SPEAKER_00Hey everyone, thanks for being here. It's my first podcast. I've got Ed Zarensky here. Ed is a construction economic analyst. He basically forecasts large scale construction projects. He has a thriving practice and he's very active on Twitter. You know, when the LA fires erupted, I reached out to him to chat offline. about not just the scale of the devastation, but what it would take to rebuild L.A. So we're going to first just kind of let Ed introduce himself,
SPEAKER_00what he does, maybe his framework for how he goes about doing these things, and then we'll dive into L.A. And we're going to get a kicker at the end with an outlook on the construction outlook for the U.S. Ed, so tell me, Ed, what do you do?
SPEAKER_02Well, thank you, David, for having me. So what do I do? Well, first off, I've been in construction since 1971. So I've got over 50 years of construction experience. I was an estimator for 35 years. And in the final days before I retired back in 2014, not only did I do estimating project costs, but I was an analyst to come up with Outlook. And so I looked at all of the information about what's going on
nationally and
SPEAKER_02what's driving construction. Now, when you look at projects, are you looking at like, you know, what's the scale here?
SPEAKER_00Are we talking civil engineering, bridges? Are we talking skyscrapers? No,
SPEAKER_02most of the projects that I've done in my career were buildings, schools, offices, hospitals.
SPEAKER_01Prisons.
SPEAKER_02Big buildings. For instance, one of the projects that I had in the middle of my career was the, and this was back in the 1980s, the $2 billion renovation of the Prudential Center area in Boston. That included maybe about six buildings. That included work over the turnpike. So there is some civil work involved in some of the things that I did in the past.
SPEAKER_02What I do now is strictly analytics on construction economics. I haven't estimated the cost of a building per se in 10 years. but I've been doing every year and sometimes two or three times a year, revising the outlook of what's coming down the pike, what new starts should we expect, what's gonna drive the construction economy over the next year. And I keep a blog, edzerinsky.com.
SPEAKER_02It's a free blog for everyone's use. And the most visited aspect of that blog is the information that I capture on construction inflation. Literally, I get 1,000 views a week on construction inflation.
SPEAKER_00Going back to the construction estimates, how granular do you get? Let's say you're doing a building. Are you talking just the main materials? Are you getting down to... you know, down to the thousands. I mean, big round numbers or granular numbers?
SPEAKER_02No. So there are different levels of estimating where you go from conceptual estimate, where you don't know much about the building yet, but you know it's going to be 100,000 square feet and it's an office. you would look at some historical costs and you would work up a historical cost from previous buildings that were built, how big they were, and advance all of those costs by inflation up to the current time and say, okay, a 100,000 square foot office building should cost this much today.
SPEAKER_02When you're doing for construction the estimate for a cost of a of a building might be 30 or 40 pages with 50 or 60 line items on a page so you really do get down you estimate all finishes every every type of finish in the building whether it be paint whether it be carpeting, whether it be ceiling tile, what kind of ceiling tile. So you might have five different kinds of ceilings in the building. You might have five different kinds of walls in the building,
SPEAKER_02one layer of gypsum each side, two layers of gypsum each side, firewall. So you get into the knit and the grit when you do a total building cost estimate for the final guaranteed maximum price.
SPEAKER_00Got it. Man, I should have you over at my house next time I do a home renovation project so you can keep my contractor in check, huh?
SPEAKER_02Yeah, yeah, yeah. Yeah, go ahead. Go ahead. Big projects. I mean, you know, there's often a call for we're going to do a renovation of these floors of the building. Tell us what the renovation costs might be. Those types of things. I've estimated a million square feet for Fidelity. I've estimated for the Bank of America. I've estimated for Prudential. I've estimated for the state of Massachusetts prisons,
the state of Rhode Island schools.
SPEAKER_00All right. So we know you know what you're talking about. All right. So let's get to L.A. Let's first define the scope of the problem. And obviously... This is a very fluid situation. It's literally developing in real time and it literally changes with the winds. As we know, the Santa Ana winds are a big catalyst for changing the direction of the fire and the location of the danger spots. So literally changing with the winds. What do you know about the scope of the problem in Los Angeles
with respect to
SPEAKER_00damaged buildings? Not economic damages, Not, you know, utilities, but just buildings. What do you know? What I've read so far, and I try to revisit every day to see what new information has come out. The best estimate that I've seen is about 10,000 buildings have been destroyed.
