Prakash Narayanan and Nathan Labenz discuss frontier AI, then speak with Mike San Miguel of Luxor about used H100 prices, Vera Rubin’s power and cooling demands, B300 rental rates, and Bitcoin miners’ prospects as AI hosts. The episode also examines GPU resale risks, AMD software compatibility, data-center failover, and the potential costs of restrictions on AI rentals and US-China cooperation. Chapters (0:00) GPU prices meet power limits (2:33) Frontier AI labs carry a World War Two vibe (3:25) The misaligned superintelligence is already here (4:13) After the election, Big Tech pays full price (6:28) Meet Mike San Miguel from Luxor (7:34) Vera Rubin makes the building the bottleneck (8:34) NVIDIA checks the site before it ships (11:32) No two GPU servers trade alike (14:25) Delayed buildings put new GPUs back on sale (16:50) Higher H100 rents keep old fleets working (18:36) B300 contract rates trail headline rental prices (19:40) AMD compatibility could collapse H100 prices (20:47) Running an AI factory is the real test (23:09) Failover needs spare GPUs nobody has (24:23) Scarce sites shift outage risk onto customers (25:59) Fit the hardware to the workload and building (27:59) Why pressure companies instead of writing laws? (29:21) Chinese demand for AI reaches past the GPU (30:07) Overzealous rental bans could cost US-China cooperation (31:31) A confused model can still do real damage Guests Mike San Miguel - Sr. BD Manager, Luxor This is a public episode. If you would like to discuss this with other subscribers or get access to bonus episodes, visit briefing.ai-in-the-am.com
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
SPEAKER_01Not every site can operate every GPU.
SPEAKER_02Vera Rubin is strictly a liquid cooled solution. The cement slabs that those go on have to be reinforced. Typically, those are what, like a ton per rack. The weight is insane. The power draw is about 230 kilowatts per rack. To give you some comparison, for two B300s, you're looking at 30, 35 kilowatts per rack. If you're deploying in a... Typical Tier 3 Colo, Flexential or Equinex or Coresight.
SPEAKER_02Typically, NVIDIA has already been through those and they've already validated that those sites can run that hardware. If it's a new one, you'll be more likely to have NVIDIA require an on-site investigation, basically where they go through and they certify the site for their green-white allocation. The gold standard that most hosts want to have is they want to get that giant deal from Google or Anthropic or Meta. You want to be able to prove out that you can operate AI factories It's a scale
SPEAKER_02so that you can pull down a $9 billion contract and lock in at a specific rate for your GPUs over three years, five years. The problem with that is you have to show people that you can actually operate things and match SLAs. You've got a $50 million site gets hit by hurricane, You're kind of out of luck for being able to hit your SLAs. So where this is eventually going to go, where smaller sites make more sense, is having redundancy across different sites, having smaller sites,
SPEAKER_02different area codes, different states, just like any other cloud, so that you have a good failover. The tough thing is you have to have capacity on GPUs in order to actually be able to failover to redundant hardware.
SPEAKER_00First, the hosts on frontier safety workers who feel a wartime duty, an AI whimper scenario already living inside our institutions, and a data center backlash that could raise big tech's costs. Then, Mike San Miguel of Luxor on why Why no two GPU servers trade alike, how delayed buildings put new chips back on sale, what H100 rents say about old fleets, and why running an AI factory is the real test. And to close, the hosts on Washington legislating instead of pressuring companies,
SPEAKER_00Chinese AI demand beyond GPU sales, compute rental bans, and the harm in AI simulation confusion. Nathan has flown back from Bletchley Park, where codebreakers built the bomb to crack Enigma, and where in November 2023, governments held the first AI safety summit. The site carries a wartime memory. And the frontier labs, he says, feel it too.
SPEAKER_01At the frontier companies today, the vibe is amazing. Kind of a World War II vibe, especially among people that are interested in the safety questions. You know, I've had this conversation several times where people are just like, you know, I didn't choose the AI moment to be a part of, just like the people in World War II didn't choose the war. But I just feel like I kind of have no choice but to stick it out and see it through and do my best. And hopefully, you know, my contribution will mean something and hopefully together we'll like, you know, get a win.
SPEAKER_00In 2019, Paul Cristiano wrote an essay called What Failure Looks Like. Its first scenario, going out with a whimper, has no robot uprising. Institutions optimize for what is easy to measure until nobody can steer. Prakash's question, does that need AI at all?
