You're not gonna believe it. She's not gonna pay for anything, James. That's no, you knew I needed it. It says as close as possible, and there's a closer possible match than this. So I you have to pay the difference. Ah, you guys are trying to get one over on and so it was this whole, this whole, this whole ordeal, and it's over this, you know, the$600 change order from a$700 to$1,300. Right. And so we had the conversation, we spelled it out on the quote, and now we're at the at the crossroads of dollars or reputation.

SPEAKER_00Do we just say, you know what, I want you to have a good experience? We're gonna eat this$600 for this. This is the way I'm sorry, there was a miscommunication about it. Even though we just want to stick it to her, we can say that and keep our reputation and probably get a decent review from her. Or I can You think you get a good review from? I think so. I think I think he he'll pull it out for the way we've handled it. But we're eating 600 bucks for that review, right? And so again, uh she sent us an email on fire. I said, Hey, can we have a phone call? Because I feel like Tone's not good over email.

SPEAKER_00She sent back, No, I want it all in writing, blah, blah, blah, blah, blah. So I sent back, I'd love to have a conversation to understand your side of it because I've only heard our side, and obviously there's two sides to every story. And she doesn't want to get on the phone because she wants it in writing, which God, I feel so good right now. So, all that being said, this is over 600 bucks. I'm like, we're not going to court over 600 bucks, and I'm not gonna get a negative review over 600 bucks on a job this size, especially. Um that to be said, we did everything right.

SPEAKER_00We set the tone, we did that, we did, and we are still losing because we care more about a reputation than the dollars. So this isn't a end all be all, do it this way, and it will always work well. This is for the reasonable clients. And I'm not calling her unreasonable, but I know she had a budget that she didn't have any money over that budget to spend. And I get it that she's like, I don't have that cash. I can't do that. And so that being said, this is going to not be a fix-all.

SPEAKER_00This is more a mentality of relationship and prepping to where when it does happen, I rarely charge extra when I have to redo something post-pre-con. Um, but I've but if I'm not charging extra, they're at least saying, Thank you for doing this extra work, Clark, because I see that you're doing it now. I didn't know that it actually happened. They don't say all that, but subconsciously they're like, Oh yeah, he's got to redo all this.

SPEAKER_02He looked at me and with just his eyes, he said, I love you, man. We're best friends. We'll always be best friends. He said that to me. And I appreciate you more than you'll ever know.

SPEAKER_01Yeah.

SPEAKER_02Just with his eyes.

SPEAKER_01Just with his eyes. Yes.

SPEAKER_00But um powerful stuff. Uh honestly, like that conversation goes like this. If you don't do the pre-con of the relationship the right way, the conversation is, hey, I want this done. Okay, I will uh I will rewrite this. Great, thanks. That's your job as my contractor, right? Like that's the attitude. Yeah. If you set it up with the relationship and let them know during the pre-con, like the the ripple effect that's gonna happen, the the conversation is exactly the same, except they're on your team where it's like, hey, James, I know it's gonna be extra.

SPEAKER_00Like you get you just did all this stuff, and I'm so sorry, but I need to change this. Hey, I got you. I got you. And so all of a sudden it's it's giving you credit and thank yous from the client for you doing the exact same thing from before. They're like, you owe this to me. This is your job. What do you mean? And so it the relationship and having the conversation of why change orders are ripple effect during pre-construction, during the CEA, is going to change the attitude and the subconscious uh treatment that the client's getting from and to you.

SPEAKER_00Um and that's really kind of helping you as the job progresses to navigate that. And then you gotta be the good guy and be like, I'll get this changed around. Anything else before I do it one last time, because I can't, we can't change this again on my plumber. Right. And so they're like, yeah, no, no, I'm not gonna touch anything. And that also fast forward two months, and they're like, I really want that moved. You know what? I know uh I know the ripple effect of moving that. I'm not gonna, we're good. I'm just gonna take that how it is because I don't, I'm fine with the toilet sitting there, right?

SPEAKER_00And so they understand and they're on my team, just like my wife would be when we're doing our kitchen of like, hey, Clark, I need this done redone. Like, cool, I got you because of that attitude, as opposed to you owe me the right, and it's just the the relation, relationship, and the attitude, and really the posture towards each other is different when you set it up this way. If you want to dive deeper into your your pre-construction, there's two ways to do that.