SPEAKER_02Holy cow. I've seen estimates as high as 12,000 and I've seen estimates down in the 5,000 range. And is there a distinction between residential, commercial, civil, whatever? At this point is not a distinction between residential and commercial. I have seen no estimates of what civil damages there may be, but we know there will be some. So...
SPEAKER_00Civil being things like bridges, roads.
SPEAKER_02Bridges, roads. There's going to be damage to roads. They're going to have to be pulled up and repaved. We know that. There could be damages to things like wastewater facilities that we don't know about yet. There could be damage, certainly damage to bridges, I would expect.
SPEAKER_00And utilities too, right? I mean, utilities would be, I mean, all these utility poles, all this stuff is going to be a big hit.
SPEAKER_02Right. That's all civil. So all of that stuff yet hasn't been quite defined. So what we read more about is the damages to the number of buildings.
SPEAKER_00Got it. But here's an offbeat question. This is purely more on the aesthetic side. Being from California, I spent a lot of time in L.A. And L.A., like a lot of cities that really grew spectacularly after World War II, has a lot of standing utility poles. I mean, even... Wilshire Boulevard, Santa Monica Boulevard, these really nice streets, they have literal eye pollution with these janky leaning utility poles.
SPEAKER_00What are the chances that during the rebuild, the affected areas have utilities put underground versus throwing poles back up? Because that's just a real ugly eye survey. I hate utility poles.
SPEAKER_02I mean, obviously, there's a chance. I haven't read anything that addresses that issue yet.
SPEAKER_00Is it cost effective? Is it cost effective, though? Like, is that just like? Now that you've got the hood open, might as well drop the cables in, right?
SPEAKER_02Well, if they're digging up all the roads, then that is a possibility. Is it cost effective? I haven't done an analysis to know that. I mean, it's cheaper, much cheaper, we know, to put up poles and wires overhead than it is to put underground. However, they're always more damaged. So it's cheaper to put it up. It costs more to maintain it.
SPEAKER_00Yep. And it's just ugly.
SPEAKER_02Maintenance cost goes down.
SPEAKER_00And it's just ugly as all hell. My God. You go drive, you know, we're talking to LA, Wilshire Boulevard, Santa Monica, you know, just gorgeous streets. And you got these poles leaning over full of cables. It's just like, my God. Anyway, moving on. So, all right. So going back, I think you mentioned 10,000 structures. Was that what it was?
SPEAKER_02Yep.
SPEAKER_00Okay. And we don't have any idea of the total square footage. So it could be a structure could be a porta potty or it could be a warehouse.
SPEAKER_02We do know some schools have been damaged or completely destroyed. You know, a house is on the range of two to four thousand square feet. A school is in the range of. 100,000 to 300,000 square feet. So we don't know yet in square footage what the total damaged buildings are. We just know a building count. One of the things that's going to be for us to look at is the building count and
the total estimated cost of buildings and ignore the square footage because square
SPEAKER_02footage cost changes with every type of building that you put up.
SPEAKER_00Well, I was going to say it's not uniform, right? In other words, it costs, you know, a square foot cost per square foot on a school versus a house versus a prison versus a warehouse versus, you know, these are very, you know, yeah. All right. So, all right. Starting with 10,000 structures. Let's get into the economics and the time of what it's going to take to replace that. And I've got some data on other natural disasters as a benchmark,
but let's just start with LA.
SPEAKER_00What are we looking at? And take us through your process to get to your final number in terms of or preliminary number on time and money. Let's go through it. So the two pieces of information that I started out with to do my analysis was
SPEAKER_0210,000 units, 10,000 buildings, and $150 billion worth of damage. Now, again, of the $150 billion worth of damage, we don't know how much of that is buildings, how much of that is cost to relocate people, how much of that is fire protection services. We just don't know. So the approach that I took was, let me estimate the cost to do $10 billion worth of work
And one of the things that I know from many years of dealing with construction data is it takes about 4,000 to 5,000 workers one year to put a billion dollars worth of
SPEAKER_02work in place. Wow. So what would it take to do 10 billion? It would take 40 to 50,000 workers one year to put $10 billion worth of work in place.
