This week, our guest is John Kousinioris, President and CEO of TransAlta, one of Canada's largest power generators. TransAlta owns, operates, and develops a diverse fleet of electrical power generation assets in Canada, the US, and Western Australia, producing electricity from renewable sources and thermal generation. Here are some of the questions Jackie and Peter asked John: What are the reasons behind TransAlta’s merger with TransAlta Renewables? What are your expectations for electricity load growth in North America, and how will AI data centers impact demand? Does TransAlta have plans for new investments to meet data center demand? Are there risks to electric system reliability due to fast data center growth? Are there supply chain bottlenecks for new generation projects, and do tariffs compound the issue? What are your perspectives on Alberta’s plan to redesign its electricity market? Do you see merit in building an east-west electricity grid in Canada? Please review our disclaimer at: https://www.arcenergyinstitute.com/disclaimer/ Check us out on social media: X (Twitter): @arcenergyinst LinkedIn: @ARC Energy Research Institute Subscribe to ARC Energy Ideas Podcast Apple Podcasts Amazon Music Spotify
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
SPEAKER_03The information and opinions presented in this Arc Energy Ideas Podcast are provided for informational purposes only and are subject to the disclaimer link in the show notes.
SPEAKER_00This is the Ark Energy Ideas Podcast with Peter Turzakian and Jackie Forrest, exploring trends that influence the energy business.
SPEAKER_01Welcome to the Ark Energy Ideas Podcast. I'm Jackie Forrest.
SPEAKER_02And I'm Peter Turzakian. Welcome back. Well, we have to timestamp again this podcast. It is April 28th, 1145 a.m. Mountain. It is election day. So we don't know, obviously, the results. It's a very exciting and consequential day. And we will talk about the election next time when we convene. Jackie and I will uh run through it, but you're gonna find out before we finish this podcast, right?
SPEAKER_01Right. Well by the time you hear this, the results will probably be out because we'll release this on Tuesday, and we will be talking about it once the dust has settled next uh Tuesday podcast. But today I wanted to talk a bit about the power markets, and there's a few updates. Uh remember when we had Dwayne Reed Carlson on the podcast, Peter, on March 25th, and we explained the negative feedback from stakeholders on Alberta's proposed changes to the electricity market. There were some real concerns there. And I have some good news to report. Far as I know, the ASO has announced they are going to make some changes to the design.
SPEAKER_01They're going to push the date back a little bit in terms of when they're going to finalize it. However, they are still planning to bypass the Alberta Utilities Commission in reviewing the design, but still positive that there have been some changes proposed. I also, one other little piece of news that's related on April 10th, Bill 52 Energy and Utilities Statutes Amendment Act. And this bill allows the ASO to make changes directly to the electricity markets without a regulator.
SPEAKER_02Okay, well, we can talk more about that. In fact, we can talk more about electrical power. So why don't we? I'm delighted to introduce our guest who is none other than the president and CEO of Transalta, John Kuznares, president and CEO. Welcome, John.
SPEAKER_03Thanks so much, uh, Peter and Jackie for having me.
SPEAKER_01Yeah, so lots to talk about in power markets across Canada and US. But first, let's start about TransAlta. I think almost every Albertan knows your brand name. It's on a lot of things in this province. So just tell us a bit about the company. And I just noticed you're had you're over a hundred years old. So that's unusual.
SPEAKER_03We are, and I'll apologize a little bit in advance here for my voice. I've been struggling a little bit with it. Our story as a company is really largely the story of the province in terms of development. We began with our horseshoe facility, which is a hydroelectric facility on the on the bow just west of the city of Calgary in 1911, actually before the Stampede began. We sort of just beat the Stampede in terms of timing. So we're a 114-year-old company, began initially as Calgary Power, and over the years have diversified into all different types of generation and have grown as the province of Alberta has grown.
SPEAKER_03Our evolution, especially over the last 20 years or so, has been pretty significant, I would say, Jackie, not just in terms of the change in generation mix that we have, but also in terms of our environmental footprint. I often reflect, and it's amazing, if you go back to sort of 2005, 2010, our company was probably responsible for about 5% of Canadian emissions, CO2 emissions in aggregate, like a pretty significant footprint. Roll forward to us today for a bunch of reasons, largely due to sort of the evolution of coal generation towards gas.
SPEAKER_03That footprint is down about 70% from what it used to be. So, you know, we often kind of muse about this, but our company's actually contributed about 10% of Canada's Paris commitments in terms of a decarbonization target. So that's been interesting to do while ensuring that we're contributing to affordability and reliability of power in the province. It's a great history with a lot of, you know, and I think back to the early foundations of the company, you know, people like R.B. Bennett and Lord Beaverbrook and even A. Cross, like, you know, names that I think if you're a history buff, especially somebody that knows, you know, this part of the world are like pretty, pretty big names, you know, characters and individuals that were really foundational to where we are today.
SPEAKER_03It's really, really great.
SPEAKER_02Mm-hmm. Yeah, well, Jackie, when you first said 100 years old, I thought you meant John was 100 years old. That's how I feel.
SPEAKER_03That's how I feel.
SPEAKER_02But no, uh yeah, it's an amazing history. But why don't we just rewind back to 2013, where TransAlta had originally spun out the renewables business, but in 2023 you reacquired it. Why did you decide to reverse the decision to bring in the renewables into the power business, into your power business?
