Fixed Income · Curve-Based and Empirical Fixed-Income Risk Measures. Read by an AI voice. The lesson page, its interactive solver and the quiz: https://analystdojo.com/level-1/fixed-income/curve-based-risk-measures/price-change-with-effective-duration Next lesson: Key rate duration CFA Institute does not endorse, promote or warrant the accuracy or quality of Analyst Dojo. CFA® and Chartered Financial Analyst® are registered trademarks owned by CFA Institute.
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Chapters
Introduction
Price change with effective duration and convexity
The formula in three steps
The callable bond, up and down 100 bp
The interactive: up and down at once
Reading the result: callable and putable
Go deeper
Traps and takeaways
Quiz
Transcript
From the show. Tap a time to play from there.
This is Analyst Dojo: lessons for the CFA Level One exam. Today: Price change with effective duration and convexity, from Fixed Income · Curve-Based and Empirical Fixed-Income Risk Measures. Price change with effective duration and convexity. This is the second lesson of Curve-Based and Empirical Fixed-Income Risk Measures, the thirteenth module of Fixed Income. The lesson before it was Effective duration and effective
convexity. Now you turn those two measures into an actual estimate of how much a bond's price moves. It is the same two-term formula you met in the convexity module, with the curve shift in place of the yield change. The new twist is what negative convexity does to the answer. On the exam you will calculate the percentage price change for a shift in the benchmark curve, given effective duration and effective convexity. Expect a callable bond with negative convexity and a move of 100 to 200 basis points.
The wrong options treat the convexity as positive, ignore it altogether, or use basis points instead of decimals. The formula uses three substitutions. Effective duration replaces modified duration, effective convexity replaces convexity, and the benchmark curve shift replaces the yield change. And the shift is a parallel shift: every maturity on the curve moves by the same amount. Here it is: the percentage change in the full price is about minus effective duration
times the curve shift, plus one half times effective convexity times the curve shift squared. In plain words, a straight-line estimate from duration, then a correction for the bend. Work it in three steps, with the shift as a decimal, so 100 basis points is 0.0100. Step one, the duration term is minus effective duration times the shift. Its sign is opposite to the shift. Step two, the convexity term is one half times effective convexity times the shift
squared. Because the shift is squared, this term takes the sign of the effective convexity, whichever way rates move. Step three, add the two. Here is what sets the sign of each term. The duration term goes against the shift, so a curve rise means a price fall. The convexity term follows the sign of the effective convexity, whichever way the curve moves. A callable bond at low rates has negative convexity, so that term hurts you both ways.
A putable or an option-free bond has positive convexity, so that term helps you both ways. Take the callable bond from the previous lesson, with an effective duration of about 4.7 and a large negative effective convexity. First the curve goes up 100 basis points. The duration term alone is a loss of about 4.7 percent. The convexity term is negative for this bond, so it adds a further loss of about 0.8 percent. Together, the price falls by about 5.5 percent.
Now the curve goes down 100 basis points. The duration term flips and becomes a gain of about 4.7 percent. But the convexity term does not flip. It is still a loss of about 0.8 percent, so the total is a gain of just under 4 percent. Look at the asymmetry. The bond loses about 5.5 percent when the curve rises, but gains only about 4 percent when it falls by the same amount. That lopsidedness is what negative convexity means.
Now an option-free bond with the same duration and a positive effective convexity. Here the convexity term is a small gain both ways. Up 100 basis points gives a loss of about 4.6 percent, a little smaller than duration alone. Down gives a gain of about 4.9 percent, a little larger. Here the gain is bigger than the loss, so the asymmetry runs the other way. Same duration, opposite shape, and the sign of the convexity makes all the difference.
Here is the same calculation in words. Multiply the effective duration by the shift and flip the sign, and you get the duration term, a loss of about 4.7 percent. Then take half the effective convexity times the shift squared, keeping its minus sign, and you get a further loss of about 0.8 percent. Add them, and the price falls by about 5.5 percent. For the fall, the duration term flips to a gain of about 4.7 percent.