SPEAKER_00Does LA even have that spare, you know, Let's take a step back here. What's the labor pool and what's the available labor pool to do this?
SPEAKER_02Okay, so that's the second part of the way I approach my estimate. Knowing what I have in the value that I'm going to estimate, $10 billion, I wanted to see how many jobs exist, how many construction jobs exist in the LA area. And you can't just look at L.A. itself, L.A., Anaheim, Long Beach. What I did was I drew a radius 50 miles around up to the north. I went as far north as Oxnard and Santa Barbara.
Yep.
SPEAKER_00And that's because people commute, right? Is that the idea?
SPEAKER_02I'm just saying, yeah. You can't just look at LA. Some of the fires have been up in Malibu area. The Palisades Fire is starting to climb up towards. And both ends of Malibu Beach have fires on them. And that's getting closer and closer to Santa Barbara. So I went to Santa Barbara. I went to Riverside. And I went further. I forget what was to the south of L.A.
SPEAKER_00Long Beach.
SPEAKER_02Long Beach. Anaheim is, I think, to the south. So I drew this radius around and I opened up the Bureau of Labor Statistics, the census statements of how many jobs exist. And what they do is they give you metropolitan areas. And that covered those. That's why I chose those cities. All of the surrounding area of L.A. has a total of 400,000 construction jobs. And it's been pretty stable for the last four years.
It hasn't changed by more than one percent a year for the last four years.
SPEAKER_00Let me ask you this. Is this the on-the-books labor, or is this the off-the-books migrant, potentially illegal, undocumented?
SPEAKER_02It's the on-the-books labor. And we know, we just got a study published by the Harvard Center for Buildings, I forget what it is. the name of their... Anyway, all of that is in my article, which is why I write things down. I have a hard time remembering all of the things that I want to keep up in my head, so I write about it. Once I write about it, I can edit what I wrote and make it correct.
Anyway, we know that 50% of the construction labor in California is immigrant labor.
SPEAKER_02Now, that doesn't break out what is a documented immigrant and what is an undocumented immigrant. But we know, and we've read articles in the past, I read an article about six or seven years ago, published by Pew Research, that described how day labor works. And the day laborers, the undocumented immigrants, might drive to a parking lot.
SPEAKER_00Yeah, Home Depot. Go to Home Depot and you'll find a way to work. They wait for a contractor to come to them and say, I need five guys to do framing today.
SPEAKER_02Right. You, you, you, you and you come with me and your day laborer and you're back to the parking lot tomorrow. Yep. So we know that there are undocumented people working, but we don't have a count on that. And I can't even begin to guess at that.
SPEAKER_00I mean, yeah.
SPEAKER_02All right.
SPEAKER_00Anyway, so you got 400,000. total construction business in all the trade in all the construction trades all trades roofers framers everything that you can think of foundation people right blah blah blah okay right painters right electricians you know sheet metal guys everything okay now what i said is i've got this big area which is a 50 mile radius around the los angeles area that's a really big area and most
of that area is not
SPEAKER_02damaged by fire So I have 400,000 workers in that area. If I make an assumption that I'll take 10% off of that, and the 10% of those workers will now be concentrated working in the fire damaged areas. So now the rest of the 50 mile radius only has 90% of the labor that they were working with. So to some degree, the amount of work in that remaining not damaged area will go
down a little bit.
SPEAKER_02because they've lost 10% of their labor. I've concentrated 10% of their labor in the fire damaged area. So now I have 40,000 workers to work on damaged, to rebuild the fire damaged areas.
SPEAKER_00So what was your estimate for your comment earlier? 4,000 workers for every billion?
SPEAKER_02Yes, or 40,000 workers for every 10 billion.
SPEAKER_00Okay, and 40,000 is that 10% you just mentioned. And that just happens to, I hadn't planned it that way, but geez, that works out perfectly.
SPEAKER_02I pulled off 40,000 workers. I made my assumption that I would analyze $10 billion worth of work before I found out how many jobs there were in the Los Angeles metro area. And as it turns out, there's 400,000. I'm pulling 10%. I get 40,000 workers. So how much work can I do in a year? My 40,000 workers can do $10 billion worth of work in a year. Construction work. That does not include demolition.