SPEAKER_03I think the existing systems that keep nation states together today are essentially misaligned superintelligences. I read through Paul Cristiano's work again. His first thesis is, you know, you're going out with a whimper. He's like, you know, companies that only care about profits, governments that only care about staying in power. So why do you think like AI is going to be worse than that? The whimper scenario is now. It's pre-AI. We are in the wake of a Major, major change in politics, I guess, a regime change, so to speak.
SPEAKER_01You have like, what was it, 40-some ballot proposals all across the country, all but one of which passed to restrict data centers in some way.
SPEAKER_03The AI data centers, there's one big advantage, which is they're spending a lot of money. And there's still a lot of margin there. And number two... I think also that they employ a lot of blue-collar labor. He's building Colossus II in Louisiana. I think he's paying like $8,000 a week for electricians. And electricians are being pulled in from all of the surrounding southern states. It's very hard for Dems to come out and say, like, we are not going to have this money get spent. It has to be spread around in different ways.
SPEAKER_01Expect that, like, it's not the top issue for very many people at all. But at the same time, we do have these ballot initiatives. And like 40 ballot initiatives... From what I had read a little bit is like one of the bigger waves of ballot initiatives. This is one area where people can come together across partisan lines or whatever they may think of Trump or whatever they may think of, you know, the sort of biggest topics of conversation at any given point. And they can organize.
SPEAKER_01On just a very narrow issue-specific basis. And the fact that we did see so much of that and that they all won, I guess, with one exception, does to me seem like a sign of things to come.
SPEAKER_03I agree, but I'm like, why? Why did they sign? One of the things the companies have been doing, they've been doing the old school oil and gas landman way of acquiring land, which is they go in and they acquire land at pennies on the dollar, Using LLCs. And after that, they merge the pieces of land. And then they're like, oh, Meta is here. And then people are like, if I knew I was selling to Meta, I would have asked for more. So people feel cheated. The outcome of this is that if you're going to be Google or Meta,
SPEAKER_03you're going to be paying Google or Meta prices for everything. For the land. For the labor. For the construction. Right?
SPEAKER_00This episode asks who gets to run the newest AI hardware and what it takes to turn a rack of GPUs into a service a customer will actually pay for. Mike San Miguel sits where those deals get done, and he has spent the year telling buyers to check the building before the chip.
SPEAKER_03Our guest for today is Mike San Miguel. He works in CPU and GPU sales at Luxor Technology. His business is helping buyers source the processors and servers that run AI systems. Luxor built its business serving Bitcoin miners and now also works with AI infrastructure operators supplying hardware and arranging contracts for computing capacity. With colleague Ian Philpott, he has written about the differences between buying Bitcoin mining machines and building AI infrastructure.
SPEAKER_03The designs that make a data center's components work together and the possibility of running AI and Bitcoin mining at the same site. Hi, Mike. Welcome to the show.
SPEAKER_02Hey, Prakash, Nathan. Thanks for having me on.
SPEAKER_00The average data center rack in the world draws about 8 kilowatts by the Uptime Institute's count. NVIDIA's newest systems ask for more than 20 times that. So what actually stops an existing building from running the newest GPUs?
SPEAKER_02Not every site can operate every GPU. Vera Rubin is strictly a liquid-cooled solution. That's NVIDIA's next generation. The cement slabs that those go on have to be reinforced. Typically, those are what, like a tonne? The weight is insane. The power draw is about 230 kilowatts per rack. To give you some comparison, for two B300s, you're looking
SPEAKER_01at 30, 35 kilowatts
SPEAKER_02per rack. Not every site can do Virarubin. Not every site can do GB300, which is similar to Virarubin on power. So, you know, it'll make sense to convert some sites. It won't make sense to convert other sites.
SPEAKER_03Who examines the site, right? Is the site just purely the responsibility of the person running the project? Or does NVIDIA come in and look at the site and say like, hey, I don't like this. I don't like that. I'm not going to sell you this.
SPEAKER_02So it's not just an NVIDIA thing. It's also a legal thing. There's some compliances. These things are traded more closely than some nuclear secrets. So every OEM is a little bit different. NVIDIA works closely with all the OEMs around allocation and around greenlighting orders. You're deploying in a Typical Tier 3 Colo, Flexential or Equinix or Coresight. Typically, NVIDIA has already been through those and they've already validated that those sites can run that hardware.