SPEAKER_03Yeah, and I I actually joined the company in December of 2012. So it was actually, I think, the first sort of major thing that I worked on, Peter, in 2013. So at the time, Transelta had a number of contracted assets. So it wasn't just renewables. People often forget about, you know, Transalta renewables was probably about 40 to 45% natural gas fire generation, but it was contracted generation. So these were assets, they were probably, you know, somewhere in the range of just under 30% of the EBITDA, let's say, of the company, highly valuable, highly reliable, very predictable cash flows.
SPEAKER_03The parent company heavily into coal-fired generation. We just commissioned a coal plant in 2011, expecting it to run well into the 2060s, probably carrying a bit more debt at the time, a higher dividend. So it was a way to actually try to surface value on assets that were hidden, and also to sort of set the stage to delever essentially the parent company. So, Peter, to your point, roll forward 10 years, and a lot of those things were actually done. You know, we were essentially well on the way to, well, we had actually stopped essentially coal-fired generation in Canada.
SPEAKER_03In terms of growth, the strategies of the two companies had begun to converge. So we were looking at renewables and gas for both the parent company and for transalta renewables. The parent company had delevered pretty significantly. We had readjusted our dividend rate. And so you actually had a complexity in sort of our capital structure with converging strategies, with, you know, a yield co that had a growth imperative, but also a high payout ratio in terms of, you know, what its dividend was. So given the scale and size of the company, it made sense to put the two together and just simplify who we were and essentially bring the family back together again, which is what we did at that point in time.
SPEAKER_02Yeah, because there's also you get sort of brand confusion and all those sorts of things under the same corporate name.
SPEAKER_03We did. And for a company of our scale and size, I would say, Peter, it also made us more complex for people in the capital markets to actually assess. You know, it's one thing if you're a$50 billion market cap company, people will do the work. But if you're not that, it's just harder, just being honest about it. So simplicity, I think, had value.
SPEAKER_01Greater market cap. Now, your footprint is beyond Alberta. So maybe for those that don't know, tell us a little bit about where you have generation assets and other types of businesses.
SPEAKER_03It is. We've got 88 facilities, and uh they're scattered in three different countries. So Canada, the United States, and Australia. In Canada, we're in Alberta, British Columbia, Ontario, Quebec, New Brunswick, in the U.S., Washington State, Wyoming, Michigan, Pennsylvania. I'm just giving you a flavor, you know, New Hampshire, Massachusetts, North Carolina, Minnesota. And then in Australia, we're in Western Australia, where we've been operating for, I think it's approaching 25 years now, uh, in that jurisdiction.
SPEAKER_03And quite a mix of generation, I would say. We have hydro, gas fire generation, wind and solar generation. So quite a mix of facilities, you know, 30, about 35 wind facilities, 25 or so hydro facilities, and the balance would be uh natural gas fire generation scattered in in the country. So quite a bit of diversity.
SPEAKER_01And how much of, like you said, you have 88 generation facilities, like how big is Alberta and part of that? Is it still a the majority or so?
SPEAKER_03Alberta is in terms of the installed capacity, around 58%. So just under 60% of the total installed capacity. And about 70% of that would be merchants. So our contracted business is largely outside of Alberta. And our more merchant-exposed business would be in the province of Alberta. And so, you know, rather than looking at the actual megawatts, we tend to think in terms of, you know, where does our EBITDA come from? So Alberta would be just less than half of the EBITDA of the company.
SPEAKER_03And then, you know, the rest of the world, if I can use that expression, uh, even though it's Canada, would be would be the rest. And it's probably that rest of the world, if I can call it, that's actually growing more rapidly than certainly the intra-Alberta businesses.
SPEAKER_01Right. And we'll talk a bit about Alberta as well.
SPEAKER_02So all the buzz last year uh was about AI and data centers and the growth. And that was only displaced by tariff chaos, which we're still somewhat experiencing. But the AI story certainly hasn't gone away. We were, I mean, Jackie and I on the podcast talked extensively about the fantastical numbers behind the electricity load growth in data centers. And so three, four months have gone by since the whole Trump election and the tariff chaos, as I call it.
SPEAKER_02Where are we at in terms of the whole data load growth expectations, both here in Canada and in the United States and more broadly?
SPEAKER_03It's a super fascinating question, Peter. And look, I'll digress for 10 seconds. What a lot of people don't realize is if you go back about 20 years ago, we were actually, because of efficiency and whatnot, actually seeing sort of, you know, load per capita or the amount of consumption that people were reusing on an individualized basis actually decline, you know, over time, only to see that level up and now move into a place where you're seeing higher growth. So I would say traditionally, certainly in the Canadian context and in Alberta, for example, one, one and a half percent a year growth wouldn't have been kind of a bad number, you know, in terms of a long-term average.
SPEAKER_03What we're thinking of now, and look, and we do a lot of fundamental forecasting internally in our company, it's up quite a bit. So we're thinking two, three now, and that excludes data centers. So just in terms of efficiency measures, general economic growth, population growth, and depending on the jurisdiction, you can see that nudge to four. And in fact, I think load growth last year, so 2024 globally, was 4.4%, like a pretty big, you know, number. Like that wasn't sort of a North American number, but it's a it's a pretty big number to deal with.