SPEAKER_00Number one, come to the retreat. Come to the retreat. James is doing day three uh on the additional workshop of the conference. We keep on a retreat, it's a full conference. Retreats the first two days, the workshop's the third day. James is doing a deep dive into estimate building, and he's gonna be covering some pre-construction uh part in that on day three. Um, we got a couple different uh electives throughout the day on day three. It's gonna blow your mind. It's going to be like, this is amazing. Yeah. So we'd love to see you there. If you want to sign up or hear about it, we talk to everyone that's coming.

SPEAKER_00It's not a giant thing. We we limit it to the number of companies that can come. And I do an interview of everyone that's interested in coming to kind of talk about what they want. We have we have our one-day boot camp on Sunday, uh, which is kind of a full blitz for guys in the field. It's just a single one-off one-day event or uh and it runs simultaneously to the retreat on Sunday. So we have a retreat room that's kind of broken into two different rooms depending on level of company and how long you've been with us and where your growth is. And we also have a third room that's the boot camp room, that's going to be really how do I get my field ops running?

SPEAKER_00How do I get the project management process, the in the field, the quoting, the estimating? It's kind of the one-man show that's still swinging a hammer trying to get out of the, out of out of the uh truck. That's the one-day intensive. We're a lot of our clients are bringing their project managers to that just to get some kind of field training on client relationship, time management, um, even uh dabbling in financials and what you need to be in place when we're looking at jobs. Um, so it's gonna be a really, really cool retreat. So get on treachercuts.com, set up a meeting.

SPEAKER_00I'd love to tell you a little bit more about the retreat and figure out your spot on it. We also have a few more, a very, very small amount of scholarships left. So don't let money be an issue. We got a you can apply to for the scholarship. I'll have a conversation with you. And if you fit uh the requirements of it, we we love to we love to sponsor you and and get you a scholarship there where you really we we cut it down super, super cheap to where it's just your out-of-pocket cost that you're covering for us uh to show up. So if you are interested, go to contractorcast.com or if you want to talk about coaching, you also you can go to contractorcast.com and there's a link there to to sign up to have a conversation about coaching.

SPEAKER_00So love to meet with you, help you with anything you need. That's all. All right, we'll talk to you later uh next week. Okay, good night.

unknownAll right, bye.

Open the transcript file

Hosts and Guests

Nobody is credited on this episode yet.

Credit the people on this episode

Be the first to rate this episode

More episodes

All episodes
  1. Grade Your Contracting Company: Day 1 of Our Conference

    Nov 16, 202648 minAudio

    Every December, contractors look back and decide whether the year was a success or a failure - usually based on revenue. But revenue is the result of a well-built company, not the goal. In this episode of Contractor...

    Credit the people on this episode

  2. Who’s Wrong Is It Anyway? The Nice Guy and the Burned Couple

    Nov 9, 202639 minAudio

    Two listener-submitted stories, two very different clients. The Nice Guy: Dave is friendly, knowledgeable, and has seen Mark’s truck around the neighborhood for years. Then he asks for 10% off, starts pulling paint,...

    Credit the people on this episode

  3. Are You the Bottleneck in Your Contracting Company?

    Oct 26, 202636 minAudio

    When you’re a one-man show, every decision runs through you - that’s the job. But once you hire, if every question still lands on your phone, you haven’t built a company. You’ve built a bigger job with assistants. In...

    Credit the people on this episode

  4. Are You Too Loyal to Fire? How to Know When It’s Time to Let an Employee Go

    Oct 19, 202641 minAudio

    You know he’s not working out. You’ve known for months. But you like him, his kids come by the office, and if he leaves, all his work lands back on your plate. So you wait. Clark and James have counted the cost of that...

    Credit the people on this episode

  5. Why Good PMs and Subs Start Dropping the Ball

    Oct 12, 202638 minAudio

    They were great for the first few months. Now things keep slipping - missed follow-ups, half-finished tasks, the stuff you told him to do last Tuesday still sitting there. So you start thinking maybe he’s just not the...

    Credit the people on this episode