It does not include the slowdown of the process because everybody's trying to do
SPEAKER_02the same thing at the same time.
SPEAKER_00Permitting.
SPEAKER_02It doesn't include the supply lines, which are going to get jammed. And there aren't going to be enough supplies in the area to keep everything going at a smooth pace. So things are going to go a little bit slower. A little bit less is going to actually get done. But I'm sticking with my 40,000 men to do $10 billion worth of work because it's a good solid estimate that I can show numbers to prove that that kind of amount of work can be done.
SPEAKER_00Okay. All right. So that puts us at a, you know, assuming 150 billion in construction damage.
SPEAKER_02Yeah, I assumed out of that $150 billion, $100 billion. It's the question I posed in my paper. So if I know it takes 40,000 men a year to do $10 billion worth of work, suppose the amount of damaged homes is $100 billion, it will take 10 years to rebuild this area. Now, one of the things that I have supporting that is if you remember about six or seven years ago,
SPEAKER_02the Santa Rosa area north of San Francisco.
SPEAKER_01Correct, the Tubbs fire.
SPEAKER_02Yep. The Santa Rosa area lost 3,000 homes to fire. Yep. As of today, only 80% of them have been rebuilt.
SPEAKER_00I think I have that data in front of me. Give me one second. I've got here 37,000 acres, 6,000 structures. And you said how much has been rebuilt? 80%. 80%. And that was in 2017.
SPEAKER_02Okay. So seven years have gone by. We're going on 80 years. Only 80% of the homes have been rebuilt in that area. Again, to build the homes in Santa Rosa, if you looked at Santa Rosa, they have 10,000 carpenters, 10,000 construction workers. It's the San Francisco- San Francisco, Oakland, that provides all of the labor to get.
SPEAKER_00And Sacramento. Sacramento also has a lot of people, too.
SPEAKER_02Sacramento has a lot of people. But I spoke to a contractor in Sacramento. He said, there's no way workers are going from Sacramento over to Santa Rosa. You got to go over the mountains to get there. And it's a two or three hour drive. So I used all the labor. I did a study for that one, too. I used all the labor in the San Francisco area. And I came up with, I forget how many, but I thought that it would take years to rebuild. And we have the exact same situation now with Palisades.
The data I have for residential is 3,043 residential units destroyed in Santa Rosa. As of October 22, 2,176 were rebuilt, 440 under construction, 288 under permit.
SPEAKER_00So this is October 22, so about two years ago, roughly. So make whatever adjustments. But to the broader point, I mean, the exactness doesn't matter. What matters is, This is a big deal. It takes a while. It doesn't happen overnight.
SPEAKER_01It takes a while.
SPEAKER_02Yes. One of the things that came up, I was having a discussion again yesterday on the same topic. There are not enough supply stores. You need lumber mills, you need lumber stores, you need Home Depots, you need appliance stores. You need all of these, you need concrete people. Not only do you need labor, but you need the supply lines to supply an extra thousand homes
a year in a very
SPEAKER_02concentrated area. So if you go down a street, in some of the photographs that I saw, you could look down a walking distance and there are 50 homes that are gone. You know, you're going to have so many truckloads of stuff coming into an area that size that you won't be able to deliver. Well, it's going to be the supply, but I mean, it gets delivered to the job sites. You just... The more crowded you make an area with workers and construction going on,
SPEAKER_02the less gets accomplished every hour you work. Let me ask you this.
SPEAKER_00Some people are going to say, you know what, I'm done with California, you know, earthquakes, fires, you know, state governances, you know, whatever. And they're just going to say, you know, maybe I've lived through one too many natural natural disasters in my lifetime. I'm done. I'm leaving. There's that crowd. There is a crowd that is uninsured and they just simply are displaced and will have to find shelter elsewhere.
There are parts that may be deemed by the state to be non-buildable again.
SPEAKER_00In other words, some of these things were developed after World War II, maybe before the war and zoning was different and no one cared. Now with different environmental regulations, different social priorities, Maybe the state says, you know what? We're not going to build it anymore. It's just, it's too dangerous. It's a tinderbox and we're crazy for doing it again. There's a laundry list of reasons of some element that will not get rebuilt. What do you put that at in terms of percent? You know, five, 10? What do you think?