SPEAKER_03So then that would be excluding data centers. If we put data centers into the mix, and and I agree with you, Peter, there's been a lot of fantastical, I think is the only way to describe it kind of numbers that you hear from people. You could see anywhere, if you look at forecasting, and let's just take them at face value, you could see data centers going from effectively a very small component of load today to something in the 10 to 15% range by kind of 2030 time frames, if people are correct.
SPEAKER_03And that would be not just in Canada, but you know, in the United States. And just to give you context of what that means, we've seen forecasts of you know load growth for data centers alone anywhere between 40 gigawatts to 100 gigawatts by a 2029-2030 timeframe. So imagine building 50 to 100 large-scale nuclear facilities. I mean, that's the way you know, think of a gigawatt as a really large nuke.
SPEAKER_03Like, I don't know how you do it. So, like I hear all of and like, you know, we can talk about the supply chain too during the call, because I I'm just being a realist. I'm not sure how you do that. But even if you cut it in half or cut it by two-thirds, it's still a huge number and a number that is going to take a lot of work, both from industry, customers, and frankly, um, you know, regulators to be able to kind of meet the need for. It's it's staggering.
SPEAKER_02Yeah. So if we say a nuke is okay, just call it a gigawatt. Call it a gig, just so if you wanna, if you need a hundred gigawatts, it's a hundred nuclear plants. And the average natural gas fired power plant is typically what, a third of a gig, right? Sure. Three, four hundred megawatts. Call it four hundred megawatts just to make it simple. The equivalent number would be then three hundred equivalent natural gas-fired power plants, which is just huge, isn't it?
SPEAKER_03Let alone setting up the wires to move the power around effectively from the way that you need it done. So it's easy to put out the numbers. You know what I mean, Peter? When you kind of break it down to what it actually means, it's staggering.
SPEAKER_01Yeah. Well, here, just for example, in Alberta, there's something like 12 gigawatts of projects in the ASO load queue, which is like the equivalent of our average consumption for the year.
SPEAKER_03That's peak.
SPEAKER_01Yeah. So, you know, that's not all true. And I know Transalta has some projects as well in that. Maybe you could talk a bit about those. But also, you know, as an Albertan, and I'm looking at, we'll get into the Alberta power market. I'm getting concerned about are the right incentives going to be there with this new design for people to invest. And meanwhile, you know, we have uh maybe some of this generation being uh moved over to serving data centers. And what does that mean for the reliability of power in the province?
SPEAKER_03Yeah, we could probably spend, I think, probably three hours on this one alone. So I'm gonna try to sort of break it down. I mean, and look, and we can we can just chat it through. So it is a tremendous opportunity for companies like ours and the province. We're focused on our key pills facility in particular as being a center where we would have data centers come in. And when you think of natural gas, speed to power is critically important. So there's existing infrastructure in Alberta that is underutilized now, and that includes a number of our facilities that maybe 10 years ago would have been running, call it 80% of the time, and now are running, call it 30% of the time.
SPEAKER_03So the ability to, you know, repurpose some of that to meet incremental load that comes in, I think is probably a first place that we should be looking at when you think about reliability going forward. But Alberta's blessed with, you know, good temperatures, a good workforce. We're long power right now, generally speaking. We're blessed with plentiful natural gas supplies that are, you know, from a North American perspective, very well priced. So when you put it all together, and and we have a government that is supportive, generally speaking, of moving it forward.
SPEAKER_03So there's a lot of work that's being done. I know sometimes there's some patience with our investors, is sort of like, you know, why can't you do it in a week or so? It does take a lot of time to get it done. But I would say the broader environment in the province of Alberta is a very good sort of prospective one for data centers, um, you know, when you think of it going forward. But we do need to do it thoughtfully. 12 gigawatts. I don't know how we do it, Peter. Just going back to the conversations we were having on the build required. Not sure how you do that. I'm not sure it's all real, candidly, in terms of, you know, where, because it doesn't take much to put an application and get in the queue.
SPEAKER_03So I think they'll come. And then I think there is an amount that I think you can bring in using existing generation that maintains reliability of the system. And the ISO is doing that work now. And I, you know, we're looking for them to confirm that next month, actually, in May. You know, our view is it's probably some number less than two gigawatts that you can bring in and kind of manage. Think of it as one and a half to two, given transmission and reliability constraints. And then thereafter, you're gonna need to be thoughtful about overall reliability on the system.
SPEAKER_03And, you know, to get the kind of reliability that a lot of these data centers are gonna need, I mean, I think they will be looking to greater connections. So you'll have generation that will be on site to supply them, but to get that tier four, 99.999 that some of them may need, having the ability to backstop 5%, 10%, whatever your needs are off the grid is important. So being thoughtful about that, being thoughtful about what it means to pricing in the province and reliability is going to take a little bit of work for sure.
SPEAKER_02Right. So just to elaborate on that, a lot of these data centers are proposing to have their a dedicated, say, natural gas-fired power plant that is not connected to the big transmission lines, in other words, the big the grid, but that your power from Transalta would be fed into these data centers as sort of backup and at times to provide that 99.999% reliability that they need over and above their dedicated power plant.
SPEAKER_03That is right. You know, when I think of our proposal and the way we're thinking of it, Peter, you know, our facility would be able to go both ways. So we'd be able to supply the data center. And if for whatever reason there was excess, you know, our ability to excess generate power beyond their needs, we could put it onto the grid to supply things that way. But I think you've you've described it very well.