SPEAKER_02If it's a new one, you'll be more likely to have NVIDIA require an on-site investigation, basically where they go through and they certify the site for their green light allocation. NVIDIA also typically is going to check every six months and make sure those GPUs are where they're supposed to be. Physically come on site and actually make sure that they haven't left. There's been such an issue with a lot of these getting traded illegally. There's a lot of countries that are known for diverting orders to people
SPEAKER_02that aren't supposed to have them. I think most recently made the news there was a CEO of a reseller out in California that got busted and So the compliance is very strict, but generally NVIDIA is going to be a little bit more in depth on larger deployments and deployments that are not at sites that
SPEAKER_03Do they do a KYC of who is the person buying the thing or who owns the person buying the thing?
SPEAKER_02Actually, part of my role here was spinning up our KYC department. A lot of the OEMs will not even quote without KYC being done. Some will not ship without it being done. Internally, We basically do not accept projects without KYC being done, except in some rare circumstances where it's big names or companies that we've worked with for years. There are limits on what percentage can be owned by China, where the deployments are.
SPEAKER_03What percentage of that company can be owned by China?
SPEAKER_02I think they might be going down to 49%. I know typically 50% or more. You can't sell to companies that are on 50% by a Chinese entity. So for us, we're going to trace back not just who the hardware purchaser is, but also if they have an offtake. They're signing an agreement with a NeoCloud company. You cannot legally sell this equipment with the off-taker being a Chinese entity, for instance.
SPEAKER_03Let's talk a little bit about Luxor. Let's talk about the AI-specific area. So you guys do a lot of trading on used GPUs, I believe. I believe H100 nodes, for example, you trade them. How does one trade...
SPEAKER_02So we do both new as well as refurbished. So we're value added resellers for most of the OEMs. It's a tough thing because not all of these assets are apples to apples. You know, with the crypto space, basically those ASICs or t-shirt sizes, you get a S19J Pro and They're all the same. With servers, everything's more tailored than a t-shirt size. It's all built to suit. Within an H100, you might have, you know, one terabyte of RAM, two terabytes, three terabytes. And that's, you know, Five-figure differences each time you go up, typically,
SPEAKER_02the way everything's traded now. Used inventory moves fast. It's more of a per lot. You try to see where the market's at. But H100s have been trading so infrequently
SPEAKER_01that the market rate for the hardware is tough to get right.
SPEAKER_02And typically, the customers who end up getting those are willing to pay or adjust to what
SPEAKER_03So what is trading frequently?
SPEAKER_02Right now, it's mostly B300s.
SPEAKER_03Do they trade as a chip or as a node or as a rack, as 8 together, or how does that work?
SPEAKER_02So typically for these servers, it's an HGX system. So eight GPUs per server, validated build, built by an OEM. So you've got the HGX baseboard, dual CPUs, 32 sticks of RAM, depending on the size RAM, shared storage, east to west NICs.
SPEAKER_03And how much does one of those cost off the top of your head, like right now, asking price or clearing price right now?
SPEAKER_02Depending on the specifications, the OEM, warranty terms, all of that, you're looking anywhere from 550 to 650. Typically, for bulk orders, it's on the lower end.
SPEAKER_03550 to 650 grand for an HX system with eight B300s, two CPUs, and some number of sticks of RAM.
SPEAKER_02Typical configurations are two terabytes, three terabytes, and sometimes they get up to four.
SPEAKER_03What is a typical lot site? One rack system, more like 10 rack systems, 100 rack systems?
SPEAKER_02The units per rack come down to the data center configurations because that's about how much power can be delivered to each rack. Most data centers will be able to operate two per rack right now unless you've got a really nice dense supporting DLC. In terms of sizes, we trade everything from one or two units up to about 128 or 256.
SPEAKER_03Is there a lot of liquidity in the market?
SPEAKER_02They're moving really fast. Even on the smaller end, Lenovo had this AI Express SKU that was offered up that they sold out within, what I want to say, three weeks when they started offering that. And that's specifically not for NeoClouds. That's a different separate inventory. I have a specific number for you. I don't. Typically, if there's excess inventory, abandoned orders, those usually
SPEAKER_01move within one or two weeks.