SPEAKER_00Ballpark. Good question. I think the percent is going to be rather high because of the insurance issues in
SPEAKER_02the state of California. It's going to be higher than anywhere else because of that. As you've just mentioned, there are going to be non-insured homes. Those people are going to walk away. Right. What else can they do? Now, how many of those uninsured homes are owned by people that have $5 million in their pocket to rebuild?
SPEAKER_00Yeah, the Malibu crowd will be fine. Most of the Malibu crowd will be fine. But the people in Altadena or other parts that are not insured, those folks are going to have – there's going to be a higher rate of displacement or attrition. They're moving in with their in-laws, their son and daughter-in-laws. They're going to spend the next few years trying to figure out where's our next move.
SPEAKER_02Correct. And what that does – is that damages the surrounding economy. Some of these people are going to have to walk away from their jobs. If they don't have a home in proximity to where they work, and they've now moved 100 miles away to live with other family, they're not going to travel 100 miles to work where they used to work. Right. Which is fine for remote workers, but that's, you know,
that's, you know, the young people.
SPEAKER_00But if you're a teacher,
SPEAKER_02if you're in construction, there are no work at home people in construction.
SPEAKER_00None. Correct. Correct. Okay. So spitballing here. What do you think? Five, 10% don't come back. They say I'm done.
SPEAKER_02This is a wild guess, but I mean, you know, even if 10%, is the number. That's out of every $10 billion worth of work that we're estimating, a billion dollars worth of work goes away. So that's a lot of work. That's a lot of work. Although $10 billion is when you're looking at homes that range from, you know, 800,000 to a million dollars each.
SPEAKER_00I mean, that's not even a starter home in certain parts of LA. I mean, certainly not in Malibu, but even a place like Altadena, a starter, I'm kind of spitballing here, but based on my knowledge of, you know, LA, California real estate, you know, a starter ranch is going to be about a million. But anyway, that's a whole other thing. All right, so we've got a general number, which is 100 billion in construction for units,
SPEAKER_00whether those units are schools or structures. 100 billion for structures. It takes 4,000 for every 10 billion.
SPEAKER_024,000 for every billion. 40,000 for every 10 billion.
SPEAKER_00Okay, so we're looking at 10 years. But this is linear. This is a linear calculation. It doesn't factor in inflation. It doesn't factor in the feedback loops from demographics and the shifts in demographics that are going to happen as a result of this, whether it's less people moving in or whether it's people moving out or whatever. So this is a very static number, right?
SPEAKER_02As I have said, This is probably the best case scenario estimate. Because every one of the things that we came up with, supply lines, insurance issues, people that can't afford to rebuild, all of those things are going to reduce what can get rebuilt over time or how long it might take, it's going to extend how long it might take to rebuild it. So what I've come up with is probably a best case scenario.
SPEAKER_00So this kind of segues into, you know, what you talked about, one of the things you do is inflation forecasting for construction materials, right? So how do you think LA is gonna affect the construction costs at the national level? So, you know, supply chains, cost of construction, cost of labor,
SPEAKER_02I don't think it will have that much effect. Not on national level inflation data. There are so many other things that really are the key drivers to inflation. A massive amount of work in one location of the country will have an effect on the inflation in that area. So Los Angeles inflation will be elevated higher than the national average by an amount that is greater than what Los Angeles would normally be. Los Angeles and San Francisco are always higher than the
national average.
SPEAKER_02They're going to be even a little bit higher.
SPEAKER_00Got it. And what's your construction outlook for the, you know, when we got started, you mentioned that's something that you do. What's your construction outlook for going forward at the national level?
SPEAKER_02Well, construction is still advancing. I have residential construction slowing down a bit in the next two years. We went through a couple of years of massive increases in residential construction, but I'm anticipating about 5% a year for the next two years for residential construction. However, non-residential construction, I'm looking at 6% coming up this year and a decline next year.