SPEAKER_01Okay. So another constraint to this whole thing will be uh you know, at some point, not just here in Alberta, in every jurisdiction, you're gonna need some new generation to serve all of this load. And uh we understand that it's very hard to get natural gas generation equipment because there's long lead times and you know, they're sold out. On top of that, I think tariffs are probably complicating the whole situation. Like if you import equipment from China, it got a lot more expensive. If you're in Canada and you're bringing in some goods from the US, they suddenly have tariffs uh potentially on them. So, how are tariffs impacting that?
SPEAKER_01And, you know, the situation was bad before, but are tariffs making it worse?
SPEAKER_03So on the tariff piece, I think there's really two pieces there. We we actually do export power into the US. So there was initially a bit of a concern about tariffs just impacting power flows, you know, between the two countries. That doesn't appear to be a major issue, it being more of a service than than kind of an item, you know, a good. So so right now, I think that's less of an issue. So your point on the supply chain is exactly right. Like we don't, you know, if we're building a wind farm, I just think of the wind farms that we just built in Oklahoma, for example. We had components that were coming in into the US there that were made in the US, in Mexico, in Belgium, in Denmark.
SPEAKER_03In the past, having blades coming from China or other parts of Europe weren't uncommon. Gas fire generation, you know, we would be typically, for example, gee, looking at U.S. supply for that. Steel can come from both sides of the border. I mean, we do get a lot of steel here produced here in Canada, but then there's breakers and transformers and, you know, it fuses all of those kinds of things. So there is a lot of uncertainty right now. It makes it very hard to plan, makes it very, very hard to price.
SPEAKER_03And I would say it's compounding a tight supply chain to begin with. And I'll I'll give you a sense of what that looks like. So, you know, you used to be able to get a transformer, say, in 50 weeks. You may now need 120. The price of the transformer has gone up 60 to 80 percent. If you need a high voltage transformer, you won't get it in 120. You may need 200 to get it.
SPEAKER_03It could take four years for you to get the transformer. You know, 500 kV. Copper prices are up, electrical steel prices are up pretty dramatically. You know, you used to be able to reserve your slot from a manufacturing perspective, including for turbines. Hard to do that now. They want firm commitments. So you're gonna have to actually make a financial commitment. You may need to pay prepay, you know, 30% of the price of that today to make sure that you'll be able to get the hardware that you need, call it two to four years from now, to be able to get something done.
SPEAKER_03And then you add to that kind of the vagaries from a tariff perspective, like it's hard. Like it is super hard. So, Peter, going back to the discussion on day data centers, imagine, you know, building out those kind of very difficult to do. I mean it's just it's a practical matter. Yeah, very, very challenging to do today because everything is elongated and it's hard for the supply chain to respond. Just being straight up about it.
SPEAKER_02Yeah. I mean, even steel prices for transmission towers and all that stuff.
SPEAKER_03All of it is up. If I go back five years ago, we would often talk about sort of a million and a half dollars a megawatt, rough price, Canadian. And it kind of didn't matter what the generation type was. Like honestly, whether it was solar or gas or wind, broadly the same. So 100 megawatts would cost you call it 150 million, right? It wouldn't surprise me if that's 300 million today. So that one and a half in a relatively short period of time has gone to 3 million a meg. And depending on what you're doing, you can easily nudge up well beyond that. You know, we've seen some projects being proposed that are more in the four range.
SPEAKER_03So the power prices you need to basically justify a return of an on-capital and justify doing that project are like they're higher. It's harder to get that. And I'm not even talking about transport. I just want to give you a flavor of kind of what that now they might come down, you know, as we get through this supply chain issue that we've got. But if you assume the load growing the way that we're talking about it, it growing, I like I think we're in this for quite some time in terms of tightness.
SPEAKER_01Well, and you know, you talked about you have to make decisions early, but with all these tariffs that may or may not be there, how can you make decisions? Because you're like, maybe I wait six months and there isn't a tariff and uh it puts everything on hold. Doesn't it?
SPEAKER_03And it's hard for our customers too, right? Because they're trying to figure out what their pricing is going to be as well. So it's challenging, no question.
SPEAKER_02Yeah, I think there's going to be a data center reality check coming here at some point. Because I mean, these things compete with the ability of people to turn the lights on or turn the stove on or the hairdryer or whatever. And You know, haven't even talked about electric cars because they're still growing in the background. They are. So it's just uh there's just a sense of unrealism. But let's let's migrate to Canada here or bring it home to Canada and talk specifically about the opportunities here. So what are you seeing in the different provinces and what's underway?
SPEAKER_02Uh, there's some nuclear in Ontario, there's renewables in Quebec here or there. What's going on?
SPEAKER_03So it's interesting when you look at Canada, and you know, you can go sort of west to east. So you look at BC, they're gonna be short power. You look at Saskatchewan, they're gonna be short. Manitoba's gonna be short. Ontario's short. Quebec's gonna be short. And these, you know, look, you look at Manitoba and even Ontario and Quebec, these are these are BC um jurisdictions, Crown Corps generally, uh, or significant Crown Corps in in the markets, with a lot of hydro and, you know, just blessed with all these great resources. So there is a sense that they're tight.