The convexity term does not change, because the shift is squared, so it stays a loss of about 0.8 percent. The net result is a gain of just under 4 percent. The lesson page has a solver for this price change. You can pick what the question asks for, such as the effective convexity, and the shift box takes basis points. For instance, type minus 100 in the shift box to see the down move, or change the convexity to plus 30 to see the option-free contrast.
If you want a go, use the lesson page after the episode. For now, I'll keep going. The lesson page has an interactive that shows the up move and the down move at once. It has a box for effective duration, a slider for effective convexity, and a slider for the benchmark curve shift. On the lesson page, you can slide the convexity from negative up to plus 30 and watch which bar is bigger, the loss or the gain.
Or you can push the shift out to 200 basis points and see the convexity term grow faster than the duration term. If you want a go, use the lesson page after the episode. Here is a tip: check the sign last. The duration term goes opposite to the shift, and the convexity term takes the sign of the convexity and never flips. Now how to read the result. The two signs tell you who wins and who loses. With a callable bond, the upside is limited when rates fall.
The call is the issuer's refinancing option: buy the bond back at the call price, then borrow again more cheaply. The investor gets a smaller gain and has to reinvest at lower rates. A putable bond is the mirror image. The downside is limited when rates rise, because the investor can sell it back at the put price, usually par, and reinvest at the higher rate. Effective duration and convexity both fall as rates rise, but the convexity
stays positive. Now a putable bond with an effective duration a little over 4, moved up and down by the same amount. The duration term goes against the shift, and the positive convexity term adds in both directions. So when the curve rises, the loss is trimmed to about 5 percent. When the curve falls, the gain is about 5.7 percent. So the gain from a fall in rates comes out bigger than the loss from an equal rise. That is the shape an investor would like.
One point explains why the estimate is only local. A callable's effective duration is not constant: it shortens as rates fall and the call moves into the money. So the estimate is accurate near today's rates, and a very large fall can change the inputs. A second point makes a sharp case about negative convexity. If up and down moves are equally likely, the average of the loss and the gain is a small loss of about 0.8 percent, which is exactly the convexity term.
So a symmetric shock gives a negative expected price change. The bond must therefore offer extra yield. A manager expecting falling rates may still accept it, but only if the extra yield is worth the capped upside. First trap: plugging in the size of the effective convexity and adding it as positive. Keep the negative sign. Second trap: entering the curve shift in basis points, 100, instead of as a decimal, 0.01.
Third trap: expecting the up and down moves to give mirror-image answers. They don't. Fourth trap: forgetting the one half in the convexity term. Fifth trap: flipping the sign of the convexity term when the curve falls. Only the duration term flips. Takeaways. The formula is minus effective duration times the shift, plus one half times effective convexity times the shift squared. Keep the sign of the convexity: negative convexity hurts you both ways.
Callables have capped upside, and putables have a cushioned downside. And the estimate is local, because effective duration changes with the level of rates. That is price change with effective duration and convexity, the second lesson of Curve-Based and Empirical Fixed-Income Risk Measures. Next in this module is Key rate duration. Now three quick questions, and none of them needs a calculator. Each one pauses for a moment before the answer.
Question one. A callable bond has negative effective convexity. The curve rises, then falls by the same amount. How does the convexity term behave? A: It is negative on the rise and positive on the fall. B: It is negative both times. C: It is positive both times. The answer is B. The shift is squared, so the convexity term keeps the sign of the effective
convexity whichever way the curve moves. Only the duration term flips with the direction of the shift. Question two. Relative to a duration-only estimate, negative effective convexity makes a callable bond's estimated price rise when rates fall... A: Larger. B: The same. C: Smaller. The answer is C. The convexity term is negative whichever way rates move, so it is subtracted
from the duration gain. Question three. An option-free bond with positive convexity and a callable bond with negative convexity have the same effective duration. The curve rises by the same amount for both. Which loses more? A: The callable bond. B: They lose the same. C: The option-free bond. The answer is A. The duration terms match, but the callable bond's negative convexity
term adds to its loss, while the positive convexity term cushions the option-free bond's loss. That was Price change with effective duration and convexity. The lesson, its solver and the quiz are at analystdojo dot com. Next: Key rate duration.