SPEAKER_02But I consider the decline to be normal. And here's why. Two years ago, three years ago now, in 2022, we had massive amounts of starts in manufacturing facilities and data centers. And data centers has continued to increase and is still increasing. Manufacturing, on the other hand, is slowing down the number of new starts. And all of those buildings that started in 2022 have now been in construction for at least 24 months and potentially as much as 36 months.
So what you now have with the largest number that's affecting residential construction,
SPEAKER_02manufacturing spending, is starting to taper off. So the taper in manufacturing is going to show, and it's expected. When you have a massive influx of new starts within a two or three year period, the fourth and fifth year, all of a sudden there's a big dip. And all you're doing is returning back to normal. So yes, we're going to experience a decline in spending in non-residential buildings, but it's a normal function of having a big advancement and
coming down the other side.
SPEAKER_00Now, would you say some of this was from federal dollar-driven?
SPEAKER_02Oh, yes, very much so. The manufacturing is all of that. Manufacturing spending four or five years ago, I don't want to give you a wrong number, so I'm going to read the numbers out. Manufacturing from 2015 through 2021 Very little, and it was $75 to $80 billion a year. This past year, it was $224. Oh, wow. Okay?
And that's approximately a third of all non-residential building construction.
SPEAKER_02So the difference now, some of that is inflation. I've written an article about that also, the manufacturing taper. When you want to get the exact numbers of anything that I talk about, go to my blog. It's all there in black and white. It's free. It's free. And that's important because that's my way of giving back to the industry. I've been retired for 10 years. People who read my blog sometimes call me up and say, we're planning a big spending plan over the next five years.
SPEAKER_02Can you do an analysis for us in Dallas, Texas or Phoenix, Arizona? And that's consulting efforts that I would take on, all starting from people who read my blog. A blog is where it's all at.
SPEAKER_00Yeah, no, I found you on X, formerly Twitter. years ago, and your blog and your work were instrumental in my outlook for the home builders and fixed residential construction back in 2003. It actually printed me a bullet of cash. Luckily, we've already met for lunch back in the summer in Providence, Rhode Island. But no, the blog is great.
SPEAKER_00So your outlook. Let's wrap this up. Just finish your thoughts here.
SPEAKER_02Well, just to finish up the thoughts, manufacturing is tapering. Data centers are still increasing. So data center spending is going to go up for the next two or three years. Bridge and highway spending is still increasing. That's going to go up for the next few years. Those types of projects take five, six years, the highway bridge projects. They're not 24 month projects. Data centers, on the other hand, can be 24-month projects, but there's been a lot of starts.
So that's going to keep adding to non-residential building spending over the next few years.
SPEAKER_00What about my area of interest is residential construction?
SPEAKER_02Residential construction. Well, I have 5% a year for this year and next year. And in 2026, I have 10%. In 2027, I have 13%. Now, how do I get my spending numbers?
SPEAKER_00I was going to say, I was going to ask. What's the voodoo like?
SPEAKER_02I read Dodge starts data. And Dodge gives us construction starts by year. And they tell us that and their analysis is all encompassing all the information that they're gathering from around the United States. And what they're saying is residential starts after the big influx that we had in 2008. 2022, 2023 has gone down, which is why we saw a little bit of a decline this year. You know,
SPEAKER_02it didn't go negative, but compared to what spending was, it dropped way down and it may come back up again in 26 and 27. I take starts data and I cashflow it over time. So as I watch the starts data, if I have $40 billion worth of starts every month, then I expect $40 billion worth of starts to get spent over the next whatever the duration of the type of buildings that I'm dealing with,
whether it's 24 months for non-residential or 12 months for residential buildings.
SPEAKER_00Got it. Got it. Ed, this has been great. Thank you for your time. This has been amazing. Highly recommend folks out there. Follow Ed on Twitter. Ed, what's your Twitter handle?
SPEAKER_02Edzerinsky.com.
SPEAKER_00No, your Twitter handle.
SPEAKER_02Oh, Edzerinsky.
SPEAKER_00Okay. And then your blog is Edzerinsky.com.
SPEAKER_01Right.
SPEAKER_00Excellent. Awesome. That was really informative. Thank you for your time. Thank you, Dan. And we'll cross paths again on X at some point. Great. All right. Take care. Thanks. Bye. Goodbye. Bye.