SPEAKER_03Some of their needs from a supply perspective are going to be and are being met by calls for power, contracted arrangements through RFPs and whatnot going forward. So we are seeing growth across the country in pockets and in areas where traditionally the Crown Corporation would have done it by itself, just given what the capital requirements are. So there are opportunities. We are both jurisdictionally, I would say, and technologically agnostic. Like what we care about is returns, you know, how competitive our processes.
SPEAKER_03We actually don't have a lot of contractual arrangements with government entities, like most of our customers, it's either the wholesale market or it's really industry, you know, commercial and industrial players that we serve. So it's a little bit different. So our team looks at these opportunities and we consider whether it makes sense for us to participate in them or not. But I don't see us right now, just speaking for our company, we're focused a lot on meeting kind of uh the Canadian RFPs that we're seeing. We're we're more focused on the Western US and some of the opportunities that we're seeing in Western Australia, in part because our near-term growth opportunities, which were in Alberta, we've kind of paused because some of the uncertainty around, you know, the market redesign.
SPEAKER_03It's just very hard to be building in this market right now, pending a bit more clarity in terms of how things are gonna go. So we are focused a little bit more outside of our borders. And look, the US is a huge market. The opportunity set is significant and candidly, you know, significantly bigger than ours as a country. So there are opportunities for sure. And I think we're gonna see more of them over time as things get tighter.
SPEAKER_01I want to come back to your thoughts on Alberta, but just before we leave this Crown Corp procurements, because you know, they seem like they're kind of risk-free and that, you know, they're backed by the government versus a corporation, but they're quite competitive. And I know a lot of them have like binding prices. And when you look at the uncertainty right now, we just talked about it. What are the price of this equipment really gonna be? Are there gonna be tariffs on it? We're gonna, I guess, find out with the election. Um, but you know, there's concerns around ITCs. Yep. Uh now CPC did clarify on their platform, which by the way did come out after our podcast last week that they will keep the ITCs, but there was uncertainty around carbon pricing.
SPEAKER_01Is it gonna be in or out? And so it's you can win these bids and then find out all your assumptions are wrong, right?
SPEAKER_03Yeah. And in fact, we saw it when, you know, we saw wind procurement here in the province of Alberta. There was a number of parties that won, but they didn't actually end up building the projects. I mean, they just bid them at prices that were unrealistic and you were unable to get them done. So they're challenging processes for sure. And there's supply chain risks. Uh, there's timeline risks too. A lot of them have relatively aggressive, you know, time frames to get things done and permitted and actually constructed in what is a relatively turbulent environment. So, yeah, they're it's look, they can be very good counterparties, and I think you can do well with them, but you know, eyes wide open, there can be challenges as well.
SPEAKER_03And going in and renegotiating a contract with a government entity, if things have gone sideways, I suspect is harder than doing it with maybe a private sector. I mean, there's actually been evidence of that that it's just hard.
SPEAKER_01Right. Yeah, and more uncertainty than ever in terms of uh these bidding processes.
SPEAKER_02So uh Jackie, first of all, I want to issue you a warning from the jargon police here, ITC. That's investment tax credit. And specifically the investment tax credits for decarbonization, things like uh CCS carbon capture and sequestration. And in indeed, I mean, we we have to see what the the new federal government is view is gonna be on these ITCs because they're highly consequential.
SPEAKER_01Yeah. Also for clean generation, but it does actually look like the conservatives are gonna keep it, and of course the liberals as well. Um, so I think that one's a little less risky, but like John brought up, there's other policies too, like the clean electricity rag, and yeah, it can affect your costs.
SPEAKER_02I think it'll depend upon what sort of budget is brought down. But anyway, that's post-election talk. Let's bring her home to Alberta, John, and tell us what's happening here. Talk about the redesign, changes the way transmission is charged, all that kind of stuff. Because we are the only deregulated province in the country. All of the other provinces have basically state-owned utilities like BC Hydro, Ontario Hydro, Hydro Quebec, et cetera, et cetera.
SPEAKER_03Sask Power and the rest. Yeah, for sure. I would say our jurisdiction has gone through a remarkable transformation. I mean, we went from a period not very long ago, Peter, like, you know, roll back eight years ago, maybe, where we had, think of it as sort of 17,000 megawatts of installed capacity to deal with an 11,000 megawatt peaking load. Roll forward to today, it's more like 25,000 megawatts of installed capacity to deal with, you know, a 12,000 megawatt load.
SPEAKER_03And effectively, because we were the only deregulated market in Canada, if for whatever reason, you know, ESG obligations that that companies establish. So if you're, you know, pick a Canadian big bank and you wanted to notionally say, I'm going to decarbonize my branch system in the province of Ontario, you would procure to have your wind farm built in Alberta, essentially, to notionally power that load in a different, and those electrons weren't migrating from Alberta to Ontario, by the way.
SPEAKER_03There's no way to get them there. So the build happened here, largely. And we had a very vibrant, like, look, we build wind farms too. It was a very vibrant uh marketplace and a lot of a lot of things were built. Now, the build-out that occurred in the province had nothing to do with fundamental supply and demand within the province. It was sort of, this was the jurisdiction that you built things because it was pretty much the only jurisdiction where you could in a similar sort of way. So roll forward to today. Look, I think the government is trying to, and it's not just our government, you see it all over the world.