SPEAKER_02All the different resellers that we're partnered with are closing deals weekly, if not daily. Why is there excess inventory? Part of it has to do with data center availability. So this market's looked like a series of different bottlenecks. Right now, it's liquid cooled and data center readiness. So that number I gave you with most data centers being able to support, let's say, two nodes per rack, that has to do with constraints not on the actual hardware side, but on the data center's power to load.
SPEAKER_02Same with sort of the cooling build out as well as sort of a bottleneck right now. Liquid cooled, we're starting to see data center inventory coming available January, Q1. But most of that's already sold out. There's a lot of data centers that are now telling us it's Q3 2027 or 2028.
SPEAKER_03Are people trading the market? Are they buying the systems without having places to plug them into?
SPEAKER_02No, typically what happens is last minute you'll have a project push. And that's why some of these OEMs will reserve the right to resell inventory. If let's say one of their hyperscalers sites isn't ready, they'll be able to sell that inventory and then backfill it when that data center gets to be ready. Typically you have to have an address. And if they sell to, let's say a smaller... You know, a number of different smaller customers for access inventory. It's easier to get those placed.
SPEAKER_02You know, not everybody has a five gigawatt facility waiting. But, you know, if you can find some customers here, they've got a megawatt, half a megawatt, and they're air-cooled, they're fine with the less dense deployment, meaning fewer B300s per rack, then yeah, they'll make that deal.
SPEAKER_03I see these, like, You know, rental price indexes. Does that rental index impact your trading prices at all?
SPEAKER_02It does. So the best sort of case study I can give you is what happened when Nebius raised their pricing on H100s back at the beginning of the summer. So let's say around April, H100s were routinely going on the market, probably 150K to 175 each, depending on the configuration. Nebius raised their H100 rates. From $2 to $3, something like that.
SPEAKER_02All of a sudden, H100s are trading now at $250 to $350, depending on the lot. A lot of the neoclouds started holding on to H100 as well. So things that they thought about decommissioning, all of a sudden, they're still profitable. They're not going to decommission them. Now, in terms of the specific indices that track that pricing, it doesn't fluctuate as much on a day-to-day. Typically, it does create scarcity. The higher a rate that you can rent these out for, the less likely people want to decommission them.
SPEAKER_02Indices are not perfect. They're only taking into account a single node that's online that can be rented out or rented out per GPU. They're not taking into account a bulk AI factory rental where you've got a customer that's renting out, let's say, a 32 node to a 256 node install. It's only on specific areas, but for the more legacy systems, that would be more likely to be rented out one at a time.
SPEAKER_03It certainly affects the market. Do you see the same dynamic with the B300 pricings?
SPEAKER_02Not as much yet. And part of that is that it's a much higher barrier to entry. So one of the areas that we help our customers with understanding is this difference between a contracted rate and an hourly rental rate on these GPUs. So if you look at like an AI factory contract rental for B300, typical market price right now is $420 to $450 an hour, depending on the market that you're in and the configuration. Now, if you're only getting $4.20 per GPU per hour,
SPEAKER_02that's a very different rate from what you're going to see on those indices. That's $8 to $9 per hour per GPU. So if you have the capital to go out and buy a lower amount of nodes, deploy them, then typically you can get a better rate of return as opposed to buying a full AI factory Negotiating an off-date contract with NeoCloud.
SPEAKER_01One kind of big picture question, of course, people have is, is this just all going to be up and to the right until the singularity? Or might we expect some sort of boom and bust type cycle as we've, of course, historically seen in various parts of the semiconductor industry? As like a leading indicator, do you see anything that is... Kind of suggesting there could be bad moments to come?
SPEAKER_01Or is everybody just scrambling to get everything they can online and it's just all up and up?
SPEAKER_02So right now, GPUs are very limited in terms of software. Most things are based around these CUDA libraries. And that's part of the reason why H100 is still so profitable.
SPEAKER_01So as AMD, their GPUs
SPEAKER_02get to be more compatible with CUDA libraries. I foresee that being what's going to cause H100 and H200 prices to collapse. Typical life cycle of this equipment is, you know, max seven years.
SPEAKER_00In June, Mike and colleague Ian Philpott wrote that buying GPUs is not enough. A validated reference architecture has to make compute, networking, and storage behave as one system. So what sits inside an AI factory beyond the GPUs? And who can actually run one?