SPEAKER_03People are struggling with how do I balance affordability, reliability, and responsible decarbonization in a way that makes sense. We often talk about a three-legged stool, right? And if one of the legs is broken, the whole thing tips. So you gotta, you gotta do it right. And over the last number of years, there was a lot of discussion around decarbonization, not a lot on reliability and a bit on affordability. Reliability matters. So what's been interesting is as the intermittency from the renewable build out has occurred, our systems in many cases are becoming less reliable.
SPEAKER_03It's becoming more challenging to actually make sure that the lights stay on. Because in any given hour, you might see, you know, multiple thousands of megawatts of change in supply. And you need the system to respond to that. And today, I know I woke up this morning only to see that the grid was down in Spain and Portugal. And I'm just like, oh my God, like, you know, these two countries, you know, were blackouts, right? National kind of blackouts, which are sort of staggering to see what they're dealing with. So I think the idea was let's look at the system we have today and try to address a bunch of different issues, one of which was what is the impact that renewables are having on reliability in the marketplace?
SPEAKER_03And how are they, you know, for lack of a better way of expressing it, displacing maybe natural gas fire generation and making it harder to be economic, you know, going forward. And I think what compounds things is a sense that certainly in Alberta, but other jurisdictions are grappling with this. You know, if if you just have a spot price for your power, you expect everything to be paid out of that. So for example, there is a ton of value in fast start capability.
SPEAKER_03There is a ton of value in being able to load follow. There's a ton of value in ancillary services, there's a ton of value in inertia. All of these constituent components have value. Not all generation can meet all of these things. So, you know, natural gas fire generation is particularly good at meeting all of these attributes. And look, we're one of the country's largest wind generators. Wind is not. It just isn't in terms of doing all of that. Yet they're all basically receiving the same price, if you see what I'm saying. So it is challenging.
SPEAKER_03And, you know, we're at a$38 a megawatt, I think is what our average price is so far, Canadian, in Alberta this year. And that is challenging. That is not a price that certainly incents new generation in a province like ours, and is a price that at times will be challenging to kind of keep gas in the market to ensure reliability. I think the government was trying to address that. And I think we tend to like simplicity in the province. And you hear a lot of, you know, a lot of the commentary was it's too complicated and whatnot. Fair enough.
SPEAKER_03But we are going to have to address reliability and make sure that all of the various elements are getting paid appropriately. And, you know, one of the things we observe is over time, the electrons are becoming less valuable. And it's all of the ancillary elements that keep the system working and the lights on that are becoming more valuable. So the question becomes how do you ensure that value is recognized and compensated for to make sure that our that our system works? Not an easy thing to do, uh, and not an easy thing to do in a way that is simple.
SPEAKER_03And there's no, and you know, I can't point to a single jurisdiction in the world where and we look at them. Like we look at everything from Ireland to Singapore, from you know, Germany to PJM, from the CAISO to, you know, ISO New England, like everywhere to see like every jurisdiction has challenges and every jurisdiction has, you know, limitations in terms of doing what it needs to do. So, but they're all fussing with the same kinds of issues.
SPEAKER_01Right. Well, it sounds like you're optimistic. There needs to be change, but you did say that you're not investing in Alberta right now. We're not. Yeah.
SPEAKER_03We're at one of the companies that do think the market does need to evolve in an appropriate way. You know, whether what was on the table is the right thing or there are better ways to do it is a different discussion altogether. But, you know, I'm not sure a system that was developed 25 years ago. Like we at times were enamored with the status quo, but like I'm not sure it was gonna get us to where we needed to get to in the future. For us, you know, we had probably about 600, 650 million dollars of growth projects are our kind of our latest stage growth projects, you know, wind farm, peaking gas.
SPEAKER_03We had a very large battery project tied to our hydro west of Calgary. We did put that all on pause in, I think it was mid-2023 when some of the market redesign was done. It's just too uncertain for us. I was gonna say risky, but it it's not, it's not so much the risk. We we need to understand the risk. Do you see what I'm saying? And so landing the construct of the market redesign is important, at least for our company, to understand like where will it actually settle? And then at least for us, like I want to see what is the fidelity of the pricing?
SPEAKER_03Like, is it investable or not? Does it make sense for us to make the kind of investments that we need to make in the province given the new construct? And it's hard to predict that today. We still have work to do. And in fact, the ISO, you know, has pivoted a little bit from what it was proposing to do to something that's a bit more streamlined. So we, you know, we had a large modeling team working on the design that was on the table. We've had to pivot now over the course of the last couple of weeks uh to reimagine kind of what that looks like for our units. So it's more getting an element of certainty, frankly, in order for us to be confident on the investments.
SPEAKER_03And remember, yeah, our capital competes with other jurisdictions too, right? So if there's other jurisdictions that are more certain, it's just easier to put it there.
SPEAKER_02I just want to ask about, well, as an independent corporation, Transalta, it's all about competition, competition for capital, investability, listening to price signals. The price signal right now, as you said, is$3.80 a megawatt hour, 3.8 cents a kilowatt hour, okay? Which is not really very much because in many jurisdictions it can be five times that easily. So we have a very cheap power here. In fact, it's so cheap in the near term, there's no incentive for Transalta to build new power.