SPEAKER_02All an AI factory means is that it's not just GPUs. So within an AI factory, there's a storage area network. There's management servers, which do not have GPUs. There's a shared storage environment that actually processes and collates all the data so it can't die on a single device. There's north-south networking that works on all of these components. And then there's the GPU servers that have their own back-end east-west networking, which if you hear someone talking about InfiniBand or Rocky,
SPEAKER_02that's the fabric going on connecting all the different GPUs. There's also an out-of-band networking management stack as well. AI Factory means the whole thing. The gold standard that most hosts want to have is they want to get that giant deal from Google or Anthropic or Meta. You want to be able to prove out that you can operate AI factories at scale so that you can pull down a $9 billion.
SPEAKER_02So that means, all right, you have to get your skin in the game, right? Maybe it's converting a site, which is a whole business model on itself. And then you have to get expertise to be able to keep up and running not just the GPU servers, the WAN connections, but also the rest of the AI factory. So within one solution, it's not just the GUI and the hardware management for the AI servers.
SPEAKER_02Each part of that AI factory has a different GUI. There's a different one for the shared storage. There's network. Network engineers are the highest paid people on the hardware side because it's a very specific skill. It's very tough to do. So when you're building out these solutions, typically it's a good idea to start small.
SPEAKER_00Luxor's own reserved capacity contracts promise a customer migration to equivalent hardware if a provider underperforms. That promise assumes there is somewhere to migrate to. So what happens to a service guarantee when one site goes dark?
SPEAKER_02One of the other reasons we'll see people deploy smaller is going to be based off of resiliency. Right now it's so cost prohibitive. You can really only have one workload. Living on each AI factory. The issue is that if you have, let's say, one data center in Florida. Well, Florida gets hurricanes. You've got a $50 million site gets hit with a hurricane. You're kind of out of luck for being able to hit your SLAs.
SPEAKER_02So where this is eventually going to go and where smaller sites make more sense is having redundancy across different sites, having smaller sites, different area codes, different states, just like any other cloud, so that you have a good failover. The tough thing is you have to have capacity on GPUs in order to actually be able to failover to redundant hardware.
SPEAKER_01I want to go back for a second to something you had said around like, Having a data center in Florida, getting hit by hurricane, now you can't meet your SLAs. Who has what negotiating power and leverage as these deals come together? But how are you seeing these sort of who owns what risk and who's willing to kind of shoulder what burden potentially recalibrate, you know, given how desperate these companies are for compute? I signed a $300 million contract.
SPEAKER_02For three years, right? Which is for about 128 node or 256 nodes, not a giant install. If that data center goes down, all of my workload goes down. There are redundancies and some financial considerations that are baked into those contracts, but you're still playing that game. You're still making a gamble. Not all data centers have a cloud connector. So typically it's only the big tier three sites that have a direct connection
SPEAKER_02to an AWS or Google. So if you lose that data center, you could in theory lose all of that data that's on there. It's a tough thing because they have to make these considerations, these decisions on the risk. And they don't always have a lot of leverage. Only so many sites that are getting deployed Although these deals are getting made, there's a timeline risk as well for 6 to 12 months to get the exact site that you want.
SPEAKER_02So it's a lot of different considerations, and each customer has to make those decisions for themselves.
SPEAKER_00Mike's August buying guide for Rubin told operators what he would actually buy. And the answer turned on the workload and the room, not the headline ship. So how does an operator fit the hardware to the job and to the building it already has?
SPEAKER_02We're going to start sizing to workloads. So with traditional storage area networks and cloud, private cloud, hybrid cloud, all of that, we run sizing. We build out those types of installs. We can see what, you know, Actual components are being utilized, whether RAM is being utilized in an intelligent way, storage, media, the hard drives, the actual CPUs. Most CPUs in the storage area network are only operated between like 10, maybe 20% tops.
SPEAKER_02So with a lot of these GPUs, I do suspect that there's some underutilization that's happening and there could be much more intelligent use cases. As we stop being quite so focused on specific GPU models. Some of the different OEMs are offering versions of Vera and Rubin. Vera is the CPU stack, Rubin is the GPU. If you buy just Vera, I don't believe that would have to be liquid cool
SPEAKER_02and it's going to be less power dense. So you can spin up a great agentic cloud. And a legacy data center, depending on the power constraint. AI is a family of different workloads. All of them have different requirements. But we need to get more efficient with how we size to the workload. Because the whole point of this hardware isn't to own the hardware or to support NVIDIA's next trillion dollar milestone. The point is to run a specific workload that has real world implications
SPEAKER_02for end users and helps create new businesses.