SPEAKER_02Yet in the longer term view, you look at it, and from our prior discussion, you said, I mean, like you've got key components that take two to four years to procure for like uh gas turbines or transformers and things like that. So by the time you get four years out and you go, oh my God, the price has gone up five times, you've got to build and you get the right price signals. Now you got to wait four more years potentially because of all this data center stuff that's still probably not going away. You know, this is one of the problems with the deregulated system compared to the state-owned, is the state-owned can think long-term, whereas the deregulated has other benefits in terms of innovation and so on.
SPEAKER_02But the price signals are not sometimes strong enough to invest. There's other structural problems and some. I know I'm going on and on here, but I kind of want to understand this problem because I guess at the end of the day, the grid redesign has to try and accommodate the fact that we are not state-owned, but has to overlay a structure such that it incents long-term thinking. Is that what we're trying to do here?
SPEAKER_03So, at least from a transalta perspective, my short answer would be that is what we should be trying to do, Peter, just to kind of address your, you know, your last point, I think. So you're exactly right. So if I were to look at, let's just use your 400 megawatt example for a gas plant, Peter. So let's say I want to build that in the province of Alberta. I've got pricing right now that is called$38 Canadian a megawatt hour. And our expectations are data centers aside, coming in and maybe tightening our supply and demand fundamentals, we're in a protracted period of weaker pricing.
SPEAKER_03So that is pick your number,$25 US. And it's probably a bit artificially that high because there's a carbon price component to it as well. If I need$50,$60,$70 US to$120 US in terms of a levelized cost of building something new, I can't do it. And then you factor that in in a merchant market where I have instability, both in terms of regulatory intervention and how things evolve, because I'm going to need 15 to 20 years, right, to get my return of it on capital on that investment.
SPEAKER_03It is really hard to do. So going back to that 400 megawatt power plant, let's say it cost me$3 million a megawatt. So I need$1.2 billion for the plant. And now I've got the clean electricity regulation. So I'm worried about carbon emissions and whether the plant's going to be able to run after, you know, the late 2040s or the 2050s. And something we always muse about is we've been burned as a company. So one of our lessons are you tend to think that the regulatory environment is static. And it doesn't, it changes on you right over time.
SPEAKER_03And it could change either way, but even if it stays, carbon captures like 2 billion more on that. Maybe, maybe more. So for a company like ours, given our size, to make a pick your number, call it a$3 billion investment with something that has contained carbon in a merchant market in a relatively small jurisdiction like Alberta in the grand scheme of things, is hard. I'm I'm just at least from our company. And then, you know, your capital is then competing against contracted opportunities in other jurisdictions, whether it's in Western Australia or in the United States.
SPEAKER_03And so it's a challenge, right? It's a real challenge. Just being straight up about it.
SPEAKER_01And you talked about the potential for regulation to change. Am I wrong that this change the Alberta government just made makes that even more of a risk for you because it's easier for them to make change? Or I'm not sure.
SPEAKER_03I so I, you know, look, we spent a billion and a half dollars. It was Transalton Capital Power to build keep hill 3. It was commissioned in 2011. That was a plant that we were expecting to run. I think it was to 2063. And that plant is no longer on coal, it's on natural gas. And like I will it get to 2040? Do you I'm just being, you know, straight up about it. Like we've had, you know, we had a previous government that passed legislation that resulted in coal fire generation having to be shut down by 2030, for example.
SPEAKER_03You know, we have current market redesign. And that's all happened in the space of, you know, a decade, basically, all of those kinds of changes. And I'm not even including, you know, things like the clean electricity regulation and carbon pricing that is being mandated from a federal government perspective. So, you know, it's kind of trite to say it, but I pray for certainty. Like just kind of almost like leave the rules alone for a while. Do you know what I mean? And and and just so that I have a sense of what to do, but we're buffeted, I would say.
SPEAKER_02I don't think I think the word is not certainty. I think the word is stability.
SPEAKER_03Stability is a better word. You're right.
SPEAKER_02There's always uncertainty. It's just managing uncertainty.
SPEAKER_03That's right.
SPEAKER_02But if there's no stability, then you can't even handicap the uncertainty.
SPEAKER_03Like, what do you what do you model? You know what I mean, Peter? Like, I don't, you know, and is it real? Yeah. In terms of where we are, and add to that a supply chain that is super challenged.
SPEAKER_01Well, John, this has been a great conversation. We're running out of time. We could more to ask you, but one question that's on my mind, because it's a been a big discussion in the election, is this idea of an east to west transmission line. Uh, we want to trade electricity across our country just like every other good, and we have all these interprovincial barriers. What are your thoughts on the likelihood of that? And is that a good thing or a bad thing, especially when you consider our makeup of what we are, 12 different electricity jurisdictions?
SPEAKER_03Look, I wish we were talking about building more pipelines candidly across the country more than transmission lines. It's a laudable kind of thought. I think it is hard to do, and I'll and I'll tell you why. So I think, and you've touched on it. So how does Alberta trade with Saskatchewan, for example, from a power perspective when they don't even have a price? Like what's their price? Like, I have a price. BC doesn't have a price. Manitoba doesn't really, you know, I'm just like it's a different, like they've got Crown Corps, and we don't.
SPEAKER_03So the seams issues between the jurisdictions are not insignificant in terms of seeing it through. And I think it does require an evolution in the markets to kind of see it through. Like it works well in countries that have sort of a unified kind of construct. We don't. Very hard to deal with that. Secondly, I think it's super expensive. Like building transmission from, you know, I don't know, Quebec through the Canadian Shield, like through the prayer, like over the Rockies. Like we're talking billions of dollars, and we're talking jurisdictions that are all largely expected to be short.