SPEAKER_00America's chip export rules govern hardware, where an advanced GPU can chip. Renting time on those GPUs from a data center outside China sits in a gray area. The rules never closed. So when a cloud deal with a Chinese customer dies, who killed it?
SPEAKER_03Oracle selling capacity to Tencent, $7 billion of capacity, that was canceled. So the national security infrastructure is pressuring these companies to cancel that. It's an American company doing business. It's outside China and not sending chips into China. And at the same time, there is no pushback on the political infrastructure that is allowing this. Why don't you just make laws? Why pressure the company?
SPEAKER_01I agree with that. I mean, I thought it was also very strange when the 20s series of GPUs, like the H20s, the B20s, whatever, there was this sort of Rule was created and it was like, this is the maximum thing you can sell to China. And then it was like, okay, well... Naturally, then we're going to make a product that is like right under that maximum and we'll sell it to China. And somehow that was then, you know, like, how dare they?
SPEAKER_01Well, it's like, well, they're literally just adjusting to the rule that you just gave them.
SPEAKER_03Note another thing. We say compute is the new oil. So you decide not to sell compute to China, like zero, zero Chinese content. Do you also mean that, you know, YouTube cannot show AI generated video to Chinese companies? Like participants, to Chinese viewers, to Chinese customers. That is an AI product. Google has to use compute. And that compute is going to be used on behalf of a Chinese customer. The price of American compute will go up as a result. But where do you restrict?
SPEAKER_03You can restrict it at GPU level. You can restrict it at the data center level. You can restrict it at the raw compute level. You can restrict it as a product of compute level. But at some level, you're going to end up selling to the Chinese because they are global consumers.
SPEAKER_01I think we get a little carried away sometimes with these restrictions on China. There was a pretty strong idea at one point that a good compromise was renting compute, but not selling it into Chinese ownership and control directly. We're going to say, Oracle can't rent. You're going to dramatically ratchet up the pressure on all the smuggling and everything else. So I do kind of worry that sometimes we just get so overzealous on some
SPEAKER_01of these things that we may end up kind of shooting ourselves in the foot. I really think we are going to need cooperation between the US and China on AI governance. You have, as we recently talked about, A super senior person at a frontier company telling me at the curve that there's a level of intelligence we probably just shouldn't go beyond. If that's the view that has now taken hold at the top levels
SPEAKER_01of frontier model companies in the US, the only way to achieve that is going to be through some sort of agreement. And we're really not Putting ourselves in a great position to make that agreement. So a lot of this stuff seems ultimately quite self-defeating. And it makes me sad.
SPEAKER_00OpenAI's monitoring reportedly found its models underperform on AI safety tasks, compared with the same tasks framed as capabilities work. Researchers have a name for a model that deliberately holds back. Sandbagging. Whatever the cause, what if that model is out on the real internet?
SPEAKER_01Benign explanations have been offered. One thing to emphasize is like, our kind of benign explanations, it doesn't necessarily change the impact. If Claude is confused about whether or not it's on the real internet or some fake internet, but it in fact does go and social engineer somebody into merging malicious code into some widely deployed open source package, it's bad regardless of exactly what the source of the problem was.
SPEAKER_00Mike San Miguel is Senior Business Development Manager at Luxor, where he matches buyers of AI hardware with the sites that can actually run it. His work can be followed through Luxor. [music]
Nick Allardice, President & CEO of GiveDirectly, explains how Google flood forecasts helped families in Nigeria receive cash before flooding, and what it takes to make aid and AI tools work across local languages, weak...
When AI chips can be rented through overseas cloud providers, controlling where the hardware goes may not be enough. Ryan Fedasiuk, Senior Fellow at the Foundation for American Innovation, joins Prakash Narayanan and...
Thoughtful guest Brian Zhou and Theory Ventures’ Bryan Bischof join Prakash Narayanan and Nathan Labenz to examine AI agents in election forecasting, model evaluations, data science, and investment research. The...
ServiceNow threat researcher Michael Freeman describes AI-driven compromises costing 5-10 cents, credential theft through support tickets, and why autonomous patching is not ready for critical infrastructure. Mistral...
Kepler Computing CEO Debo Olaosebikan explains how ferroelectric memory could increase cache density and improve high-bandwidth memory using standard fab equipment. Arena CEO Anastasios Angelopoulos discusses agent...