SPEAKER_03So it's not like we've got a glut of power in one jurisdiction that you can move to kind of deal with the issues of the other one. What happens if it's really cold in BC and Alberta? Alberta needs the power. So does BC. Is BC going to actually move the power to make sure that Alberta's needs are met? I mean, I like I don't know how you deal with those kinds of issues. Given the cost, I think it might be cheaper to just deal with the power needs of each jurisdiction, like within the jurisdiction, if you see what I'm saying, rather than doing a big grid that goes across the country.
SPEAKER_03I just from a cost perspective. Like we're talking billions of dollars, billions.
SPEAKER_02Yeah, and and and match the energy source to the supply in the region. That's critically important. Yeah. So if you've got a lot of hydro, hydro makes sense. If you've got a lot of natural gas, natural gas makes sense and just sort of match what makes most sense for each region.
SPEAKER_03And that's one of the reasons we have, and I'm going to digress for just 30 seconds, like the clean electricity regulation, which we sort of talked about a little bit obliquely. Its lens is sort of a national lens. And to just touch on what Peter said, you can't do that. Like you got to look at, like in Alberta, like without natural gas, we are in serious trouble. Literally, I was in investor meetings in London probably about two and a half years ago. And I remember, you know, here I am defending Alberta. Like, why don't you guys have more renewables, blah, blah, blah. And it was minus 30 back home.
SPEAKER_03And literally I said to him, look, I showed him actually the ISO page. And I said, we have thousands of megawatts of wind, hydro, solar, and we're water poor in Alberta, let's be honest, right? We own all the hydro basically in Alberta, but it's not going to save the province. We had three megawatts of wind that day. Like if it's minus 30, there's no wind. If it's minus 30 and it's night, there is no solar. Same thing. If it's plus 35, there is no wind. So if we didn't have natural gas and it's minus 30, what are we doing here in the province, right?
SPEAKER_03So to Peter's point, I think you need to look at each region's natural advantages. And when we're thinking of decarbonization, we can't forget about reliability and affordability. Like we can't, like building 10,000 megawatts of nukes in Alberta, like who's going to build that? Like who's going to pay for that?
SPEAKER_01So we got to look at local advantage, frankly. Well, the clean electricity rag, though, would let you put CCS on those natural gas plants.
SPEAKER_03But I can't afford like who's going to pay, like the CCS, at least based on what we know today. So, first of all, I am not sure because I can't point to a single circumstance in the world today where the kind of capture rate I would need to capture on the CCS is like slam dunk. And the cost of the CCS is more in the power plant.
SPEAKER_01So it's going to definitely increase the electricity cost.
SPEAKER_03So who's going to pay for that? And what does it mean about the competitiveness, which we don't talk about enough in this country, about our industries, especially when our, I know we're having a little bit of turbulence in our marriage right now with the US, right? But the US is critical to us. And we need to make sure that when we power our industry, that it is competitive with, you know, what the circumstances are there. I mean, that's just a personal, you know, view. And I, and if we're pricing things, whether it's through carbon policy or or, you know, whatever the industrial needs are, we will be impacting our industry.
SPEAKER_03And I think we need to be very thoughtful and careful about, you know, what that means in the in the broader global context. And I don't I just I don't think we talk about that enough.
SPEAKER_01Right. Yeah, like by our math, if you want CCS on a power plant, you're talking about electrons that are twice as expensive, maybe more. At least if they don't have that, then industry probably will go there.
SPEAKER_03And I will need a certainty of revenue stream, just going back to your earlier comment, Peter, to be to kind of have the confidence to be able to make that investment, right? To get that through. So what's the construct that lets me do that?
SPEAKER_02Well, John, we've talked about so much. It's fascinating. Talked about electricity demand, trends, tariffs, equipment shortages. We talked about this country, provincial, regional issues. It's just been a great conversation. We hope to have you back as these things develop. The only thing we didn't talk about is politics. But Jackie and I will take it on next week after the federal election. So once again, John Kuzat Nyaras, President and CEO of Transelta. Thanks so much for joining us.
SPEAKER_03Jackie Peter, thanks so much. A real pleasure.
SPEAKER_01And thanks to our listeners. If you enjoyed this podcast, please rate us on the app that you listen to and tell someone else about us.
SPEAKER_00For more ideas and insights, visit Archenergy Institute.com.
This episode is also available as a video on YouTube. US imports of Venezuelan crude oil rose from nearly 100,000 B/d before this year’s US intervention to almost 700,000 B/d in August. This influx into the US Gulf...
This episode is also available as a video on YouTube. This week on the podcast, Peter and Jackie cover the US midterm election results and their potential implications for energy policy and Canada. They discuss why...
This episode is also available as a video on YouTube. British Columbia has seen a major political shift with the election of a majority Conservative government led by Premier-designate Lorne Doerkson after nine years of...
This episode is also available as a video on YouTube. This week on the podcast, Peter and Jackie review the latest election news, including the BC election, which produced a Conservative majority government over the...
In this week's podcast, Peter and Jackie discuss global oil and diesel markets, the government’s role in major infrastructure projects, including the Pacific Link pipeline, and widening Canadian heavy oil discounts....